Professional Documents
Culture Documents
Final Completion Report - GSHP-1
Final Completion Report - GSHP-1
GSHP-1
Sarkhej to Viramgam
(km. 11+000 to km. 59+000)
1-1
Table of Content
1 INTRODUCTION................................................................................................4
1.1 Description of Contract...............................................................................4
1.2 Project Summary........................................................................................4
1.3 Supervision Consultancy Contract Details..................................................4
2 PROGRESS SUMMARY....................................................................................5
2.1 Pre-Construction Activities..........................................................................5
2.1.1 Hand Over of Site..................................................................................5
2.1.2 Acquisition of Land................................................................................5
2.1.3 Utilities...................................................................................................5
2.1.4 Removal of Trees..................................................................................5
2.2 Work Programmes......................................................................................5
2.2.1 Submission of Programmes..................................................................5
2.2.2 Comparison of Progress against Programme.......................................6
2.3 Road Works................................................................................................6
2.3.1 Road Works - General...........................................................................6
2.3.2 Formation – Earthworks........................................................................7
2.3.3 Base Courses........................................................................................7
2.3.4 Asphalt Surfacing..................................................................................8
2.4 Structures................................................................................................... 8
2.4.1 General – Bridges.................................................................................8
2.4.2 Other Cross Drainage Structures..........................................................8
2.5 Drainage.....................................................................................................9
2.6 Socio Economic Development & Safety.....................................................9
2.7 Access Roads...........................................................................................10
2.8 Miscellaneous Items.................................................................................11
2.8.1 Site Offices..........................................................................................11
2.8.2 Highway Landscaping.........................................................................11
2.9 Extension of Time.....................................................................................11
2.10 Variation Orders....................................................................................... 11
2.11 Substantial Completion.............................................................................12
2.12 Maintenance.............................................................................................12
3 Quality Control................................................................................................12
3.1 General.....................................................................................................13
3.2 Details of the borrow areas & sources......................................................13
4 PROBLEMS AND THEIR RESOLUTION........................................................13
4.1 Key Events of Project...............................................................................14
4.2 Delays.......................................................................................................15
4.3 Technical Problems and their Resolution.................................................15
4.3.1 Over Toping of Water During Floods of 2003......................................15
4.3.2 Pavement Behavior.............................................................................15
5 PERFORMANCE OF CONTRACTOR.............................................................16
5.1 General.....................................................................................................16
5.2 Contractor’s Mobilisation..........................................................................17
5.3 Plant and Equipment................................................................................17
5.4 Staffing..................................................................................................... 18
6 Construction Supervision..............................................................................19
6.1 Consultancy Contract...............................................................................19
6.2 Supervision Team.....................................................................................19
1-2
6.3 Procedures...............................................................................................20
7 Review of Design & Specification.................................................................20
8 Environment and Social Management..........................................................21
8.1 Training of contractor staff........................................................................21
8.2 Environmental Inspection.........................................................................21
8.3 Environmental Monitoring.........................................................................21
8.4 EMAP compliance....................................................................................21
8.4.1 Dust.....................................................................................................21
8.4.2 Air Pollution.........................................................................................22
8.4.3 Noise...................................................................................................22
8.4.4 Borrow area.........................................................................................22
8.4.5 Drainage..............................................................................................22
8.4.6 Contamination from Waste..................................................................22
8.4.7 Contamination from Fuel and Lubricants............................................22
8.4.8 Soil Erosion.........................................................................................22
8.4.9 Topsoil.................................................................................................22
8.4.10 Compaction Of Soil.............................................................................23
8.4.11 Loss of Trees.......................................................................................23
8.5 SOCIAL ENVIRONMENT.........................................................................23
8.5.1 Sanitation and Waste Disposal in Construction Camps......................23
8.5.2 Safety..................................................................................................23
8.5.3 Loss of Access....................................................................................23
8.5.4 Traffic Jams and Congestion...............................................................24
8.5.5 Cultural Remains.................................................................................24
8.6 Other.........................................................................................................24
9 Documentation................................................................................................25
1-3
1 INTRODUCTION
1-4
2 PROGRESS SUMMARY
The site was Handed Over on 17th October 2000 and mobilization started very
slowly.
Apart from one or two locations, Acquisition of Land was not a problem to
construction progress. The road is constructed mainly parallel to the existing
railway line, which has required coordination between the R&BD and the
railways to resolve interface problems and minor land acquisition to improve
alignment and safety.
2.1.3 Utilities
Generally removal of trees was not the problem in this package, tree cutting
started in 11th December ’00 and completed by August 2002.
Contractor submitted a works programme in the form of a bar chart. This was
subsequently replaced during construction by 3 revised works programme
under General Conditions of Contract (FIDIC Clause 46.1).
1-5
The improvement of Sarkhej and Sanand required that a dual carriageway with
parking facility and street lighting, a covered drain and paved walkways were
added to improve the town facilities. Total 5.7 km has been dualed in this
contract.
Start End
Mobilisation 17 Oct 00 Feb 02
Survey 17 Oct 00 16 June 03
Tree Cutting 11 Dec 00 Aug 02
Materials Testing 3 Jan 01 16 Jun 03
Clear & grubbing 14 Dec. 00 30 Sep 02
1-6
Start End
Earth works 20 Dec 00 Trial Emb. 31 Dec 02
Selected Subgrade 16 Feb 01 01 Feb 03
GSB 25 Jan 02 09 Feb 03
Start End
WMM (Mechanical) 13 May 01 15 May 03
WMM (Paver) 29 May 01 30 May 03
DBM 11 Jun 01 10 Jun 03
AC 15 July 01 16 Jun 03
Diversions 8 Feb 01 16 Jun 03
Culvert construction Dec 01 16 Jun 03
At many of the locations the existing road of the carriageway had shown signs
of distress, which could be a weak spot for the performance of the pavement
over its life. These locations were dismantled and replaced with selected sub
grade/granular sub base.
Materials were hauled from
Sabarmati River to stockpiles
located at strategic parts of the site
and blending with aggregates and
soil to make GSB for laying. Close
monitoring and testing was carried
out to ensure satisfactory GSB
materials. To ensure continuity of
GSB works during the disturbances
(February to June 2002), another
source and (55,000 m3) at Charia
near Limdi (in addition to Sabarmati Compaction in Progress
River) was approved temporarily
1-7
between (Feb. 2002 to June 2002) were used to ensure continuity and avoid
stoppage.
WMM was manufactured at 4 pug mills located at Km 14, 20, 43 & 57. The
materials were strictly controlled for grading and optimum moisture while laying
to ensure a quality product. WMM was laid by both mechanical methods and
paver.
2.4 Structures
1-8
Construction carried out for 24 No box culverts – 15/1, 16/1, 19/1, 19/3, 24/1,
26/1, 27/1, 28/1, 28/2, 29/1, 30/2, 30/5, 33/1, 34/1, 35/1, 37/1, 38/1, 39/1, 42/1,
44/1, 46/1, 54/1, 54/2 & 58/3.
Construction carried out for 43 No pipe culverts on the main carriageway and
pipe culverts in accesses and/or access roads. Additional pipe culverts were
located and extended - 17/1, Km 16+080 (3 x 900 mm dia.); 18/2, Km 17 +840;
59/3 (2 x 900); 59/4 (3 x 900) & 59/5 (4 x 900).
Pipe culvert at Km 12+000 was moved to Km 12+420 and a new pipe culvert
44/2, Km 43 +460 (1 x 1000) was installed. Pipe culverts at 24/3 Km 22+400;
Km 23 +626; Km 23+900 and 56/1, Km 55 +998 (canal crossing) were
cancelled.
2.5 Drainage
A special covered drain was
provided in the urban areas of
Sarkhej and Sanand, in order that
the socio economic impact on the
area would be improved. In addition
to that a large outlet drain was
incorporated in the works at Sarkhej
to mitigate the monsoon affects.
Near Sanand village, lined drain
along with the footpath has been
constructed to improve the Social
environment and safety of bath Open Drain near Sanand
pedestrian and motorists.
1-9
1-10
At critical locations number of signboards, cat’s eyes and crash barriers are
installed as safety measures. Total 23 bus stands were constructed in Brick
masonry with covered RCC roof and sitting arrangements along the corridor.
In the area near km 47+000 (Sachhana village) the railways were persuaded to
give up land in order that a safer road alignment could be built and an improved
footpath compiled to a better safety barrier constructed.
The movement and improvement of 3 temples were carried out with the
assistance of the local people. In some cases, the alignment was adjusted to
avoid small temples and venerated trees.
1-11
Total 234 access roads were constructed along the corridor. The category and
type of access roads are as follows:
Housing /
Type Villages Factory Fields Total
shops
Contractor’s offices, labour quarters, Hot mix plant, pug mill for WMM, crusher
and concrete plants were located at km 43. The main laboratory at km 43 is
used for bituminous and concrete works. The contractor had also set up two
other laboratories; one at km 21 and the other at km 57.4.
Generally the highway is passing from plain terrain. Running parallel to the
Railway line. Both the side slopes have been covered with turffing for stability
and protection of the slope. At some stretches the grass has not grown properly
due to lack of watering.
An extension of time for 2 months was granted for the earthquake of 26 th January
2001.
1-12
Total 7 variation orders have been submitted to the R&BD and they are as
follows:
Variation Order No 1 : Variation due to Stump Removal under BOQ item no.
2.01 (c)
Variation Order No 2 : Variation due to Extension of time due to Earthquake with
no additional cost
Variation Order No 3 : Variation due to use of Provisional sums
Variation Order No 4 : Variation due to re-assessment of BOQ items and
introduction of Granular Sub Base.
Variation Order No 5 : Variation due to additional testing on concrete structures
Variation Order No 6 : Variation due to Light scarification of the existing
bituminous road surface in accordance with Section 3 –
Bidding Data
Variation Order No 7 : Variation due to balancing quantities to the completion of
the contact
2.12 Maintenance
1-13
3 Quality Control
3.1 General
The Final Materials Report Volumes 1, 2 & 3 are submitted along the with the
final completion report for the reference. The detail report includes the works
carried out for earth works, sub grade, selected sub grade, culverts, minor
bridges, GSB, WMM, DBM, AC and miscellaneous items. The main laboratory at
km 43 is used for bituminous and concrete work. The batch type hot mix plant is
also functional at Km. 43.
Laboratory Setup
Sub base - Sabarmati River (80%), crushed Agg. (10%), local soil
(10%).
- Charia near Limdi used as a temporary source during
riots of 2001.
Selected sub-grade - Dhakdi (km 59), borrow area ID Mark
SV-III, and Sabarmati sand+30% Local
Soil.
Aggregate - 2 sources – Sayla.
All materials used were in accordance with the requirements of the specifications
together with the relevant IRC and IS codes. The frequency of sampling and
testing of various materials are as per Clause 900 of the specifications.
1-14
1-15
4.2 Delays
At some locations near km 42, water had passed over the road and LHS
shoulders were washed out in August ‘03. The contractor has been instructed
to backfill both areas with graded rock fill as a preliminary to save any further
damage. The real cause is that there is no culvert opposite the present railway
culvert and this has increased the volume. The road is also lower than the
railway at this location and as such acts as a weir during the worst of the flood.
1-16
5 PERFORMANCE OF CONTRACTOR
5.1 General
The initial progress of he contractor was very slow but once the project manager
was changed and the principal contractor took over the sections work
progresses, the contractors work was on schedule.
Then in August 2001, the main Contractor (after his own assessments) began the
change process towards re-organisation of the site activities. The re-organisation
and remobilization of more resources took place from the end of October 2001 to
March 2002. The main Contractor took over all of the asphalt works along with
sections of work Km 21 to 25; Km 25 to 30; 35 to 43 and the 2 No subcontractors
also increased their equipment. The progress and quality in the second half can
be considered as good.
1-17
Contractor’s offices, labour quarters, HMP, WMM, crusher and concrete plants
were located at km 43. The production of aggregates at km 43 from imported
site boulders was carried out from 15 February 2002 to 28 February 2003.
Oriental’s staffs headed by the Chief Project Manager are worked from both the
established Sanand office (with all communication facilities) and km 43 new
offices.
The contractor also set up two other laboratories; one at km 21 and the other at
km 57.4. At each of these locations, Contractor had also installed a wet mix
Macadam Plant (Pug-mill type). The laboratories at these locations are well
equipped for soil, granular sub-base and wet mix macadam. The Subcontractors’
crushers were located (120 km away from the project road) at Sayla. In summer
2002, the sub contractor erected another wet mix macadam plant (pug-mill type)
at Km 14.
1-18
5.4 Staffing
1-19
6 Construction Supervision
Consultant’s office from 1 Jan 2001- 30 June 2003 functioned with the following
staff:
1-20
6.3 Procedures
In house training on materials and construction methods have been made during
the course of the Project for contractor staff and R&BD Engineers as part of
technology transfer.
From 2 June to 23 October 2001, the Subgrade top in the shoulder-widened portion
was being adjusted to the same level as that of the existing road asphalt in order to
facilitate the drainage. However, after 23 October 2001, Contractor was instructed to
follow the revised pavement design -- following PCC’s review of the design and
Contractor’s submission of letter under Clause 8.1 absolving him from costs of failure
due to defect in the design. Accordingly revised finished road levels and areas of failed
existing road requiring treatment were issued to the Contractor. The use of granular
sub base (GSB) was introduced in the pavement.
The re-adjustment of the vertical profile for improvement of the vertical alignment was
carried out to minimize the quantity of profile corrective course (PCC) in sub base.
Following the issue of the modified pavement design, materials from the nearby
Sabarmati river were hauled to various parts of the site for blending into granular sub
base materials (GSB). Contractor following discussions with R&BD and CSC Engineer
reached agreement of a rate for GSB.
During the disturbances (February to June 2002), another source (55,000 m3) at
Charia near Limdi (in addition to Sabarmati River) was approved temporarily (February
to June 2002) to accelerate the works on GSB and avoid the idling of equipment.
At many of the locations the existing road extension of the carriageway had shown
signs of distress, which could be a weak spot for the performance of the pavement
over its life. These locations were dismantled and replaced with selected sub
grade/granular sub base.
Near the end of the project another additional culvert was constructed over IOC
pipeline at Km. 57 after approval of the Employer In October 2002.
1-21
In GSHP, a new initiative towards environmental protection and management has been
taken. To make this initiative work, special focus has been given to two strategies.
One - adopting a structure in which compliance with the environmental clauses
becomes mandatory. This is achieved by making the EMAP a part of the contract
between the employer, R&BD, and the contractors, thus empowering the Engineer with
the monitoring powers. The second, and more important, is the recognition that “good”
engineering practices to take care of a number of environmental issues. The process
of environment management in the project started with following steps.
The staffs of the contractor were trained to make understand the need for
environment management and the contractual obligation on the part of the
contractor in complying the same. The process followed both classroom and on
the site training.
The environmental and social issue that has been successfully complied as per
EMAP requirement is detailed out below:
1-22
8.4.1 Dust
Water sprinkling was done at regular intervals to prevent dust
nuisance at the crushing and aggregate processing sites, and temporary roads,
during construction.
Access roads and any unpaved construction roads were watered to
prevent excessive dust nuisance.
Vehicles delivering materials were covered to reduce spills.
Asphalt mixing plants were located over one km away from
communities/residences.
Mixing equipments were well sealed and operators were provided with
dust masks, eye and ear protection aids.
8.4.3 Noise
Workers in vicinity of strong noise were provided with earplugs and
helmets and their working time were limited.
Maintenance of machinery and vehicles was regularly maintained to
keep their noise at a minimum.
8.4.5 Drainage
All necessary measures were taken to prevent earthworks and stone
works from impeding the rivers and water causes or existing irrigation and
drainage system.
8.4.9 Topsoil
Preservation of topsoil was a highlight of the project. The process of
topsoil preservation was done at construction camp, agriculture land used for
earth borrowing etc. At the end of the project the topsoil was relayed to
minimize the impact on productive lands.
8.5.2 Safety
Safety of workers by providing safety gear such as helmets, gloves,
masks, ear plugs, safety jackets etc.
Road user’s safety was met by providing sign boards at regular
intervals including retro reflective sign boards for night traffic. In addition to this,
delineators, sand bags, painted drums, safety tapes etc were used.
All the construction vehicle had red flags on them in order that they
could be noticed from distance
In case of emergency the provision of a first aid box at each camp
location and the display of important telephone numbers were incorporated.
Speed of construction vehicles was controlled to avoid mishaps.
To avoid accidental risks from blasting in quarries the project use the
material from existing quarry.
1-24
8.6 Other
The public were informed through large signboard at both end of the
project giving details such as scope, timeframe, consultant, and contractor of
the project.
1-25
9 Documentation
The various correspondence and files are compiled and packed in the boxes for your
reference.
1. Re to Contractor 1 to 10
2. MPR CSC 1 to 3
1. OSE To RE 1 to 6
2. RE To Team Leader 1 to 6
3. From Team Leader 1 to 3
4. MPR OSE 1 to 3
1. CSC Manual 1
2. OSE Delhi 1
3. PCC 1
4. R&BD 1
5. FRL’s 1
6. Guide Rail 1
7. As Built Structure 1
8. As Built Road 1
9. Access Road OSE 1 to 2
10. Access Road CSC 1
11. Environment 1 to 2
12. Vo’s 1
13. Work Methodology 1
14. Final Est. Cost 1
15. Work File Re 1
16. Delay Claim 1
1. Claim 1
2. Initial Levels 1
3. Contractor Equipment 1
4. Structures 1
5. CBR 1
6. Daily Progress Record 1 to 3
7. CSC Manual Record 1
8. CSC Manual 1
9. Agreement Office 1
1-26
10. Survey 1
11. Widening Slab Culverts 1
12. Weekly Progress Report 1
13. Progress 1
14. Work Shops 1
15. Diversion 1
16. Miscellaneous 1
1. Letter Summary 1
2. Work Programme 1
3. Staff Memo 1
4. Staff CSC 1
5. Survey CD 1
6. General 1
7. Attendance Sheladia 1
8. Sheladia Memo 1
9. TBM 1
10. Bus Shelters 1
11. Public Shelters 1
12. Guide Rail 1
1-28
Box No – 13 To 23
Road Work
1-29