PART 1 - SUBCONTRACTOR

Site Office Complex Temporary Office

Location Near SS5 Subcontractor 77 INSAAT

Requested By
The above-mentioned Site Office Complex was inspected on (DD / MTH / YYYY) and all findings
from the inspection have been closed and the evidences are as attached. We request for approval
to occupy the above-mentioned Site Office Complex.

Name Zeki Ozbelin Designation Construction Manager

Signature Date / Time

PART 2 - EPCC CONTRACTOR


Confirmed By (EPCC CONTRACTOR SHE Manager)
I confirm that the all findings from the Pre-Occupation Inspection have been addressed and that the
Site Office Complex indicated above is safe for occupation.

Name Designation

Signature Date / Time

Approved By (EPCC CONTRACTOR SCM)


I approve the use of the Site Office Complex specified above. Subcontractor shall ensure that the
Office Complex is used in accordance with the requirements specified in the Site Office Safety
Procedure and any other limitations expressed in the note below.

Name Designation

Signature Date / Time

Limits of Approval: