Professional Documents
Culture Documents
Task
Task
Score
A. Quality System Requirements
NA 0 1 2 3 4
Has the external service providers
1 - The QMS certification done ,Poorly
defined and documented its quality 2 - The Quality system is documented & 4 - The Quality system is documented,
ISO 9001, ISO/IATF 16949 not controlled. Found major Gaps like Quality 3 - The Quality system is documented &
A1 policy, objectives and commitments to NA - Not Applicable controlled but found minor gaps in practice e.g controlled and clearly describe the external
certified/Discontinued policy, QMS manual, Departmental objectives controlled but records not updated timely.
quality? (ISO 9001, ISO/IATF 16949 revision status not updated. service providers's current practice.
not available/not clearly defined
etc..)
3 – MRM meetings are conducted regularly 4 – MRM meetings are conducted regularly
Does the external service providers top 2 – MRM meetings are conducted regularly
0 – No Evidence of MRM is being 1 – Formal MRM is being conducted but not and Analysis of Customer complaints, Internal and Analysis of Customer/Field complaints,
A3 management conduct Management NA - Not Applicable and Quality system is reviewed & deployment
conducted. as per frequency defined in QMS rejections, internal audit points are discussed, internal rejections, inspection yield, internal
Review Meetings. is not done.
Effectiveness of actions not monitored. audit feedbacks are monitored
3 - Daily tracking done for despatches. 4 - Daily OTIF is being monitored. ASN
0 - No evidence. Not aware of OTD 1- Monthly delivery plan available for all the 2 - Weekly delivery plan arrived & adherrence
A 4 c) On-time delivery Monitoring ( OTD ) NA - Not Applicable Actions are in place where daily despatch (Advance shipment Note) is being sent to
Monitoring customers. Monthly tracking is in place monitored
schedule not met. customer regularly.
Does the external service providers have 4 – Internal audits are well planned,
2 – Internal audits are conducted as per yearly
planned Internal Audit schedule & proper 0 – No Evidence of Internal audit being 1 – Formal Internal audits calender made as 3 – Internal audits are planned, conducted communicated, conducted regularly and &
A5 NA - Not Applicable calender. Improvement points identified &
closure of the Non-conformances raised conducted. per Quality manual but poor adherrence. regularly and & NCs are addressed & Closed NCs are effectively addressed. No repeated
reviewed in MRM
during Internal audits NCs evidenced
Are training needs being identified for all 3 - Training schedule & Effectiveness 4 - Training schedule & Effectiveness
1 - On the job training given only for operators 2 - On & Off the job training given. But Not
A7 employees & training calendar are NA - Not Applicable 0 - No evidence of Training given monitoring procedure are available. Not monitoring procedure are available.
but no training material available . documented properly
available & conducted as per plan. updated Frequently reviewed & Updated
Score
B. Contract Review System Requirements
NA 0 1 2 3 4
3->25% capacity is available. If the existing 4->45% capacity is available. If the existing
2- Presently < 25% capacity is available,
0-Supllier does not have any documents 1-Currently external service providers is not customers demand goes up, still there will be customers demand goes up, still there will be
mostly due to reduced demand from existing
B1 Capacity assessment NA - Not Applicable evidencing the present capacity & having any surplus capacity & no investment surpluss capacity >15%. external service surpluss capacity >25%. external service
customers. Very limited investment plan to
available capacity. plan to enhance providers is open to investment for enhancing providers is open to investment for enhancing
enhance the capacity
the capacity whenever required. the capacity whenever required.
Are there procedures for the 3 - Document change records are available for 4 - Document change records are available for
1 - Document change records are available 2 - Document change records are available for
identification, documentation, review and 0 - No Evidence of Documentation of all the changes. Design/ document review all the changes. Design/ document review
C4 NA - Not Applicable with very poor adherrence. Design/ document all the changes. Design/ document review not
approval of all Engineering changes and changes done before drawing release. But all the done before drawing release. But all the
review not done before drawing release done before drawing release.
modifications? review points have not been addressed. review points have been addressed.
3 - Control Plan Done, revised as per drawing 4 - Control Plan Done, revised as per drawing
chnges. Controls based on cusomer chnges. Controls based onCusomer
2 - Control plan Done at the initial product
complaints have been incorporated. Control complaints have been incorporated. Control
Does external service providers 0 - No evidence, No knowledge about 1 - Control plan Done, All CTQs identified. But development time, CFT members have
C8 NA - Not Applicable plan is directly accessible to operator. plan is directly accessible to operator.
demonstrates adherence to control plan. Control Plan not properly documented, Not followed involved. But no further review. Customer
Focused approach for mistake Focused approach for mistake
complaints have not been addressed.
proofing/Pokayoke. Stringent reaction plan is proofing/Pokayoke. Stringent reaction plan is
not available available.
3 - Special processes identified & validation 4 - Special processes identified & validation
criterion defined. Validation carried out during criterion defined. Validation carried out during
2 - Special processes identified & validation
part development. Re-validation plan & part development. Re-validation plan &
Process validation for special processes 0 - No evidence, No knowledge about 1 - Special processes identified & validation criterion defined. Validation carried out during
C 10 NA - Not Applicable frequency defined. Implementation is as per frequency defined. Implementation is as per
e.g plating, welding, powder coating etc. Process validation criterion defined. Implementation is very poor part development & validation reports
plan. Operator qualification record is available. plan. Operator qualification record is available.
available.
Proper guidance has not been provided for Skill matrix defined & proper guidance
semi skilled operators. provided for semi skilled operators.
0 - No evidence, No knowledge about 2 - Limited Experience Using PSW and has 3 - Done, Properly documented, Need some 4 - Well documented Evidences of usage of
C 12 Part submission warrant (PSW) NA - Not Applicable 1 - Done, But not properly documented
PSW training plan more training PSW
D. Production Planning and Product & Process Score
Control Requirements NA 0 1 2 3 4
Is FIFO operated in RM consumption
0 - No proper records have been 1 - Consumption Recorded, FIFO Not 2 - Consumption Recorded, FIFO Not 3 - Consumption Recorded, FIFO Followed, 4 - Consumption Recorded, FIFO Followed,
D1 point and are individual component batch NA - Not Applicable
maintained for RM consumption followed. No traceability followed. Have traceability Have traceability - need improvement Have traceability
numbers traceable ?
3 – Operator instructions are located at the 4 – Appropriate work instructions /Visual aids
Are SOP/WI are available at the point of 1 – Work instructions are made, not available 2 – Visual aids posted on work stations &
work station, sufficient to ensure that the job are available where needed and clear &
use. Are they clearly/ adequately defined in required place. Specific instructions are not where operator influence can impact the
D2 NA - Not Applicable 0 – No work instructions available can be done correctly. Machine no, Program complete enough to carry the process,
with the machines, equipments, tools, available, inspection methods are not clear- quality.Inspection methods are not clear-
no & inspection criterion defined and they are inspection methods etc. 100% implementation
fixtures, and program to be used. Need improvement. Need improvement.
followed. evidenced.
2 – Procedure defined for production starting 3 – Robust system defined for production 4 – Robust system defined and implemented.
Is there a procedure to authorize the line 1 – Procedure defined for production starting
& approval. Displayed near work area. starting with QA/QC approval. QA/QC Checklist made for operator to ensure all
D3 to start production for a particular part NA - Not Applicable 0 – No procedure is defined. & approval. Only limited to QMS manual. Very
Operators are well aware & implementation is approval being taken before production during necessary parameters before production start
number & shift changing ? poor implementation.
satisfactory. shift changes. in case of setting changes & shift changes
Is external service providers monitoring 3 - Improvement plan evidenced , Actions 4 - Improvement plan evidenced , Actions
1 - Cp, Cpk Monitored , But plan for 2 - Improvement plan evidenced , But Actions
D7 Cp ,Cpk and following continual NA - Not Applicable 0 - Cp,Cpk Not monitored Implemented , But No monitoring on Implemented , Effectiveness Mapped and
improvement does not evidenced not Implemented
improvement plan effectiveness further improvement planned
Are the critical machines are identified 2 - Critical machines were identified, No
0 - No machines were identified as 1 - Awareness exists on Critical machines, No 3 - Critical machines were identified, 4 - Critical machines were identified,
D8 and Contingency plan for the same is NA - Not Applicable contingency plan but Preventive maintenance
Critical for quality, delivery Contingency plan Contingency plan exists, Need improvement Contingency plan exists, Effectively followed
available. in place
Critical operations / stations operator skill 1 - On the job training given, No written 3 - Training schedule & Effectiveness
2 - On & Off the job training given. But Not 4 - Training schedule & Effectiveness
D9 matrix are available & Further training NA - Not Applicable 0 - No evidence of Training given training Manuals, No verification of monitoring procedure are available. Not
documented properly monitoring procedure are available. Updated
being given effectiveness updated
Is PCR(Process Change Request) 0 - No Awareness, No knowledge about 2 - Documented Evidenced but customer 3 - Well documented Evidenced along with 4 - Well documented Evidenced along with
D10 NA - Not Applicable 1 - Awareness exists but not followed
approval system from customer exist PCR. approval not taken customer approval but effectively not followed. customer approval and effectively followed.
Score
E. Product Inspection, Identification and Lot
Traceability
NA 0 1 2 3 4
2 - First off /Last off approval system in place 3 - First off /Last off approval system in place , 4 - First off /Last off approval system in place
Is there a system for First off and Last off 0 - No Evidence of First off/Last off 1 - First off approval system in place and but
E3 NA - Not Applicable but all parameters not covered & records not all parameters are covered but records not and followed devotionally. Records are
approval of the production part. approval system in place. last off approval is not done
maintained. maintained properly. maintained for verification all the time
All the measurement tools & 1- All the dimensional checking instruments 3-All the instruments/gauges are available for 4-All the instruments/gauges are available for
2-All the instruments/gauges are available for
mastermentioned in the control plan are are available, but geometrical dimension dimensional & geometrical inspection, dimensional & geometrical inspection,
0 - No control plan / Measurement tools dimensional & geometrical inspection, but
E4 directly available for the operator? Insp. NA - Not Applicable checking instruments are not available. inspection frequency is matching to the control inspection frequency is matching to the control
are entirely differrent from control plan. inspection frequency is not matching to the
Frequency is adhered as per Control Inspection frequency is not matching to plan. Proper verification by supervisor or QC plan. Properly verified by supervisor or QC
control plan
plan control plan person is not evidenced. personnel.
3 – Rework procedure is clearly defined & 4 – Rework procedure is clearly defined &
Does the external service providers
2 – Rework procedure is clearly defined & proper lead time with responsibility has been proper lead time with responsibility has been
quantify and analyse nonconforming 0 – No evidence of a process for
E9 NA - Not Applicable 1 – Rework criteria is verbally communicated. proper lead time with responsibility has been fixed. Implementation is satifactory. fixed. Implementation is satifactory.
product and Rework Procedure is verifying the quality of reworked parts.
fixed. Found gaps in implementation. Containment action & corrective action has Containment action & corrective action has
followed?
not been addressed been addressed
NA - Not Applicable
F. Measuring Instruments availability & Calibration
NA 0 1 2 3 4
2 - List of instruments with unique ID no is 3 - List of instruments with unique ID no is 4 - Detailed master list of instrument with
1 - List of instruments with unique ID no is
available. ID no is not mentioned on the available. ID no is not mentioned on the robust calibration tracking system is
available. But the ID nos are not mentioned on
Are there list of measuring instruments 0 - List of measuring instruments & ID perticular instrument. Calibration certificate is perticular instrument. Calibration certificate is evidenced. Instrument history card available
the perticular instrument. Calibration
F1 available with clear trecebility & NA - Not Applicable nos is not available. No recod available available for all the instruments, but there is available for all the instruments, also for all the instruments, where calibration
certificate is available for most of the
calibration status for calibration date & calibration due. no trecebility for calibration on perticular trecebility for calibration is available on frequency, calibration status & location of the
instruments, but there is no trecebility on
instrument. Calibration tracking system is not perticular instrument. Robust system is instruments are available. Tecebility for
perticular instrument.
upto the mark evidenced for Calibration tracking system. calibration is available on every instruments.
2 - WCPG/WCRG is available for few running 4 - WCPG/WCRG is available for all the
0 - There is no WCPG/WCRG available. 1 - There is no WCPG/WCRG available. parts. These are available for all the threads 3 - WCPG/WCRG is available for all the thread gauges. Calibration checklist is
Are WCPG & WCRG available to do
F3 NA - Not Applicable No evidence of any calibration of thread Thread gauges are being sent for 3rd party on which complaint received.Other gauges thread gauges. Calibration checklist is evidenced before issuing to procuduction.
inhouse calibration for Thread gauges
gauges calibration in a defined time frequency. are being sent for 3rd party calibration in a evidenced before issuing to procuduction. Unique ID no is available and calibration
defined time frequency. frequency define for WCPG & WCRG
4 - Customer specific gauges are being used
Are Customer specific gauges are being 3 - Customer specific gauges are being used for all of the components. Thiese are being
2 - Customer specific gauges are being used
used for the inspection purpose. 0 - No evidence of using any customer 1 - Customer specific gauges are available for for most of the components. Found minor developed while part development &
F4 NA - Not Applicable for most of the components. Found minor
E.g.Bore plug guge, Spigot snap gauge specific gauges very few cases. Found major gaps gaps. Masters made to validate these gauges horizontally deployed across. Masters made
gaps
& position gauges etc. before issuing to the production. to validate these gauges before issuing to the
production.
Score
G. Purchase System Requirements
NA 0 1 2 3 4
Is PPAP validated only if external service 3-Stringent PPAP made with Tier-1 external 4-Stringent PPAP made with Tier-1 external
1- PPAP is being done with Tier-1 external 2-Stringent PPAP made with Tier-1 external
providers has approved Tier 2 PPAP's service providers & Tier-2 external service service providers & Tier-2 external service
G2 NA - Not Applicable 0-No evidence of such system service providers. service providers, but Tier-2 external service
and equivalent internal component providers's quality monitored.Tier-2 PPAP not providers's quality monitored.Tier-2 PPAP has
Major gap observed in the PPAP documents providers's quality not monitored
validations? validated been verified & validated.
3 - Audit done for all Tier-1 external service 4 - Audit done for all Tier-1 external service
2 - Audit done for all Tier-1 external service
1 - Audit done for only major Tier-1 external providerss & major Tier-2 external service providerss & all Tier-2 external service
Is there any audit carried out for Tier-1 & providerss. Action plan taken for
G8 NA - Not Applicable 0 - No Evidence of any audit. service providerss. Action plan taken for providerss. Action plan taken for providerss. Action plan taken for
Tier-2 external service providerss improvement, monitored & implemented. Re-
improvement. improvement, monitored & implemented. Re- improvement, monitored & implemented. Re-
audit not done
audit done after improvement. audit done after improvement..
Score
H. 5S & Machine shop control practices
NA 0 1 2 3 4
Is the appropriate tool used as per the 3 - Tools maintained properly, Control
1 - Tools are Maintained. Operator use the 2 - Tools maintained properly, Control 4 - Tools maintained properly, Operators are
control plan? 0 - No Control plan. No Evidence of plan/Work Instruction updated.All the
H1 NA - Not Applicable tools correctly. Control plan/WI needs plan/Work Instruction updated. Few Operators strictly following the Control plan/WI. 100%
Are tools properly maintained? usage as per Control plan/WI operators are aware about this & following the
updation. are following as per this. adherence. Tool life is being monitored.
Does the operator use the tool correctly? same
Is skilled manpower & adequate spare 0 - No Skilled Labours for maintenance, 1 - Have Semi Skilled, No Evidence of 4 - Have Skilled, Adequate spares available.
2 - Have Semi Skilled. Spares available. - 3 - Have Semi Skilled. Spares available. -
H2 parts are available to carryout NA - Not Applicable No proper control on machine availability of spares- only breakdown Effectively followed periodic maintenance
Needs major improvements Needs minor improvements
uninterrupted maintenance? Maintenance Maintenance. plan.
3 - OEE for critical machines are monitored 4 - OEE for critical machines are monitored
Does all the Productive machines OEE 1 - OEE for critical machines are monitored 2 - OEE for critical machines are monitored
0 - OEE monitoring system is not through a proper system. Actions are not through a proper system. Appropriate actions
H5 are monitored and improvement plans in NA - Not Applicable through a system. Adherence is only 50% & through a proper system. No actions are
evidenced. No knowledge on the same. taken in advance prior to the end of life of the are taken in advance prior to the end of life of
place? No actions are based on the same. based on the same.
same. the same.
Score
I. Handling, Storage, Packaging, and Delivery
NA 0 1 2 3 4
Does the external service providers have 4 - Clearly defined Procedure Available ,
the system to and means of handling that 2 - Procedure Available for Handling and Monitored Improvement action evidenced -
0 - No procedure available for Handling 1 - Procedure Available for Handling and 3 - Procedure Available for Handling and
prevent damage or deterioration / Shelf storage and Shelf life monitoring. Monitoring external service providers Has got Very good
I3 NA - Not Applicable and Monitoring the condition of long storage only (Shelf life not covered) , storage and Shelf life monitoring. Monitoring
life? Is the condition of product in stock evidenced for some critical parts. Self life control on inventory (FIFO & JIT system
storage items But No evidence for Monitoring evidenced, FIFO implementation not followed
assessed at a regular frequency in order monitoring is not proper followed) No parts are stored for long
to detect deterioration? duration.
Are flammable, corrosive, and toxic
materials properly stored and 3 - Proper storage place available . 4 - Proper storage place available .
0 - No proper storage and no monitoring 1 - Proper storage place available . 2 - Proper storage place available .
segregated? Are temperature, humidity, Temperature, Humidity, Noise level are Automatic Monitoring and triggering process
I4 NA - Not Applicable of Temperature, Humidity , Noise level No monitoring of Temperature, Humidity , Temperature, Humidity, Noise level are
Noise level, vibrations monitored in these monitored , Manually recorded and Not available to control the Temperature,
etc. Noise level etc. monitored. No records evidenced
storage areas on a regular basis? (Must updated regularly Humidity, Noise level .
for Plating external service providerss)
Does the external service providers have 2 - External service providers handles
3 - External service providers handles 4 - External service providers handles
a process in place to handle premium 1 - External service providers handles only on Premium shipping ,But No Improvement
0 - External service providers does not Premium shipping, Improvement actions Premium shipping, Root cause analysis and
I5 shipping requests? Does Premium NA - Not Applicable some cases (delayed till month/ year ends) for actions evidenced (Frequent premium
handle Premium shipment evidenced ( Situation occurs rarely (e.g.. Improvement actions defined and monitored -
shipments are monitored and actions are selected region - And depends on customer shipping - In process machine break down ,
Transport strike, RM shortage in Market etc. ) Reviewed by Top management
in place to control the same? huge Rejection )
Do employees knows / Training given for 1 - General safety training given , But not 2 - Formal safety training given without any 3 -Document training module is evidenced, for
0 - No Evidence of safety & Health 4 -Document training module is evidenced, for
J6 the safety and health hazards specific to NA - Not Applicable evidenced through records nor evidenced in records or document , Hence consistency in all people and work area with high potential
training to employees all people and all work area
their job assignments? work culture coverage and practice not evidenced safety hazard
Whether All Electrical safety is identified 0 - Issue Not Addressed at all , & Lots of 1- Some potential electrical hazard observed , 3- Good electrical installation , But No 4 - Fool proof electrical installation with
J7 NA - Not Applicable 2 - No obvious electrical hazard ,
and adequately addressed potential for electrical Hazard evidenced untrained persons handling electrical issues. periodical inspection carried out periodic inspection by authorise person
2 - Prompt recording are evidenced , But 4 - Prompt recording are evidenced , Very
Is there a proper recording , reporting 1 - Irregular and inconsistence records are 3 - Prompt recording are evidenced , Counter
J8 NA - Not Applicable 0 - No System counter measures are not effective Counter measures are initiated and
and addressing of safety incidences evidenced measures are initiated , But not effective
initiated / .Evidenced evidenced
Are fire extinguishers available? Are the 4 - Adequate and Appropriate fire
0 - No Safety measures / control 2 - reasonable no of fire extinguishers are 3 - Adequate and Appropriate fire
fire extinguishers suitable to the type of 1 - Few fire extinguishers are evidenced, But extinguishers are available . Well trained and
J 14 NA - Not Applicable systems in place, No awareness, No available but trained people are not extinguishers with adequately trained people
fire that may occur (e.g. carbon dioxide not properly maintained adequate no of fire fighters are evidenced.
plan evidenced are not available
for electrical fires). Periodic Mock dill conducted
Whether appropriate and adequate First 1 - First Aid Box improperly Maintained , 2 - First Aid Box properly Maintained , with 3 - Well Maintained First Aid Box, With 4- Well Maintained Medical centre With
J 15 NA - Not Applicable No Facility
aid facilities are provided No Proper trained person evidenced trained person evidenced formally First Aid trained person available qualified staff
(For private companies, financial information must be Score
obtained from the company. However this
information will not be audited, and the numbers NA 0 1 2 3 4
Does the external service providers NA - Not Applicable 0 - No Concept of Annual Business Plan 1 - Makes the Sales Projection for next 3 2 - Plan Available for 1 year only , Actuals 3 - Plan Available for next 3 year only , 4 - Plan Available for next 3 year only ,
make a Business plan every year and years but no detailed Business Plan monitored , But no Gap Analysis carried out & Actuals monitored,(>30 % gap noticed ) in last Actuals monitored,(<10% gap noticed ) in last
K1 track the performance against same. No improvement Plan noticed year, Gap Analysis & Improvement Plan year, Gap Analysis & Improvement Plan
Evidenced Evidenced
Does external service providers work to NA - Not Applicable 0 - No system in place to monitor 1 - external service providers can not 2 - external service providers can 3 - external service providers can 4 - external service providers can
K2 realize production efficiencies in order to efficiencies over time, No improvement demonstrate system efficiency, And does not demonstrate system efficiency, But does not demonstrate system efficiency, Does willing to demonstrate system efficiency, and ready to
share savings with customer? plan. willing to share with customers. willing to share with customers. share with customers partially. work with customers on all cost cutting
Are Accounting Systems and Working NA - Not Applicable 0 - No system in place to monitor 1 - Materials are purchased on a need basis 2 - There is System in place. But needs major 3 - There is System in place. Needs minor 4 - Company
initiatives has ERP
& willing System to monitor all
to share.
K3 capital management in Place is material costs/ fund flow and paid. There is no system followed improvement. improvement. the fund flow. Strong & stable system in place.
adequate?
Does the external service providers NA - Not Applicable 0 - Own Funds are <20% of the total 1 - Own Funds are >20% but <50% of the 2 - Own Funds are >50% of the total 3 - Own funds are >50% of the total 4 - external service providers is part of a well
having Sufficient funds to run the Investment in Business. Balance Funds total Investment in Business. Balance Funds Investment in Business. Balance Funds are Investment in Business. Balance Funds are known Business group. Fincially strong. Own
Business are borrowed from Market or Financial are borrowed from Market or Financial borrowed from Market or Financial institutions. borrowed from Market or Financial institutions. funds are >50% of the total Investment in
institutions institutions. external service providers is not having external service providers is having capability Business. Balance Funds are borrowed from
capbility to Invest further funds into Business to Invest more funds into Business for Market or Financial institutions. external
K4
or borrow funds Business growth or borrow from market. Have service providers is having capability to Invest
demonstrated the same in past. more funds into Business for Business growth.
K5 Type of Business Entity NA - Not Applicable 0 - Sole Propreitorship firm. 1 - Partnetship firm 2 - Pvt limited company 3 - Public limited company (Not listed) 4 - Public limited company (Listed Entity)
Aud
SL No
10
11
12
13
14
15
16
17
18
Audit Prepera
Requirments
Prepare Roles & Responsibility & Authorised -QMP-5.3-D/A , As per new Organizaion Chart.
Include one more quality objectives in QMP-6.2 D/A Objective, to have inhouse rejections less than 500 PPM Always.
Inhouse rejection ( Inprocess NC & CA, QMP-10.2-R/B Rev - 00.( Update the format number).
Status
Updated
Change QMP 6.2 D/A to include inhouse rejection PPM target in quality
Updated
Updated
Prepare CP/PFMEA/PFD
Auditor
Auditor
Auditor
Auditor
Auditor
STEEL PROFILES INDIA PVT LTD
Doc. No : QMP - 5.3 - D/B
Mr.VikramSingh
Singh Mr.Niranjana
Ms.Saritha
Ms.Saritha Mr.Vikram Mr.UmeshKamath
Mr.Umesh Kamath Mr.NiranjanaNU
NU
HR&Accounts
&Accounts Dispatch QA-Incharge
HR Dispatch PPC & Production I/cI/c
PPC & Production QA-Incharge
Store's Final
FinalInspector's Line
Store's Inspector's LineInspector's
Inspector's
Conventional M/c.
VMC Programmers Maintanance .Operators CNC Programmers
MR :
Format No : QMO-7.2 - R/A REV -00
SKILL's
customer requirements
( Visual inspection)
Knowledge About
Awareness About
Drawing Reading
Goods Handling
parts Handling
Programming
Recautions
Job Set Up
VMC / CNC
VMC / CNC
Handling
Operate Min Score 10
Safty
Sl Name Of The Photograph Of
Designation VMC / CNC
No Employee The Employee
Machine Max Score - 100
7
SKILL MATRIX
PROFILE SECTION
SKILL's
Customer requirements
( Visual inspection)
Band Saw Cutting
Knowledge About
Awareness About
Drawing Reading
Goods Handling
parts Handling
Precautions
Job Setting
Band Saw
Handling
Min Score 10
Machine
Sl Name Of The Photograph Of Cutting
Safty
Designation
No Employee The Employee Machine
Max Score - 100
Operting
1 Venkatesh Operator
ü ü ü ü ü ü ü ü ü
2 Revanna Operator
ü ü ü ü ü ü ü ü ü
3 Venugopal Operator
ü ü ü ü ü ü ü ü ü
4 Suresh Operator
ü ü ü ü ü ü ü ü ü
5 Rohith Operator
ü ü ü ü ü ü ü ü ü
7 Nagaraj Operator
ü ü ü ü ü ü ü ü ü
8 Krishna Operator
ü ü ü ü ü ü ü ü ü
9 Mithlesh Operator
ü ü ü ü ü ü ü ü ü
11 Manjunaath Operator
ü ü ü ü ü ü ü ü ü
Doc. No.:QMP - 7.2 - R/B
Issue Date:
Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24
Sl No Training Topic
P A P A P A P A P A P A P A P A P A P A P A P A
1 QMS Awareness P A
2 House Keeping P A
4 Reading drawing P A
5 Control of Rejection P A
8 Tapping process P A
11 PPAP Documentation P A
Training Subject :
Attended By
Prepared By : Approved :
Prepared By : Approved :
STEEL PROFILES INDIA
Rec. No : QMP-9.1.2 R/A
Please provide us your valuable inference of our performance as per the 5 - point scale based on the parameters and factors
as indicated below.
Rating 1 2 3 4 5
Inference Poor Bad Average Good Excellent
Rating
SL No Factor (Please P in the boxes)
1 2 3 4 5
1. Quality
1 Consistency in Quality.
7 Packing
2. Purchase
1 Order acknowledgement from us.
2 Flexibility in scheduling.
6 Price Competitiveness.
3. Delivery
1 On time Delivery.
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
STEEL PROFILES INDIA
Month: Jun-24
Pending
Total Bin Schedule Planned Actual
Sl. No. Part number Supplier Schedule
Qty Qty Qty Qty
Qty
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Steel
Customer C
Name Of
Sl No Date Part Name Part Number Machine Name
Customer
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
el Profiles India
nal Rejection Tracker Register
Production
Reason For Rejection Rejection Detection Stage Rejection Qty
Qty
Operator Inspector
Status
Name Name
INTERNAL REJECTION TREND IN PPM - 2024-25
STEEL PROFILES INDIA
PPM of
Month Production qty Internal rej.
Rej.
Apr-24 10000 5 500.00
May-24 16582 2 120.61
PPM of Rej. Jun-24 17942 9 501.62
600.00 Jul-24 19302 6 310.85
Aug-24 20662 4 193.59
Sep-24 22022 0 0.00
500.00 501.62
500.00 Oct-24 23382 2 85.54
Nov-24 24742 6 242.50
Dec-24 26102 6 229.87
400.00 Jan-25 27462 5 182.07
Feb-25 #DIV/0!
310.85 Mar-25 #DIV/0!
Axis Title
300.00
208198 45 #DIV/0!
242.50
229.87
193.59
200.00 182.07
120.61
100.00 85.54
0.00
0.00
Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25
Axis Title
Target 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0 500.0
Pictures/Photographs
Gas Cutting mark observed
Profile Radius Found Ok free
NOT OK
from gas cutting marks
Not ok Ok
D3 - Containment actions
Check List Quantity Containment actions planned Resp Action status
3.1 Stocks at Customer 15 no's Available Stock 100% Segregated all pieces found ok. SPI Completed
*Abbreviations: RPN-Risk priority number, FI&T - Final inspection and checklist, WIP - Work in progress, SC - Sub contractor
# Internal to Wipro
Status Report No
Compl Date 24.04.2024
8D report
VQPR # D0324
Report date 25.04.2024
Power failure
Page: 2/3
D4 - Root cause analysis
Cause and effect diagram
Man power :
Operator not checking in Final
inspection Inspection Skipped at Final Inspection
1 stage Gas Cut Mark not identified Significant OK
Machine :
Material :
Method:
Speed, feed ,Radius & depth cut
1 variation Verified the same found ok In-significant Not OK
Measurements :
Environment :
SCM-CL-73. Rev 02. Dtd: 17-01-2022. Retention period: 2 years_x000D_ Internal to Wipro
#
Status Report No
Compl Date 24.04.2024
8D report
VQPR # D0324
Report date 25.04.2024
Process Flow
Why 1? Customer unable to use the material Customer unable to use the material Flame Gas Cutting
Deburring &
During the process power cut happend,due to gas flow During Chipping and cleaning not highlighted by deburring person Chipping,Cleaning
Why 3? due to no awareness about profile aesthetic
& oxygen level veriation.
Why 4? Due to Oxygen level flow variation cutting pressure is Identification Punching
unneven happened Final inspection stage only sampling inspection done
2. During Cutting process not verifed visually 100% skipped ,During Chipping and cleaning
not highlighted by deburring person due to no awareness about profile aesthetic
3. Final inspection will do 100% with white paint mark "OK" identification on part. Niranjana NU
4/25/2024
D6 - Updating of documents for sustenance Responsibility
Revision/correction of following Documents (Wherever applicable) & Target date
Design drawings -
Process sheets -
FMEA -
Control Plan -
Work Instructions -
Audit checklists -
Others if any Quality Alert displayed near the Final Inspection Area Immediate
D7 - Actions to prevent re-occurrence on other models
Problem Identified CAPA agreed CAPA Implemented, Under monitoring Issue closed & signed off
email communication hence unsigned
Page: 3/3
# Internal to Wipro
533.75 533.75
535.91 650
-2.16 116.25