Professional Documents
Culture Documents
KPI-SNA-RU3-EEL-EBD-3001 - A - Electrical Design Basis
KPI-SNA-RU3-EEL-EBD-3001 - A - Electrical Design Basis
UNIT OM RU III
PT KILANG PERTAMINA INTERNASIONAL RU-III
TABLE OF CONTENTS
1. INTRODUCTION
1.1 Background
PT Pertamina International Refinery Unit (RU) III Palembang, is one of the refineries owned by PT
Pertamina (Persero) which produces petrol, NBBM, and petrochemicals. Fuel products produced by
RU III Palembang, especially gasoline products and their derivatives, are increasing in proportion to
market needs. Considering this, it requires adequate sarfas utility readiness to be able to support the
achievement of gasoline series (Pertalite) needs in the South Sumatra area.
a. For the operational activities of transporting Naptha and Pertalite products, only 2 pumps are
available in the RPM OVAK area, namely Pump P-6 and P-7 with a capacity of 500 m3 / hour each.
However, these pumps have not been operated since July 2022 due to cavitation and low
performance and are temporarily replaced by pumps P-2 and P-3. However, if pumps P-2 and P-3
are used for other services, the transport of Naphta and Pertalite cannot be carried out.
b. As for Naptha transportation activities from the Plaju area to the Gerong River, only 1 (one) pump
is available, namely P-3 with a capacity of 750 m3 / hour. Transportation of Naptha cannot be done
if the pump is damaged.
c. For Pertalite (HOMC) product component transfer pumps located in the RPM-5 Sungai Gerong
area, only 1 (unit) is available, namely P-119. Transportation cannot be carried out if the pump is
damaged.
d. For circulation pumps P-237, which is used during start-up and shut down activities CDU VI, HVU
II, and FCCU, serves to empty fluid in vessels, distillation columns, etc., using dissolution methods
with diesel, kerosene or flux media pumped from tanks in the Oil Movement area. Delays in the
s/you and s/d processes may occur in case of damage. This can hamper fuel fulfillment services in
the Sumbagsel area.
Therefore, to support the operation of transporting fuel needs in the Sumbagsel area and prevent
disruption of the fuel transportation process, cooperation with PT Solusi Energy Nusantara (SENA) is
needed to assist PT Kilang Pertamina Internasional RU III Palembang in the preparation of engineering
package documents.
1.2 Objective
The purpose of this document is to convey documents on the Electrical Design Base in the preparation
of Front-End Engineering Design (FEED) Pumps Unit OM RU III
JASA PENYUSUNAN FEED POMPA-POMPA
UNIT OM RU III
PT KILANG PERTAMINA INTERNASIONAL RU-III
2.1 Definition
TERMINOLOGI DEFINITION
PROJECT : Jasa Penyusunan FEED Pompa-Pompa Unit OM RU III
EMPLOYER : PT KILANG PERTAMINA INTERNASIONAL RU III.
CONSULTANT : PT Solusi Energy Nusantara (PT SENA).
MANUFACTURER : The party who makes and supplies goods or equipment in
the performance of the WORK specified by the USER or
CONSULTANT.
VENDOR : The party who makes and supplies equipment or services
in the performance of the WORK specified by the USER or
CONSULTANT.
SHALL : Indicate requirement strictly to be followed in order to
conform to this specification and from which deviation is not
permitted
SHOULD : Indicates that among several possibilities, one is
recommended as particularly suitable, without mentioning
or excluded others, or that certain course of action is
preferred but not necessarily required. Other possibilities
may be applied subject to approval.
MAY : Verbal form used to indicate a course of action permissible
within the limit of the specification.
2.2 Abbreviation
AC : Alternating Current
ETAP : Electric Transient and Analysis Program
FEED : Front End Engineering Design
MCC : Motor Control Center
RU : Refinery Unit
JASA PENYUSUNAN FEED POMPA-POMPA
UNIT OM RU III
PT KILANG PERTAMINA INTERNASIONAL RU-III
REFERENCE TITLE
REFERENCE TITLE
REFERENCE TITLE
3.2 Performance
Performance requirements shall be attained by good engineering practice. Reasonable contingencies
shall be considered so that machines and equipment are not operated at well above and / or below
their capabilities when the installation is starting system design and / or equipment selected shall be
of those that has a high availability factor.
Therefore, equipment installed indoors shall be designed for operation in the atmosphere likely to be
dusty, with a design maximum ambient temperature of 40°C.
All systems shall be designed for ease of operation and maintenance with fail-safe features and
simplicity consistent with maximum performance.
The power systems shall be designed and sized such that the largest motor, per voltage level, can be
successfully started at all levels of load utilization without detriment to other connected loads.
A contingency factor shall be applied when considering these loads for equipment sizing, for future
expansion. CONTRACTOR shall constantly update and revise this load summary during the project.
JASA PENYUSUNAN FEED POMPA-POMPA
UNIT OM RU III
PT KILANG PERTAMINA INTERNASIONAL RU-III
At the end of the project, this load summary shall be updated after integration of final VENDOR data,
as part of “As built” documentation.
5 POWER SUPPLY
The electricity power for New Pumps Unit OM RU III Project will be supplied from existing MCCs.
4 New P-237
6.2 BUSBAR
• Where a busbar is required, they shall be installed in a compartment separated from the
functional units.
• The busbar shall be made of hard drawn bare copper, high conductivity copper type, fully
insulated with flame retardant, non-hygroscopic material and installed with barriers between
adjacent compartments.
• Busbar shall be rated for the nominal current and not lower than the incoming unit.
• Busbar and connections shall be adequately sized, braced and supported to withstand the
mechanical constraints and thermal effects resulting from short circuit current.
• The horizontal and vertical busbars shall be clearly marked with their respective phase colors
shall be as follow:
- Phase R Brown
- Phase S Black
- Phase T Grey
- Phase N Blue
- Grounding E Yellow and Green
6.8 LOCKS
Each door of cubicle shall have a lock.
6.12 PAINTING
All surfaces of steel enclosure and structure shall be coated with corrosion resistant and rust inhibitive
paint with semi-gloss finish as per manufacturer's standard practice. The finish color shall be light gray
(RAL 7032).
7 TERMINAL BOXES AND JUNCTION BOXES
Where armored cables are terminated into boxes with non-metallic enclosures, these shall have a
stainless-steel earth tag installed under the locknut of the gland. These earth tags may be inside or
JASA PENYUSUNAN FEED POMPA-POMPA
UNIT OM RU III
PT KILANG PERTAMINA INTERNASIONAL RU-III
outside the box depending on the space available. Each earth tag shall be connected to the box earth
system.
Terminal boxes and junction boxes shall be rated for the area classification (hazardous or non-
hazardous) where they installed as per KPI-SNA-RU3-EEL-EDG-3006 Hazardous Area Classification
Drawing (HACD).
8 CABLING AND RACKING
All electrical cables installed at New Pumps Unit OM RU III shall conform to KPI-SNA-RU3-EEL-EPS-
3005 Specification for Electrical Cables. All control cables shall have a minimum of twenty percent (20%)
spare cores.
Cables shall be direct buried except when crossing road/pipe shall be via cable sleeve following RU-III
standard. This shall be covered in typical installation details drawing.
9 GROUNDING AND BONDING
General
Suitable earthing shall be installed for:
• Safety of personnel.
Metallic non-current carrying parts for all major electrical equipment, such as motors, transformers,
switchgear, motor starters, etc., shall be earthed by a suitable connection to the frame, skid, or steel
platform.
On equipment, earth conductor connections which are regularly disconnected for maintenance of the
equipment shall be made with screw type solderless connectors. All other connections shall be made
with crimp type connectors.
Earthing or bonding jumpers shall be of copper conductor with yellow/green color insulation.
Minimum size of earth conductors shall be 6 sq.mm.
All electrical joints made for earthing shall be accessible and checked for tightness and electrical contact.
Removable parts shall be earthed by means of a flexible insulated earth wire (links to doors)
yellow/green.
The resistance of earth cables shall not exceed the values stipulated by IEC-60079.
The armor of the electrical cables is not accepted as an earthing continuity conductor.
Mechanical protection for the earthing conductors shall be provided in the same manner as all the other
cables.
All mechanical and electrical equipment, which may become energized due to electrical faults, shall be
directly connected to the earthing system.
JASA PENYUSUNAN FEED POMPA-POMPA
UNIT OM RU III
PT KILANG PERTAMINA INTERNASIONAL RU-III
Field mounted panels, mounting stands, metallic junction boxes etc. shall be bonded to the safety earth.
On package equipment with a number of electrical components to be earthed, parallel earthing shall be
employed and not the series looping of equipment. This means earthing of equipment shall be done by
branching off from the earth loop to each individual enclosure.
Sizing of earthing conductor shall be in accordance with IEC Standard, but not less than 95 sq.mm for
main conductor and 6 sq.mm for the branches.
The earthing for the onshore processing facilities shall comply with IEEE std 80. The actual soil conditions
must be determined by soil resistance measurements. The required conductor spacing, the total length
of earthing grid and the required earthing material cross section shall be calculated considering the
maximum earth fault current, to maintain touch and step voltages within permissible values.
The earthing network shall consist of main ground mat comprising of directly buried earthing conductors,
the earth electrodes, the foundation earthing of concrete foundations or shafts and the equipment
earthing. All underground connections shall be made by means of exothermic weld.
The minimum sizes shall be as below: