SASOL SPECIFICATION SP-40-05A

REVISION 5
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
Signed by:Gerhard Visser Signed by:Petrus Jacobus Kies
Signed at:2023-05-22 17:56:35 +02:00 Signed at:2023-05-23 07:42:50 +02:00
Reason:I approve Reason:I approve

Originator : Reviewer :
G VISSER P KIES
Signed by: Andrew Dacre
Signed at:2023-05-22 17:27:05 +02:00
Reason:I approve

Approved by :
AP DACRE

For interpretation of Specification, the following person(s) can be contacted:


G VISSER, PJ KIES

A Revision Description Sheet is included to assist in identifying the changes


in the latest revision.

PREVIOUS REVISIONS

ISSUE
REV No PROPOSED BY REVIEWED BY APPROVED BY DATE
DATE
1 Dec 1997 JP Nell P Pereira HJ Bestbier 5 Nov 1997
2 Feb 2002 PJ Kies AP de Gavino C Thirion 24 Feb
Dias 2002
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

3 July 2008 DP Brits / KS PJ Kies JPG Wykes 21 July


Johnson 2008
4 Aug 2018 D Moodley W de Klerk G Visser Aug 2018
Any questions, queries, comments and proposals for revisions or additions can be
directed in writing to the Sasol specification Coordinator at specifications@sasol.com

VALIDATION This Specification is only regarded as controlled in the electronic format on the official SASOL IHS website.
When printed, this document is deemed as uncontrolled and thus for information only. It is the responsibility of the user of a
printed copy of the document to ensure validity before use. If it is issued for a specific project, it is valid for the duration of the
project, unless agreed otherwise.
COPYRIGHT This Specification is protected by copyright and is the sole property of SASOL. The information is proprietary
to SASOL and is for the sole use of the identified project or defined scope of work. Any unauthorised use, disclosure or copying
or any other means of duplication or reproduction, is prohibited.
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023

SASOL SPECIFICATION SP-40-05A

MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

TECHNICAL COMMITTEE OF SPECIFICATION SP-40-05A, Revision 5

NAME COMPANY AND DEPARTMENT

DE KLERK, WP (Willem) Projects and Engineering, Engineering


Services

DE VILLIERS, JE (Jacques) Sasol Group Services, Supply Chain

ROUX, GS (Fanus) Projects and Engineering, Engineering


Services

KIES, PJ (Pieter) Projects and Engineering, Engineering


Services

ASUMANI, O (Oscar) Projects and Engineering, Engineering


Services

VIVIERS, JJ (Johnny) Projects and Engineering, Capital Projects

MOODLEY,D (Denver) Projects and Engineering, Engineering


Services

Secunda Chemicals Operations, Technical


BADENHORST, CH (Kallie)
Support

BRENKMAN, HF (Francois) Natref, Technical Support

GREEF, H (Henriette) Projects and Engineering, Capital Projects

HORN, JW (John) Sasol Synfuels, Secunda Synfuels


Operations

Page i of v
Copyright © 2023. SASOL. All rights reserved.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023

SASOL SPECIFICATION SP-40-05A

MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

REVISION DESCRIPTION SHEET

REVISION 5

This specification has been revised to address the mandatory requirements for piping and
pipelines as defined in the OHS Act, Pressure Equipment Regulations, SANS 347 and SANS
10227.

The title was changed to “Mandatory Requirements for Piping and Pipelines” to conform to
the terminology of the Pressure Equipment Regulations.

Paragraph 1.4.17 Reference to Annex B is removed

PIPING DESIGNER – As defined in SANS 347. Annex B was corrected.

Reference to E0640 Pipeline list process datasheet was added.

Appendix D: Paragraph 3 Remove: as per Eng Bulletin 0015 and replaced with: refer to
SP-40-5A par 4.3.1. b

Appendix D: Paragraph 8.6, 3rd bullet removed Annex B.1.2

Page ii of v
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023

SASOL SPECIFICATION SP-40-05A

MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

FOREWORD
Each paragraph of the specification is classified as a Core, Site Specific or Negotiable
requirement.
Example:
1.1.1 Paragraph ends. CORE
The definition of each classification, and associated tag, colour code and format are indicated
below:

Classification Tag Colour Definition

CORE CORE Red Non-negotiable requirements that are applicable to all Sasol sites
in Southern Africa, and may also be applied to international sites,
having taken into consideration:
• Safety
• World best practice
• Standardization requirements
• Environmental implications
Site Specific RSA Blue Non-negotiable requirements applicable to all South African based
sites, taking into consideration:
(RSA)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Site Specific Secunda Blue Non-negotiable requirements applicable to the Secunda site only,
taking into consideration:
(Secunda)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Site Specific Sasolburg Blue Non-negotiable requirements applicable to the Sasolburg site only,
taking into consideration:
(Sasolburg)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Site Specific Natref Blue Non-negotiable requirements applicable to the Natref site only,
taking into consideration:
(Natref)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Site Specific International Blue Non-negotiable requirements applicable to all non-South African
based sites only, taking into consideration:
(International)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Negotiable Negotiable Green Requirements that must be agreed by both the project team and
client at an appropriate time. Once agreed, this requirement
becomes mandatory for the specific job.
Guideline (indicated in Black Guidelines and explanatory notes to assist in the understanding of
the rationale behind a specific requirement and application of the
Italics)
specification and concessions.

Page iii of v
Copyright © 2023. SASOL. All rights reserved.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023

SASOL SPECIFICATION SP-40-05A

MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

TABLE OF CONTENTS
PAGE

1 GENERAL ................................................................................................................ 1
1.1 SCOPE ....................................................................................................... 1
1.2 LEGAL REQUIREMENTS .......................................................................... 1
1.3 ABBREVIATIONS....................................................................................... 2
1.4 DEFINITIONS ............................................................................................. 3
1.5 APPLICABILITY ......................................................................................... 6
1.6 DEVIATIONS .............................................................................................. 7
1.7 CONTRADICTORY OR CONFLICTING REQUIREMENTS ...................... 7
2 REFERENCE DOCUMENTS ................................................................................... 7
2.2 SOUTH AFRICAN LEGISLATION.............................................................. 8
2.3 SOUTH AFRICAN NATIONAL STANDARDS (SANS) ............................... 8
2.4 AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME CODES) 8
2.5 SASOL SPECIFICATIONS......................................................................... 8
2.6 OTHER SASOL DOCUMENTATION ......................................................... 9
3 REQUIREMENTS .................................................................................................... 9
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

3.1 GENERAL LEGAL REQUIREMENTS ........................................................ 9


3.2 GAS RETICULATION SYSTEMS ............................................................ 10
3.3 IMPORTED PIPING ................................................................................. 10
3.4 CODE REQUIREMENTS ......................................................................... 10
3.5 SPECIFICATIONS.................................................................................... 11
3.6 EXEMPTIONS FROM REGULATIONS OF THE OHS ACT .................... 11

4 RESPONSIBILITIES .............................................................................................. 11
4.1 SASOL AS THE OWNER ......................................................................... 11
4.2 SASOL PROJECTS AND ENGINEERING............................................... 12
4.3 ENGINEERING CONTRACTOR .............................................................. 13
4.4 CONSTRUCTION CONTRACTOR .......................................................... 18
4.5 APPROVED INSPECTION AUTHORITY (AIA) ........................................ 22

Page iv of v
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023

SASOL SPECIFICATION SP-40-05A

MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

4.6 IMPORTER............................................................................................... 25

5 AUDIT AND SURVEILLANCE ............................................................................... 25

6 END OF JOB DOCUMENTATION REQUIREMENTS........................................... 26


6.1 INTRODUCTION ...................................................................................... 26
6.2 MASTER DOCUMENT ............................................................................. 26
6.3 TEST PACKS ........................................................................................... 26
6.4 DIMENSIONAL CHANGES TO ISOs ....................................................... 29
6.5 EOJ DOCUMENTATION FORMAT .......................................................... 30

7 END OF JOB DOCUMENTATION DELIVERY DATE ........................................... 31


APPENDIX A RECOMMENDED AGENDA FOR PRE-MANUFACTURING MEETING
FOR PIPING ........................................................................................................... 32
APPENDIX B TYPICAL CERTIFICATE OF DESIGN..................................................... 39

APPENDIX C – ADDITIONAL REQUIREMENTS FOR PROJECTS EXECUTED IN


MOZAMBIQUE ...................................................................................................... 41

APPENDIX D – AIA SCOPE OF WORK TEMPLATE ......................................................... 44

Page v of v
Copyright © 2023. SASOL. All rights reserved.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

1 GENERAL

1.1 SCOPE

1.1.1 This Specification is applicable to Secunda and Sasolburg locations in South Africa
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

as well as Mozambique. This Specification can be used for other locations,


provided that specific requirements are added to provide for local conditions and
regulations. These typically include differences in statutes, quality of available work
force and environmental and climatic factors. RSA

1.1.2 This Specification covers the duties of the Owner (Sasol), the Engineering
Contractor (EC), the Construction Contractor (CC) and the Approved Inspection
Authority (AIA) for the design, erection, verification, inspection and certification of
piping and pipelines for compliance with the Occupational Health and Safety Act
(OHS Act), and Sasol requirements. RSA

1.1.3 This Specification specifies the requirements for piping and pipelines as defined in
the OHS Act RSA

1.1.4 Appendix C of this specification addresses additional requirements for piping and
pipeline projects executed in Mozambique in accordance with the Republic Of
Mozambique Petroleum Operations Regulations, Decree No. 24/2004, of 20 August.
MOZAMBIQUE

1.2 LEGAL REQUIREMENTS

All engineering, design, equipment and installations in accordance with this


specification shall meet the mandatory requirements specified in the Acts,
Regulations, South African National Standards incorporated into law and
Compulsory Specifications of the Republic of South Africa. RSA

Engineering, design, equipment and installations outside the Republic of South


Africa shall meet applicable National, Federal, State or Provincial Regulations as
required by law in the respective country. INTERNATIONAL

Page 1 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

1.3 ABBREVIATIONS

AFC Approved for Construction


AIA Approved Inspection Authority

BOM Bill of Material

C Consultation

CC Construction Contractor
CI Chief Inspector

EC Engineering Contractor

EOJ End of Job


GA General Arrangement

H Hold

HAZOP Hazard and Operability Study


HSS Health and Safety Standards

ISO Isometric Drawing

IPE Inspector of Pressurised Equipment

MC Mechanical Completion
MFD Mechanical Flow Diagrams

NCR Non Conformance Report

NDE Non Destructive Examination

OHS Act Occupational Health and Safety Act (Act No. 85 of 1993) of the
Republic of South Africa
P&ID Process and Instrumentation Diagram

PER Pressure Equipment Regulations

PMM Pre-Manufacturing Meeting


PQR Procedure Qualification Record

QA Quality Assurance

QC Quality Control
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

QCP Quality Control Plan

Page 2 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

QMS Quality management system

R Responsibility

REC Records
RFC Ready for Commissioning

RFO Ready for Operation

S Surveillance
V Verification

WPS Welding Procedure Specification

1.4 DEFINITIONS

SP-00-03 defines common terms used in specifications. The definitions below


clarify, replace or are in addition to those of SP-00-03 as noted. Conflicts should be
referred to Sasol for clarification.

1.4.1 Accountability (A)

1.4.2 Audit (O)

1.4.3 Approved Inspection Authority (AIA)

1.4.4 Approved for Construction (AFC-Drawings) – In the context of this specification,


AFC- Drawings are drawings issued by the EC for the construction of piping and
pipelines and generally refers to ISO’s. For overland pipelines, AFC alignment
sheets are used in conjunction with ISO’s for construction purposes. The EC
approves these AFC Drawings to indicate that the AFC drawings are:

a. Consistent with the set of MFD’s that were approved in the final HAZOP study,
or subsequent official revisions thereof approved by the attendees of the final
HAZOP.

b. Designed and verified in full compliance with the specified HSS, specifications
and contractual requirements.

c. In full compliance with the requirements of the OHS Act.

Page 3 of 63
Copyright © 2023. SASOL. All rights reserved.--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

d. In full compliance with the requirements of the Republic Of Mozambique


Petroleum Operations Regulations, Decree No. 24/2004, of 20 August. This
requirement is applicable to projects executed in Mozambique only (See
Appendix C).

1.4.5 Certificate of Design -The proposal for the certificate of design shall be submitted to
Projects and Engineering for review and prior written approval but not later than the
start of pipe manufacture by the CC.

1.4.6 Certificate of Manufacture - A certificate issued by the CC and countersigned by the


AIA to certify that:

a. The requirements of the AFC- drawings have been met.

b. Piping and pipelines were constructed and tested under the AIA’s supervision.
c. The piping and pipeline material and components conform to the specified
HSS, specifications and contractual requirements. The names of the HSS and
specifications are clearly listed.

d. All deviations, exceptions or modifications of the applicable specification and


other contractual requirements are clearly noted, described and approved.
e. All NCR’s and concessions have been closed out and accepted by the EC,
AIA, Projects and Engineering and Sasol when required for GMR 2.(1)
reasons.

f. The prescribed pressure tests were conducted and witnessed as successful.


g. Piping and pipelines were constructed in full compliance with the OHS Act.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

h. For piping and pipeline projects executed in Mozambique, that the piping and
pipelines are constructed in full compliance with the Republic Of Mozambique
Petroleum Operations Regulations, Decree No. 24/2004, of 20 August (See
Appendix C).

Note: The CC needs to submit the format they intend to use for the Certificate of
Manufacture to Projects and Engineering for review and approval. The onus rests on
the CC to obtain this approval in writing well in advance.

Page 4 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

1.4.7 TPI Certificate of Compliance - A certificate issued by the appointed AIA certifying
that piping and pipelines were:

a. Constructed in strict accordance with the AFC-Drawings. A list of the relevant


AFC Drawings has to form part of the certificate of compliance.

b. Constructed and tested under the AIA’s supervision. The specified code(s),
specifications and standards have to be clearly listed on the certificate.

c. Pressure tested successfully in full compliance with contractually agreed


requirements.

d. In full compliance with the requirements of the OHS Act.

e. The certificate of compliance must be an integral part of the certificate of


manufacture.

Note: In addition to the above, the TPI Certificate of Compliance shall include full
compliance with the requirements of the Republic Of Mozambique Petroleum
Operations Regulations, Decree No. 24/2004, of 20 August, for projects executed in
Mozambique.

1.4.8 Chief Inspector (CI)

1.4.9 Construction Contractor (CC) - The contractor responsible for the fabrication,
assembly, erection and certification of piping and pipelines.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
1.4.10 Consultation (C)

1.4.11 Engineering Contractor (EC) - A firm, organisation or department who has been
contracted by Sasol to perform the duties of design, purchasing, inspection, testing,
control over construction, certification, punching and commissioning of piping and
pipelines.

1.4.12 Importer - In the context of this specification it is a firm, organisation or a department


who has been contracted or assigned to fulfil the roles and responsibilities of the
Importer in accordance with the PER when applicable. In certain instances the
Importer roles and responsibility can be fulfilled by a Sasol representative.

Page 5 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

1.4.13 Intervention Points

1.4.14 Line List

1.4.15 Owner

1.4.16 Pipeline – “means piping or a system of piping designed for the transport and
distribution of any fluid from an installation that is onshore or offshore, starting from
and including the last isolation device located within the confines of the installation,
including all the auxiliary equipment designed specifically for that pipeline” as
defined in the South African Pressure Equipment Regulations.

1.4.17 Piping

1.4.18 Piping Designer

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
1.4.19 Records (REC)

1.4.20 Responsibility (R)

1.4.21 Surveillance (S) (according to SANS 10227) - Systematic iteration of conformity


assessment activities as a basis for maintaining the validity of the statement of
conformity.

1.4.22 Verification (V)

1.5 APPLICABILITY

The latest revision of Sasol specifications shall apply to all new and / or to be
modified plants and facilities, on the Sasol Site, unless otherwise specified in writing
by Sasol. CORE

For existing plants and facilities that have not been modified, the specifications
effective as at date of installation shall apply, unless otherwise specified in writing by
Sasol. CORE

Page 6 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

1.6 DEVIATIONS

Deviation from this specification is subject to an approved concession as per


specification SP-90-39, except where explicitly stated that written approval by Sasol
(as defined in SP-00-03) is allowed. Special or unique applications not covered by
this specification and capital cost/lifecycle cost saving opportunities shall be
presented with recommendations to Sasol for approval. CORE

1.7 CONTRADICTORY OR CONFLICTING REQUIREMENTS

In the event of contradictory or conflicting requirements between Sasol


Specifications, Standard drawings and other referenced codes and standards, Sasol
shall be contacted for resolution in writing. CORE

2 REFERENCE DOCUMENTS

Where reference is made to a code, specification or standard, the reference shall be


taken to mean the edition of the code, specification or standard, including addenda,
supplements and revisions thereto that are in effect at the time of publication of this
Specification, with the following exceptions:

a. Where a referenced code, specification or standard is incorporated in law, the


incorporated edition or year shall apply as per the Standards Act of South
Africa (Act 08 of 2008)

b. Where a specific edition or date of a specification is referenced in this


specification, that edition or date shall apply unless otherwise approved by
Sasol.
c. Where a contractual document references a specific edition or date of a code,
specification or standard, that edition or date shall apply, with the approval of
Sasol.

d. Other specific requirements (as indicated per referenced code and standard).
CORE

Page 7 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

2.2 SOUTH AFRICAN LEGISLATION

OHS ACT Occupational Health and Safety Act, 1993

Republic of Mozambique Petroleum Operations Regulations – Decree No. 24/2004,


of 20 August

2.3 SOUTH AFRICAN NATIONAL STANDARDS (SANS)

SANS 347 Categorisation and conformity assessment criteria for all pressure
equipment

SANS 10227 Criteria for the operation of inspection authorities performing


inspection in terms of the pressure equipment regulations

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
2.4 AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME CODES)

ASME B31.1 Power Piping

ASME B31.3 Process Piping

ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and


other Liquids

ASME B31.8 Gas Transmission and Distribution Piping Systems

Note: The use of additional Health and Safety Standards will require Sasol approval.

2.5 SASOL SPECIFICATIONS

SP-00-03 Specifications Definitions

SP-40-05 Mandatory Requirements for Boilers, Pressure Vessels and


Portable Gas Containers

SP-50-03 Piping Design and Fabrication

Page 8 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

SP-50-03A Piping Material Specification

SP-50-09 General Piping - Process and Utility Field Pressure Testing

SP-90-01A Welding Consumables

SP-90-02 Welding of Metallic Piping

SP-90-23 Positive Material Identification

SP-90-37 Requirements for Sasol Final Owner Documentation

SP-90-39 Change Management – Deviations and Concessions

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
2.6 OTHER SASOL DOCUMENTATION

F980 Conformity Assessment review of Imported Pressure


Equipment

E0640 Pipeline List Process datasheet

Commissioning 360 Commissioning Manuals

SGR-MOR-000011 Procedure for hot tapping on pressurised equipment

SAMLPFF Sasol Approved Manufacturers list for pipe, fittings and


flanges.

Note: The use of additional specifications requires Sasol approval.

3 REQUIREMENTS

3.1 GENERAL LEGAL REQUIREMENTS

3.1.1 The Owner (Sasol) will not be allowed to use, require or permit the use of piping and
pipelines unless:

a. It has been designed, constructed, tested and certified in accordance with

Page 9 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

PER and SANS 347.

b. It has been designed, constructed, tested and certified in accordance with a


health and safety standard listed in the PER.

c. It has been manufactured and installed under the surveillance and supervision
of an AIA where applicable. RSA

3.2 GAS RETICULATION SYSTEMS

3.2.1 General process piping in processing plants is not deemed to be reticulation,


distribution or transmission systems. RSA

3.2.2 The Owner shall ensure that a gas system has a valid certificate issued by an
authorised person. The certificate required is included in the PER and shall be
issued by an authorised person and not by an IPE. RSA

3.2.3 Also see PER Guideline notes. RSA

3.3 IMPORTED PIPING

3.3.1 Imported piping with project specific design and construction requirements shall be
conformity assessed in accordance with Module G. Alternative Modules may be
considered for serial produced off the shelf piping items only. RSA

3.4 CODE REQUIREMENTS

3.4.1 The relevant ASME Code has been selected and approved as the basis for the
design and construction of piping and pipelines. RSA

3.4.2 When an EC proposes Health and Safety Standards other than ASME for the design
and fabrication of piping and pipelines, it shall be subjected to approval by Sasol
and shall be one of the Health and Safety Standards listed in the PER, prior to any
design being done. Approval to use such HSS and the specific requirements and
conditions to be adhered to shall be obtained in writing from Sasol. RSA

Page 10 of 63
Copyright © 2023. SASOL. All rights reserved. --``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

3.4.3 It is not permitted to selectively use design criteria from different HSS unless
approved by the AIA and by Sasol in writing. RSA

3.5 SPECIFICATIONS

3.5.1 Piping shall be designed, constructed, inspected and hydraulically tested in


accordance with Sasol Specifications SP-50-03, SP-50-03A, SP-50-09 and
SP-90-02. RSA

3.5.2 Piping designed to HSS other than ASME Codes, shall take cognizance of the
specific requirements in Specifications SP-50-03 and SP-50-03A. The EC shall
obtain written approval from Sasol for any proposed deviation from these
specifications. RSA

3.5.3 For Pipelines applicable requirements from SP-50-03, SP-50-03A, SP-50-09 and
SP-90-02 shall be applied to the design, construction, inspection and hydraulic
testing of pipelines. RSA

3.6 EXEMPTIONS FROM REGULATIONS OF THE OHS ACT

3.6.1 Only exemptions that have been submitted by Sasol and approved by the Chief
Inspector shall be allowed. RSA

3.6.2 All other exemptions, i.e. not submitted by Sasol, shall be approved by Sasol before
being used. RSA
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

4 RESPONSIBILITIES

4.1 SASOL AS THE OWNER

4.1.1 Sasol is accountable for approving all concessions, substitutions, and exemptions
authorised by the AIA for maintaining and modifying existing piping and pipelines in
accordance with the system employed by Sasol. RSA

Page 11 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

4.1.2 The Owner shall be accountable for retaining EOJ documentation and relevant
records pertaining to piping and pipelines. RSA

4.1.3 When Sasol as the Owner performs work without the assistance of Sasol Projects
and Engineering, the accountability of Sasol Projects and Engineering, as per
Paragraph 4.2, will be exercised by Sasol as the Owner. RSA

4.1.4 Sasol is responsible to:

a. Agree to the proposed flow diagrams and take part in the HAZOP studies.

b. Agree to the plan of execution.


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

c. Agree to the HSS and specifications used in design and construction.

d. Participate in system checkouts and punch-outs.

e. Accept the EOJ documentation.

f. Agree to the commissioning plan and start-up procedures for the system. RSA

4.2 SASOL PROJECTS AND ENGINEERING

4.2.1 Sasol Projects and Engineering (P&E), when acting on behalf of Sasol, shall be
accountable for:

a. Mechanical flow diagrams (MFD), process and instrument flow diagrams


(P&ID) and Material and Corrosion flow diagrams (MCFD).

b. HAZOP studies.

c. Detail Plan of execution.

d. Design HSS, specifications and specific requirements.

e. Model reviews.

f. Appointing the AIA for piping and pipelines.

g. Approving concessions, substitutions and exemptions authorised by the AIA


for piping and pipelines in accordance with the system employed by Sasol
Projects and Engineering.

Page 12 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

h. Approval of piping and pipelines as ready for commissioning and/or operation.

i. All accountabilities of the EC, as per Paragraph 4.3, only when Sasol Projects
and Engineering performs work without the assistance of an EC. RSA

4.2.2 Sasol Projects and Engineering, is responsible to:

a. Review AFC drawings on a random basis to ensure compliance with


contractual requirements.

b. In consultation with the Owner, appoint an AIA.

c. Manage the EC.

d. Attend the PMM and participate.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
e. Review on a random basis, the systems employed by the EC, CC, AIA and
sub-contractors dealing with material traceability, material take-off and control,
material ordering/expediting, material receiving, material identification, material
issue, quality control plan development; approval and implementation, welding
quality control records, NDE procedures and implementation, PWHT
procedures and implementation, pressure test procedures and implementation
thereof.

f. Approval of concessions.

g. Review and agree that the end-of-job documentation is acceptable and


complete.

h. Receive EOJ documentation and transfer them to the Owner. RSA

4.3 ENGINEERING CONTRACTOR

4.3.1 Design

The EC shall be accountable and responsible for:

a. Performing all design work. RSA

b. Categorising piping and pipelines as required by SANS 347. Compile a line list
with relevant information defined in E0640. All piping and pipelines shall be

Page 13 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

specified in the design to be constructed in accordance with Conformity


Assessment Module G. Alternative Modules for piping and pipelines with a
design pressure below 50 kPa or a SANS 347 categorization of SEP may be
accepted with Sasol Approval.

c. Implementing the requirements specified in the fully HAZOP’d and approved


MFDs including all HAZOP notes, post HAZOP changes, updates stemming
from model reviews, design codes, standards, specifications and any
requirements specifically mentioned in the contract. All changes relating to
MFD’s shall be managed through a quality control system to ensure that the
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

latest signed off revision of MFDs are issued for construction.

d. Verification and checking of design work. Ensure that the stress engineer has
approved all AFC drawings that require sign off. Issuing the certificate of
design as required in Paragraph 1.4.5

e. Issuing of approved AFC-Drawings complying with contractual requirements.


Issue an updated list of latest revisions of AFC-Drawings whenever an update
on one or more drawings is issued for construction. This will include electronic
copies when used on the contract by the EC.

f. Appointment of AIA upon request from Projects and Engineering

g. Ensuring that copies of documentation are issued in time to the AIA for
verification.

h. Ensuring that the AFC-Drawings are correctly implemented in fabrication:

i) Managing and rectifying any design documents due to deviations


occurring during the construction phase.

ii) Approving all procedures included in the piping/pipeline quality package


issued by the CC. Ensure that these procedures are strictly
implemented.

Any deviations from contractually agreed requirements shall be handled with a


formal concession following the approved non-conformance procedures of the
EC, the CC and its sub-contractors. Record keeping of these approved

Page 14 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

concessions will be in an agreed space and be open to the AIA for review.
RSA

4.3.2 Quality Management Systems

The EC shall be responsible for:

a. Material take-off and control.

b. Specifying material, ordering, expediting, receiving, inspection, storing,


issuing, identification, certification and traceability. Ensuring compliance to
code / contractual requirements is an explicit responsibility of the EC.

c. Implement a quality system to ensure that the design work is properly done,
verified and checked for conformance to the requirements mentioned in
4.3.1above prior to marking it as “Approved for Construction”.

d. Implement a system to ensure that all Model Review changes and comments
are included correctly to the full extent.

e. Appointment (in consultation with Sasol Projects and Engineering),


management and control of the Construction Contractor and any and all sub-
contractors.

f. Ensure that the piping/pipeline quality package(s) are in full compliance with
the contractually agreed requirements and are strictly followed by all the sub-
contractors. The piping quality package is defined in Paragraph 4.4.3c.

g. Generate, manage and control a detail plan of execution for the work to be
done by CC.

h. Generate, implement and control documentation flow between all parties.


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

i. Review the contents of the QCP prepared by the CC to ensure that piping and
pipelines are in full compliance with the HSS, specifications and contractual
requirements and thus conforming to the OSH Act. Establish intervention
points on the QCP to ensure full compliance with HSS, specifications and
contractual requirements. The “First of a Kind” principle shall be used to
ensure that all “First of a Kind” activities are hold points.

Page 15 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

j. Ensuring the use of approved and qualified procedures for welding,


fabrication, inspection and testing required to execute the work.

k. Ensuring the use of a quality control plan comprising material control, weld
quality control, traceability, QA records and intervention points.

l. Evaluate all non-conformances in house or those from sub-contractors.


Formulate concessions for written approval by Sasol.

m. Implement a system to ensure that material traceability and control is


maintained throughout the execution of the work.

n. Ensuring that EOJ documentation requirements as detailed in section 6 are

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
fully complied with within the contractually agreed timeframe.

o. Implement a system to gather, verify, check, control and hand-over all the EOJ
documentation as requested in this specification.

p. Using SGR-MOR-000011 – This procedure shall be used as a guideline for


hot tapping on pressure equipment. RSA

4.3.3 Interface Management

a. The EC shall be accountable for managing and controlling all interfaces with
the AIA, appointed by Sasol Projects and Engineering or the EC. When
appointed by the EC, only Sasol approved AIA’s shall be considered and the
AIA Scope of Work shall include all Legal, Code and User requirements as a
minimum (See Appendix D for AIA Scope of Work Template). Sasol Projects
and Engineering QA shall approve the AIA Scope of Work prior to submission
for quotations. The EC is accountable to manage, coordinate and control the
AIA within the contractually agreed HSS, specifications, requirements and
contractually agreed schedule. Any technical difficulties that cannot be
resolved within the contractually agreed HSS, specifications and requirements
between the EC and the AIA shall be referred to Sasol Projects and
Engineering for a final interpretation and/ or decision.

Page 16 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

b. The EC shall be responsible to timeously provide the AIA with two copies of all
relevant technical documents necessary for meaningful verification and
supervision of all piping and pipelines covered by this specification.

c. The EC is responsible to interface with the operating plant to complete the


required repair approval documentation and QA functions when work is done
in an existing unit e.g. tie-ins and hot taps. RSA

4.3.4 Pre-Manufacturing Meeting

The EC is responsible for chairing the PMM following thorough preparation and
population of the agenda with the relevant technical detail, issuing the minutes of
meeting and working off all action items.

The EC shall take the lead and assume primary responsibility for planning the pre-
manufacturing meeting:

a. Arrange the date and technical populated agenda, conducting and issuing the
minutes of the pre-manufacturing meeting prior to fabrication of the piping or
pipelines.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
b. Arrange and ensure that the relevant participants understand that they are all
responsible for the information that needs to be discussed at the pre-
manufacturing meeting. See Appendix A for recommended pre-manufacturing
meeting agenda and minimum content requirements.

c. Present at the above meeting shall be:

• The ECs representatives,

• Sasol’s mechanical, welding, QA and project representatives,

• The relevant commercial representative,

• The CC’s fabrication, welding, QA/QC and works representatives,

• AIA.

d. Prior to the pre-manufacturing meeting, the ECs review shall include, but not
be limited to, material requisition scope, purchase order scope, receiving

Page 17 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

inspection, QCP, AFC-Drawings, welding, PWHT and fabrication procedures/


requirements, production programme and documentation control. In addition,
the EC shall ensure that the CC is fully aware of, and compliant with, all AFC-
Drawings, material, fabrication, inspection and testing requirements of the
contractual requirements, including minimum technical content to be
addressed in the pre-manufacturing meeting. The EC shall ensure that the
CC understands ALL contractual requirements. RSA

Note: The pre-manufacturing meeting shall be conducted only when all


relevant AFC-Drawings, material purchase specifications, WPS`s,
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

PQR`s including all fabrication and NDE procedures and weld filler
material purchase specifications have been submitted for review and
obtained at least “B” approval status. RSA

4.4 CONSTRUCTION CONTRACTOR

4.4.1 For Piping and Pipelines the piping construction contractor is deemed to be the
manufacturer in terms of the PER and therefore accepts the duties and
responsibilities of the manufacturer to ensure compliance to the PER. The definition
of manufacturer in the PER includes construction. The definition of construction in
the PER includes design and materials. Where these are free issued to the
manufacturer, the manufacturer shall accept these and takes full responsibility. RSA

The CC shall have adequate quality control processes in place to ensure that free
issued material meets contractual requirements as part of the handover process.

4.4.2 The Construction Contractor shall be accountable to the Engineering Contractor for:

a. The construction, inspection, testing and certification of piping and pipelines in


full compliance to all contractual requirements including:

i) Implementing construction in accordance with the Conformity


Assessment Module specified in the design.

ii) Writing, implementation and approving by AIA and EC of the material


traceability, checkout and punch-out procedures.

Page 18 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

iii) Material take-off and control (in case of the CC controlling material take-
off).
iv) Ordering specified material, expediting, receiving, inspection, storing,
issuing, identification and certification (in case of the CC purchasing
material). Ensuring compliance to Code/contractual requirements is an
explicit responsibility of the CC when ordering material.
v) Compiling test packs as detailed in Section 6.

vi) Ensuring that only the latest revisions of approved documents are
always used.

vii) Ensuring that the approved QCP is strictly followed.

viii) Only using contractually agreed material.


ix) Performing system checkouts and punch-outs according to procedures
approved by the EC and the AIA.
x) Pressure testing piping and pipelines in accordance with contractually
agreed requirements.

b. Issuing a certificate of manufacture countersigned by the AIA. The format of


the certificate of manufacture shall be submitted to Sasol Projects and
Engineering for review and prior approval. RSA

4.4.3 The Construction Contractor shall be responsible for:

a. Following the detail plan of execution.

b. Using the latest construction drawings that have been checked and approved
by EC as “Approved for Construction”. Implement a system to ensure that the
latest revisions of AFC-Drawings are always used in fabrication.

c. Developing a piping quality package consisting of all Quality related


procedures for prior approval by the EC and the AIA. The piping quality
package shall have procedures for all quality activities that are employed
during the fabrication of piping and pipelines to ensure compliance with
contractual requirements. It shall at least consist of approved:

i) Drawings

Page 19 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

ii) QCP(s)

iii) Material Traceability procedure

iv) Welding documentation (weld map/ISO indicating shop and field welds,
WPS’s and PQR’s)

v) NDE map and all NDE procedures used (RT, UT, MT, PT, PMI,
hardness, dimensional control, etc.)

vi) PWHT procedures (where applicable)

vii) Forming procedures (where applicable and with wall thinning values)
viii) Painting procedures (where applicable)

ix) Pressure test and leak test procedures

Note: Approval for systems to be considered for commodity testing shall be


identified early to ensure pressure test exemptions are considered
and or approved well in advance. Systems to be considered for
pneumatic testing shall be identified and request for approval
submitted for approval on the prescribed forms.

d. Developing and utilising a QCP approved by the EC and AIA. The QCP shall
typically include:

i) Detail information showing all activities that will be used during the
fabrication/ manufacturing of piping and pipelines and the associated
quality checks to ensure compliance to design requirements

ii) Intervention points of the CC

iii) Sufficient space for the EC to add their intervention points

iv) Sufficient space for the AIA to add their intervention points

Note: The intervention points contemplated for the EC, CC and AIA are
generally as listed in Paragraph 4.5.2d

e. Using only specified materials in construction. Implement a system to ensure


that base and filler materials used are always traceable to material certificates
and the AFC-ISO by attending to material take-off and control, material
ordering/expediting (in cases where the CC purchase material) material

Page 20 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

receiving, material identification and material issue. PMI on low/high alloy


material shall be done as stipulated in SP-90-23.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Note: In the case of “free-issue” material the onus still rest with the CC to
ensure the material they accept complies with contractual
requirements.

Compliance is verified by the CC at receiving inspection. Non-


conformances are immediately announced to Sasol.

f. Using approved and qualified welding procedures, welders and welding


operators, post weld heat treatment procedures, impact testing when required,
etc.

g. Ensure that weld surface finish conforms to requirements and that minimum
throat requirements and leg ratios are maintained. (Typically including
supports and anchor chairs).

h. Using approved NDE procedures. Only qualified personnel, verified by the


AIA and EC, shall perform examinations.

i. System for management of deviations: Raising deviations, concessions,


substitutions and exemptions; recording, implementation of corrective action
and closing of deviations and concessions.

j. Interpret all NDE and in particular radiographic films prior to presenting them
to the EC and AIA for approval.

k. Carry out punching to ensure that the line has been constructed in accordance
with the scope of work prior to involving the EC and AIA.

l. After completion of a process system, provide the EC with the required


documentation that the system is mechanically complete.

m. Ensuring that all material certificates, NDE reports, and other documents
contained in the test packs are correct, legible, valid, witnessed and certified
by the CC/EC and AIA. These shall be traceable to the relevant shop and field
welds. The material certificates shall enable traceability, from the material
certificates to the AFC ISO’s to the physical item installed and vice versa.

Page 21 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

[From the AFC ISO’s to the physical item installed to the material certificate
and from the physical item to the AFC ISO’s to the material certificate]. A table
shall be included showing the traceability as described herewith. The table
shall at least address the following details: Approved MFD number, AFC-ISO

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
number, Heat number or unique number hard stamped on the physical item,
Sasol item code to SP-50-03A, material description (pipe, valve, etc.) and
material certificate number.

n. Compiling the test packs for all the process systems, comprising as a
minimum of the items specified in Section 6.

o. Issuing a Certificate of Manufacture countersigned by the AIA. The format of


the Certificate of Manufacturer shall be submitted to Sasol Projects and
Engineering for review and prior approval. RSA

4.5 APPROVED INSPECTION AUTHORITY (AIA)

4.5.1 The AIA shall be accountable for the issue of a TPI certificate of compliance for
piping and pipelines manufactured/ fabricated under their supervision to Sasol. The
format to be used shall be submitted to Sasol Projects and Engineering for review
and prior approval.

The TPI certificate of compliance from the AIA is a separate document to the
certificate of manufacture issued by the CC which needs to be countersigned by the
AIA.

The AIA shall use IPE qualified inspectors with piping code experience for all
aspects of their supervisory role and to issue the certificate of compliance. RSA

4.5.2 The AIA is responsible to:

a. Ensure that the EC, CC and sub-contractors have acceptable QA/QC systems
that are used as a routine to implement the contractual requirements.

b. Verify and approve by signature and stamping all required documentation to


ensure they are in compliance with the contractual requirements between

Page 22 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

Sasol (or its agent, Sasol Projects and Engineering), the EC and the CC and
any sub-contractors. The following documents shall be verified as a minimum:

i) Welding procedure qualification records and specifications


ii) Welders and operators’ qualifications

iii) PWHT procedures (where applicable)

iv) NDE procedures and operators’ qualifications

v) Pressure testing procedures (hydraulic and pneumatic)


vi) AFC-ISO’s; the AIA is only responsible to ensure that the applicable
code calculations were done and checked by the EC and that the stress
engineer from the EC has approved all ISO’s. No design verification
calculations by the AIA are required

c. Review the contents of the QCP prepared by the CC to ensure that piping and
pipelines are in full compliance with the HSS, specifications and contractual
requirements and thus conforming to the OSH Act.

Establish intervention points on the QCP to ensure full compliance with HSS,
specifications and contractual requirements.

The “First of a Kind” principle shall be used to ensure that all “First of a Kind”
activities are hold points.

d. Perform, at the CC’s and his sub-contractor’s shop and the job-site all required
verification inspections continuously in order to be satisfied that OSH Act
requirements are adhered to. The results of such inspections shall be
documented: Either by signing the QCP; issuing an inspection report or NCR
to the CC, EC and Sasol with a copy in the file of the AIA. The inspection
shall, as a minimum include the following:

i) Base and filler material identification, correlation with material


certificates, HSS requirements and AFC-ISO’s;

ii) Ensure traceability of cast numbers by transferring them prior to cutting;


iii) Verify weld preparation and fit-up to ensure compliance with contractual
requirements;

Page 23 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

iv) Verify PMI on components and filler as specified in SP-90-23;

v) Ensure welding is done as prescribed in the approved welding


documentation (including pre-heat where applicable);

vi) Weld surface finish conforms to requirements and that minimum throat
requirements and leg ratios are maintained (typically including supports
and anchor chairs);
vii) PWHT shall be witnessed and approved to indicate conformance to the
approved procedure (location and number of thermocouples, thickness
and extent of insulation). The PWHT charts shall be approved indicating
that the heating rate / holding time / temperature and cooling rate are as
per the approved procedure per line number.
viii) Dimensional inspection;
ix) NDE procedures are approved and QC personnel are qualified;

x) Witness NDE’s as per contractual requirements;

xi) Pickling, passivation and painting are performed to the requirements of


the approved procedure where applicable;

xii) Witness that all pressure testing is performed to HSS, specification and
approved procedures, using only valid calibrated testing equipment and
pressure testing water which complies with the contractual requirements
(the witnessing of pressure testing cannot be waived);

xiii) Accept by stamping and signing on the pressure test certificate that
piping and pipelines were pressure tested successfully in compliance
with contractual requirements;

xiv) Verify that as-built drawings reflect final fabrication / installation /


configuration as prepared by the EC.

e. Evaluate, register and comment on all concessions prior to sending them to


the EC. The AIA shall ensure that the results of the approved corrective
actions have been properly complied with and are documented.

f. Ensure that NCR’s and concessions have been closed out and accepted by
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

the relevant parties.

Page 24 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

g. Countersign the certificate of manufacture issued by the CC.

h. Issue a TPI certificate of compliance. RSA

4.6 IMPORTER

4.6.1 RESPONSIBILITIES

The importer is required to fulfil all the duties stipulated in the PER and SANS 347
to ensure that all imported equipment is in full compliance with the OHSA. NOTE:
The importer shall verify that the foreign inspection bodies meet the requirements of
PER with respect to ISO 17020 accreditation and scope of accreditation together
with the applicable HSS. RSA

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
4.6.2 DOCUMENTATION

a. The importer is required to retain records in accordance with the PER.

b. The importer’s conformity assessment review shall be completed on Sasol


Form F980 as follows:

• Verify that section A of Sasol Form F980 has been completed.

• Complete the declaration in Section B of Sasol Form F980.

• For SANS 347 category II and higher ensure that section C of Sasol
Form F980 is verified and signed by the Importer’s AIA.

c. Ensure that the completed Sasol Form F980 has been included into the
Manufacturer’s code data book. RSA

5 AUDIT AND SURVEILLANCE

5.1 Sasol Projects and Engineering will audit the design of piping and pipelines and the
systems employed by the EC to ensure proper verification of the design work is
done. RSA

Page 25 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
5.2 Sasol Projects and Engineering will audit or perform surveillance of the AIA and CC
as required. RSA

5.3 Sasol Projects and Engineering will perform surveillance to verify that the design of
piping and pipelines is done in strict accordance with the contractual requirements.
RSA

5.4 Supervision by the AIA shall ensure that piping and pipelines have been fabricated,
assembled, inspected and tested in accordance with the relevant HSS,
specifications and all contractual requirements, thus in full compliance with the OHS
Act. RSA

6 END OF JOB DOCUMENTATION REQUIREMENTS

6.1 INTRODUCTION

All documentation generated during the design and manufacturing of piping and
pipelines must be traceable to a master document. RSA

6.2 MASTER DOCUMENT

The master document is defined as the revision of the MFD’s that were approved in
the final formal HAZOP study, or subsequent official revision thereof. The master
document must be completely detailed by the isometric drawings that are generated
during the design phase. Isometric drawings must be consistent with the master
document. The master document shall form part of the EOJ documentation. RSA

6.3 TEST PACKS

The master document shall be divided into process systems; each divided into a
number of test packs. The test packs, and a summary of test pack numbers, shall
be included in the EOJ documentation, per process system, showing where the
specific test pack fits in on the master document acting as a checklist that the

Page 26 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

complete master document is covered. The minimum content of a test pack for
piping and pipelines are: RSA

6.3.1 Line Numbers

Each test pack includes a summary sheet providing the line and sheet numbers that
are covered in the test pack.

The relevant marked up portion of the master MFD is also included in the test pack.
RSA

6.3.2 Isometric Drawings (ISO) with Bill of Materials (BOM)

AFC ISOs containing the BOMs shall be included. These AFC ISO’s shall be used
during formal checkouts and punch-outs. The AFC ISO’s shall detail the complete
master document for the specific test pack boundaries.

The AFC ISOs and BOMs shall define the following detail for each and every item
on the ISO:

a. Material specification
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

b. Sizes and dimensions

c. Item code according to the Sasol specification item codes listed in SP-50-3A

d. Material description, i.e. pipes, valve, flange, etc. RSA

6.3.3 Alignment Sheet (Pipelines Only)

AFC Alignment Sheets when issued for pipeline projects shall be included.
Alignment sheets shall be used in conjunction with ISO’s during formal checkouts
and punch-outs. RSA

6.3.4 Material Certificates and Traceability

The material certificate of each component used, thus shown on the AFC ISOs shall
be included in the EOJ packages. A system should be in place to ensure traceability
from the installed piping, via the AFC ISOs, to the actual material certificates. RSA

Page 27 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

6.3.5 Pressure Testing Equipment Calibration Certificates

The calibration certificates of all pressure gauges that were used to perform the
pressure testing (hydrostatic or pneumatic) as prescribed in the OHS Act must be
traceable to a National Standard and performed by an Accredited Laboratory. RSA

6.3.6 Pressure Test Record


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

The hydrostatic or pneumatic pressure test record, approved by the IPE inspector of
the appointed AIA, certifying that the system, as detailed in the AFC ISO’s of the test
pack, are completely tested in accordance with OHS Act and the project
requirements and that the system withstood the pressure as specified. RSA

6.3.7 Weld Map, Welding Procedure Specifications (WPS) and Procedure Qualification
Records (PQR)

a. The weld map shall be indicated on the AFC-ISO by numbering either, each
weld, shop and field, or each item installed in a unique, sequential manner
supporting the traceability system employed.

b. The installed items shall have the heat number or unique number hard
stamped or etched (as per approved procedure) on each and every item
forming part of piping and pipelines in the test pack.

c. A summary table is required (and shall be included) to allow traceability


between the WPS, PQR and welder that were used in producing the weld and
the weld map indicated on the AFC-ISO. The table must also indicate and
allow traceability to all NDE’s and NDE results that were done. The IPE
inspector shall sign off all NDE results.

The summary table shall therefore address the following points: Weld number
(or item number), heat numbers (or unique numbers) of items connected by
welding, description of items, welders ID, WPS number, PQR number, NDE’s
performed and reference to the NDE reports.

d. For cold service only, the welder’s certificate shall also be included as well as
proof of impact testing of weld consumables used in production. RSA

Page 28 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

6.3.8 NCR’s, Concessions (including material substitutions), Waivers and Hot Taps

All NCR’s, concessions (including material substitutions), waivers and hot tap
approval forms shall be included in the test pack. The NCR’s, concessions and
waivers shall be signed by the AIA-IPE inspector, confirming that they were
completely implemented. RSA

6.3.9 Certificate of Manufacture

The applicable certificate of manufacture issued by the CC and countersigned by


the AIA for piping and pipelines shall be included in each and every test pack that
forms part of the specific process system. RSA

Note: Only one certificate of compliance, issued by the AIA is required for the
work done on the master document under their surveillance. RSA

6.3.10 Signed Off Punch List

Each test pack shall have signed off punch lists (pre-hydrostatic test and post
hydrostatic test), as proof that all outstanding work has been completed. Standard

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
checkout documentation shall be used as detailed in the Sasol Projects and
Engineering Commissioning Manual. RSA

6.4 DIMENSIONAL CHANGES TO ISOs

Any dimensional change shall be investigated to assess the need for re-analysis of
stresses, e.g. high temperature or high-pressure systems or large diameter piping.

a. Not involving the addition of welds:

Dimensional changes (minor) that are necessary during construction of the


pressurised piping system which do not require the addition of material, or
which do not require the addition of a weld(s) are not defined as a deviation
requiring an update and re-issue of the AFC ISO. Dimensional changes to be
marked up on red-lined ISO for as building.

Page 29 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

b. Additional welds:

Dimensional changes to the AFC ISO’s resulting in the addition of weld(s) or


material are defined as a deviation requiring an update and re-issue of the
AFC ISO. RSA

6.5 EOJ DOCUMENTATION FORMAT

The EOJ documentation shall be presented in the English language. RSA

6.5.1 Documentation in Electronic Format

The master document, summary sheet of test pack numbers, line numbers summary
sheet, AFC Drawings, BOM’s, WPS’s, PQR’s, summary table allowing traceability
as defined in Paragraph 6.3.7c shall be supplied in electronic format.

The approved sequential numbering procedure used by the EC in developing the


weld map shall be supplied in electronic format. This procedure shall document the
exact numbering specification used. It shall also address the numbering of additional
welds due to changes.

The numbering shall be unique and shall allow proper traceability. The AIA shall
certify by stamping and signature that this specification was used strictly throughout

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
the project to number welds and/or items uniquely. RSA

6.5.2 Scanned Documentation

The material certificates, pressure test calibration certificates, pressure test record,
NCR’s concessions, waivers, hot tap approval forms, NDE results, certificate of
manufacture, certificate of compliance and signed off punch list must be scanned,
and handed over in electronic format. RSA

6.5.3 Hand Marked-Up (redlined) Weld Map

The weld maps shall be hand marked on the AFC-ISO. One paper copy of the hand
marked-up AFC-ISO shall be included in the single paper copy of the EOJ

Page 30 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

documentation handed to Sasol Projects and Engineering.

The EOJ documentation shall hence only consist of one or more CD’s, with one
paper version of the EOJ documentation to be handed to Sasol Projects and
Engineering. RSA

7 END OF JOB DOCUMENTATION DELIVERY DATE

The EOJ documentation shall be delivered prior to signing the Ready for
Commissioning (RFC) approval. Category 2 and 3 punch list items that are done
after RFC shall have the resulting close out documentation delivered not later than 2
weeks after RFO has been signed, unless otherwise contractually agreed. RSA
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Page 31 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

APPENDIX A RECOMMENDED AGENDA FOR PRE-MANUFACTURING MEETING


FOR PIPING

1 WELCOME, INTRODUCTION AND PURPOSE

2 MINUTES OF MEETING – WHO AND WHEN

3 SCOPE OF WORK

3.1 Scope Changes

4 PIPE FABRICATION/MECHANICAL INSTALLATION CONTRACT:

4.1 Line systems with a reference to the different line classes

4.2 Client reference number(s)

4.3 Manufacturer’s reference number(s)

4.4 AIA reference number(s)

4.5 Purchase Order Number

5 RESPONSIBLE PERSONNEL

5.1 Sasol Projects and Engineering

5.1.1 Quality Assurance

5.1.2 Inspector

5.1.3 Welding Engineer

5.1.4 Design Engineer

5.1.5 Project Engineer

5.1.6 Commercial Officer

5.1.7 Procurement Official

5.1.8 Expediting Official

5.2 Engineering Contractor

Page 32 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

5.2.1 Quality Assurance

5.2.2 Design Engineer

5.2.3 Project Engineer

5.2.4 Commercial Officer

5.2.5 Welding Engineer

5.2.6 Procurement Official

5.2.7 Expediting Official

5.3 Approved Inspection Authority

5.3.1 Design Verification Engineer (If applicable)

5.3.2 Quality Assurance

a. Co-ordination and Documentation Verification (IPE)


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

b. Inspector (IPE)

5.4 Construction Contractor

5.4.1 Quality Assurance / Quality Control (Shop/Field)

5.4.2 Project Engineer

5.4.3 Welding Engineer (Shop/Field)

5.4.4 Workshop Manager/Site Manager

Field Engineers and key staff on site

5.4.5 Sub-Vendors/ Sub-Contractors

a. Welding Consumables

b. Welded Components (if any)

c. Heat Treatment (Shop and field)

d. NDE (Shop and field)

e. Sand blast and paint (Shop and field)

Page 33 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

f. Rig spray if applicable

g. Others

5.5 Roles and Responsibilities

6 CONTRACT

6.1 Contract Finalised and signed?

6.2 Minutes of Pre-award and Bid clarification data – Points outstanding

6.3 Agreed basis of work to commence


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

6.4 Precedence of documents

6.5 Fabrication schedule

6.5.1 Fabrication schedule and contractual delivery dates

6.5.2 Progress reporting and expediting

6.5.3 Current documentation approval status (NDE and fabrication procedures)

6.5.4 Status of AFC ISO`s from EC

7 DOCUMENTATION

7.1 Master drawing/document index – List all documents to be submitted for review and
approval as agreed in contract.

7.1.1 ISO`s

7.1.2 Procedures and other documents

7.1.3 MFD`s, Civil Drawings, GA’s

7.2 Number of document copies for construction

7.3 Documentation flow diagram – review of current procedure

7.4 Documentation turn-a-round time - Client, - AIA

7.5 Documentation schedule

8 DESIGN CRITERIA

Page 34 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

8.1 HSS

8.2 Specifications / Standards / Statutory Regulations / Engineering Bulletins / Standard


Drawings

8.3 Design changes during construction (ISO`s etc.)

8.4 Design changes during Fabrication - Notification

8.5 Service conditions requiring PWHT/impact testing etc.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
9 FABRICATION SEQUENCE

9.1 Workshop

9.2 Field

9.3 Others

10 MATERIAL REQUIREMENTS

10.1 Material specifications

10.2 Free issue material

10.3 Material repairs

10.4 Certification of material by all parties

10.5 Other

11 FABRICATION QUALITY CONTROL

11.1 QCP (content and FOAK)

11.2 Receiving inspection

11.3 Traceability of material

11.4 Post Weld Heat Treatment

11.5 Weld Map –shop and field welds

11.6 Welding requirements versus service requirements

11.7 Procedure Qualification Record (PQR)

Page 35 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

11.8 Welding Procedure Specification (WPS systems)

11.9 Welder Performance Qualification Record (WPQR)

11.10 Weld process control

Consider requirements like impact testing, special requirements etc.

11.11 Welder’s control

11.12 Weld Repairs

11.13 Electrode / Welding Consumable certification

11.14 Material map and data packs

12 NDE

12.1 NDE requirements table and NDE control sheet

12.2 Shop and field percentages control

12.3 NDE personnel Qualification / Experience requirements

12.4 Radiographic testing

12.5 Liquid Penetrant Testing (PT)

12.6 Magnetic Particle Testing (MT)

12.7 Ultrasonic Testing (UT) [probes and location of fusion line]

12.8 PMI

12.9 Hardness Testing

12.10 Visual and Dimensional inspection

12.11 Other

12.12 Special Procedures

12.12.1 Pressure Testing (Hydraulic and pneumatic/special Sasol requirements)

12.12.2 Closing welds

12.12.3 Painting & Special Procedures

Page 36 of 63
Copyright © 2023. SASOL. All rights reserved.--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

12.13 Inspection Condition

12.13.1 Dimensional and visual examination

12.13.2 Inspection & measuring equipment

13 QUALITY ASSURANCE REQUIREMENTS

13.1 Manufacturer’s QA/QC personnel and qualifications

13.2 Exemptions

13.3 Non – conformances

13.4 Concessions

13.5 Calibration of Equipment

13.5.1 PWHT Recorders

13.5.2 NDE Equipment

13.5.3 Inspection Measuring Equipment

13.5.4 Pressure Test Gauges

14 INSPECTION NOTIFICATION (SYNFUELS INSPECTION INCLUDED)

15 FINAL INSPECTION INCLUDING FINAL INSPECTION PROCEDURE

16 EQUIPMENT RELEASE

16.1 CC release (Mechanical completion)

16.2 Client (Engineering Contractor) release


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

16.3 AIA release

16.4 Notification to Sasol Projects and Engineering QA

17 END OF JOB DOCUMENTATION

17.1 General

17.2 Include PMM minutes in packs

17.3 Format and time of submittal

Page 37 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

17.4 Number of hard and electronic copies

17.5 Distribution route

18 GENERAL

19 LESSONS LEARNT DURING PREVIOUS PROJECTS – FEEDBACK

20 VIEW OF FACILITIES AND QUALITY SYSTEMS / MANUALS REQUIRED

21 ACTION ITEMS (IF REQUIRED)

22 CLOSE OUT

Page 38 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX B
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

APPENDIX B TYPICAL CERTIFICATE OF DESIGN

EC LETTERHEAD

TYPICAL CERTIFICATE OF DESIGN FOR PIPING

Project Name:

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Project Description:

EC Project Number:

End User:

End User Contract No:

Code of Design and Addenda: ASME B31.3 1999 Edition with Addenda through 2001B

We hereby certify that the design of the Piping identified below have been checked, verified
and approved to be in compliance with the contractual requirements as follows:

• Engineering Design complies with the code of Design, contractual specifications and
applicable Sasol line classes

• The pipe stresses for the piping isometric drawings were reviewed according to the
EC Critical Line List categorization that is based on the criticality of service and the
degree of complexity

• The pipe material specified for the construction of the pipe systems meets contractual
requirements

• Piping design is as defined in the approved redlined isometric drawings found in the
test packs for the pipe systems and applicable Concessions

• All design issues have been addressed and concessions approved where applicable.

Page 39 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX B
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

EC Piping Designer:

Name in print Signature Date

EC Project Engineering Manager:

Name in print Signature Date

EC Project Manager

Name in print Signature Date

Systems Covered by this Declaration:


Complete list to be added in suitable table format

Note: The above template must be customized for application in pipeline projects.

Page 40 of 63
Copyright © 2023. SASOL. All rights reserved. --``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SG-40-05A
Revision 5
May 2023
APPENDIX C
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

APPENDIX C – ADDITIONAL REQUIREMENTS FOR PROJECTS EXECUTED IN


MOZAMBIQUE

All projects executed in Mozambique shall comply in full with the requirements of SP-40-05A
unless amended in Appendix C.

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
All projects executed in Mozambique shall meet the requirements specified in the OHS Act,
PER and Mozambican Decree No. 24/2004.

It is the Duty of the EC to review the Decree to identify all instances where the Decree is
more stringent than the OHS Act and PER and ensure that these requirements are correctly
interpreted and implemented in the design and construction of piping and pipelines in
Mozambique
Table C1 below gives an indication of some of the major differences between the PER and
the Decree requirements for piping and pipelines only. This is by no means a comprehensive
list. It is the duty of the EC to develop a comprehensive project specific list of differences
between the OHS Act, PER and the Mozambican Decree and supply this list to Sasol for
review and approval before commencement of detailed design. MOZAMBIQUE

PER/SANS 347 - RSA MOZAMBICAN DECREE


1 Some of the definitions and terminology used The Decree uses the terms Processing
in the PER differs from those used in the Facility and Operator to imply the same
Decree, for instance, the definition of Pressure meaning.
Equipment or the term User.
2 Duties of various entities are clearly defined All duties/responsibilities to ensure
and sectionalized (example, Duties of compliance are assigned to the
manufacturers, importers, users). Operator.
3 Scope of application and design pressure limit Scope of Decree is applicable to all
is defined (50kPa). Petroleum applications in Mozambique
with no pressure limitations.
4 PER requires categorization in accordance The Decree does not prescribe a system

Page 41 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SG-40-05A
Revision 5
May 2023
APPENDIX C
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

PER/SANS 347 - RSA MOZAMBICAN DECREE


with SANS 347. SANS 347 categorization is of categorization or specific
based on fluid group, pipe diameter and requirements based on fluid group, pipe
pressure (Note 1). Specific requirements are diameter or pressure (Note 1). No EC
prescribed based on categorization, for design approval from a professionally
instance: registered person explicitly prescribed.
• SEP - Equipment categorized as SEP Third Party design verification is
need not be subjected to conformity required. The use of an Inspection
assessment, however, it shall be designed Authority to execute the verification is
in accordance with a Health and Safety not explicitly prescribed.
Standard if an applicable code is
available.
• Cat 1 – The manufacturer shall ensure
that such equipment complies with the
requirements of an applicable Health and
Safety Standard and issue a certificate of
conformity confirming that the equipment
is manufactured in accordance with the
applicable Code of Construction.
• Category II and higher Pressure
Equipment requires EC design approval
by a professionally registered person in
this field.
• Category III and higher Pressure
Equipment also requires design
verification by an AIA.
5 Only Health and Safety Standards from the Requires the application of an
prescribed list included in the PER can be internationally recognized Health and
considered. Safety Standard but the Decree is non-
prescriptive on Standards that can be
considered.

Page 42 of 63
Copyright © 2023. SASOL. All rights reserved. --``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SG-40-05A
Revision 5
May 2023
APPENDIX C
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

PER/SANS 347 - RSA MOZAMBICAN DECREE


6 Requires piping design to allow for in service Mandatory inspection requirements are
inspections in accordance with relevant in- prescribed, for instance, pipelines must
service Health and Safety standard (no specific be pigable.
requirements prescribed as mandatory).
7 Generally, requirements for piping are applied Piping design requirements are covered
to the design and construction of pipelines. No under the “Design of Processing
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

specific requirements for pipelines are Facilities”. General and specific


prescribed. requirements for the design of pipelines
are addressed independently.
8 Third Party Access to Pipeline Systems not Operator of an Oil or Gas pipeline shall
covered in the PER. grant third parties access to transport
petroleum. Terms and conditions of such
arrangements are prescribed.
9 The manufacturer of pressure equipment shall This requirement is not prescribed in the
supply a certificate of manufacture. Decree.
10 Certificate of conformity/compliance is issued This requirement is not prescribed in the
by the AIA in accordance with the Decree.
requirements of SANS 347.

Notes:
The Mozambican Decree is more stringent than the PER since the requirements of the
Decree are applicable to the design and construction of all piping/pipelines used in
Petroleum Operations with no system of hazard categorization being applied.
MOZAMBIQUE

Page 43 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

APPENDIX D – AIA SCOPE OF WORK TEMPLATE

SCOPE OF WORK
FOR APPROVED INSPECTION AUTHORITY
FOR THE SUPERVISION AND CERTIFICATION
OF
PIPING SYSTEM FOR THE
NAME OF THE PROJECT.

All the statements in black form the basis of the scope of work for AIA as per SP 40-05A rev 05.

Things to be added by the responsible engineer are marked in red.

GENERATED: …………………. …………………………


(Name here) Date

DESIGNATION: …..

APPROVED: ……………….. ……………………….


Date

Page 44 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

TABLE OF CONTENTS

1 Introduction ........................................................................................................................ 46
2 Abbreviations ..................................................................................................................... 48
3 Categorization and conformance assessment .................................................................. 49
4 Pre-Manufacturing meeting (PMM) ................................................................................... 49
5 Review of Quality control plan (QCP) and establishment of inspection activities and
inspection points ................................................................................................................ 49
6 Verification and approval of fabrication, inspection and testing documentation or
procedures......................................................................................................................... 50
7 Document control .............................................................................................................. 51
8 Inspection / Supervision .................................................................................................... 52
8.1 Materials ............................................................................................................................ 52
8.2 Welding Surveillance ......................................................................................................... 53
8.3 Witnessing & Surveillance of NDE .................................................................................... 54
8.4 Pressure Testing ............................................................................................................... 54
8.5 Non-Conformances and Concessions ............................................................................... 54
8.6 Review and certification of records.................................................................................... 55
8.7 Acceptance ........................................................................................................................ 56
8.8 As-built Isometrics/drawings .............................................................................................. 56
9 Reporting ........................................................................................................................... 56
10 Language........................................................................................................................... 56
11 Precedence ....................................................................................................................... 57
12 Certification........................................................................................................................ 57
13 Approval/Verification of documents ................................................................................... 58
14 Activity Schedule For lump sum: ....................................................................................... 58
15 Quoting .............................................................................................................................. 60
16 Annexures ......................................................................................................................... 61
1.1 Annexure 1 Flow of Documentation SAMPLE – To be customised ................................. 61
1.2 Annexure 2 Form E-212: Supplier’s Drawing and Data Commitment .............................. 63
1.3 Annexure 3 Piping Packages ........................................................................................... 63

Page 45 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

1. Introduction

This document defines the scope of work for the Approved Inspection Authority (AIA) to
supervise, inspect and certify that the pressurised piping systems for the NAME OF
THE PROJECT to be built on the Sasol Plant, Secunda, was manufactured, fabricated,
assembled, erected, inspected, tested and certified in compliance with the contractual
requirements between the User and the Manufacturer as defined in the purchase
orders.

The piping system shall be designed, fabricated, constructed, inspected, tested and
certified as required by the OHSA. The responsibilities of the Contractor and the AIA
are detailed in Sasol Specification SP-40-05A latest revision.

The AIA scope of supply includes both shop and field inspection activities.

The following are expanded functions of the above that need to be performed by the
AIA:

• Verify that the manufacturer have cognisance of all contract requirements.

• Confirm that the manufacturer is in possession of verified designs and applicable


approved AFC isometrics.

• Confirm that the piping within the scope of this order is categorized and subjected
to the applicable conformance assessments.

• Review the content of the QCP for compliance with contractual requirements.

• Ensure that the EC, CC, and the sub-contractor have acceptable QA/QC systems
that are used as routine to implement the contractual requirements. If not issue
an NCR.

• Verification of fabrication, inspection and testing documentation /procedures.

• Inspection/supervision during fabrication, assembling, erection and testing.

• Witness all pressure tests

• Reporting.

Page 46 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

• Handling of non-conformances

• Review and approval of piping data packages

• Ensure painting or pickling and passivation is performed in accordance with the


approved procedure (where applicable)

• Co-signing the certificate of manufacture

• Issuing the Certification of Compliance.

• Verify that the EC has issued a letter of design verification completeness to certify
the design work is in full compliance with contractual requirements.

Contractual requirements are defined as:

• OHS Act: Pressure Equipment Regulations.

• SANS 347, SANS 10227.

• Code of Construction, i.e.: ASME B31.3, ANSI B16.5, ASME, B16.47 and ASME
B31.1 (whichever is applicable.)

• Licensor piping requirements.


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

• Engineering requirements listed in the RFQ, Data Sheet, Purchase Orders,


Minutes of the Bid Clarification Meetings and Pre-manufacturing Meetings.

• Engineering Bulletins

• SP Specifications, especially SP-50-03A, SP-50-03, SP-50-09 and SP-90-02

• Standard Drawings

The AIA has the responsibility to check if the construction contractor is in possession of
the applicable project contract requirements, revision and latest additions.

Note: Where reference is made to the code, specification or standards, the reference
shall mean the latest edition of the code, specification or standard including addenda,
supplements and revisions thereto as per agreed project contractual requirements
between Sasol and the engineering contractor.

Page 47 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

The AIA shall include an organisational structure detailing the names of the inspectors
that are going to be responsible for completing the project. The listing shall include the
names of recent Sasol projects (the previous year or last two projects) in which the
individuals were involved.

The inspector shall be, as a minimum, a certified Inspector of Pressure Equipment –


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

IPE, with experience in ASME B31.3 or ASME B31.1 and other relevant piping
standards (specify them if they are applicable)

2. Abbreviations

The following abbreviations are used throughout this document:

• AIA Approved Inspection Authority

• AFC Approved For Construction

• CC Construction Contractor

• EC Engineering Contractor

• FOAK First OF A Kind

• IPE Inspector of Pressurised Equipment

• MT Magnetic Particle Testing

• MTP Material Test Plates

• NDE Non-destructive Examinations

• NCR Non-conformance Report

• OHSA Occupational Health and Safety Act of the R.S.A., ACT


no. 85 of 1993 as amended

• PS Piping System

• PT Dye Penetrate Testing

• PTP Production Test Plates

• PWHT Post Weld Heat Treatment

• QA Quality Assurance

Page 48 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

• QC Quality Control

• QCP Quality Control Plan

• RFQ Request for Quotation

• RT Radiographic Testing

• SP Specifications Sasol Specifications

• UT Ultrasonic Testing
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

3. Categorization and Conformance Assessment

Confirm that the piping within the scope of this order is categorized and submitted to
the applicable conformance assessments of SANS 347 in addition to the requirements
of the relevant health and safety standard. Where the User selects a higher category
for piping than determined from the SANS 347 categorization and conformity
assessments, it shall be contractually binding. All rules related to the category selected
by the User shall then apply. Sasol will apply Hazard Category III and Conformity
Assessment Module G for all piping refer to SP-40-05A par 4.3.1.b.

4. Pre-Manufacturing meeting (PMM)

The AIA shall attend a Pre-manufacturing Meeting at the Supplier's works before
commencement of fabrication. It is the responsibility of the managing/engineering
contractor to arrange the date, agenda and notify the parties to be attending the
meeting.

The AIA shall carry out all the responsibilities of this contract as outlined in section 4.5
of SP-40-5A Latest revision and as detailed below.

5. Review of Quality control plan (QCP) and establishment of inspection activities


and inspection points

The AIA Inspector shall, with the Inspector of the User (The User representative),
review the QCP for compliance with contractual requirements. They shall verify the
necessary inspection activities and inspection points for the manufacturer and his

Page 49 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

vendors based on the proposed fabrication sequence and contractual requirements.

The AIA Inspector is responsible for establishing hold points in the QCP and to ensure
all First Of A Kind (FOAK) activities are hold points. An example of FOAK is the first
girth weld of each welder. First of a kind shall not be confused with one of a kind. The
inspector shall satisfy himself that the Fabricator has an acceptable QA/QC system,
which is used as a routine to implement the contractual requirements, particular
attention to be paid to material traceability. The NDE to be witnessed by the AIA shall
also follow the FOAK principles, i.e. the first weld of each welder should be NDE tested
as soon as practical to ensure that potential mistakes are not repeated. The same
principles should be applied to the Visual and Dimensional Inspection regarding, for
instance, root gap, distortion control, branch fillet weld profile, etc.

A hold point shall be established for visual inspection of weld seams that will not be
accessible resulting from subsequent fabrication/installation operations. It shall be
verified that any NDE is only carried out after final grinding of the weld has passed
visual inspection.

A Hold point shall be established for a 100% visual and dimensional inspection before
and after PWHT and before Pressure Testing.

Marked up QCP shall be stamped, signed and dated with the relevant approval status
at the end of each visit.

6. Verification and approval of fabrication, inspection and testing documentation or


procedures

The AIA is responsible to verify and approve by signature and stamping all the required
documentation to ensure they are in compliance with the contractual requirements
between Sasol (or its agent, Sasol Projects and Engineering), the EC and the CC and
any sub-contractors

The AIA shall review and verify, as a minimum, all of the following
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

documentation/procedures for compliance with contractual requirements. When

Page 50 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

satisfied, the AIA shall stamp the documentation and/or procedures with the relevant
approval status.

• Material traceability procedure

• Base and Filler Material Purchasing Specification (unpriced)

• Welding Procedure Qualifications and Specifications

• Welders and Operators qualifications

• NDE procedures and NDE operators qualifications

• PWHT (where applicable)

• Pressure testing procedure(s)

• Leak testing procedure

• “AS BUILT” drawings

• AFC-ISO’s

When satisfied, the AIA shall stamp the documentation/procedures with the relevant
approval status. An approved drawing/procedure shall not approve contractual
deviations. The AIA shall retain copies of verified documentation for a period of at least
six months after commissioning of the pressurised system(s).

The AIA shall monitor the Manufacturer/Constructor quality system in accordance with
the applicable design code. Particular attention shall be given to material identification
and material traceability from first cut of material.

7. Document control

The inspector shall verify that, before the start of welding, the applicable piping
calculations and stress analyses have been made, are available and were approved by
a qualified engineer and stress engineer of the engineering contractor. All required
documentation shall have “B” approval status as a minimum before commencing of
welding.

Page 51 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

8. Inspection / Supervision

The AIA Inspector has the duty of performing all required inspections and such other
inspections, as he considers necessary in order to be satisfied that all contractual
requirements have been met.

The AIA Inspector shall perform inspections at the manufacturer’s and sub-vendor’s
shops at the manufacturer’s country, where welding fabrication is taking place. All
components of a pressurised system shall be checked for conformance with the OHSA,
code of construction, contractual requirements and approved drawings, etc.

During each visit the AIA Inspector shall sign off and date his intervention point on the
QCP. The AIA shall verify that the manufacturer has performed the required inspections
and signed off the QCP progressively for completed work. Non-acknowledgement of
hold points or witness points will result in a non-conformance note issued by the AIA
Inspector to the manufacturer and managing/engineering contractor requesting
immediate resolution. After each inspection, a report detailing his findings will be issued
to the manufacturer and Sasol Projects and Engineering Project Manager, with a copy
placed in the AIA working file. If deviations are encountered, the AIA Inspector must
issue a non-conformance report (NCR) to the Manufacturer, the managing/engineering
contractor and to Sasol Projects and Engineering Project Manager, co-signed by the
manufacturer’s representative acknowledging the receipt of the non-conformance
report.

The following are some of the major inspection activities to be carried out by the AIA
Inspector:

8.1 Materials

The AIA Inspector shall ensure that all materials (base & filler) used during fabrication
are certified to contractual requirements by: 100% identification of materials, correlation
with material test certificates, and verification of material test results to Code and
Specification requirements. The AIA inspector shall also carry out visual inspection of

Page 52 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

all received materials.

The AIA Inspector shall verify on-going traceability by review of manufacturer’s system
and specific checks and witness the transfer of heat numbers of materials. AIA
Inspector shall satisfy himself that the manufacturer’s traceability system is competent
to enable him stamping of all material for pressure piping. Traceability of cast numbers
on all pressure piping components and non-pressure retaining parts welded to the
pressure piping must be maintained at all times. Heat number transfer on materials
and control of material hard stamping are included in the AIA’s scope. The AIA
Inspector shall verify that a traceability procedure is implemented during all construction
phases.

8.2 Welding Surveillance


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

The AIA Inspector shall examine and record on a continuous basis weld preparation
and fit-up of piping systems for shop and field welds in accordance with the code of
construction, specification and approved drawing requirements. When UT is required,
this examination includes the physical measurement of bevel angle, landing, root gap
and alignment of adjacent parts. Root gap shall be recorded for all joints when notch
toughness requirements apply.

The AIA Inspector shall verify that all welding is carried out using qualified and
approved welding procedures and qualified welders/operators.

The AIA Inspector shall visually inspect all welds, and verify the weld surface finish
comply with the contractual requirements. He shall verify that all fillet welds are
complying with the minimum throat thickness requirements.

The AIA Inspector shall verify that control of all welding activities is being maintained
throughout the complete fabrication cycle.

The AIA Inspector shall verify housekeeping, maximum qualified heat input (where and
when applicable), as well as handling and control of welding consumables.

Page 53 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

8.3 Witnessing & Surveillance of NDE

The AIA shall take all necessary steps to verify that the NDE equipment have been
serviced and calibrated. The AIA shall verify that NDE are performed by suitably
qualified personnel, complying with the approved standards, specification, procedures
and drawings.

The AIA Inspector shall evaluate and interpret all RT films and witness UT, MT, PT and
hardness tests in sufficient numbers to assure compliance with the specified
acceptance levels. The Inspector shall also verify that all NDE results are properly
documented and comply with contractual requirements.

8.4 Pressure Testing

The AIA inspector shall make sure that all pressure testing is done according to the
code and specifications and verify the validity of calibration of testing equipment

The AIA Inspector shall witness (Hold point) all pressure testing, and verify procedure
requirements are met, especially metal and water temperature, chloride content,
venting sequence, gauge pressure rating and test calibration date. The Inspector shall
verify that all results have been properly documented and comply with all contractual
requirements, inclusive of the applicable design and contraction code, Sasol
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

specification and other contractual requirements.

The witnessing of pressure testing cannot be waived.

8.5 Non-Conformances and Concessions

The AIA shall monitor the non-conformance system of the fabricator. If necessary, they
shall issue their own NCR.

The AIA shall submit their recommendation for every concession, prior to submission to
Engineering Contractor Project Manager.

Page 54 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

No concessions / deviations from the design / fabrication code/ standards are


acceptable unless an exemption is approved by the Chief Inspector. All requests for
exemptions from the PER shall be made in writing and shall clearly state the extent of
the non-conformance and the reasons for the application. The AIA shall verify and
comment all requests for exemptions before these are submitted to Sasol. All requests
shall be addressed to Sasol for processing and written approval by the Chief Inspector.

Sasol (and its agent, Sasol Projects and Engineering) is accountable for approving all
concessions, substitution and exemptions authorised by the AIA for maintaining and
modifying existing PS in accordance with the systems employed by Sasol.

The AIA shall verify the approved corrective actions have been properly complied with
and are documented.

8.6 Review and certification of records

The AIA shall review and certify the Manufacturer’s Records for compliance with the
contractual requirements, reflecting the physical piping, completeness and legibility.

The AIA shall be accountable for issuing a certificate of compliance for PS


manufactured / fabricated under their surveillance to Sasol. The AIA shall countersign
the certificate of manufacturer issued by the CC. prior to handover to Sasol

• The AIA shall verify that the engineering contractor’s certificate of compliance for
piping systems as required by SP40-5A was issued.

• The AIA shall verify the piping designer’s qualifications in accordance with SANS
347

• The AIA shall verify the completeness of the piping design package and ensure
the following is included as a minimum: (SANS 347)

o The medium, hazard category and conformance module as per SANS 347.

o The health and safety standard(s) used for the design.

o The design and operating conditions.

Page 55 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

o The fabrication, inspection and testing requirements.

o The pipe routing and support information; and

o A stress isometric, when stress analysis is required.

8.7 Acceptance

No pressure piping system shall be considered complete until accepted by both AIA
and Sasol representative. Acceptance of the pressurised system does not relieve the
manufacturer nor the managing/engineering contractor from contractual requirements.

8.8 As-built Isometrics/drawings

The AIA inspector shall stamp and verify that the manufacture’s marked-up isometrics
or fabrication drawings reflect the as-built condition of the piping and is in accordance
with contractual requirements before the inspection release note can be issued.

9. Reporting

The AIA shall issue written reports on the fabrication and inspection progress to the
Manufacturer and Sasol Projects and Engineering Project Manager, in accordance with
the agreed schedule (at least bi-weekly). These written reports must be sent
electronically. The AIA shall also highlight potential slippage on schedule to the Project
Managers of both Sasol Projects and Engineering and the Engineering Contractor in
the same progress report.

The AIA shall immediately advise the Manufacturer and Sasol Projects and Engineering
Project Manager of any non-conformance that requires corrective action considered of
importance, or that requires evaluation by the Manufacturer and/or by Sasol.

10. Language

The contract language is English and this shall be used on all documents related to this
RFQ and any purchase order that may arise from it.

Page 56 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

11. Precedence

The OHSA and the Code of Construction (ASME B31.3,) shall be met at all times. In
case of conflict between HSS, Specifications and Engineering Requirements the
precedence is defined as:

1. Purchase order

2. Engineering Bulletins

3. SP Specifications.

4. Sasol Standard Drawings

In case of conflict, Sasol Projects and Engineering shall be notified immediately for
interpretation. Sasol Projects and Engineering’s interpretation shall be binding.

12. Certification

The Inspector of the AIA shall issue a Certificate of Compliance as per SP-40-05A
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

certifying that:

• The requirements of the specified construction code, as modified and


supplemented by the specifications and engineering requirements, have been
met

• The piping were manufactured under the surveillance of the AIA and conform to
the specified HSS, specifications and approved drawings

• The prescribed pressure tests were witnessed and were successful

• All deviations, exceptions, or modifications of the applicable specification


requirements are clearly noted, described and approved

• All NCR’s and concessions have been closed out.

Copy of the Certificate of Compliance shall be issued to Sasol Projects and


Engineering Project Manager.

Page 57 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

13. Approval/Verification of documents

The maximum turnaround time for documentation is five (5) working days. The AIA
shall provide information of their approval system at the quotation stage.

14. Activity Schedule For lump sum:

The AIA’s Quotation on the piping systems shall be fixed and firm based on the ISOs.
The AIA shall also supply a schedule of rates based on the following activities:

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Page 58 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

Table 1: AIA LIST OF MINIMUM ACTIVITIES TO BE INCLUDED IN THE QUOTATION

Item Incl Activity Required Rate Total


No Manhours

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
1 Kick-off meeting
2 Pre-manufacturing meeting
3 Design verification (4)
4 Review categorization and conformity assessment.
5 Review and approval of QCP and establishment of
inspection activities and inspection points (1) (2)
6 Verification and approval of inspection
documentation and procedure (1) (2)
7 Documentation control before start of welding
8 Inspection/Fabrication supervision (see SP40-5A
par. 4.5.4)
8.1 Materials
8.2 Welding surveillance
8.3 NDE witnessing and surveillance
8.4 Full visual and dimensional inspection before
PWHT (when applicable)
8.5 Inspection of piping before loading for PWHT and
PWHT chart(s) (when applicable)
8.6 Pre pressure test inspection (3)
8.7 Pressure testing
8.8 Non-conformances and concessions
8.9 Review and certification of records (5)
8.10 Acceptance of pressurised system(s)
8.11 As-built isometrics/drawings
8.12 Final inspection and release from shop
Final inspection and release from field
9 Reporting to Sasol Projects and Engineering project
manager and EC’s project manager
10 Issuing certificate of compliance
11 Travel cost Hrs
Km

1. Provision made for initial submission and two re-submissions


2. Turn-around time of 5 working days and 5 working days for consolidation with
Engineering Contractor. Final approval at Manufacturer’s premises
3. Same as before PWHT and when PWHT is not applicable
4. Verify that the design calculations and stress analysis (if applicable) were performed for
each system and verify the piping designer’s qualification in accordance with SANS 347.
5. Verify the completeness of the piping design package as required by SANS 347.

Page 59 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

15. Quoting

FOR THE ABOVE:

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
The AIA Quotation shall also indicate:

• The number of inspectors that will be utilised.

• CVs of inspectors to be potentially involved.

• The number of hours allocated to each inspector for a project.

• Forecast of workload of inspector(s) for the duration of assignment.

NOTE: The responsible Sasol Projects and Engineering engineer to include the
place where fabrication, inspection, testing and installation are to be
done.

Page 60 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

16. Annexures

16.1 Annexure 1 Flow of Documentation SAMPLE – To be customised


--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Page 61 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Page 62 of 63
Copyright © 2023. SASOL. All rights reserved.

Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES

Notes:
1. Confirm the number of copies during the Pre-inspection meeting.

2. The Fabricator should allow for this documentation turn-around in his schedule.

3. “C” Approval Status is considered a critical comment.

4. During the Review and Consolidation phases, the Engineering Contractor and AIA do
not wait for Sasol Projects and Engineering’s comments.

5. The Engineering Contractor does final consolidation.

6. Utilize electronic documentation as far as possible.

16.2 Annexure 2 Form E-212: Supplier’s Drawing and Data Commitment

16.3 Annexure 3 Piping Packages

Page 63 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---

Copyright SASOL