Professional Documents
Culture Documents
SP-40-05A Rev 5 - MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
SP-40-05A Rev 5 - MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
REVISION 5
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
Signed by:Gerhard Visser Signed by:Petrus Jacobus Kies
Signed at:2023-05-22 17:56:35 +02:00 Signed at:2023-05-23 07:42:50 +02:00
Reason:I approve Reason:I approve
Originator : Reviewer :
G VISSER P KIES
Signed by: Andrew Dacre
Signed at:2023-05-22 17:27:05 +02:00
Reason:I approve
Approved by :
AP DACRE
PREVIOUS REVISIONS
ISSUE
REV No PROPOSED BY REVIEWED BY APPROVED BY DATE
DATE
1 Dec 1997 JP Nell P Pereira HJ Bestbier 5 Nov 1997
2 Feb 2002 PJ Kies AP de Gavino C Thirion 24 Feb
Dias 2002
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
VALIDATION This Specification is only regarded as controlled in the electronic format on the official SASOL IHS website.
When printed, this document is deemed as uncontrolled and thus for information only. It is the responsibility of the user of a
printed copy of the document to ensure validity before use. If it is issued for a specific project, it is valid for the duration of the
project, unless agreed otherwise.
COPYRIGHT This Specification is protected by copyright and is the sole property of SASOL. The information is proprietary
to SASOL and is for the sole use of the identified project or defined scope of work. Any unauthorised use, disclosure or copying
or any other means of duplication or reproduction, is prohibited.
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023
Page i of v
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023
REVISION 5
This specification has been revised to address the mandatory requirements for piping and
pipelines as defined in the OHS Act, Pressure Equipment Regulations, SANS 347 and SANS
10227.
The title was changed to “Mandatory Requirements for Piping and Pipelines” to conform to
the terminology of the Pressure Equipment Regulations.
Appendix D: Paragraph 3 Remove: as per Eng Bulletin 0015 and replaced with: refer to
SP-40-5A par 4.3.1. b
Page ii of v
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023
FOREWORD
Each paragraph of the specification is classified as a Core, Site Specific or Negotiable
requirement.
Example:
1.1.1 Paragraph ends. CORE
The definition of each classification, and associated tag, colour code and format are indicated
below:
CORE CORE Red Non-negotiable requirements that are applicable to all Sasol sites
in Southern Africa, and may also be applied to international sites,
having taken into consideration:
• Safety
• World best practice
• Standardization requirements
• Environmental implications
Site Specific RSA Blue Non-negotiable requirements applicable to all South African based
sites, taking into consideration:
(RSA)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Site Specific Secunda Blue Non-negotiable requirements applicable to the Secunda site only,
taking into consideration:
(Secunda)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Site Specific Sasolburg Blue Non-negotiable requirements applicable to the Sasolburg site only,
taking into consideration:
(Sasolburg)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Site Specific Natref Blue Non-negotiable requirements applicable to the Natref site only,
taking into consideration:
(Natref)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Site Specific International Blue Non-negotiable requirements applicable to all non-South African
based sites only, taking into consideration:
(International)
• Legal requirements of the country
• Standardization requirements
• Environmental implications
Negotiable Negotiable Green Requirements that must be agreed by both the project team and
client at an appropriate time. Once agreed, this requirement
becomes mandatory for the specific job.
Guideline (indicated in Black Guidelines and explanatory notes to assist in the understanding of
the rationale behind a specific requirement and application of the
Italics)
specification and concessions.
Page iii of v
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023
TABLE OF CONTENTS
PAGE
1 GENERAL ................................................................................................................ 1
1.1 SCOPE ....................................................................................................... 1
1.2 LEGAL REQUIREMENTS .......................................................................... 1
1.3 ABBREVIATIONS....................................................................................... 2
1.4 DEFINITIONS ............................................................................................. 3
1.5 APPLICABILITY ......................................................................................... 6
1.6 DEVIATIONS .............................................................................................. 7
1.7 CONTRADICTORY OR CONFLICTING REQUIREMENTS ...................... 7
2 REFERENCE DOCUMENTS ................................................................................... 7
2.2 SOUTH AFRICAN LEGISLATION.............................................................. 8
2.3 SOUTH AFRICAN NATIONAL STANDARDS (SANS) ............................... 8
2.4 AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME CODES) 8
2.5 SASOL SPECIFICATIONS......................................................................... 8
2.6 OTHER SASOL DOCUMENTATION ......................................................... 9
3 REQUIREMENTS .................................................................................................... 9
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
4 RESPONSIBILITIES .............................................................................................. 11
4.1 SASOL AS THE OWNER ......................................................................... 11
4.2 SASOL PROJECTS AND ENGINEERING............................................... 12
4.3 ENGINEERING CONTRACTOR .............................................................. 13
4.4 CONSTRUCTION CONTRACTOR .......................................................... 18
4.5 APPROVED INSPECTION AUTHORITY (AIA) ........................................ 22
Page iv of v
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
Revision 5
May 2023
4.6 IMPORTER............................................................................................... 25
Page v of v
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
1 GENERAL
1.1 SCOPE
1.1.1 This Specification is applicable to Secunda and Sasolburg locations in South Africa
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
1.1.2 This Specification covers the duties of the Owner (Sasol), the Engineering
Contractor (EC), the Construction Contractor (CC) and the Approved Inspection
Authority (AIA) for the design, erection, verification, inspection and certification of
piping and pipelines for compliance with the Occupational Health and Safety Act
(OHS Act), and Sasol requirements. RSA
1.1.3 This Specification specifies the requirements for piping and pipelines as defined in
the OHS Act RSA
1.1.4 Appendix C of this specification addresses additional requirements for piping and
pipeline projects executed in Mozambique in accordance with the Republic Of
Mozambique Petroleum Operations Regulations, Decree No. 24/2004, of 20 August.
MOZAMBIQUE
Page 1 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
1.3 ABBREVIATIONS
C Consultation
CC Construction Contractor
CI Chief Inspector
EC Engineering Contractor
H Hold
MC Mechanical Completion
MFD Mechanical Flow Diagrams
OHS Act Occupational Health and Safety Act (Act No. 85 of 1993) of the
Republic of South Africa
P&ID Process and Instrumentation Diagram
QA Quality Assurance
QC Quality Control
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Page 2 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
R Responsibility
REC Records
RFC Ready for Commissioning
S Surveillance
V Verification
1.4 DEFINITIONS
a. Consistent with the set of MFD’s that were approved in the final HAZOP study,
or subsequent official revisions thereof approved by the attendees of the final
HAZOP.
b. Designed and verified in full compliance with the specified HSS, specifications
and contractual requirements.
Page 3 of 63
Copyright © 2023. SASOL. All rights reserved.--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
1.4.5 Certificate of Design -The proposal for the certificate of design shall be submitted to
Projects and Engineering for review and prior written approval but not later than the
start of pipe manufacture by the CC.
b. Piping and pipelines were constructed and tested under the AIA’s supervision.
c. The piping and pipeline material and components conform to the specified
HSS, specifications and contractual requirements. The names of the HSS and
specifications are clearly listed.
h. For piping and pipeline projects executed in Mozambique, that the piping and
pipelines are constructed in full compliance with the Republic Of Mozambique
Petroleum Operations Regulations, Decree No. 24/2004, of 20 August (See
Appendix C).
Note: The CC needs to submit the format they intend to use for the Certificate of
Manufacture to Projects and Engineering for review and approval. The onus rests on
the CC to obtain this approval in writing well in advance.
Page 4 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
1.4.7 TPI Certificate of Compliance - A certificate issued by the appointed AIA certifying
that piping and pipelines were:
b. Constructed and tested under the AIA’s supervision. The specified code(s),
specifications and standards have to be clearly listed on the certificate.
Note: In addition to the above, the TPI Certificate of Compliance shall include full
compliance with the requirements of the Republic Of Mozambique Petroleum
Operations Regulations, Decree No. 24/2004, of 20 August, for projects executed in
Mozambique.
1.4.9 Construction Contractor (CC) - The contractor responsible for the fabrication,
assembly, erection and certification of piping and pipelines.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
1.4.10 Consultation (C)
1.4.11 Engineering Contractor (EC) - A firm, organisation or department who has been
contracted by Sasol to perform the duties of design, purchasing, inspection, testing,
control over construction, certification, punching and commissioning of piping and
pipelines.
Page 5 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
1.4.15 Owner
1.4.16 Pipeline – “means piping or a system of piping designed for the transport and
distribution of any fluid from an installation that is onshore or offshore, starting from
and including the last isolation device located within the confines of the installation,
including all the auxiliary equipment designed specifically for that pipeline” as
defined in the South African Pressure Equipment Regulations.
1.4.17 Piping
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
1.4.19 Records (REC)
1.5 APPLICABILITY
The latest revision of Sasol specifications shall apply to all new and / or to be
modified plants and facilities, on the Sasol Site, unless otherwise specified in writing
by Sasol. CORE
For existing plants and facilities that have not been modified, the specifications
effective as at date of installation shall apply, unless otherwise specified in writing by
Sasol. CORE
Page 6 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
1.6 DEVIATIONS
2 REFERENCE DOCUMENTS
d. Other specific requirements (as indicated per referenced code and standard).
CORE
Page 7 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
SANS 347 Categorisation and conformity assessment criteria for all pressure
equipment
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
2.4 AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME CODES)
Note: The use of additional Health and Safety Standards will require Sasol approval.
Page 8 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
2.6 OTHER SASOL DOCUMENTATION
3 REQUIREMENTS
3.1.1 The Owner (Sasol) will not be allowed to use, require or permit the use of piping and
pipelines unless:
Page 9 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
c. It has been manufactured and installed under the surveillance and supervision
of an AIA where applicable. RSA
3.2.2 The Owner shall ensure that a gas system has a valid certificate issued by an
authorised person. The certificate required is included in the PER and shall be
issued by an authorised person and not by an IPE. RSA
3.3.1 Imported piping with project specific design and construction requirements shall be
conformity assessed in accordance with Module G. Alternative Modules may be
considered for serial produced off the shelf piping items only. RSA
3.4.1 The relevant ASME Code has been selected and approved as the basis for the
design and construction of piping and pipelines. RSA
3.4.2 When an EC proposes Health and Safety Standards other than ASME for the design
and fabrication of piping and pipelines, it shall be subjected to approval by Sasol
and shall be one of the Health and Safety Standards listed in the PER, prior to any
design being done. Approval to use such HSS and the specific requirements and
conditions to be adhered to shall be obtained in writing from Sasol. RSA
Page 10 of 63
Copyright © 2023. SASOL. All rights reserved. --``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
3.4.3 It is not permitted to selectively use design criteria from different HSS unless
approved by the AIA and by Sasol in writing. RSA
3.5 SPECIFICATIONS
3.5.2 Piping designed to HSS other than ASME Codes, shall take cognizance of the
specific requirements in Specifications SP-50-03 and SP-50-03A. The EC shall
obtain written approval from Sasol for any proposed deviation from these
specifications. RSA
3.5.3 For Pipelines applicable requirements from SP-50-03, SP-50-03A, SP-50-09 and
SP-90-02 shall be applied to the design, construction, inspection and hydraulic
testing of pipelines. RSA
3.6.1 Only exemptions that have been submitted by Sasol and approved by the Chief
Inspector shall be allowed. RSA
3.6.2 All other exemptions, i.e. not submitted by Sasol, shall be approved by Sasol before
being used. RSA
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
4 RESPONSIBILITIES
4.1.1 Sasol is accountable for approving all concessions, substitutions, and exemptions
authorised by the AIA for maintaining and modifying existing piping and pipelines in
accordance with the system employed by Sasol. RSA
Page 11 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
4.1.2 The Owner shall be accountable for retaining EOJ documentation and relevant
records pertaining to piping and pipelines. RSA
4.1.3 When Sasol as the Owner performs work without the assistance of Sasol Projects
and Engineering, the accountability of Sasol Projects and Engineering, as per
Paragraph 4.2, will be exercised by Sasol as the Owner. RSA
a. Agree to the proposed flow diagrams and take part in the HAZOP studies.
f. Agree to the commissioning plan and start-up procedures for the system. RSA
4.2.1 Sasol Projects and Engineering (P&E), when acting on behalf of Sasol, shall be
accountable for:
b. HAZOP studies.
e. Model reviews.
Page 12 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
i. All accountabilities of the EC, as per Paragraph 4.3, only when Sasol Projects
and Engineering performs work without the assistance of an EC. RSA
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
e. Review on a random basis, the systems employed by the EC, CC, AIA and
sub-contractors dealing with material traceability, material take-off and control,
material ordering/expediting, material receiving, material identification, material
issue, quality control plan development; approval and implementation, welding
quality control records, NDE procedures and implementation, PWHT
procedures and implementation, pressure test procedures and implementation
thereof.
f. Approval of concessions.
4.3.1 Design
b. Categorising piping and pipelines as required by SANS 347. Compile a line list
with relevant information defined in E0640. All piping and pipelines shall be
Page 13 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
d. Verification and checking of design work. Ensure that the stress engineer has
approved all AFC drawings that require sign off. Issuing the certificate of
design as required in Paragraph 1.4.5
g. Ensuring that copies of documentation are issued in time to the AIA for
verification.
Page 14 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
concessions will be in an agreed space and be open to the AIA for review.
RSA
c. Implement a quality system to ensure that the design work is properly done,
verified and checked for conformance to the requirements mentioned in
4.3.1above prior to marking it as “Approved for Construction”.
d. Implement a system to ensure that all Model Review changes and comments
are included correctly to the full extent.
f. Ensure that the piping/pipeline quality package(s) are in full compliance with
the contractually agreed requirements and are strictly followed by all the sub-
contractors. The piping quality package is defined in Paragraph 4.4.3c.
g. Generate, manage and control a detail plan of execution for the work to be
done by CC.
i. Review the contents of the QCP prepared by the CC to ensure that piping and
pipelines are in full compliance with the HSS, specifications and contractual
requirements and thus conforming to the OSH Act. Establish intervention
points on the QCP to ensure full compliance with HSS, specifications and
contractual requirements. The “First of a Kind” principle shall be used to
ensure that all “First of a Kind” activities are hold points.
Page 15 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
k. Ensuring the use of a quality control plan comprising material control, weld
quality control, traceability, QA records and intervention points.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
fully complied with within the contractually agreed timeframe.
o. Implement a system to gather, verify, check, control and hand-over all the EOJ
documentation as requested in this specification.
a. The EC shall be accountable for managing and controlling all interfaces with
the AIA, appointed by Sasol Projects and Engineering or the EC. When
appointed by the EC, only Sasol approved AIA’s shall be considered and the
AIA Scope of Work shall include all Legal, Code and User requirements as a
minimum (See Appendix D for AIA Scope of Work Template). Sasol Projects
and Engineering QA shall approve the AIA Scope of Work prior to submission
for quotations. The EC is accountable to manage, coordinate and control the
AIA within the contractually agreed HSS, specifications, requirements and
contractually agreed schedule. Any technical difficulties that cannot be
resolved within the contractually agreed HSS, specifications and requirements
between the EC and the AIA shall be referred to Sasol Projects and
Engineering for a final interpretation and/ or decision.
Page 16 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
b. The EC shall be responsible to timeously provide the AIA with two copies of all
relevant technical documents necessary for meaningful verification and
supervision of all piping and pipelines covered by this specification.
The EC is responsible for chairing the PMM following thorough preparation and
population of the agenda with the relevant technical detail, issuing the minutes of
meeting and working off all action items.
The EC shall take the lead and assume primary responsibility for planning the pre-
manufacturing meeting:
a. Arrange the date and technical populated agenda, conducting and issuing the
minutes of the pre-manufacturing meeting prior to fabrication of the piping or
pipelines.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
b. Arrange and ensure that the relevant participants understand that they are all
responsible for the information that needs to be discussed at the pre-
manufacturing meeting. See Appendix A for recommended pre-manufacturing
meeting agenda and minimum content requirements.
• AIA.
d. Prior to the pre-manufacturing meeting, the ECs review shall include, but not
be limited to, material requisition scope, purchase order scope, receiving
Page 17 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
PQR`s including all fabrication and NDE procedures and weld filler
material purchase specifications have been submitted for review and
obtained at least “B” approval status. RSA
4.4.1 For Piping and Pipelines the piping construction contractor is deemed to be the
manufacturer in terms of the PER and therefore accepts the duties and
responsibilities of the manufacturer to ensure compliance to the PER. The definition
of manufacturer in the PER includes construction. The definition of construction in
the PER includes design and materials. Where these are free issued to the
manufacturer, the manufacturer shall accept these and takes full responsibility. RSA
The CC shall have adequate quality control processes in place to ensure that free
issued material meets contractual requirements as part of the handover process.
4.4.2 The Construction Contractor shall be accountable to the Engineering Contractor for:
Page 18 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
iii) Material take-off and control (in case of the CC controlling material take-
off).
iv) Ordering specified material, expediting, receiving, inspection, storing,
issuing, identification and certification (in case of the CC purchasing
material). Ensuring compliance to Code/contractual requirements is an
explicit responsibility of the CC when ordering material.
v) Compiling test packs as detailed in Section 6.
vi) Ensuring that only the latest revisions of approved documents are
always used.
b. Using the latest construction drawings that have been checked and approved
by EC as “Approved for Construction”. Implement a system to ensure that the
latest revisions of AFC-Drawings are always used in fabrication.
i) Drawings
Page 19 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
ii) QCP(s)
iv) Welding documentation (weld map/ISO indicating shop and field welds,
WPS’s and PQR’s)
v) NDE map and all NDE procedures used (RT, UT, MT, PT, PMI,
hardness, dimensional control, etc.)
vii) Forming procedures (where applicable and with wall thinning values)
viii) Painting procedures (where applicable)
d. Developing and utilising a QCP approved by the EC and AIA. The QCP shall
typically include:
i) Detail information showing all activities that will be used during the
fabrication/ manufacturing of piping and pipelines and the associated
quality checks to ensure compliance to design requirements
iv) Sufficient space for the AIA to add their intervention points
Note: The intervention points contemplated for the EC, CC and AIA are
generally as listed in Paragraph 4.5.2d
Page 20 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Note: In the case of “free-issue” material the onus still rest with the CC to
ensure the material they accept complies with contractual
requirements.
g. Ensure that weld surface finish conforms to requirements and that minimum
throat requirements and leg ratios are maintained. (Typically including
supports and anchor chairs).
j. Interpret all NDE and in particular radiographic films prior to presenting them
to the EC and AIA for approval.
k. Carry out punching to ensure that the line has been constructed in accordance
with the scope of work prior to involving the EC and AIA.
m. Ensuring that all material certificates, NDE reports, and other documents
contained in the test packs are correct, legible, valid, witnessed and certified
by the CC/EC and AIA. These shall be traceable to the relevant shop and field
welds. The material certificates shall enable traceability, from the material
certificates to the AFC ISO’s to the physical item installed and vice versa.
Page 21 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
[From the AFC ISO’s to the physical item installed to the material certificate
and from the physical item to the AFC ISO’s to the material certificate]. A table
shall be included showing the traceability as described herewith. The table
shall at least address the following details: Approved MFD number, AFC-ISO
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
number, Heat number or unique number hard stamped on the physical item,
Sasol item code to SP-50-03A, material description (pipe, valve, etc.) and
material certificate number.
n. Compiling the test packs for all the process systems, comprising as a
minimum of the items specified in Section 6.
4.5.1 The AIA shall be accountable for the issue of a TPI certificate of compliance for
piping and pipelines manufactured/ fabricated under their supervision to Sasol. The
format to be used shall be submitted to Sasol Projects and Engineering for review
and prior approval.
The TPI certificate of compliance from the AIA is a separate document to the
certificate of manufacture issued by the CC which needs to be countersigned by the
AIA.
The AIA shall use IPE qualified inspectors with piping code experience for all
aspects of their supervisory role and to issue the certificate of compliance. RSA
a. Ensure that the EC, CC and sub-contractors have acceptable QA/QC systems
that are used as a routine to implement the contractual requirements.
Page 22 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
Sasol (or its agent, Sasol Projects and Engineering), the EC and the CC and
any sub-contractors. The following documents shall be verified as a minimum:
c. Review the contents of the QCP prepared by the CC to ensure that piping and
pipelines are in full compliance with the HSS, specifications and contractual
requirements and thus conforming to the OSH Act.
Establish intervention points on the QCP to ensure full compliance with HSS,
specifications and contractual requirements.
The “First of a Kind” principle shall be used to ensure that all “First of a Kind”
activities are hold points.
d. Perform, at the CC’s and his sub-contractor’s shop and the job-site all required
verification inspections continuously in order to be satisfied that OSH Act
requirements are adhered to. The results of such inspections shall be
documented: Either by signing the QCP; issuing an inspection report or NCR
to the CC, EC and Sasol with a copy in the file of the AIA. The inspection
shall, as a minimum include the following:
Page 23 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
vi) Weld surface finish conforms to requirements and that minimum throat
requirements and leg ratios are maintained (typically including supports
and anchor chairs);
vii) PWHT shall be witnessed and approved to indicate conformance to the
approved procedure (location and number of thermocouples, thickness
and extent of insulation). The PWHT charts shall be approved indicating
that the heating rate / holding time / temperature and cooling rate are as
per the approved procedure per line number.
viii) Dimensional inspection;
ix) NDE procedures are approved and QC personnel are qualified;
xii) Witness that all pressure testing is performed to HSS, specification and
approved procedures, using only valid calibrated testing equipment and
pressure testing water which complies with the contractual requirements
(the witnessing of pressure testing cannot be waived);
xiii) Accept by stamping and signing on the pressure test certificate that
piping and pipelines were pressure tested successfully in compliance
with contractual requirements;
f. Ensure that NCR’s and concessions have been closed out and accepted by
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Page 24 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
4.6 IMPORTER
4.6.1 RESPONSIBILITIES
The importer is required to fulfil all the duties stipulated in the PER and SANS 347
to ensure that all imported equipment is in full compliance with the OHSA. NOTE:
The importer shall verify that the foreign inspection bodies meet the requirements of
PER with respect to ISO 17020 accreditation and scope of accreditation together
with the applicable HSS. RSA
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
4.6.2 DOCUMENTATION
• For SANS 347 category II and higher ensure that section C of Sasol
Form F980 is verified and signed by the Importer’s AIA.
c. Ensure that the completed Sasol Form F980 has been included into the
Manufacturer’s code data book. RSA
5.1 Sasol Projects and Engineering will audit the design of piping and pipelines and the
systems employed by the EC to ensure proper verification of the design work is
done. RSA
Page 25 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
5.2 Sasol Projects and Engineering will audit or perform surveillance of the AIA and CC
as required. RSA
5.3 Sasol Projects and Engineering will perform surveillance to verify that the design of
piping and pipelines is done in strict accordance with the contractual requirements.
RSA
5.4 Supervision by the AIA shall ensure that piping and pipelines have been fabricated,
assembled, inspected and tested in accordance with the relevant HSS,
specifications and all contractual requirements, thus in full compliance with the OHS
Act. RSA
6.1 INTRODUCTION
All documentation generated during the design and manufacturing of piping and
pipelines must be traceable to a master document. RSA
The master document is defined as the revision of the MFD’s that were approved in
the final formal HAZOP study, or subsequent official revision thereof. The master
document must be completely detailed by the isometric drawings that are generated
during the design phase. Isometric drawings must be consistent with the master
document. The master document shall form part of the EOJ documentation. RSA
The master document shall be divided into process systems; each divided into a
number of test packs. The test packs, and a summary of test pack numbers, shall
be included in the EOJ documentation, per process system, showing where the
specific test pack fits in on the master document acting as a checklist that the
Page 26 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
complete master document is covered. The minimum content of a test pack for
piping and pipelines are: RSA
Each test pack includes a summary sheet providing the line and sheet numbers that
are covered in the test pack.
The relevant marked up portion of the master MFD is also included in the test pack.
RSA
AFC ISOs containing the BOMs shall be included. These AFC ISO’s shall be used
during formal checkouts and punch-outs. The AFC ISO’s shall detail the complete
master document for the specific test pack boundaries.
The AFC ISOs and BOMs shall define the following detail for each and every item
on the ISO:
a. Material specification
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
c. Item code according to the Sasol specification item codes listed in SP-50-3A
AFC Alignment Sheets when issued for pipeline projects shall be included.
Alignment sheets shall be used in conjunction with ISO’s during formal checkouts
and punch-outs. RSA
The material certificate of each component used, thus shown on the AFC ISOs shall
be included in the EOJ packages. A system should be in place to ensure traceability
from the installed piping, via the AFC ISOs, to the actual material certificates. RSA
Page 27 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
The calibration certificates of all pressure gauges that were used to perform the
pressure testing (hydrostatic or pneumatic) as prescribed in the OHS Act must be
traceable to a National Standard and performed by an Accredited Laboratory. RSA
The hydrostatic or pneumatic pressure test record, approved by the IPE inspector of
the appointed AIA, certifying that the system, as detailed in the AFC ISO’s of the test
pack, are completely tested in accordance with OHS Act and the project
requirements and that the system withstood the pressure as specified. RSA
6.3.7 Weld Map, Welding Procedure Specifications (WPS) and Procedure Qualification
Records (PQR)
a. The weld map shall be indicated on the AFC-ISO by numbering either, each
weld, shop and field, or each item installed in a unique, sequential manner
supporting the traceability system employed.
b. The installed items shall have the heat number or unique number hard
stamped or etched (as per approved procedure) on each and every item
forming part of piping and pipelines in the test pack.
The summary table shall therefore address the following points: Weld number
(or item number), heat numbers (or unique numbers) of items connected by
welding, description of items, welders ID, WPS number, PQR number, NDE’s
performed and reference to the NDE reports.
d. For cold service only, the welder’s certificate shall also be included as well as
proof of impact testing of weld consumables used in production. RSA
Page 28 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
6.3.8 NCR’s, Concessions (including material substitutions), Waivers and Hot Taps
All NCR’s, concessions (including material substitutions), waivers and hot tap
approval forms shall be included in the test pack. The NCR’s, concessions and
waivers shall be signed by the AIA-IPE inspector, confirming that they were
completely implemented. RSA
Note: Only one certificate of compliance, issued by the AIA is required for the
work done on the master document under their surveillance. RSA
Each test pack shall have signed off punch lists (pre-hydrostatic test and post
hydrostatic test), as proof that all outstanding work has been completed. Standard
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
checkout documentation shall be used as detailed in the Sasol Projects and
Engineering Commissioning Manual. RSA
Any dimensional change shall be investigated to assess the need for re-analysis of
stresses, e.g. high temperature or high-pressure systems or large diameter piping.
Page 29 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
b. Additional welds:
The master document, summary sheet of test pack numbers, line numbers summary
sheet, AFC Drawings, BOM’s, WPS’s, PQR’s, summary table allowing traceability
as defined in Paragraph 6.3.7c shall be supplied in electronic format.
The numbering shall be unique and shall allow proper traceability. The AIA shall
certify by stamping and signature that this specification was used strictly throughout
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
the project to number welds and/or items uniquely. RSA
The material certificates, pressure test calibration certificates, pressure test record,
NCR’s concessions, waivers, hot tap approval forms, NDE results, certificate of
manufacture, certificate of compliance and signed off punch list must be scanned,
and handed over in electronic format. RSA
The weld maps shall be hand marked on the AFC-ISO. One paper copy of the hand
marked-up AFC-ISO shall be included in the single paper copy of the EOJ
Page 30 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
The EOJ documentation shall hence only consist of one or more CD’s, with one
paper version of the EOJ documentation to be handed to Sasol Projects and
Engineering. RSA
The EOJ documentation shall be delivered prior to signing the Ready for
Commissioning (RFC) approval. Category 2 and 3 punch list items that are done
after RFC shall have the resulting close out documentation delivered not later than 2
weeks after RFO has been signed, unless otherwise contractually agreed. RSA
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Page 31 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
3 SCOPE OF WORK
5 RESPONSIBLE PERSONNEL
5.1.2 Inspector
Page 32 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
b. Inspector (IPE)
a. Welding Consumables
Page 33 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
g. Others
6 CONTRACT
7 DOCUMENTATION
7.1 Master drawing/document index – List all documents to be submitted for review and
approval as agreed in contract.
7.1.1 ISO`s
8 DESIGN CRITERIA
Page 34 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
8.1 HSS
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
9 FABRICATION SEQUENCE
9.1 Workshop
9.2 Field
9.3 Others
10 MATERIAL REQUIREMENTS
10.5 Other
Page 35 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
12 NDE
12.8 PMI
12.11 Other
Page 36 of 63
Copyright © 2023. SASOL. All rights reserved.--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
13.2 Exemptions
13.4 Concessions
16 EQUIPMENT RELEASE
17.1 General
Page 37 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX A
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
18 GENERAL
22 CLOSE OUT
Page 38 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX B
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
EC LETTERHEAD
Project Name:
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Project Description:
EC Project Number:
End User:
Code of Design and Addenda: ASME B31.3 1999 Edition with Addenda through 2001B
We hereby certify that the design of the Piping identified below have been checked, verified
and approved to be in compliance with the contractual requirements as follows:
• Engineering Design complies with the code of Design, contractual specifications and
applicable Sasol line classes
• The pipe stresses for the piping isometric drawings were reviewed according to the
EC Critical Line List categorization that is based on the criticality of service and the
degree of complexity
• The pipe material specified for the construction of the pipe systems meets contractual
requirements
• Piping design is as defined in the approved redlined isometric drawings found in the
test packs for the pipe systems and applicable Concessions
• All design issues have been addressed and concessions approved where applicable.
Page 39 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX B
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
EC Piping Designer:
EC Project Manager
Note: The above template must be customized for application in pipeline projects.
Page 40 of 63
Copyright © 2023. SASOL. All rights reserved. --``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SG-40-05A
Revision 5
May 2023
APPENDIX C
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
All projects executed in Mozambique shall comply in full with the requirements of SP-40-05A
unless amended in Appendix C.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
All projects executed in Mozambique shall meet the requirements specified in the OHS Act,
PER and Mozambican Decree No. 24/2004.
It is the Duty of the EC to review the Decree to identify all instances where the Decree is
more stringent than the OHS Act and PER and ensure that these requirements are correctly
interpreted and implemented in the design and construction of piping and pipelines in
Mozambique
Table C1 below gives an indication of some of the major differences between the PER and
the Decree requirements for piping and pipelines only. This is by no means a comprehensive
list. It is the duty of the EC to develop a comprehensive project specific list of differences
between the OHS Act, PER and the Mozambican Decree and supply this list to Sasol for
review and approval before commencement of detailed design. MOZAMBIQUE
Page 41 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SG-40-05A
Revision 5
May 2023
APPENDIX C
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
Page 42 of 63
Copyright © 2023. SASOL. All rights reserved. --``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SG-40-05A
Revision 5
May 2023
APPENDIX C
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
Notes:
The Mozambican Decree is more stringent than the PER since the requirements of the
Decree are applicable to the design and construction of all piping/pipelines used in
Petroleum Operations with no system of hazard categorization being applied.
MOZAMBIQUE
Page 43 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
SCOPE OF WORK
FOR APPROVED INSPECTION AUTHORITY
FOR THE SUPERVISION AND CERTIFICATION
OF
PIPING SYSTEM FOR THE
NAME OF THE PROJECT.
All the statements in black form the basis of the scope of work for AIA as per SP 40-05A rev 05.
DESIGNATION: …..
Page 44 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
TABLE OF CONTENTS
1 Introduction ........................................................................................................................ 46
2 Abbreviations ..................................................................................................................... 48
3 Categorization and conformance assessment .................................................................. 49
4 Pre-Manufacturing meeting (PMM) ................................................................................... 49
5 Review of Quality control plan (QCP) and establishment of inspection activities and
inspection points ................................................................................................................ 49
6 Verification and approval of fabrication, inspection and testing documentation or
procedures......................................................................................................................... 50
7 Document control .............................................................................................................. 51
8 Inspection / Supervision .................................................................................................... 52
8.1 Materials ............................................................................................................................ 52
8.2 Welding Surveillance ......................................................................................................... 53
8.3 Witnessing & Surveillance of NDE .................................................................................... 54
8.4 Pressure Testing ............................................................................................................... 54
8.5 Non-Conformances and Concessions ............................................................................... 54
8.6 Review and certification of records.................................................................................... 55
8.7 Acceptance ........................................................................................................................ 56
8.8 As-built Isometrics/drawings .............................................................................................. 56
9 Reporting ........................................................................................................................... 56
10 Language........................................................................................................................... 56
11 Precedence ....................................................................................................................... 57
12 Certification........................................................................................................................ 57
13 Approval/Verification of documents ................................................................................... 58
14 Activity Schedule For lump sum: ....................................................................................... 58
15 Quoting .............................................................................................................................. 60
16 Annexures ......................................................................................................................... 61
1.1 Annexure 1 Flow of Documentation SAMPLE – To be customised ................................. 61
1.2 Annexure 2 Form E-212: Supplier’s Drawing and Data Commitment .............................. 63
1.3 Annexure 3 Piping Packages ........................................................................................... 63
Page 45 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
1. Introduction
This document defines the scope of work for the Approved Inspection Authority (AIA) to
supervise, inspect and certify that the pressurised piping systems for the NAME OF
THE PROJECT to be built on the Sasol Plant, Secunda, was manufactured, fabricated,
assembled, erected, inspected, tested and certified in compliance with the contractual
requirements between the User and the Manufacturer as defined in the purchase
orders.
The piping system shall be designed, fabricated, constructed, inspected, tested and
certified as required by the OHSA. The responsibilities of the Contractor and the AIA
are detailed in Sasol Specification SP-40-05A latest revision.
The AIA scope of supply includes both shop and field inspection activities.
The following are expanded functions of the above that need to be performed by the
AIA:
• Confirm that the piping within the scope of this order is categorized and subjected
to the applicable conformance assessments.
• Review the content of the QCP for compliance with contractual requirements.
• Ensure that the EC, CC, and the sub-contractor have acceptable QA/QC systems
that are used as routine to implement the contractual requirements. If not issue
an NCR.
• Reporting.
Page 46 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
• Handling of non-conformances
• Verify that the EC has issued a letter of design verification completeness to certify
the design work is in full compliance with contractual requirements.
• Code of Construction, i.e.: ASME B31.3, ANSI B16.5, ASME, B16.47 and ASME
B31.1 (whichever is applicable.)
• Engineering Bulletins
• Standard Drawings
The AIA has the responsibility to check if the construction contractor is in possession of
the applicable project contract requirements, revision and latest additions.
Note: Where reference is made to the code, specification or standards, the reference
shall mean the latest edition of the code, specification or standard including addenda,
supplements and revisions thereto as per agreed project contractual requirements
between Sasol and the engineering contractor.
Page 47 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
The AIA shall include an organisational structure detailing the names of the inspectors
that are going to be responsible for completing the project. The listing shall include the
names of recent Sasol projects (the previous year or last two projects) in which the
individuals were involved.
IPE, with experience in ASME B31.3 or ASME B31.1 and other relevant piping
standards (specify them if they are applicable)
2. Abbreviations
• CC Construction Contractor
• EC Engineering Contractor
• PS Piping System
• QA Quality Assurance
Page 48 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
• QC Quality Control
• RT Radiographic Testing
• UT Ultrasonic Testing
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Confirm that the piping within the scope of this order is categorized and submitted to
the applicable conformance assessments of SANS 347 in addition to the requirements
of the relevant health and safety standard. Where the User selects a higher category
for piping than determined from the SANS 347 categorization and conformity
assessments, it shall be contractually binding. All rules related to the category selected
by the User shall then apply. Sasol will apply Hazard Category III and Conformity
Assessment Module G for all piping refer to SP-40-05A par 4.3.1.b.
The AIA shall attend a Pre-manufacturing Meeting at the Supplier's works before
commencement of fabrication. It is the responsibility of the managing/engineering
contractor to arrange the date, agenda and notify the parties to be attending the
meeting.
The AIA shall carry out all the responsibilities of this contract as outlined in section 4.5
of SP-40-5A Latest revision and as detailed below.
The AIA Inspector shall, with the Inspector of the User (The User representative),
review the QCP for compliance with contractual requirements. They shall verify the
necessary inspection activities and inspection points for the manufacturer and his
Page 49 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
The AIA Inspector is responsible for establishing hold points in the QCP and to ensure
all First Of A Kind (FOAK) activities are hold points. An example of FOAK is the first
girth weld of each welder. First of a kind shall not be confused with one of a kind. The
inspector shall satisfy himself that the Fabricator has an acceptable QA/QC system,
which is used as a routine to implement the contractual requirements, particular
attention to be paid to material traceability. The NDE to be witnessed by the AIA shall
also follow the FOAK principles, i.e. the first weld of each welder should be NDE tested
as soon as practical to ensure that potential mistakes are not repeated. The same
principles should be applied to the Visual and Dimensional Inspection regarding, for
instance, root gap, distortion control, branch fillet weld profile, etc.
A hold point shall be established for visual inspection of weld seams that will not be
accessible resulting from subsequent fabrication/installation operations. It shall be
verified that any NDE is only carried out after final grinding of the weld has passed
visual inspection.
A Hold point shall be established for a 100% visual and dimensional inspection before
and after PWHT and before Pressure Testing.
Marked up QCP shall be stamped, signed and dated with the relevant approval status
at the end of each visit.
The AIA is responsible to verify and approve by signature and stamping all the required
documentation to ensure they are in compliance with the contractual requirements
between Sasol (or its agent, Sasol Projects and Engineering), the EC and the CC and
any sub-contractors
The AIA shall review and verify, as a minimum, all of the following
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Page 50 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
satisfied, the AIA shall stamp the documentation and/or procedures with the relevant
approval status.
• AFC-ISO’s
When satisfied, the AIA shall stamp the documentation/procedures with the relevant
approval status. An approved drawing/procedure shall not approve contractual
deviations. The AIA shall retain copies of verified documentation for a period of at least
six months after commissioning of the pressurised system(s).
The AIA shall monitor the Manufacturer/Constructor quality system in accordance with
the applicable design code. Particular attention shall be given to material identification
and material traceability from first cut of material.
7. Document control
The inspector shall verify that, before the start of welding, the applicable piping
calculations and stress analyses have been made, are available and were approved by
a qualified engineer and stress engineer of the engineering contractor. All required
documentation shall have “B” approval status as a minimum before commencing of
welding.
Page 51 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
8. Inspection / Supervision
The AIA Inspector has the duty of performing all required inspections and such other
inspections, as he considers necessary in order to be satisfied that all contractual
requirements have been met.
The AIA Inspector shall perform inspections at the manufacturer’s and sub-vendor’s
shops at the manufacturer’s country, where welding fabrication is taking place. All
components of a pressurised system shall be checked for conformance with the OHSA,
code of construction, contractual requirements and approved drawings, etc.
During each visit the AIA Inspector shall sign off and date his intervention point on the
QCP. The AIA shall verify that the manufacturer has performed the required inspections
and signed off the QCP progressively for completed work. Non-acknowledgement of
hold points or witness points will result in a non-conformance note issued by the AIA
Inspector to the manufacturer and managing/engineering contractor requesting
immediate resolution. After each inspection, a report detailing his findings will be issued
to the manufacturer and Sasol Projects and Engineering Project Manager, with a copy
placed in the AIA working file. If deviations are encountered, the AIA Inspector must
issue a non-conformance report (NCR) to the Manufacturer, the managing/engineering
contractor and to Sasol Projects and Engineering Project Manager, co-signed by the
manufacturer’s representative acknowledging the receipt of the non-conformance
report.
The following are some of the major inspection activities to be carried out by the AIA
Inspector:
8.1 Materials
The AIA Inspector shall ensure that all materials (base & filler) used during fabrication
are certified to contractual requirements by: 100% identification of materials, correlation
with material test certificates, and verification of material test results to Code and
Specification requirements. The AIA inspector shall also carry out visual inspection of
Page 52 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
The AIA Inspector shall verify on-going traceability by review of manufacturer’s system
and specific checks and witness the transfer of heat numbers of materials. AIA
Inspector shall satisfy himself that the manufacturer’s traceability system is competent
to enable him stamping of all material for pressure piping. Traceability of cast numbers
on all pressure piping components and non-pressure retaining parts welded to the
pressure piping must be maintained at all times. Heat number transfer on materials
and control of material hard stamping are included in the AIA’s scope. The AIA
Inspector shall verify that a traceability procedure is implemented during all construction
phases.
The AIA Inspector shall examine and record on a continuous basis weld preparation
and fit-up of piping systems for shop and field welds in accordance with the code of
construction, specification and approved drawing requirements. When UT is required,
this examination includes the physical measurement of bevel angle, landing, root gap
and alignment of adjacent parts. Root gap shall be recorded for all joints when notch
toughness requirements apply.
The AIA Inspector shall verify that all welding is carried out using qualified and
approved welding procedures and qualified welders/operators.
The AIA Inspector shall visually inspect all welds, and verify the weld surface finish
comply with the contractual requirements. He shall verify that all fillet welds are
complying with the minimum throat thickness requirements.
The AIA Inspector shall verify that control of all welding activities is being maintained
throughout the complete fabrication cycle.
The AIA Inspector shall verify housekeeping, maximum qualified heat input (where and
when applicable), as well as handling and control of welding consumables.
Page 53 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
The AIA shall take all necessary steps to verify that the NDE equipment have been
serviced and calibrated. The AIA shall verify that NDE are performed by suitably
qualified personnel, complying with the approved standards, specification, procedures
and drawings.
The AIA Inspector shall evaluate and interpret all RT films and witness UT, MT, PT and
hardness tests in sufficient numbers to assure compliance with the specified
acceptance levels. The Inspector shall also verify that all NDE results are properly
documented and comply with contractual requirements.
The AIA inspector shall make sure that all pressure testing is done according to the
code and specifications and verify the validity of calibration of testing equipment
The AIA Inspector shall witness (Hold point) all pressure testing, and verify procedure
requirements are met, especially metal and water temperature, chloride content,
venting sequence, gauge pressure rating and test calibration date. The Inspector shall
verify that all results have been properly documented and comply with all contractual
requirements, inclusive of the applicable design and contraction code, Sasol
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
The AIA shall monitor the non-conformance system of the fabricator. If necessary, they
shall issue their own NCR.
The AIA shall submit their recommendation for every concession, prior to submission to
Engineering Contractor Project Manager.
Page 54 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
Sasol (and its agent, Sasol Projects and Engineering) is accountable for approving all
concessions, substitution and exemptions authorised by the AIA for maintaining and
modifying existing PS in accordance with the systems employed by Sasol.
The AIA shall verify the approved corrective actions have been properly complied with
and are documented.
The AIA shall review and certify the Manufacturer’s Records for compliance with the
contractual requirements, reflecting the physical piping, completeness and legibility.
• The AIA shall verify that the engineering contractor’s certificate of compliance for
piping systems as required by SP40-5A was issued.
• The AIA shall verify the piping designer’s qualifications in accordance with SANS
347
• The AIA shall verify the completeness of the piping design package and ensure
the following is included as a minimum: (SANS 347)
o The medium, hazard category and conformance module as per SANS 347.
Page 55 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
8.7 Acceptance
No pressure piping system shall be considered complete until accepted by both AIA
and Sasol representative. Acceptance of the pressurised system does not relieve the
manufacturer nor the managing/engineering contractor from contractual requirements.
The AIA inspector shall stamp and verify that the manufacture’s marked-up isometrics
or fabrication drawings reflect the as-built condition of the piping and is in accordance
with contractual requirements before the inspection release note can be issued.
9. Reporting
The AIA shall issue written reports on the fabrication and inspection progress to the
Manufacturer and Sasol Projects and Engineering Project Manager, in accordance with
the agreed schedule (at least bi-weekly). These written reports must be sent
electronically. The AIA shall also highlight potential slippage on schedule to the Project
Managers of both Sasol Projects and Engineering and the Engineering Contractor in
the same progress report.
The AIA shall immediately advise the Manufacturer and Sasol Projects and Engineering
Project Manager of any non-conformance that requires corrective action considered of
importance, or that requires evaluation by the Manufacturer and/or by Sasol.
10. Language
The contract language is English and this shall be used on all documents related to this
RFQ and any purchase order that may arise from it.
Page 56 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
11. Precedence
The OHSA and the Code of Construction (ASME B31.3,) shall be met at all times. In
case of conflict between HSS, Specifications and Engineering Requirements the
precedence is defined as:
1. Purchase order
2. Engineering Bulletins
3. SP Specifications.
In case of conflict, Sasol Projects and Engineering shall be notified immediately for
interpretation. Sasol Projects and Engineering’s interpretation shall be binding.
12. Certification
The Inspector of the AIA shall issue a Certificate of Compliance as per SP-40-05A
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
certifying that:
• The piping were manufactured under the surveillance of the AIA and conform to
the specified HSS, specifications and approved drawings
Page 57 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
The maximum turnaround time for documentation is five (5) working days. The AIA
shall provide information of their approval system at the quotation stage.
The AIA’s Quotation on the piping systems shall be fixed and firm based on the ISOs.
The AIA shall also supply a schedule of rates based on the following activities:
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Page 58 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
1 Kick-off meeting
2 Pre-manufacturing meeting
3 Design verification (4)
4 Review categorization and conformity assessment.
5 Review and approval of QCP and establishment of
inspection activities and inspection points (1) (2)
6 Verification and approval of inspection
documentation and procedure (1) (2)
7 Documentation control before start of welding
8 Inspection/Fabrication supervision (see SP40-5A
par. 4.5.4)
8.1 Materials
8.2 Welding surveillance
8.3 NDE witnessing and surveillance
8.4 Full visual and dimensional inspection before
PWHT (when applicable)
8.5 Inspection of piping before loading for PWHT and
PWHT chart(s) (when applicable)
8.6 Pre pressure test inspection (3)
8.7 Pressure testing
8.8 Non-conformances and concessions
8.9 Review and certification of records (5)
8.10 Acceptance of pressurised system(s)
8.11 As-built isometrics/drawings
8.12 Final inspection and release from shop
Final inspection and release from field
9 Reporting to Sasol Projects and Engineering project
manager and EC’s project manager
10 Issuing certificate of compliance
11 Travel cost Hrs
Km
Page 59 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
15. Quoting
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
The AIA Quotation shall also indicate:
NOTE: The responsible Sasol Projects and Engineering engineer to include the
place where fabrication, inspection, testing and installation are to be
done.
Page 60 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
16. Annexures
Page 61 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Page 62 of 63
Copyright © 2023. SASOL. All rights reserved.
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT
SP-40-05A
Revision 5
May 2023
APPENDIX D
MANDATORY REQUIREMENTS FOR PIPING AND PIPELINES
Notes:
1. Confirm the number of copies during the Pre-inspection meeting.
2. The Fabricator should allow for this documentation turn-around in his schedule.
4. During the Review and Consolidation phases, the Engineering Contractor and AIA do
not wait for Sasol Projects and Engineering’s comments.
Page 63 of 63
Copyright © 2023. SASOL. All rights reserved.
--``,,`,``,,,,,````,,`````,`````-`-`,,`,,`,`,,`---
Copyright SASOL
Provided by Accuris under license with SASOL - Uncontrolled Copy Licensee=Sasol Supplier Account - PM Approval Required/5906396008, User=Albino,
No reproduction or networking permitted without license from Accuris Not for Resale, 10/09/2023 05:57:50 MDT