SCHEDULE STEEL WORK PAINT SHOP EXTENSION

ID Task Name Duration JulyStart Predecessors August September


11-07 18-07 25-07 01-08 08-08 15-08 22-08 29-08 05-09 12-09
1 SCHEDULE STEEL WORK HMMI PAINT SHOP 33 days Wed SCHEDULE STEEL WORK HMMI PAINT SHOP
21-07-21 21-07 02-09
33 days
2 SHOP DRAWING 14 days Wed SHOP DRAWING
21-07-21 21-07 07-08
14 days
3 MATERIAL INCOMING 14 days Mon 2FS-12 days MATERIAL INCOMING
26-07-21 26-07 11-08
14 days
4 FABRICATION 20 days Tue 3FS-20 days FABRICATION
27-07-21 27-07 20-08
20 days
5 MATERIAL ON SITE 15 days Fri 06-08-21 4FS-25 days MATERIAL ON SITE
06-08 25-08
15 days
6 ERECTION 20 days Sat 07-08-21 5SS+1 day ERECTION
07-08 02-09
20 days

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE PAINTSHOP Split Inactive Task Duration-only Finish-only Progress


Date: Wed 21-07-21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone