Method Statement - MSE Wall Sequences - Rev01

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 14

1 26 May WIKA Y.

Kondo Sequence step revision

0 25 May WIKA Y. Kondo First Issue

Rev. Rev. Date Created by Checked by Approved by Description

LUMUT BALAI GEOTHERMAL FCRS AND

POWER PLANT PROJECT

CONTRACT NO:

TITLE:

METHOD STATEMENT OF MSE WALL WORK SEQUENCES

DRAWING / DOCUMENT. No. WIKA-LMB-ENG-IK-MSES-22 REV: 01

CONTRACTOR:

Responsible Dept. Created by Checked by Approved by Format:

WIKA Y. Kondo A4 size

Issue. Type : For Approval For Information Other

Doc. Status: Approved Approved Excepted as Noted


Returned for Correction and Re-submission

Total 12 Page (including this Dwg/Doc. No. WIKA-LMB-ENG-IK-MSES-22 Rev. 01


cover Sheet)
2
TABLE OF CONTENT

1. Introduction..............................................................................................................3
2. Scope of works........................................................................................................3
3. Materials..................................................................................................................3
4. Schedule..................................................................................................................3
5. Construction equipment...........................................................................................5
6. Manpower................................................................................................................5
7. Method of works......................................................................................................5
7.1. Embankment step 1..........................................................................................6
7.2. Embankment step 2..........................................................................................6
7.3. Embankment step 3..........................................................................................8
7.4. Embankment step 4........................................................................................10
8. Drainage shifting plan............................................................................................10
8.1. Drainage shifting.............................................................................................11
9. Backfill and sloping plan area section C & G.........................................................11
10. Health, Safety & Environment...............................................................................12

3
METHOD STATEMENT OF MSE WALL SEQUENCES

CIVIL WORKS GEOTHERMAL FCRS & POWER PLANT PROJECT

1. Introduction
This method statement will explain about the MSE wall work sequences, especially to
prioritize the MSE wall of section B. The purpose of this method is to catch up the
progress of the MSE wall section B, C, F, and G that later will be used for lay down area
and heavy equipment placing when installing the CCB steel structures and transformer
equipment.

2. Scope of works
Scope of works on this method are as follow:
- MSE wall embankment section B to the bottom level of section C.
- Scrapping maneuver area of MSE access road.
- Continue embankment of section B and C parallelly to the bottom level of section
G
- Dismantling MSE access road.
- Continue embankment of section B, C, and G parallelly to the bottom level of
section F.
- Finishing MSE wall embankment of section B, C, G, and section F including the
cable tray beam foundation installation.
- Start MSE wall embankment of MSE wall section A and A1.

3. Materials
- Safety line
- Safety sign
- Rockfill (granular) material for MSE Wall
- Geotextile PEC 50 & PEC 75
- Perforated pipe

4. Schedule and organization chart


The schedule will be recruited as the following table:

4
May June July August September
Description of Works
I II III IV I II III IV I II III IV I II III IV I II III IV
Section B
Surface Preparation 1
Restore Manuver Area
Sloping CBB West
Demolish Concrete Access Road
Shifting Drainage Pipe
Section B + C
Surface Preparation 2
Sloping CBB West
Demolish Concrete Access Road
Shifting Drainage Pipe
Section B + C + G + A
Section B + C + G + A + F

5
PT. WIJAYA KARYA (Persero) Tbk,
Project Manager
Mahendra Vijaya
HSE Manager
Hannan Mukhtar

Site Manager Safety Officer


Dedeng Jefry Arthur Bobby Trisandi
Commercial Mgr. Teguh Kurniawan
Aden Sukanda Resky
Warehouse Surveyor Superintended 1 Superintended 2 Superintended 3 Superintended Eq Agus
Chief of QA/QC Joko Asep Rahman Supanto Zainal Umar Nashir Andi Zuliyanto Ali Yurianto
Jenal Aripin Yanto Widiyanto
Fajar Supervisor Supervisor Supervisor Supervisor
Chief of Engineering Assistant Survey Erwin Evo Difra Andria Riyadi Munaseh
Difa Wijaksono Alan Daruman Barna Soemantri Dian Bagyo
Heri Rismayadi
Chief of Procurement
Taib Mirza

Chef of Finance
Onky Reza

General Affair
Nekad Wahyu

6
5. Construction equipment
- Excavator PC-200( 1 )
- Dump Truck 25T ( 34 )
- Bulldozer (1)
- Vibro roller (2)
- Stamper (2)

6. Manpower
Direct manpower shall be allocated as follow
- Supervisor (1)
- QA/QC (1)
- Safety officer (1)
- Driver ( 34 )
- Operator (4)
- Assistant operator ( 1 )
- Surveyor (1)
- Assistant survey ( 2 )
- Flagman (2)

7. Method of works

MSE wall work sequences

7
7.1. Embankment Step 1

o Install perforated drainage layer and MSE wall embankment at section B


to the bottom level of section C (el. 1365.4 m).
o Volume embankment step 1 approximately 898.59 m3.
o After finished to bottom level of section C, start preparation works for
embankment step 2 below.

7.2. Embankment step 2

8
o After step 1 finished, stock the MSE material filler to east side of the MSE
wall (approx. 1000 – 2000 m3).
o Stocking material is necessary due to MSE access road that will be
demolished later.

o After stock material is considered sufficient, close the access road and
stop material mobilization, and start to shift the cross drainage that
previously at the bottom part of the MSE access to top side of MSE
access as figure above (detail in figure 8.1).
o Cast the cross drain so the access road can be passed again.
o Scrap the concrete at maneuver area and flatten the area and then
demolish the bottom side of MSE access road. Concrete rubbish will be
placed around Wika’s GPP office as surface pavement.
o Parallelly install sloping works step 1 at section C and section G.

9
o Continue on MSE wall embankment of section B and C parallelly to
bottom level of section G (el. 1372 m).
o Volume embankment step 2 approximately 9328.12 m3.
o Continue preparation works for embankment step 3.

7.3. Embankment step 3

o Stock the MSE material filler as a preparation works, approximately 1000


– 2000 m3.

10
o After stocking material finished, stop the material mobilization to MSE
wall, and then start to dismantle the MSE access road completely until the
cross drain.
o Parallelly install sloping step 2 at section C and G to top level of MSE
wall.

o Continue on embankment of section A (el. 1373 to 1376), B, C, and


section G to the bottom level of section F (el. 1376.3).
o Volume embankment step 3 approximately 17381.4 m3.

11
7.4. Embankment step 4

o After step 3 finished, continue on embankment step 4.


o Start embankment from MSE wall section A1, A, B, C, G, and section F to
the top level of MSE wall (el. 1382 m).
o Volume embankment step 4 approximately 8216.92 m3.

8. Drainage shifting plan

- Existing condition of side drainage and cross drain of MSE access road.

12
8.1. Drainage shifting

o Shifted drainage.
o Before MSE access road demolished, the cross drain should be shifted
first.

9. Backfill and sloping plan area section C & G.

- Backfill and sloping plan area section C & G

13
10. Health, Safety & Environmental
General health, safety & environmental rules and regulations:
1. Contractor will assign a safety supervisor frequently on site to ensure work is being
conducted in accordance with the Permit To Work and JSA.
2. Contractor will comply with Indonesian Government Regulations regarding health,
safety and environment.
3. Contractor will submit Permit to Work and JHA/JSA to Marubeni to get approval
before mobilization.
4. Mandatory PPE for the work are Long sleeve shirts, safety helmet, reflective vest,
safety shoes/boot.
5. All operator should wear mandatory PPE when getting out of the dump trucks and
heavy equipment.
6. Operator of heavy equipment shall have valid SIO (Operating license) and SILO
(Equipment certificates)
7. Contractor will conduct toolbox talk before commencement of works on every shift.
8. Beware of rain and potential falling debris, inform to the supervisor if any findings
regarding this matter.
9. Contractor will minimize any activities involving human-machines interaction at the
same location.
10. Contractor will establish effective communication system between operators,
supervisors and other parties.
11. All personnel should maintain awareness of potential hazards before beginning each
shift.
12. Beware with all safety signs, barricades and other type of safety controls of hazard
identification.