BOC-1962-AA-9002-0001 001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
Revision History
Revision
Revision Date Approver Summary of Changes
Number
Holds
Reference Documents
Description of the
Services:
Design and Construction of SGTF North Access Road Including Landscaping and Irrigation
Schedule Requirements:
Other:
Resource:
Personnel Category:
This Work Order Proposal does not modify any of the terms and conditions of the CONTRACT, which shall
remain in full force and effect.
In witness hereof the Parties have signed this Work Order in duplicate.
For CONTRACTOR:
CONTRACTOR 03
REPRESENTATIVE Sudeep D Poojary Jan
2024
TABLE OF CONTENTS
1.0 GENERAL .................................................................................... 5
3.0 ABBREVIATION.............................................................................. 6
15.0 COMMERCIAL............................................................................... 14
1.0 GENERAL
This Work Order Proposal is for Design and Construction of Design and Construction
of SGTF North Access Road in accordance with the Work Order request No. BOC-
1962-AA-9001-001.
All the construction works shall be executed in accordance with the SOW to the
approval of the Company and handed over to BOC.
c) Construction Phase: Once the construction design has been approved, the
construction scope shall include, but not be limited to, the following:
o Asphalting including prime coat, base course, tack coat and surface
course.
BOC-1962-AA-9002-0001 Page 5 of 17 Rev.:001
Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
o Supply of road signs and sign boards with foundation and installation.
3.0 ABBREVIATION.
COMPANY BOC
PMC KBR
CONTRACTOR MFCO
QCMP Quality Management Procedure
QCP Quality Control Procedure
ISD Information System Department
ITP Inspection and Test Plan
FLC Flow Chart
MS Method Statement
CAN Corrective Action Notice
CAR Corrective Action Request
NCR Non-conformance Report
RFI Request for Information
KPI Key Performance Indicator
QA Quality Assurance
QC Quality Control
IFC Issue For Construction
AFC Approved For Construction
4.0 REFERNCES
4.1 Company Standards and Basic Design
MGP1-PP2-KBR-C l-4018-0001-002, Access Road Layout Connecting SGTF, Power
Plant & MMPS
MGP1-PP2-KBR-C l-4018-0001-002, Access Road Layout Connecting Shams Road
and SGTF
MGP1-PP2-KBR-C l-4018-0001-003, Vertical Alignment Access Road Connecting
Shams Road and SGTF
Topographical survey for the north access and south access to SGTF
EPCM-ERW-00027-400, ERW Land Release Certificate.
MGP1-GEN-KBR-CX-7880-0002-001, General notes for Civil Works Abbreviations and
Legends
BOC-1962-AA-9002-0001 Page 6 of 17 Rev.:001
Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
5.0 MOBILIZATION
Site facilities including site office, break out room, toilets, storage, power plants and
lay-down areas will be established. Site facilities to have an adequate waste collection
with segregation and disposal measures in place.
We will ensure that only the area allocated is utilised and that the set out is logical, has
easy ingress and egress, is easy to maintain and safe.
Project Manager
Contracting &
Construction Planing and Cost
HSE Manager QC Manager Procurement Security Focal Point Administrator Logistic Incharge
Engineer Manager
Engineer
Medic DC Surveyor
Foreman
BOC-1962-AA-9002-0001 Page 7 of 17 Rev.:001
Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
7.0 MANPOWER
Contractor will supply the necessary workforce for the project, comprising both the
approved indirect manpower by KBR and fully Health, Safety, and Environment (HSE)
trained direct manpower.
Personnel Numbe
r
Project Manager 1
Construction Supervisor 2
Site Foreman 1
First Aider 1
HSSE Site Supervisor 1
Permit Holder 1
Surveyor and Chainman 1
Plant Operators 10
General Labor 20
8.0 EQUIPMENT
The contractor will provide the required project equipment, ensuring full compliance with the
MFD safety requirements.
Plan Number
t
Tipper Trucks 6
Excavators 1
Front End Loaders 1
Dozer 1
Grader 2
Roller Compactor 3
Rubber Wheel Roller 3
Steel Roller 3
Water Tanker 2
Prime/tack coat Tanker 1
Asphalt Paver/Layer 1
Flat Bed Trailer 2
55t Crane 1
Hiab 1
Minibus 1
Pick Up 4
Light Truck 1
9.0 RESPONSIBLITIES
Project Manager
Conduct HSE TBT with the full site Construction team to discuss the activities of the day,
highlighting the hazards and required controls to be in place.
Conduct daily production planning brief, prior to commencing work to discuss and ensure the
following:
Coordinate with Planning and Procurement to schedule materials delivery on time. Overall
management and control of site store and materials.
Monitoring and controlling the use of Plant/ Equipment on Site, ensuring regular maintenance
is carried out. Monitoring and compiling relevant information on production rates.
Follow-up and implementation of safety procedures, aiming for Zero Accident and ensuring
compliance by all site personnel, take necessary disciplinary actions against any person failing
to adhere to safety requirements.
Reviews Purchase orders of site staff and signs site receipt documents.
Reviews the site quality department observations noted on the inspection reports, act to
remedy with the site staff in coordination with the QA/QC.
Ensures all activities are performed in accordance with the contract and the construction
schedule.
Implements and ensures that all personnel understand their responsibilities, comply with the
Project Quality Plan during all construction operations, and at all levels they are aware of their
responsibilities with regard to the quality system requirements.
Ensures all activities are performed in accordance with approved drawings and Documents
and ensures that only the latest revisions of approved ones are used.
Ensures no work is commenced before all approvals are received.
Ensures engineers regularly verify the calibration status of surveying instruments and other
used inspection and testing equipment and that a record of calibration is retained.
Verifies that all workers have adequate training and experience to perform appointed duties.
QA/QC Manager
Review Contract Specifications and Drawings identify product criteria and prepare required
checklist for inspection and testing.
Conduct daily site Inspection/walk through to monitor work in progress for compliance with
Specification and design/shop drawings, report any non-compliance. Aim for defect/ non-
compliance free product.
Receive and log Request for Inspection and process through during the same day. Coordinate
and perform Inspection and test activities in accordance with relevant Inspection Test Plan,
ensure that completed works is conformant and ready for final inspection.
Monitor status of inspection and follow-up on actions for re- submission, ensuring all required
actions are completed prior to re-submission.
Coordination with Test Laboratory for sampling. Monitor the Quality of materials received and
report any deviations from specified requirement.
Perform materials receiving Inspection/ test to verify compliance with the requirements of
Specification and / or approved submittal. Report non-compliance via the use of receiving
inspection report.
Monitor storage area and take necessary action to prevent damage.
Maintain quality records specified by relevant inspection test plans and contract documents.
Ensure all original copies of records are handed over to Document Controller.
Planning and coordination of Project Hand Over, and establish the required plans in
coordination with Project Manager.
During the Construction life cycle, perform the above duties to ensure that 95% of Inspections
Passed first time and prevent product defect.
HSSE Site Supervisor
Conduct TBT with full site Construction Team and ensure all hazards of the activities of the
day are identified and actions are in place and understood by the work force.
Inspect and audit all site operations to monitor compliance with HSSE Policy and execution
plan.
Inspect all relevant files, forms and registers required to be kept at site to ensure the routine
tests and inspections required by safety plan have duly been carried out and the results
properly recorded.
Monitor observance of site safety rules and issue warnings to workers, work supervisions, site
management staff and subcontractors for rectification purposes in case of non- compliance
and unsatisfactory safety performances. Site improvement notices shall be raised wherever
necessary.
Investigating all accidents/ incidents etc. and make necessary recommendation.
Promote the safe execution of work on site and provide safety induction training and safety
briefings to workers.
Produce daily and weekly HSSE site reports.
Contractor will provide the below deliverables as per the project requirements.
ID Activity Name
Utilizing the southern access which involves the Reinstatement of the south side access road.
1. Supply & Install New security 12mx3m cabin and (Existing Cabin need to be operate during
change of Access from SGTF North side to SGTF South side)
2. Re Locate 3mx3m Guard Rest Cabin
3. Supply and install 50 Number T-Walls
4. Provide Electric Power From located Steel Guard Tower (if possible) which is at 75m from
Southern Gate.
5. If Electrical Power from existing Guard not possible; that mean checking for another electrical
power sources.
6. Relocated one of Existing Drop arm Barrier.
7. Relocate existing 14 No. Jersy Barriers
8. Construct 50mx30m Car Park area which includes Grading; Backfilling 0.2m thick Gatch B
Materials
9. Backfilling existing Security Ditch Infront of Gate so Traffic will be smoothly.
10. Construct new road from Southern Gate to the existing Gatch road (Length 150m and width
20m Thick 1m)
11. Supply and Install New Pedestrian Gate.
12. Relocate 2 Lighting poles including Electrical wiring.
All facilities shall meet all applicable health, safety, security, environment, and social performance
regulations and fully conform to the requirements of the CONTRACT and Section VIII – HSSE & SP and
Section XV - Contract Reference Documents in particular.
14.0 EXECLUSION
The contractor has removed landscaping and irrigation from the work order proposal, as these
elements will be addressed in a separate work order proposal associated with BOC-1962-AA-9002-
0001-SGTF and MCPP External Infrastructure Arrangement.
15.0 COMMERCIAL
Please see Anexure-1
16.0 SCHEDULE
Please see Anexure-2
Anexure-1
BOC-1962-AA-9002-0001 Rev.:001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
E1.1
Site preparation (following ERW clearance) including levelling, rolling and MGP1-PP2-KBR-CI-4018-0001-003
m2 4880 2 9760
compacting sub-grade for Well Pad and General Areas MGP1-PP2-KBR-CI-4018-0001-004
Excavation in material other than topsoil, rock or artificial hard material including
ACAD_RSK-182680-TOPO-SGTF ACCESS
E1.3 trimming of surfaces and disposal of excavated material to on-site disposal area M3 20 2.5 50
ROAD-R1-Model-Model
distance <15km, depth <5m.
R ROADS AND PAVINGS - Within Well Pad Limits
Road construction as per drawings MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Light & Heavy
R1 Duty Roads, MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Temporary & Patrol Roads and in
accordance with MGP1-GEN-KBR-CX-7880-0023, Specification for Roads and Paving
Sub-bases, flexible road bases and surfacing. Granular material Class A Road 1010.16 28.00
MGP1-PP2-KBR-CI-4018-0001-002
R1.1 m3 28284.48
Base. MGP1-PP2-KBR-CI-4018-0001-004
Geogrid. Max Tensile Strength ≥40 / ≥40 kN/m. Elongation at nominal strength,
md/cmd ≤8 / ≤8 %. Tensile strength at 2% elongation, md/cmd ≥13 / ≥13 kN/m.
Tensile strength at 5% elongation, md/cmd ≥26 / ≥26 kN/m, all to DIN EN ISO MGP1-PP2-KBR-CI-4018-0001-002
R1.5 10319 UV-resistance (remaining tensile strength) BS EN 12224 96.3 %. Weather m2 4880.00 5.50 26840
MGP1-PP2-KBR-CI-4018-0001-004
resistance, FGSV, Class, high.
MGP1-PP2-KBR-CI-4018-0001-002
R1.8 Surfacing. Hot rolled asphalt base course. Depth: 100 mm. m3 3904.00 22.00 85888
MGP1-PP2-KBR-CI-4018-0001-004
MGP1-PP2-KBR-CI-4018-0001-002
R1.9 Surfacing. Hot rolled asphalt wearing course. Depth: 50 mm m2 3904.00 11.00 42944
MGP1-PP2-KBR-CI-4018-0001-004
Sub-bases, flexible road bases and surfacing. Bituminous spray. Prime coat grade 3904.00 3.50
MGP1-PP2-KBR-CI-4018-0001-002
R1.11 m2 13664
MC70. MGP1-PP2-KBR-CI-4018-0001-004
Ancillaries. Traffic Signs (inclusive of all foundation, supporting posts, excavation, etc. as per rule C9) and
surface markings as per drawings MFD-GEN-FWK-CX-7880-0013-001-001 to 004, MFD Road Marking &
R3
Signage Typical Details and MFD-GEN-FWK-CX-7880-0014-001&2-001, MFD Sign Board Mountaing
Foundation & Structural Details
Non illuminated. Regulatory sign type R1 to R6, R13 to R 18 and R 20. Warning 3.00 500.00 1500 MGP1-PP2-KBR-CI-4018-0001-002
R3.1 nr. MGP1-PP2-KBR-CI-4018-0001-004
Sign type W1 to W 14
500.00 1000 MGP1-PP2-KBR-CI-4018-0001-002
R3.3 Non illuminated. Regulatory sign type R7 & R8 nr. 2 MGP1-PP2-KBR-CI-4018-0001-004
Ancillaries. Surface markings. Road Paint. White or yellow reflective road marking paint DFT 0.3 mm with
R4
surface applied glass beads 400 g/m2
R4.1
MGP1-PP2-KBR-CI-4018-0001-002
Ancillaries. Surface markings. Reflective road studs nr. 220.00 23.00 5060
MGP1-PP2-KBR-CI-4018-0001-004
R4.2
Ancillaries. Surface markings. Letters and shapes RM1 to RM4 nr. 4.00 39.00 156
R4.6
Ancillaries. Surface markings. Continuous lines. Yellow edge of carriageway line 976.00 12.00
MGP1-PP2-KBR-CI-4018-0001-002
m 11712
wide 150 mm RM7 MGP1-PP2-KBR-CI-4018-0001-004
R4.7
Ancillaries. Surface markings. Continuous lines. White center of carriageway line 976.00 12.00
MGP1-PP2-KBR-CI-4018-0001-002
m 11712
wide 150 mm RM8 MGP1-PP2-KBR-CI-4018-0001-004
R4.8
Ancillaries. Surface markings. Intermittent lines. White center of carriageway line 58.00 20.00
MGP1-PP2-KBR-CI-4018-0001-002
m 1160
wide 150 mm RM8 MGP1-PP2-KBR-CI-4018-0001-004
A4.6
Earthmoving. Demobilisation of all Earthmoving Equipment as required for the
Contract, including but not limited to, Excavators, Bulldozers, Loaders, Graders, sum 1.00 4500.00 4500
Vibratory Soil Compactors, Wheel Loaders, Asphalt Cutting Machines, etc.
B2 Laboratory testing
Samples. From the surface, or from trial pits or trenches. Sample size 10 kg.
B2.1 nr 10.00 120.00 1200
Class 3 to BS 5930
Total $ 347,130.48
BOC-1962-AA-9002-0001 Rev.:001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
Service Road Fron SGTF North side to SGTF South Side ( 360m)
PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES
1 E EARTHWORKS
2 E1 All earthworks shall be performed in accordance with MGP1-GEN-KBR-CX-7880-0022, Specification for Earthworks
3 E1.1
Site preparation (following ERW clearance) including levelling, rolling and 7,200.00
m2 3600 2 ANRD-INF-MFC-CI-4018-0007
compacting sub-grade for Well Pad and General Areas
Site preparation (following ERW clearance) including levelling, rolling and 1500.00 2.00 3,000.00
8 E 1.1 m2 ANRD-INF-MFC-CI-4018-0007
compacting sub-grade for Well Pad and General Areas
Fences to BS 1722-10:2006. Zinc coated mesh wire, mesh size 40-50 mm, zinc coated wire, diameter
3.0 mm. Zinc coated line wire, diameter 4.00 mm. Zinc coated stirrup wire, diameter 2.5 mm. Zinc
17 X1
coated tying wire, diameter 1.60 mm. Inclusive of all fittings. Other details as per MGP1-GEN-KBR-
CX-7880-0007 , Standard Detail for Single Chain link Fence
Supply & Install 10 meter steel light pole c/w required electrical connection 1.00 1500.00 1,500.00
18 X2.31 no ANRD-INF-MFC-CI-4018-0007
and junction boxes
19 F IN SITU CONCRETE
Concrete, formwork and reinforcement steel supply and installation shall be in accordance with
20 F MGP1-GEN-KBR-CX-7880-0021, Specification for Concrete Works and MGP1-GEN-KBR-CX-7880-
0002, Standard Drawing General Notes for Civil Works Abbreviations and Legends.
Supply, place, compact, level, cure Grade C16 blinding concrete with A252
21.0 F1.1 m3 3.00 250.00 750.00 ANRD-INF-MFC-CI-4018-0007 For Pedestain Gate
mesh < 100mm thick
Total $ 135,601.00
BOC-1962-AA-9002-0001 Rev.:001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
Work Discription
Supply deliver & Installation 40ft Guard Caravan Including Manpower & Equipment
1 20850.00 1 20850.00
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.
Supply and Install New Lighting Pole including Manpower & Equipment
3 2400 1 2400
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.
Supply and Lay 3Core 25mm2 Electrical Cable work including Manpower & Equipment.
5 6750 1 6750 75 Mtr length
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.
Supply & Installation width Pedestarin Gate work including Manpower & Equipment
7 3025 1 3025
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.
BOC-1962-AA-9002-0001 Rev.:001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
Anexure-2
Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 3 Date Revision Checked Approved
Primary Baseline Remaining Work Baseline Milestone TASK filter: All Activities
PROJECT CODE:ANRD
PROJECT NAME: BOC 1962 - Ancillary Roads and
Infrastructure
Activity ID Activity Name Planned Duration Start Finish Total Float PredecessorsSuccessors Activity Check 2024
Jan Feb Mar Apr May
A1190 Inspection & Packing 2 29-Jan-24 30-Jan-24 14 A1180 A1200 Inspection & Packing
A1200 ETA 7 31-Jan-24 06-Feb-24 14 A1190 Kmil-56, Civ-Ear-3 ETA
BOC-1962.3.6.4 Procurement of Geogrid 28 10-Jan-24 06-Feb-24 14 06-Feb-24, BOC-1962.3.6.4 Procurement of Geo
A1210 Material Requesition 5 10-Jan-24 14-Jan-24 14 Kmil-36 A1220 Material Requesition
A1220 RFQ 5 15-Jan-24 19-Jan-24 14 A1210 A1230 RFQ
A1230 TBE 2 20-Jan-24 21-Jan-24 14 A1220 A1240 TBE
A1240 PO Placement 2 22-Jan-24 23-Jan-24 14 A1230 A1250 PO Placement
A1250 Manufacturing 5 24-Jan-24 28-Jan-24 14 A1240 A1260 Manufacturing
A1260 Inspection & Packing 2 29-Jan-24 30-Jan-24 14 A1250 A1270 Inspection & Packing
A1270 ETA 7 31-Jan-24 06-Feb-24 14 A1260 Kmil-56, Civ-Ear-3 ETA
BOC-1962.3.6.5 Procurement of Camp 28 10-Jan-24 06-Feb-24 0 06-Feb-24, BOC-1962.3.6.5 Procurement of Cam
A1280 Material Requesition 5 10-Jan-24 14-Jan-24 0 Kmil-36 A1290 Material Requesition
A1290 RFQ 5 15-Jan-24 19-Jan-24 0 A1280 A1300 RFQ
A1300 TBE 2 20-Jan-24 21-Jan-24 0 A1290 A1310 TBE
A1310 PO Placement 2 22-Jan-24 23-Jan-24 0 A1300 A1320 PO Placement
A1320 Manufacturing 5 24-Jan-24 28-Jan-24 0 A1310 A1330 Manufacturing
A1330 Inspection & Packing 2 29-Jan-24 30-Jan-24 0 A1320 A1340 Inspection & Packing
A1340 ETA 7 31-Jan-24 06-Feb-24 0 A1330 Kmil-56, A1400 ETA
109 10-Jan-24 06-May-24 0 06-May-24, B
BOC-1962.5 Construction
BOC-1962.5.7 Mobilization 35 10-Jan-24 13-Feb-24 0 13-Feb-24, BOC-1962.5.7 Mobilization
BOC-1962.5.7.1 Camp & Resources Mob. 35 10-Jan-24 13-Feb-24 0 13-Feb-24, BOC-1962.5.7.1 Camp & Resourc
A1370 Manpower Mobilization to site 2 10-Jan-24 11-Jan-24 3 Kmil-3 A1390, A1460, A1470 Manpower Mobilization to site
A1380 Equipment Mobilization to site 2 10-Jan-24 11-Jan-24 3 Kmil-3 A1390, A1460, A1470 Equipment Mobilization to site
A1390 Site Preparation & Grading 3 12-Jan-24 14-Jan-24 23 A1380, A1370
A1400 Site Preparation & Grading
A1400 Caravans Erection 2 07-Feb-24 08-Feb-24 0 A1390, A1340
A1410, A1430, Mob-3 Caravans Erection
A1410 Generator installation 1 09-Feb-24 09-Feb-24 2 A1400 A1420 Generator installation
A1430 Installation of Septic Tank 1 09-Feb-24 09-Feb-24 1 A1400 A1440 Installation of Septic Tank
A1420 Utility electrical works 1 10-Feb-24 10-Feb-24 2 A1410 A1450 Utility electrical works
A1440 Plumping Works 2 10-Feb-24 11-Feb-24 1 A1430 A1450 Plumping Works
A1450 Furniture supply & Installation 1 12-Feb-24 12-Feb-24 1 A1420, A1440
Kmil-16 Furniture supply & Installation
Mob-3 Fenceing Works 5 09-Feb-24 13-Feb-24 0 A1400 Kmil-16 Fenceing Works
BOC-1962.5.2 SGTF traffic Diversion Arrangements 32 12-Jan-24 12-Feb-24 3 12-Feb-24, BOC-1962.5.2 SGTF traffic Diversio
BOC-1962.5.2.1 Service Road From SGTF North side to SGTF South Side 8 12-Jan-24 19-Jan-24 27 19-Jan-24, BOC-1962.5.2.1 Service Road From SGTF N
A1480 Excavation in material other than topsoil 1 12-Jan-24 12-Jan-24 30 A1460 A1490 Excavation in material other than topsoil
A1460 Site preparation 4 12-Jan-24 15-Jan-24 27 A1370, A1380
A1480, A1490 Site preparation
A1490 Back filling 20mm thick Class B 4 16-Jan-24 19-Jan-24 27 A1460, A1480
A1360 Back filling 20mm thick Class B
BOC-1962.5.2.2 SGTF South Gate 32 12-Jan-24 12-Feb-24 3 12-Feb-24, BOC-1962.5.2.2 SGTF South Gate
A1500 Trench Fill in g to embankments usin g selected Borrow Pit material 1 12-Jan-24 12-Jan-24 19 A1470 A1520 Trench Fill in g to embankments usin g selected Borrow Pit ma
A1470 Site preparation Parking Area and Existing Road 2 12-Jan-24 13-Jan-24 3 A1380, A1370
A1500, A1510, A1520, A1550 Site preparation Parking Area and Existing Road
A1550 Electrical Power 5 12-Jan-24 16-Jan-24 26 A1470 A1590 Electrical Power
A1590 Relcoate 1 Light Pole 2 17-Jan-24 18-Jan-24 26 A1550 A1600 Relcoate 1 Light Pole
A1600 Supply and Install 1 Light Pole 2 19-Jan-24 20-Jan-24 26 A1590 A1360 Supply and Install 1 Light Pole
A1510 Class B Extend Existing road to southren Gate&Car Park 17 12-Jan-24 28-Jan-24 3 A1470 A1520 Class B Extend Existing road to southren Gate&Car P
A1520 Supply and Install Pedestarin Gate 2 29-Jan-24 30-Jan-24 3 A1510, A1470,
A1530
A1500 Supply and Install Pedestarin Gate
A1530 Relocate of Jersey Barrier 2 31-Jan-24 01-Feb-24 3 A1520 A1540 Relocate of Jersey Barrier
A1540 Relocate Drop Arm Barrier 1 02-Feb-24 02-Feb-24 3 A1530 A1560 Relocate Drop Arm Barrier
A1560 Supply and Install 12mx3m Guard Cabin 3 03-Feb-24 05-Feb-24 3 A1540 A1570 Supply and Install 12mx3m Guard Cabin
Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 3 Date Revision Checked Approved
Primary Baseline Remaining Work Baseline Milestone TASK filter: All Activities
PROJECT CODE:ANRD
PROJECT NAME: BOC 1962 - Ancillary Roads and
Infrastructure
Activity ID Activity Name Planned Duration Start Finish Total Float PredecessorsSuccessors Activity Check 2024
Jan Feb Mar Apr May
A1570 Supply and Install 50 T-Wall 5 06-Feb-24 10-Feb-24 3 A1560 A1580 Supply and Install 50 T-Wall
A1580 Relocate 3x3 Guard Cabin Rest 2 11-Feb-24 12-Feb-24 3 A1570 A1360 Relocate 3x3 Guard Cabin Rest
BOC-1962.5.9 WO1 SGTF Road 74 14-Feb-24 06-May-24 0 06-May-24, B
BOC-1962.5.9.1 Civil Works 55 14-Feb-24 12-Apr-24 0 12-Apr-24, BOC-1962.
BOC-1962.5.9.1.1 Earth Works 7 14-Feb-24 20-Feb-24 0 20-Feb-24, BOC-1962.5.9.1.1 Earth Works
BOC-1962.5.9.1.1.1 Site Preparations 3 14-Feb-24 16-Feb-24 0 16-Feb-24, BOC-1962.5.9.1.1.1 Site Prepara
A1350 Project the road coordinates 2 14-Feb-24 15-Feb-24 0 Kmil-2 A1360 Project the road coordinates
A1360 Area preparations 1 16-Feb-24 16-Feb-24 0 A1350, A1580,
Civ-Ear-1
A1600, A1490 Area preparations
BOC-1962.5.9.1.1.2 Sub-Grade 4 17-Feb-24 20-Feb-24 0 20-Feb-24, BOC-1962.5.9.1.1.2 Sub-Grade
Civ-Ear-1 Compact Sub Grade to 95% MDD 4 17-Feb-24 20-Feb-24 0 A1360 Civ-Ear-3, Civ-Ear-2 Compact Sub Grade to 95% MDD
BOC-1962.5.9.1.2 Sub Base 12 20-Feb-24 03-Mar-24 1 03-Mar-24, BOC-1962.5.9.1.2 Sub Ba
Civ-Ear-3 Lay Geotextile 2 20-Feb-24 22-Feb-24 0 A1270, A1200,
Civ-Ear-13
Civ-Ear-1 Lay Geotextile
Civ-Ear-13 Lay Geogrid 2 22-Feb-24 24-Feb-24 0 Civ-Ear-3 Civ-Ear-4 Lay Geogrid
Civ-Ear-4 1st Layer Structural Backfilling of Class A 20cm 2 24-Feb-24 26-Feb-24 0 Civ-Ear-2, Civ-Ear-13
Civ-Ear-6, Civ-Ear-14 1st Layer Structural Backfilling of Class A
Civ-Ear-14 1st Layer Compaction 2 26-Feb-24 28-Feb-24 0 Civ-Ear-4 Civ-Ear-7 1st Layer Compaction
Civ-Ear-7 2nd Layer Structural backfilling & Compaction of Calss A 15cm 2 28-Feb-24 01-Mar-24 0 Civ-Ear-6, Civ-Ear-14
Civ-Ear-9, Civ-Ear-17 2nd Layer Structural backfilling & Comp
Civ-Ear-17 2nd Layer Compaction 2 01-Mar-24 03-Mar-24 1 Civ-Ear-7 Civ-Shoul-1 2nd Layer Compaction
BOC-1962.5.9.1.3 Road Base 15 25-Feb-24 11-Mar-24 0 11-Mar-24, BOC-1962.5.9.1.3 Roa
Civ-Sfac-1 Lay Road Base 15cm 8 25-Feb-24 04-Mar-24 0 Civ-Ear-9 Civ-Sfac-2 Lay Road Base 15cm
Civ-Sfac-2 Prime Coat Application 3 08-Mar-24 11-Mar-24 0 Civ-Sfac-1 Civ-Sfac-3 Prime Coat Application
BOC-1962.5.9.1.4 Base Course 3 11-Mar-24 14-Mar-24 0 14-Mar-24, BOC-1962.5.9.1.4 Ba
Civ-Sfac-3 Lay & Compact Binder Course 10cm 3 11-Mar-24 14-Mar-24 0 Civ-Sfac-2, Civ-Shoul-3
Civ-Sfac-4 Lay & Compact Binder Course 10c
BOC-1962.5.9.1.5 Surface Course (Asphalting) 26 14-Mar-24 12-Apr-24 0 12-Apr-24, BOC-1962.
Civ-Sfac-4 Tack Coat Application 3 14-Mar-24 17-Mar-24 0 Civ-Sfac-3 Civ-Sfac-5 Tack Coat Application
Civ-Sfac-5 Place & Compacr Surface Course 50 mm 25 15-Mar-24 12-Apr-24 0 Civ-Sfac-4 Civ-Mrk-3 Place & Compacr Surf
BOC-1962.5.9.13 Road Finishing 44 03-Mar-24 24-Apr-24 0 24-Apr-24, BOC-1
BOC-1962.5.9.13.5 Road Shoulders 5 03-Mar-24 08-Mar-24 1 08-Mar-24, BOC-1962.5.9.13.5 Roa
Civ-Shoul-1 Structural Backfilling Class A 15cm For Shoulders 3 03-Mar-24 06-Mar-24 1 Civ-Ear-17 Civ-Shoul-2 Structural Backfilling Class A 15cm Fo
Civ-Shoul-2 Compact Shoulders Layer 3 06-Mar-24 08-Mar-24 1 Civ-Shoul-1 Civ-Shoul-3 Compact Shoulders Layer
BOC-1962.5.9.13.4 Road Marking 7 13-Apr-24 24-Apr-24 0 24-Apr-24, BOC-1
Civ-Mrk-3 Touch-Up painting 1 13-Apr-24 14-Apr-24 0 Civ-Sfac-5 Civ-Mrk-1 Touch-Up painting
Civ-Mrk-1 Surface Road Marking 4 14-Apr-24 18-Apr-24 0 A1130, Civ-Mrk-3
Civ-Mrk-2 Surface Road Marki
Civ-Mrk-2 Install Traffic Signs 2 19-Apr-24 24-Apr-24 0 A1060, Civ-Mrk-1
Kmil-4 Install Traffic Sign
BOC-1962.5.9.14 Testing Phase 18 20-Feb-24 09-Mar-24 1 09-Mar-24, BOC-1962.5.9.14 Testin
Civ-Ear-2 Compaction Test for Sub Garde 1 20-Feb-24 21-Feb-24 3 Civ-Ear-1 Civ-Ear-4 Compaction Test for Sub Garde
Civ-Ear-6 Compaction Test for 1st Layer 3 26-Feb-24 29-Feb-24 2 Civ-Ear-4 Civ-Ear-7 Compaction Test for 1st Layer
Civ-Ear-9 Compaction Test for 2nd Layer 3 01-Mar-24 04-Mar-24 0 Civ-Ear-7 Civ-Sfac-1 Compaction Test for 2nd Layer
Civ-Shoul-3 Compcation Test for Shoulders 1 08-Mar-24 09-Mar-24 1 Civ-Shoul-2 Civ-Sfac-3 Compcation Test for Shoulders
BOC-1962.5.9.8 Call off Handover 11 24-Apr-24 06-May-24 0 06-May-24, B
Hovr-2 Punch List Closure 4 24-Apr-24 27-Apr-24 0 Kmil-4 Hovr-3 Punch List Closu
Hovr-3 ITRs Closure 6 28-Apr-24 05-May-24 0 Hovr-2 Hovr-1 ITRs Closure
Hovr-1 Walk-down 1 05-May-24 06-May-24 0 Hovr-3 Kmil-6 Walk-down
Actual Level of Effort Actual Work Critical Remaining Work Page 3 of 3 Date Revision Checked Approved
Primary Baseline Remaining Work Baseline Milestone TASK filter: All Activities
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road
Anexure-2
SECTION IVA
SCHEDULE OF PRICES
1 of 25
PRICING TABLES
TABLE LIST DESCRIPTION DESCRIPTION
1 PRICING TABLE 1: LUMP SUM RATE FOR MOBILISATION $ 15,000.00
2 PRICING TABLE 2: LUMP SUM RATE FOR DEMOBILISATION $ 15,000.00
3 PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES Unit Rates
4 PRICING TABLE 4: UNIT RATES FOR CONSTRUCTION PERSONNEL Unit Rates
5 PRICING TABLE 5: RATES FOR CONSTRUCTION EQUIPMENT Unit Rates
6 PRICING TABLE 6: MATERIALS AND THIRD PARTY SERVICES Mark up and fee
2 of 25
Contract BOC-1962 - Ancillary Roads and Infrastructure
Section IVA - Schedule of Prices
Revision 01
LUMP SUM
ITEM NO DESCRIPTION
(US$)
1 Mobilisation $ 15,000.00
Page 3 of 25
Contract BOC-1962-Ancillary Roads and Infrastructure
Section IVA - Schedule of Prices
Revision 01
LUMP SUM
ITEM NO. DESCRIPTION
(US$)
1 Demobilisation $ 15,000.00
Page 4 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
A1.5 Design Works for Landscaping and Irrigation for SAQR (FALCON) ROAD – CPF2 ACCESS ROAD sum $ 3,000.00
A1.6 Design Works for Landscaping and Irrigation for SGTF ACCESS ROAD sum $ 3,000.00
A1.7 Design Works for Landscaping and Irrigation for MCPP ACCESS ROAD sum $ 3,000.00
A2 Temporary Works Requirements
Fencing. Supply, erect, maintain for the duration of the works and dismantle upon completion 2m high
galvanised chainlink fence, mesh wire diameter 3.55 mm, line wire 2.55 mm, tying wire 1.6 mm,
A2.1 m $ 145.00
intemediate posts and struts CHS 48.3 x 3.2 mm, straining posts CHS 60.3 x 4 mm , in accordance with
BS 1722:10 2006 Spec. for anti-intruder fences in chainlink & welded mesh.
Specified requirements. Temporary works. Fencing. Supply, erect, maintain for the duration of the works
and dismantle upon completion galvanised double leaf gate and gate posts, clear opening 6 m. Gate
A2.2 nr $ 7,200.00
posts 1=CHS 168.3 x 5 mm. Gate in accordance with MGP1-GEN-KBR-CS-7880-0007 Standard Details
for Gates
Fencing. Take down N/S section of fencing & gate (items A279.1 & A279.2) and re-erect between
A2.3 m $ 70.00
Quadrants 1 & 3
Traffic diversions work per location, include establishment and removal of traffic signs (5x), warning
A2.4 signs (5x), directional signs (5x) to direct all traffic during the period of work as required by Company. wk $ 3,300.00
Includes for supply of 2 each trained flagman.
A3 Testing of the Works
Water Retaining structure testing where necessary in accordance with the technical requirements of the
A3.1 m3 $ 16.00
applicable design codes
Hydro testing of pipes of all materials where so required by Company. Maximum pressure 25 bar.
A3.2 m3 $ 115.00
Including water supply, saturation, pressurising, emptying, purging and disposal of testing water.
Cranes Mobilisation of all craneage required to execute the Contract including telescopic mobile cranes,
A4.1 crawler cranes and truck mounted mobile cranes in capacities from 20t to 250t as required to perform sum $ 5,000.00
the works.
Cranes Demobilisation of all craneage required to execute the Contract including telescopic mobile
A4.2 cranes, crawler cranes and truck mounted mobile cranes in capacities from 20t to 250t as required to sum $ 5,000.00
perform the works.
A4.3 Asphalting. Mobilisation of Asphalt Paving plant, Caterpillar AP500E, spreading width 3.5 m. sum $ 5,000.00
A4.4 Asphalting. Demobilisation of Asphalt Paving plant, Caterpillar AP500E, spreading width 3.5 m. sum $ 5,000.00
Earthmoving. Mobilisation of all Earthmoving Equipment as required for the Contract, including but not
A4.5 limited to, Excavators, Bulldozers, Loaders, Graders, Vibratory Soil Compactors, Wheel Loaders, sum $ 4,500.00
Asphalt Cutting Machines etc..
Earthmoving. Demobilisation of all Earthmoving Equipment as required for the Contract, including but
A4.6 not limited to, Excavators, Bulldozers, Loaders, Graders, Vibratory Soil Compactors, Wheel Loaders, sum $ 4,500.00
Asphalt Cutting Machines, etc.
Concrete Batching Plant. Mobilisation and erection of 100m3/hr Plant including all required silos,
A4.7 sum $ 10,000.00
aggregate bins, testing laboratory, loading bay, washing facilities, etc.
Concrete Batching Plant. Mobilisation and erection of 50m3/hr Plant including all required silos,
A4.8 sum $ 8,000.00
aggregate bins, testing laboratory, loading bay, washing facilities, etc.
Concrete Batching Plant. Dismantle & De-mobilisation of 100m3/hr Plant including all required silos,
A4.9 sum $ 8,000.00
aggregate bins, testing laboratory, loading bay, washing facilities etc. Reinstate site
Concrete Batching Plant. Dismantle & De-mobilisation of 50m3/hr Plant including all required silos,
A4.10 sum $ 6,000.00
aggregate bins, testing laboratory, loading bay, washing facilities etc. Reinstate site
Precast Piles. Mobilisation of pile driving plant, crew, lifting and other equipment incl. all accesories,
temporary site offices, rest facilities, toilets, etc. Delmag MH 6204, Banut 655 pile driver or similar with
A4.11 Fixed Leader Mast suitable for driving precast concrete piles, up to 8 m long, maximum size 450 x 450 sum $ 10,000.00
mm. Diesel Pile Hammer Delmag D62-22 / D80-23-32, Berminghammer B-64, APE D62-52 or similar.
(Alternative foundation for manifolds)
5 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
Precast Piles. Relocation of pile driving and all associated equipment within the Majnoon Field, distance
A4.13 sum $ 8,000.00
not exceeding 15 km. (Alternative foundation for manifolds)
Steel Tubular Piles. Mobilisation of crawler crane and pile driving plant, crew & equipment required to
A4.14 install max 18m long, 600dia tubular piles including pile guides gates and All ancilliaries. (Alternative sum $ 10,000.00
foundation for manifolds)
Steel Tubular Piles. Demobilisation of crawler crane and pile driving plant, crew & equipment required
A4.15 to install max 18m long, 600 dia tubular piles including pile guides gates and All ancilliaries. (Alternative sum $ 10,000.00
foundation for manifolds)
Steel Tubular Piles. Relocation of crawler crane and pile driving plant & equipment within the Majnoon
A4.16 sum $ 8,000.00
Field, distance not exceeding 15 km. (Alternative foundation for manifolds)
B GROUND INVESTIGATION
B1 Trial Pits and Trenches
Machine Excavation in material other than rock, width 0.6 m, maximum depth 1.2 m including
B1.1 m $ 6.00
reinstatement on completion of inspection/sampling or pipe/cable laying operations
Hand Excavation in material other than rock, width 0.6 m, maximum depth 1.2 m including reinstatement
B1.2 m $ 20.00
on completion of inspection/sampling or pipe/cable laying operations
Machine Excavation in material other than rock, width 0.6 m, maximum depth 2.4m. Supported including
B1.3 m $ 7.00
reinstatement on completion of inspection/sampling or pipe/cable laying operations
Hand Excavation in material other than rock, width 0.6 m, maximum depth 2.4m. Supported including
B1.4 m $ 40.00
reinstatement on completion of inspection/sampling or pipe/cable laying operations
B2 Laboratory testing
B2.1 Samples. From the surface, or from trial pits or trenches. Sample size 10 kg. Class 3 to BS 5930 nr $ 120.00
B2.2 Classification, Moisture content according to BS 1377 nr $ 120.00
B2.3 Classification, Atterberg limits according to BS 1377 nr $ 120.00
B2.4 Classification, Specific gravity according to BS 1377 nr $ 120.00
B2.5 Classification, Particle size analysis according to BS 1377 nr $ 120.00
B2.6 Compaction, standard Proctor test for compaction according to BS 1377 nr $ 180.00
B2.7 California Bearing Ratio Test CBR nr $ 180.00
D DEMOLITION AND SITE CLEARANCE
General site clearance. Removal of all vegetation, foreign objects and waste including disposal at
D1.1 m2 $ 6.00
Company appointed area <5km.
Other Structures Demolition of Brickwork (Volume not Exceeding 50m3) Includes volumes above and
D1.2 below existing ground elevation. Excavation is deemed to be included. m3 $ 12.00
Fill required for reinstatement of voids left by demolition shall be measured under item E.
Demolition of Reinforced Concrete (or orther artificial hard material) structures.
3
D1.3 Excavation is deemed to be included. m $ 15.00
Fill required for reinstatement of voids left by demolition shall be measured under item E.
D1.4 Demolition of Steel structures. t $ 500.00
Demolition/Removal of Pipelines. Nominal bore: 100-300 mm. Pipeline removal from trenches and
D1.5 above ground inclusive of any supports, bedding/protection layers and disposal at Company appointed m $ 15.00
area <5km. Includes for backfill and reinstatement.
Removal of Internal fences. Metal post and wire. Height upto 2.00 m. Includes for galvanised top and
D1.6 m $ 5.00
bottom rail diameter 42 mm.
Removal of Security fences. Metal post and wire. Height 2.50 m. Includes for double extension arms, 6
D1.7 m $ 7.00
rows of barbed wire and razor wire top.
E EARTHWORKS
All earthworks shall be performed in accordance with MGP1-GEN-KBR-CX-7880-0022,
E1
Specification for Earthworks
Site preparation (following ERW clearance) including levelling, rolling and compacting sub-grade for
E1.1 m2 $ 2.00
Well Pad and General Areas
Excavation in material other than topsoil, rock or artificial hard material including trimming of surfaces
E1.2 m3 $ 2.00
and disposal of excavated material to on-site disposal area, depth <2m.
Excavation in material other than topsoil, rock or artificial hard material including trimming of surfaces
E1.3 m3 $ 2.50
and disposal of excavated material to on-site disposal area distance <15km, depth <5m.
Excavation in material other than topsoil, rock or artificial hard material including trimming of surfaces
E1.4 and disposal of excavated material to on-site disposal area adjacent to Well Pad, depth <2m. (Access m3 $ 2.00
Rd Drains & Security ditch)
Excavation in material other than topsoil, rock or artificial hard material including trimming of surfaces
3
E1.5 and disposal of excavated material to on-site disposal area distance <5km, depth <5m. ( Culverts, m $ 2.50
cellars, drains & ditches)
6 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
7 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
Geomembrane supply and installation shall comply with the requirements of the Geosynthetic
Research Institute, particular Geomembrane Specification GM10 revision 3 The Stress Crack
Resistance of HDPE Geomembrane Sheet, Test Method GM13 revision 10 Test Properties Testing
E2 Frequency and Recommended Warranty for Geomembrane and Test Method GM19 revision 6
Seam Strength and Related Properties. Installation in accordance with IAGI, HDPE & LLDPE
Geomembrane Installation Specification 2007 and GRI, Geomembrane Specification GM29, Field
Integrity Evaluation of Geomembrane Seams.
Supply and installation of smooth black HDPE geomembrane thick 1 mm. The area of additional
E2.1 m2 $ 9.00
geomembrane in laps shall not be measured. Rate includes for all welding, testing and test records.
Supply and installation of smooth black HDPE geomembrane thick 1.5 mm. The area of additional
E2.2 m2 $ 11.00
geomembrane in laps shall not be measured. Rate includes for all welding, testing and test records.
Supply and installation of smooth black HDPE geomembrane thick 2 mm. The area of additional 2
E2.3 m $ 13.00
geomembrane in laps shall not be measured. Rate includes for all welding, testing and test records.
E3 Geotextile
8 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
Concrete, formwork and reinforcement steel supply and installation shall be in accordance with
F MGP1-GEN-KBR-CX-7880-0021, Specification for Concrete Works and MGP1-GEN-KBR-CX-7880-
0002, Standard Drawing General Notes for Civil Works Abbreviations and Legends.
3
F1.1 Supply, place, compact, level, cure Grade C16 blinding concrete with A252 mesh < 100mm thick m $ 250.00
Supply, place, compact, finish, strip and cure Grade C35 reinforced concrete to foundations (pad, strip,
3
F1.2 raft, ground beams, pipe supports rig tracks etc) including all required formwork, reinforcement, tie wire, m $ 750.00
etc all as shown on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C35 reinforced concrete to ground level slabs,
F1.3 paving, work area etc including all required formwork, reinforcement, tie wire, spacers, etc all as shown m3 $ 500.00
on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C35 reinforced concrete to pit walls, berms
3
F1.4 foundations (pad, strip, raft, ground beams, pipe supports rig tracks etc) including all required formwork, m $ 750.00
reinforcement, tie wire, etc all as shown on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C25 reinforced concrete to foundations (pad, strip,
F1.5 raft, ground beams, pipe supports rig tracks etc) including all required formwork, reinforcement, tie wire, m3 $ 650.00
etc all as shown on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C25 reinforced concrete to ground level slabs,
F1.6 paving, work area etc including all required formwork, reinforcement, tie wire, spacers, etc all as shown m3 $ 450.00
on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C25 reinforced concrete to pit walls, berms
F1.7 foundations (pad, strip, raft, ground beams, pipe supports rig tracks etc) including all required formwork, m3 $ 650.00
reinforcement, tie wire, etc all as shown on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C37 reinforced concrete to foundations (pad, strip,
F1.8 raft, ground beams, pipe supports rig tracks etc) including all required formwork, reinforcement, tie wire, m3 $ 800.00
etc all as shown on the Construction drawings
F1.9 Supply and installation of 1000 gauge (250 μm) polythene m2 $ 5.00
F1.10 Supply and install plastic or rubber centre-bulb waterstops at concrete joints. Width: 150 - 200 mm m $ 25.00
F1.11 Supply and install plastic or rubber back-stop waterstops at concrete joints. Width: 150 - 200 mm m $ 25.00
G Grouting
Grouting. Non-shrink cement based grout type G2 in accordance with MGP1-GEN-KBR-CX-7880-
G
0021, Specification for Concrete Works Section 22 Grouting
Concrete accessories. Grouting under plates. Area: not exceeding 0.1 m2, thickness not exceeding 50
G1.1 nr $ 50.00
mm. Cement based non-shrink grout type G2.
Concrete accessories. Grouting under plates. Area: not exceeding 0.1 m2, thickness not exceeding 50
G1.2 nr $ 80.00
mm. Epoxy based non-shrink grout type G3
Concrete accessories. Grouting under plates. Area: 0.1 - 0.5 m2, thickness not exceeding 50 mm.
G1.3 nr $ 110.00
Cement based non-shrink grout type G2
Concrete accessories. Grouting under plates. Area: 0.1 - 0.5 m2, thickness not exceeding 50 mm.
G1.4 nr $ 200.00
Epoxy based non-shrink grout type G3
G1.5 Cement Sand grout 1:3 m3 $ 1,800.00
H PRECAST CONCRETE
Precast concrete elements are typically pipe supports/sleeper, light pole foundations, CCTV
H foundations, instrument foundations, T-walls, Jersey barriers and various foundation &
pavement slabs.
9 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
10 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
High density polyethylene pipe fittings (PE100). Adapters. Nominal bore: not exceeding 200 mm. In
J.17 trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. Flange nr $ 78.00
adaptor 63 mm outside pipe diameter, inclusive of backing ring and galvanised nuts, bolts and washers.
High density polyethylene pipe fittings (PE100). Adapters. Nominal bore: not exceeding 200 mm. In
J.18 trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. Flange nr $ 78.00
adaptor 90 mm outside pipe diameter, inclusive of backing ring and galvanised nuts, bolts and washers.
11 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.29 nr $ 86.00
water gate valve, DN 63, flanged, nominal pressure 16 bar. AWWA approved or similar.
Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.30 nr $ 215.00
water gate valve, DN 100, flanged, nominal pressure 16 bar. AWWA approved or similar.
Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.31 nr $ 401.00
water gate valve, DN 125, flanged, nominal pressure 16 bar. AWWA approved or similar.
Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.32 nr $ 502.00
water gate valve, DN 150, flanged, nominal pressure 16 bar. AWWA approved or similar.
Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.33 nr $ 612.00
water gate valve, DN 200, flanged, nominal pressure 16 bar. AWWA approved or similar.
K PIPEWORK - MANHOLES AND PIPEWORK ANCILLARIES
Manholes. Polyvinyl chloride (PVC-U) manholes and inspection chambers compliant with EN
13598 -2 & -3, EN 124 and DS 2379. Polyethelyne (PE) waste water manholes shall comply with
K1
EN 13598 -2, & -3, EN 124 and DS 2379. Installation shall comply with Specification ref 45C1 Rev
2, Specification For Drainage Material and Workmanship.
Manholes. Polyvinyl chloride (PVC-U) or polyethylene (PE) . Depth: not exceeding 1.5 m. Wavin Tegra
425 or similar. DN 160 mm, double junction (left and right inlet) type X or similar. Inclusive of
K1.1 nr $ 250.00
polypropylene cover of A14 class, pipe sealing ring and 425 PP corrugated shaft extension pipe 1 m
long.
Manholes. Polyethylene. Depth: not exceeding 1.5 m. Wavin Tegra 600 or similar. DN 160 mm, double
K1.2 junction (left and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring nr $ 280.00
and 600 PP corrugated shaft extension pipe 1 m long.
Manholes. Polyethylene. Depth: 1.5 -2 m. Wavin Tegra 600 or similar. DN 160 mm, double junction (left
K1.3 and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring and 600 PP nr $ 360.00
corrugated shaft extension pipe 1 m long.
Manholes. Polyethylene. Depth: not exceeding 1.5 m. Wavin Tegra 800 or similar. DN 200 mm, double
K1.4 junction (left and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring nr $ 390.00
and 600 PP corrugated shaft extension pipe 1 m long.
Manholes. Polyethylene. Depth: 1.5 - 2 m. Wavin Tegra 800 or similar. DN 200 mm, double junction (left
K1.5 and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring and 600 PP nr $ 440.00
corrugated shaft extension pipe 1 m long.
12 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
K3.14 Ducts. Cable Ducts: 9 way (3 wide x 3 high). In trenches, depth: 1.5-2 m. Duct Bank Type III (3 Layer) m $ 526.00
K3.15 Ducts. Cable Ducts: 12 way (4 wide x 3 high). In trenches, depth: 1.5-2 m. Duct Bank Type III (3 Layer) m $ 670.00
K3.16 Ducts. Cable Ducts: 15 way (5 wide x 3 high). In trenches, depth: 1.5-2 m. Duct Bank Type III (3 Layer) m $ 670.00
K3.17 Crossing. T-Wall. Pipe bore: not exceeding 300 mm nr $ 320.00
K3.18 Crossing. T-Wall. Pipe bore: 300 - 900 mm nr $ 520.00
K3.19 Crossing. Fence. Pipe bore: not exceeding 300 mm nr $ 320.00
K3.20 Crossing. Fence. Pipe bore: 300 - 900 mm nr $ 520.00
K3.21 Crossing. Sewer or drain. Pipe bore: not exceeding 300 mm nr $ 320.00
K3.22 Crossing. Sewer or drain. Pipe bore: 300 - 900 mm nr $ 520.00
K3.23 Crossing. Security berm. Pipe bore: not exceeding 300 mm m $ 370.00
K3.24 Crossing. Security berm. Pipe bore: 300 - 900 mm m $ 590.00
Reinstatement. Breaking up, temporary and permanent reinstatement of roads. Pipe bore: not
K3.25 nr $ 670.00
exceeding 300 mm
Reinstatement. Breaking up, temporary and permanent reinstatement of roads. Pipe bore: 300 - 900
K3.26 nr $ 920.00
mm
Reinstatement. Breaking up, temporary and permanent reinstatement of in-situ cast footpaths. Pipe
K3.27 nr $ 663.00
bore: not exceeding 300 mm.
Other pipework ancillaries. Connection to existing manholes and other chambers. Pipe bore: not
K3.28 nr $ 215.00
exceeding 200 mm
13 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
K3.34 Other pipework ancillaries. Connection to existing pipes, ducts and culverts. Pipe bore: 300 - 600 mm nr $ 625.00
K3.35 Other pipework ancillaries. Connection to existing pipes, ducts and culverts. Pipe bore: 600 - 900 mm nr $ 965.00
L1.1 Special pipe laying methods. Pipe jacking. Nominal bore: 6" schedule 40 pipe. Minimum length 8 m. m $ 120.00
L1.2 Special pipe laying methods. Pipe jacking. Nominal bore: 10" schedule 40 pipe. Minimum length 8 m. m $ 185.00
Surrounds. Bed thickness 100 mm, cover 100 mm. Nominal trench width as per rule L-D1: 500
L2
mm greater than the maximum nominal distance between the inside faces of the outer pipe wall.
L2.1 Surrounds. Sand. Nominal bore: not exceeding 110 mm m $ 10.00
L2.2 Surrounds. Sand. Nominal bore: not exceeding 200 mm m $ 12.00
L2.3 Surrounds. Sand. Nominal bore: 200 - 300 mm m $ 15.00
L2.4 Surrounds. Sand. Nominal bore: 300 - 600 mm m $ 20.00
L2.5 Surrounds. Sand. Nominal bore: 600 - 900 mm m $ 22.00
L2.6 Surrounds. Sand. Nominal bore: 900 - 1200 mm m $ 25.00
L2.7 Surrounds. Imported granular material. Nominal bore: 160 mm m $ 15.00
L2.8 Surrounds. Reinforced concrete. Nominal bore: not exceeding 110 mm m $ 153.00
L2.9 Surrounds. Reinforced concrete. Nominal bore: not exceeding 200 mm m $ 183.00
L2.10 Surrounds. Reinforced concrete. Nominal bore: 200 - 300 mm m $ 256.00
L2.11 Surrounds. Reinforced concrete. Nominal bore: 300 - 600 mm m $ 356.00
L2.12 Surrounds. Reinforced concrete. Nominal bore: 600 - 900 mm m $ 658.00
L2.13 Surrounds. Reinforced concrete. Nominal bore: 900 - 1200 mm m $ 865.00
M STRUCTURAL STEELWORK
Structural metal to comply with MGP1-GEN-KBR-CS-7880-0021, Specification for Steel Works,
M1 MGP1-GEN-KBR-CS-7880-0002, Structural Steel Work General Notes
Rates do not include for painting.
M1.1 Fabrication of frames. Columns. Straight on plan. Not exceeding 3 t t $ 3,600.00
M1.2 Fabrication of frames. Columns. Straight on plan. Exceeding 3 t t $ 3,600.00
M1.3 Fabrication of frames. Beams. Straight on plan. Not exceeding 3 t t $ 3,600.00
M1.4 Fabrication of frames. Beams. Straight on plan. Exceeding 3 t t $ 3,600.00
M1.5 Fabrication of frames. Braces, purlins and cladding rails. Straight on plan. Not exceeding 3 t t $ 3,600.00
M1.6 Fabrication of frames. Braces, purlins and cladding rails. Straight on plan. Exceeding 3 t t $ 3,600.00
M1.7 Supply, Fabrication and Installation of Cladding 50mm thick m2 $ 150.00
2
M1.8 Fabrication and installation of heavy duty galvanised steel grating over cellars (41 to 90mm THK) m $ 200.00
M1.9 Fabrication and installation of heavy duty galvanised steel grating over cellars (upto to 40mm THK) m2 $ 200.00
M1.10 Fabrication and installation of heavy duty galvanised steel frames, 3.6m x 2.9m (atop cellars) t $ 4,000.00
Anchor bolts to comply with, MGP1-GEN-KBR-CX-7880-0003, MFD Anchor Bolt Details. Rate
includes for supply and installation of anchor bolts, nuts and washers, sleeves and post
M2
installation removal of sleeve and grout installation for anchor bolt hole. Grout between base
plate and concrete foundation covered in items G1.1 and G1.2
M2.1 Anchorages and holding down bolts. Straight on plan. Anchor bolt size M16 nr $ 50.00
M2.2 Anchorages and holding down bolts. Straight on plan. Anchor bolt size M20 nr $ 60.00
M2.3 Anchorages and holding down bolts. Straight on plan. Anchor bolt size M24 nr $ 75.00
M2.4 Anchorages and holding down bolts. Straight on plan. Anchor bolt size M30 nr $ 90.00
M2.5 Erection of members for frames including all bolted & welded connections. Permanent erection. t $ 2,000.00
All painting and painting preparation works shall be done in accordance with MGP1-GEN-KBR-
M3
RA-7754-0002, External Painting Specification for Equipment, Structural Steel & Piping
2
M3.1 Off site surface treatment. Blast cleaning. m $ 43.00
14 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
15 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
16 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
R4.7 Ancillaries. Surface markings. Continuous lines. White center of carriageway line wide 150 mm RM8 m $ 12.00
R4.8 Ancillaries. Surface markings. Intermittent lines. White center of carriageway line wide 150 mm RM8 m $ 20.00
Fences. Road restraint system. Bollards and crash barriers in accordance with MGP1-GEN-KBR-
R5 CX-7880-0008, Typical Details of Crash Barriers & Bollards. Includes for all associated
earthworks, concrete works, support steel and painting.
R5.1 Bollards. nr $ 75.00
R5.2 Crash barriers. Galvanised m $ 100.00
V PAINTING
All painting and painting preparation works shall be done in accordance with All painting and
V1 painting preparation works shall be done in accordance with MGP1-GEN-KBR-RA-7754-0002,
External Painting Specification for Equipment, Structural Steel & Piping;
Coating System CS-1; zinc rich epoxy primer, epoxy MIO and polyurethane. Metal, other than metal 2
V1.1 m $ 121.00
sections and pipework.
2
V1.2 Coating System CS-1; zinc rich epoxy primer, epoxy MIO and polyurethane. Metal sections & pipework m $ 128.00
Epoxy or polyurethane paint. Smooth concrete. Exposed concrete surfaces protection as per
MGP1-GEN-KBR-CX-7880-0004, MFD Concrete Protection Standard Details Standard Details
V2
Concrete Protection. Two coats of light grey colour Fosroc® Nitocoat EP403 Epoxy Resin or
similar
V2.1 Epoxy paint to all underground Precast concrete elements. m2 $ 32.00
W WATERPROOFING
All painting and painting preparation works shall be done in accordance with MGP1-GEN-KBR-
W1 CX-7880-0021, Technical Specification for Concrete Works Section10, Concrete Protection item
b. Modified bitumen.
Waterproofing. Waterproof coating. Upper surfaces inclined at an angle not exceeding 30° to the
W1.1 m2 $ 81.00
horizontal.
W1.2 Waterproofing. Waterproof coating. Upper surfaces inclined at an angle exceeding 60° to the horizontal. m2 $ 81.00
W680 Supply and installation of 1000 gauge (250 μm) polythene m2 $ 1.50
Protective layers. Sand and cement screed. Mix: sand 4, cement 1. Inclusive of construction
W2
mesh A142 to BS 4483:2005. Nominal mass 2.22 kg/m2.
Protective layers. Sand and cement screed. Upper surfaces inclined at an angle not exceeding 30° to
W2.1 m2 $ 75.00
the horizontal.
2
W2.2 Waterproofing. Sand and cement screed. Upper surfaces inclined at 30° - 60° to the horizontal. m $ 90.00
Waterproofing. Sand and cement screed. Upper surfaces inclined at an angle exceeding 60° to the
W2.3 m2 $ 90.00
horizontal.
X MISCELLANEOUS WORK
Fences to BS 1722-10:2006. Zinc coated mesh wire, mesh size 40-50 mm, zinc coated wire,
diameter 3.0 mm. Zinc coated line wire, diameter 4.00 mm. Zinc coated stirrup wire, diameter 2.5
X1
mm. Zinc coated tying wire, diameter 1.60 mm. Inclusive of all fittings. Other details as per MGP1-
GEN-KBR-CX-7880-0007 , Standard Detail for Single Chain link Fence
Internal fences. Metal post and wire. Height 1.00 m. Includes for galvanised top and bottom rail diameter
X1.1 m $ 25.00
42 mm.
Internal fences. Metal post and wire. Height 2.00 m. Includes for galvanised top and bottom rail diameter
X1.2 m $ 35.00
42 mm.
Security fences. Metal post and wire. Height 2.50 m. Includes for double extension arms, 6 rows of
X1.3 m $ 45.00
barbed wire and razor wire top.
17 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
X1.5 Installation only of Company Supplied HERAS gates. Installation as per HERAS installation manual. nr $ 200.00
X2 Additional Miscellaneous Rates as per COMPANY requirements
Concrete accessories. Inserts. Other inserts. Halfen Cast-in Channels HTA-CE 50/30, inclusive of 6
X2.1 m $ 150.00
each M20 GVs 8.8 x 60 mm anchor bolts.
Concrete accessories. Inserts. Other inserts. Halfen Frimeda Plate Anchor, Load Group 2.5 t, TPA-FP
X2.2 2,5- 8 FV hot dipped galvanized. Inclusive of 1 each recess former TPA-A1 2,5 per 25 Plate Anchors nr $ 100.00
and 1 each Ring Clutch TPA-R1 2,5 per 250 Plate Anchors.
Light duty pavements. Precast concrete interlocking flags to BS 6717. Depth: 60 mm on 50 mm sand
X2.3 m² $ 100.00
bedding
X2.4 Supply and installation of pre cast speed humps nr $ 500.00
X2.5 Supply and install New Precast jersey barriers nr $ 300.00
Supply & Installation of windsock pole c/w foundation, grouting and anchor bolts in accordance with
X2.6 MGP1-GEN-KBR-CG-4017-1029-001_002. Refer to General Arrangment Drawinig contained under nr $ 1,250.00
Vendor Document Review Sheet Doc No. MGP1-POMJOH0142-C08-0018_004
X2.7 Supply, Install Windsock (Cloth only) nr $ 150.00
X2.8 Supply, fabircation & Installation of Steel Checkered Plate 6mm thick m² $ 200.00
X2.9 Supply, fabircation & Installation of Steel Checkered Plate 8mm thick m² $ 250.00
X2.10 Supply, fabircation & Installation of Steel Checkered Plate 10mm thick m² $ 275.00
Supply and Installation of bitumen paint Sika® Igolflex-205 (coating thickness 1000microns) Two
X2.11 component, cement and bitumen rubber based waterproofing coating. Waterproofing and damp-proofing m² $ 10.00
of below ground concrete structures.
X2.12 Take up and relocate existing precast cover slabs to COMPANY stores within Majnoon concession. nr $ 50.00
Installation of COMPANY provided precast cover slabs.
X2.13 nr $ 150.00
CONTRACTOR shall transport COMPANY provided precast cover slabs from Majnoon stores to the
WORKSITE including loading and unloading.
Installation of COMPANY provided Stelcon slabs.
X2.14 nr $ 150.00
CONTRACTOR shall transport COMPANY provided precast Stelcon slabs from Majnoon stores to the
WORKSITE including loading and unloading.
X2.15 Take up and relocate existing Stelcon slabs to COMPANY stores within Majnoon concession. nr $ 150.00
18 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
19 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
20 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01
Rate (US$)
ITEM NO. CATEGORY OVERTIME HOURLY STANDBY HOURLY
DAY RATE WEEKLY RATE MONTHLY RATE
RATE RATE
1 Blacksmith $ 100.00 $ 600.00 $ 2,700.00 $ 15.63 $ 12.50
2 Carpenter $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
3 Certified Painter $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
4 Chainman $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
5 Civil Labourer $ 40.00 $ 240.00 $ 1,080.00 $ 6.25 $ 5.00
6 Concrete Labourer $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
7 Crane Operator $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
8 Crane Rigger $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
9 Crane Truck Driver $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
10 Draughtsman $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
11 Dump Truck Driver $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
12 Earthworks Equipment Operator $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
13 Electrician $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
14 Fencing erector $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
15 Flagman (Local) $ 40.00 $ 240.00 $ 1,080.00 $ 6.25 $ 5.00
16 Flatbed Driver (40 ft) $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
17 Foreman Concrete $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
18 Foreman Earthworks $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
19 Foreman General $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
20 Foreman Pavement Works $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
21 Formwork Carpenter $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
22 Gas Testers $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
23 General Labourer/Unskilled Operative (Local) $ 40.00 $ 240.00 $ 1,080.00 $ 6.25 $ 5.00
24 GRP jointer $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
25 HSE Officer $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
26 Light Duty Driver $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
27 Bus Driver (bus capacity 30 - 50 persons) $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
28 Mason $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
29 Permit to Work Holder $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
30 Pipelayers (drains/ducts) $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
31 Plasterer $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
32 Paver $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
33 QA/QC Officer $ 100.00 $ 600.00 $ 2,700.00 $ 15.63 $ 12.50
34 Rebarman $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
35 Sandblaster $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
36 Scaffolder $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
37 Structural Steel Erector $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
38 Structural Steel Welder $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
39 Warehouse Assistant $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
40 Welder $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
41 Certified First Aider $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
Note 10 The above rates shall allow for all indirect supervision including, but not limited to, all HSE personnel, QA/ QC personnel, Permit to Work Applicants / Holders and First Aiders. CONTRACTOR shall not be
separately compensated for indirect supervision, unless COMPANY expressly requests these
Page 21 of 25
Section IVA - Schedule of Prices Contract BOC-1962 - Ancillary Roads and Infrastructure
Revision 01
Rate (US$)
1 Bobcat with bucket and brush attachment $ 250.00 $ 250.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50
2 JCB 3C Excavator or equivalent $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75
3 Cat 225 Excavator or equivalent, bucket capacity 1 m3 $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50
4 Cat 225 Excavator or equivalent with rock breaker $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50
5 Cat 235 Excavator or equivalent, bucket capacity 2 m3 $ 350.00 $ 350.00 $ 40.63 $ 325.00 $ 1,950.00 $ 8,027.50 $ 40.63
6 Cat 235 Excavator or equivalent with rock breaker $ 350.00 $ 350.00 $ 56.25 $ 450.00 $ 2,700.00 $ 11,115.00 $ 56.25
7 Cat D6 track-type Tractor or equivalent, 150 hp, blade capacity >3 m3 $ 350.00 $ 350.00 $ 50.00 $ 400.00 $ 2,400.00 $ 9,880.00 $ 50.00
8 Cat D8 track-type Tractor or equivalent, 300 hp, blade capacity >8 m3 $ 350.00 $ 350.00 $ 75.00 $ 600.00 $ 3,600.00 $ 14,820.00 $ 75.00
9 Cat 950 wheel type Loader or equivalent, 130 hp, bucket capacity >1.5 m3 $ 350.00 $ 350.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
10 Cat 960 wheel type Loader or equivalent, 210 hp, bucket capacity >3.5 m3 $ 350.00 $ 350.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
11 Cat 12H Grader or equivalent, 150 hp, blade width 3.6 m, height 0.6 m $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50
12 Cat 14H Grader or equivalent, 215 hp, blade width 4.3 m, height 0.7 m $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50
13 10 ton Vibratory Soil Compactor (Roller) $ 350.00 $ 350.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
14 18 ton Vibratory Soil Compactor (Roller) $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50
15 2 ton Utility Roller (Tandem Roller), Caterpillar CB 22 or similar $ 350.00 $ 350.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
16 10 ton Tandem Vibratory Roller, Caterpillar CB 54 or similar $ 350.00 $ 350.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
17 Vibratory Rammer WackerNeuson BS 50 or equal $ 200.00 $ 200.00 $ 15.63 $ 125.00 $ 750.00 $ 3,087.50 $ 15.63
18 Single Direction Vibratory Plate Compactor, impact >18 kN $ 100.00 $ 100.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.00 $ 9.38
19 Reversible Vibratory Plate Compactor, impact >35 kN $ 100.00 $ 100.00 $ 12.50 $ 100.00 $ 600.00 $ 2,470.00 $ 12.50
20 Auger pole hole (>400 mm diameter) drilling machine or equivalent $ 500.00 $ 500.00 $ 187.50 $ 1,500.00 $ 9,000.00 $ 37,050.00 $ 187.50
21 20 ton All Terrain Crane $ 250.00 $ 250.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75
22 60 ton All Terrain Crane $ 350.00 $ 350.00 $ 62.50 $ 500.00 $ 3,000.00 $ 12,350.00 $ 62.50
23 100 ton All Terrain Crane $ 500.00 $ 500.00 $ 125.00 $ 1,000.00 $ 6,000.00 $ 24,700.00 $ 125.00
24 10 ton Truck with Telescopic Crane 3 t (HIAB) $ 250.00 $ 250.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75
25 10 ton Truck with Telescopic Crane 5 t (HIAB) $ 250.00 $ 250.00 $ 50.00 $ 400.00 $ 2,400.00 $ 9,880.00 $ 50.00
26 20 ton Truck with Telescopic Crane 10 t (HIAB) $ 350.00 $ 350.00 $ 62.50 $ 500.00 $ 3,000.00 $ 12,350.00 $ 62.50
27 5 ton Flat Bed Truck $ 150.00 $ 150.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
Page 22 of 25
Section IVA - Schedule of Prices Contract BOC-1962 - Ancillary Roads and Infrastructure
Revision 01
Rate (US$)
28 7.5 ton Flat Bed Truck $ 150.00 $ 150.00 $ 28.13 $ 225.00 $ 1,350.00 $ 5,557.50 $ 28.13
29 20 ton Flat Bed Truck $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
30 40 ton Flat Bed Truck $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75
31 5 ton Tipper Truck $ 150.00 $ 150.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75
32 20 ton Tipper Truck $ 200.00 $ 200.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
33 40 ton Tipper Truck $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75
34 20 000 litre Water Bowser $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
35 40 000 litre Water Bowser $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75
36 Vacuum Tanker 9 000 litres $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
37 Vacuum Tanker 20 000 litres $ 250.00 $ 250.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50
38 2 ton Pick up Truck 4 x 4 single/double cabin $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38
39 3 ton Pick up Truck 4 x 4 single/double cabin $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38
40 Passenger bus 15 seater $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38
41 Passenger Bus 26 / 30 Seater $ 150.00 $ 150.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75
42 Passenger Bus 50 Seater $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
43 TOYOTA Land Cruiser $ 150.00 $ 150.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75
44 140 cfm Compressor $ 250.00 $ 250.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50
45 250 cfm Compressor $ 250.00 $ 250.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75
46 4.5 kVA Diesel Generator $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38
47 100 kVA Diesel Generator $ 250.00 $ 250.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75
51 Poker Vibrator for Concrete, shaft diameter >60 mm $ 250.00 $ 250.00 $ 93.75 $ 750.00 $ 4,500.00 $ 18,525.00 $ 93.75
52 Jack hammer / Rock Drill >60 J impact $ 250.00 $ 250.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
53 Rebar cutter, maximum diameter 30 mm $ 250.00 $ 250.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75
54 Rebar bending machine, maximum diameter 30 mm $ 250.00 $ 250.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75
Page 23 of 25
Section IVA - Schedule of Prices Contract BOC-1962 - Ancillary Roads and Infrastructure
Revision 01
Rate (US$)
55 Chain blocks, up to 6.1m lift; 3 t $ 250.00 $ 250.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
56 Chain blocks, up to 6.1m lift; 4 t $ 250.00 $ 250.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
57 Pull lift (Tirfor type); 1.5 t $ 250.00 $ 250.00 $ 28.13 $ 225.00 $ 1,350.00 $ 5,557.50 $ 28.13
58 Pull lift (Tirfor type); 3 t $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
Articulated Boom Lift (manlift). Working height >20 m, lift capacity >225 kg,
59 horizontal reach >18 m, Up & Over Clearance >8.5 m. Genie (Terex) Z-80/60 or $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
equal
Slab Scissor Lift. Working height >8 m, lift capacity >350 kg, gradeability 30%.
60 $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
Genie (Terex) GS 2032 or equal
61 Total Station Leica TS 30 with all accessories $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38
62 Level, automatic, inclusive of staff Leica NA 700 $ 50.00 $ 50.00 $ 6.25 $ 50.00 $ 300.00 $ 1,235.00 $ 6.25
63 Survey equipment- pipe and cable locator, Radio detection RD 7000 $ 50.00 $ 50.00 $ 6.25 $ 50.00 $ 300.00 $ 1,235.00 $ 6.25
64 Communication set - 2 way Radio reach 2 km $ 50.00 $ 50.00 $ 6.25 $ 50.00 $ 300.00 $ 1,235.00 $ 6.25
65 Hydrotest equipment. High pressure test pump (30 bar) for piping $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
Confined Space Ventilator 12' diameter. Free air flow >70 m3/min. Inclusive of 8
66 $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
m duct hoses. Schaefer VAF 3000B or similar.
67 Hydraulic jack 30 t $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75
68 Paint spraying equipment $ 150.00 $ 150.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
Note 1 Mobilisation & Demobilisation Rates will only be applicable if Construction Equipment is not already located at site
Note 2 The above rates exclude the cost of operators or drivers
Note 3 The above rates are all-inclusive rates which shall be in compliance with all APPLICABLE LAWS
Note 4 The above rates are inclusive of Construction Equipment maintenance, repair, rental, insurance, taxes, etc. and any necessary consumables including, but not being limited to, fuel, lubricants, spare parts, etc
Note 5 COMPANY will compensate the lesser of the hourly, daily, weekly and monthly rate. At no time will COMPANY compensate CONTRACTOR in excess of the total monthly rate.
Note 6 Mobilisation & demobilisation will not be compensated under any cicumstances where N/A is marked by COMPANY in the appropriate column.
Page 24 of 25
Section IVA - Schedule of Prices Contract BOC-1962 - Ancillary Roads and Infrastructure
Revision 01
DIRECT MATERIALS
Note: CONTRACTOR shall be compensated for the net quantity and net invoiced cost of Materials delivered
to the Site in the performance of additional Work, supported by Vendor's invoice showing the actual
purchase price net, including any cash or trade discounts.
1.0 Mark-up including all cost for taking delivery, handling, storing and issuing of Materials delivered to the
Site in the performance of additional Works, including any allowances, overhead costs and profit or
any mark-up whatsoever. 18% (Mark up)
Note: CONTRACTOR shall be compensated for the provision of SUBCONTRACTOR/ Third Party Services for additional Works
as instructed by COMPANY either on or off-site for the net invoiced cost to CONTRACTOR by
the Third Party.
2.0 Mark-up including all costs for the provision of SUBCONTRACTOR/THIRD Party Services for additional Works,
including all overheads and profit, and any other margin or mark-up whatsoever. 18 % (Mark up)
Mark-up including all cost for taking delivery, handling, storing and issuing of Materials delivered to the
Site in the performance of additional Works, including any allowances, overhead costs and profit or
any mark-up whatsoever.
3.0 Mark-up including all cost for taking delivery, handling, storing and issuing of Materials delivered to the
Site in the performance of additional Works, including any allowances, overhead costs and profit or
any mark-up whatsoever. 18% (Mark up)
DEMOBILISATION & REMOBILISATION FEE (ref Section IV, Article 8.2) (Lump Sum, US$) $ 15,000.00
Page 25 of 25