Majnoon Oil Field BOC-

1962 Ancillary
Roads and Infrastructure

WORK ORDER PROPOSAL #001

DESIGN AND CONSTRUCTION OF SGTF NORTH ACCESS ROAD

001 Issued for Review 03-Jan-2024 Subodh S Monthir S Sudeep D


Rev. Reason For Issue Date Author Checker Approver

Rev.
BOC-1962-AA-9002-0001 001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Revision History

Revision
Revision Date Approver Summary of Changes
Number

03-Jan-2024 001 Sudeep First submission

Holds

Hold Ref. Description / Reason for Hold Ref. Section


HOLD 1
HOLD 2
HOLD 3

Reference Documents

Ref. Document Number Rev. Docume


nt Title
1 BOC-1962 Section V - Scope of Work Rev 2 Scope of Work

1 BOC-1962-AA-9001-001 Rev 1 Work Order Request

BOC-1962-AA-9002-0001 Page 2 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

WORK ORDER PROPOSAL#01

CONTRACTOR: MADAR ALFAYHAA FOR GENERAL WORK ORDER PROPOSAL


REF:
CONTRACTING.
CONTRACT No: BOC 1962 BOC-1962-AA-9002-0001
COMPANY WORK BOC-1962-AA-9001-001 CTR Ref:
REQUEST REF No:
REQUESTER: KBR BOC 1962
WBS CODE:
DATE: 16 OCTOBER 2023
In accordance with the above COMPANY Work Order Request, CONTRACTOR hereby provides a Work Order
Proposal to carry out the following WORK within the COST and schedule indicated and all in accordance with
the terms and conditions of the CONTRACT

Description of the
Services:
Design and Construction of SGTF North Access Road Including Landscaping and Irrigation

Schedule Requirements:

Required Start Date: 10 Jan 2024 Required 08 May 2024


completion
Date:
Remuneration:
Currency (US$)
Rate: As per contract.

Total Cost: 520,956.48 $

Other:

Resource:

Personnel Category:

This Work Order Proposal does not modify any of the terms and conditions of the CONTRACT, which shall
remain in full force and effect.

In witness hereof the Parties have signed this Work Order in duplicate.

For CONTRACTOR:

Position Name Signature Date

CONTRACTOR 03
REPRESENTATIVE Sudeep D Poojary Jan
2024

BOC-1962-AA-9002-0001 Page 3 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

TABLE OF CONTENTS
1.0 GENERAL .................................................................................... 5

2.0 PROJECT OVERVIEW ....................................................................... 5

3.0 ABBREVIATION.............................................................................. 6

4.0 REFERNCES .................................................................................. 6

4.1 COMPANY STANDARDS AND BASIC DESIGN ...................................... 6

4.2 INSPECTION TEST PLAN. ............................................................... 7

5.0 MOBILIZATION .............................................................................. 7

6.0 PROJECT ORGANIZATION ................................................................. 7

7.0 MANPOWER ................................................................................. 8

8.0 EQUIPMENT ................................................................................. 8

9.0 RESPONSIBLITIES ........................................................................ 9

10.0 ENGINEERING PHASE ..................................................................... 11

11.0 CONSTRUCTION PHASE .................................................................. 11

11.1 CONSTRUCTION SEQUENCE ......................................................... 12

12.0 TRAFFIC MANAGEMENT PLAN ........................................................... 12

13.0 TEMPORORY SITE FAICILITY............................................................. 13

14.0 EXECLUSION ............................................................................... 14

15.0 COMMERCIAL............................................................................... 14

16.0 SCHEDULE .................................................................................. 14

17.0 CONTRACT PRICING TABLE .............................................................. 14

BOC-1962-AA-9002-0001 Page 4 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

1.0 GENERAL
This Work Order Proposal is for Design and Construction of Design and Construction
of SGTF North Access Road in accordance with the Work Order request No. BOC-
1962-AA-9001-001.

All the construction works shall be executed in accordance with the SOW to the
approval of the Company and handed over to BOC.

2.0 PROJECT OVERVIEW


The CONTRACTOR shall design, widen the existing (unsurfaced) Access Road, and
construct a surfaced heavy- duty Access Road from Shams Road to the northern gate
of 8m wide and 1m shoulder in either side including. CONTRACTOR shall undertake
the following as per Scope of Work - Section V of CONTRACT BOC-1962 - Ancillary
Roads and Infrastructure, and project standards & specifications.

a) Information Gathering: The CONTRACTOR shall verify the Topographical


Survey, study the as-built drawings, and confirm that they are accurate and
highlight any obstacle that may require the CONTRACTOR's consideration and
action while developing the detailed design, including roadway investigation,
underground/above-ground services and facilities.

b) Detailed Design Phase: The CONTRACTOR is responsible for providing a


detailed design for this road, which includes, but is not limited to, the vertical
alignment, horizontal alignment, road cross sections, road marking and
signage, landscaping and its irrigation design, general arrangement, and
detailed design. All as per Scope of Work - Section V of CONTRACT BOC-
1962, clauses 3.2, 3.10, 3.11, 3.12 and, clause 8 stipulates the minimum design
requirements that must be met for all deliverables.

c) Construction Phase: Once the construction design has been approved, the
construction scope shall include, but not be limited to, the following:

o Provide Traffic Impact Assessment as stated in Scope of Work - Section


V of CONTRACT BOC-1962, clause 3.5.

o The CONTRACTOR shall submit a Traffic Management Plan prior to


the commencement of construction to ensure that all traffic is rerouted
to alternate routes.

o Complete the mobilization of site camp facilities as stated in Scope of


Work - Section V of CONTRACT BOC-1962, clauses 3.7 to 3.9 inc.

o Ploughing existing road surface.

o Levelling and grading of existing road surface.

o Topographical survey, setting out and compaction tests.

o Widening the existing road as per the AFC drawings

o Asphalting including prime coat, base course, tack coat and surface
course.
BOC-1962-AA-9002-0001 Page 5 of 17 Rev.:001
Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

o Construction of road shoulders, and side slopes.

o Supply of road signs and sign boards with foundation and installation.

o Supply of Road Markings

o Landscaping and Irrigation

3.0 ABBREVIATION.
COMPANY BOC
PMC KBR
CONTRACTOR MFCO
QCMP Quality Management Procedure
QCP Quality Control Procedure
ISD Information System Department
ITP Inspection and Test Plan
FLC Flow Chart
MS Method Statement
CAN Corrective Action Notice
CAR Corrective Action Request
NCR Non-conformance Report
RFI Request for Information
KPI Key Performance Indicator
QA Quality Assurance
QC Quality Control
IFC Issue For Construction
AFC Approved For Construction

4.0 REFERNCES
4.1 Company Standards and Basic Design
MGP1-PP2-KBR-C l-4018-0001-002, Access Road Layout Connecting SGTF, Power
Plant & MMPS
MGP1-PP2-KBR-C l-4018-0001-002, Access Road Layout Connecting Shams Road
and SGTF
MGP1-PP2-KBR-C l-4018-0001-003, Vertical Alignment Access Road Connecting
Shams Road and SGTF
Topographical survey for the north access and south access to SGTF
EPCM-ERW-00027-400, ERW Land Release Certificate.
MGP1-GEN-KBR-CX-7880-0002-001, General notes for Civil Works Abbreviations and
Legends
BOC-1962-AA-9002-0001 Page 6 of 17 Rev.:001
Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

MGP1-GEN-KBR-CX-7880-0004-001_003, Standard Details for Concrete Protection


MGP1-GEN-KBR-CX-7880-0012-001 & 002, Typical Road Sections Light Duty, and
Heavy Duty Roads
MGP1-GEN-KBR-CX-7880-0021, Specification for Concrete Works
MGP1-GEN-KBR-CX-7880-0022, Technical Specification for Earth Works
MGPl-GEN-KBR-CX-7880-0023, Technical Specifici3tion for Roads & Paving
MFD-GEN-FWK-CX-7880-0013-001_001. Cons RLM, Road Marking & Signage Typical
Details
MFD-GEN-FWK-CX-7880-0013-002_001. Cons RLM, Road Marking & Signage Typical
Details
MFD-GEN-FWK-CX-7880-0013-003_001. Cons RLM, Road Marking & Signage Typical
Details
MFD-GEN-FWK-CX-7880-0013-004_001. Cons RLM, Road Marking & Signage Typical
Details
MFD-GEN-FWK-CX-7880-0014-001_002. Cons RLM, Sign Board Mounting Foundation
and Structural Details
MFD-GEN-FWK-CX-7880-0014-002_001, Sign Board Mounting Foundation

4.2 Inspection Test Plan.

ANRD-INF-MFC-QA-5733-0001 ITP for Roads and Paving


ANRD-INF-MFC-QA-5733-0002 ITP for Earthworks

5.0 MOBILIZATION
Site facilities including site office, break out room, toilets, storage, power plants and
lay-down areas will be established. Site facilities to have an adequate waste collection
with segregation and disposal measures in place.

We will ensure that only the area allocated is utilised and that the set out is logical, has
easy ingress and egress, is easy to maintain and safe.

Project Manager

6.0 PROJECT ORGANIZATION

Contracting &
Construction Planing and Cost
HSE Manager QC Manager Procurement Security Focal Point Administrator Logistic Incharge
Engineer Manager
Engineer

HSE Supervisor QC Inspectors Foreman Security Accountant

Medic DC Surveyor

Foreman
BOC-1962-AA-9002-0001 Page 7 of 17 Rev.:001
Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

7.0 MANPOWER
Contractor will supply the necessary workforce for the project, comprising both the
approved indirect manpower by KBR and fully Health, Safety, and Environment (HSE)
trained direct manpower.

Personnel Numbe
r
Project Manager 1
Construction Supervisor 2
Site Foreman 1
First Aider 1
HSSE Site Supervisor 1
Permit Holder 1
Surveyor and Chainman 1
Plant Operators 10
General Labor 20

8.0 EQUIPMENT
The contractor will provide the required project equipment, ensuring full compliance with the
MFD safety requirements.

Plan Number
t
Tipper Trucks 6
Excavators 1
Front End Loaders 1
Dozer 1
Grader 2
Roller Compactor 3
Rubber Wheel Roller 3
Steel Roller 3
Water Tanker 2
Prime/tack coat Tanker 1
Asphalt Paver/Layer 1
Flat Bed Trailer 2
55t Crane 1
Hiab 1
Minibus 1
Pick Up 4
Light Truck 1

BOC-1962-AA-9002-0001 Page 8 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

9.0 RESPONSIBLITIES
Project Manager
Conduct HSE TBT with the full site Construction team to discuss the activities of the day,
highlighting the hazards and required controls to be in place.
Conduct daily production planning brief, prior to commencing work to discuss and ensure the
following:

• Daily production requirements.


• Work constraints.
• Availability of required resources.
• Allocation of responsibilities.
Verifying /updating of Construction Schedules and various resource requirements to meet the
required progress and production requirements.
Review short term Weekly/ Bi weekly and daily production Programs, agree with Project
Manager and review progress on a daily basis.

Coordinate with Planning and Procurement to schedule materials delivery on time. Overall
management and control of site store and materials.
Monitoring and controlling the use of Plant/ Equipment on Site, ensuring regular maintenance
is carried out. Monitoring and compiling relevant information on production rates.
Follow-up and implementation of safety procedures, aiming for Zero Accident and ensuring
compliance by all site personnel, take necessary disciplinary actions against any person failing
to adhere to safety requirements.
Reviews Purchase orders of site staff and signs site receipt documents.
Reviews the site quality department observations noted on the inspection reports, act to
remedy with the site staff in coordination with the QA/QC.
Ensures all activities are performed in accordance with the contract and the construction
schedule.
Implements and ensures that all personnel understand their responsibilities, comply with the
Project Quality Plan during all construction operations, and at all levels they are aware of their
responsibilities with regard to the quality system requirements.
Ensures all activities are performed in accordance with approved drawings and Documents
and ensures that only the latest revisions of approved ones are used.
Ensures no work is commenced before all approvals are received.
Ensures engineers regularly verify the calibration status of surveying instruments and other
used inspection and testing equipment and that a record of calibration is retained.
Verifies that all workers have adequate training and experience to perform appointed duties.
QA/QC Manager

BOC-1962-AA-9002-0001 Page 9 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Review Contract Specifications and Drawings identify product criteria and prepare required
checklist for inspection and testing.
Conduct daily site Inspection/walk through to monitor work in progress for compliance with
Specification and design/shop drawings, report any non-compliance. Aim for defect/ non-
compliance free product.
Receive and log Request for Inspection and process through during the same day. Coordinate
and perform Inspection and test activities in accordance with relevant Inspection Test Plan,
ensure that completed works is conformant and ready for final inspection.
Monitor status of inspection and follow-up on actions for re- submission, ensuring all required
actions are completed prior to re-submission.
Coordination with Test Laboratory for sampling. Monitor the Quality of materials received and
report any deviations from specified requirement.
Perform materials receiving Inspection/ test to verify compliance with the requirements of
Specification and / or approved submittal. Report non-compliance via the use of receiving
inspection report.
Monitor storage area and take necessary action to prevent damage.
Maintain quality records specified by relevant inspection test plans and contract documents.
Ensure all original copies of records are handed over to Document Controller.
Planning and coordination of Project Hand Over, and establish the required plans in
coordination with Project Manager.
During the Construction life cycle, perform the above duties to ensure that 95% of Inspections
Passed first time and prevent product defect.
HSSE Site Supervisor
Conduct TBT with full site Construction Team and ensure all hazards of the activities of the
day are identified and actions are in place and understood by the work force.
Inspect and audit all site operations to monitor compliance with HSSE Policy and execution
plan.
Inspect all relevant files, forms and registers required to be kept at site to ensure the routine
tests and inspections required by safety plan have duly been carried out and the results
properly recorded.
Monitor observance of site safety rules and issue warnings to workers, work supervisions, site
management staff and subcontractors for rectification purposes in case of non- compliance
and unsatisfactory safety performances. Site improvement notices shall be raised wherever
necessary.
Investigating all accidents/ incidents etc. and make necessary recommendation.
Promote the safe execution of work on site and provide safety induction training and safety
briefings to workers.
Produce daily and weekly HSSE site reports.

BOC-1962-AA-9002-0001 Page 10 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

10.0 ENGINEERING PHASE


The CONTRACTOR is responsible for providing a detailed design for this road, which includes, but is
not limited to, the vertical alignment, horizontal alignment, road cross sections, road marking and
signage, landscaping and its irrigation design, general arrangement, and detailed design. All as per
Scope of Work - Section V of CONTRACT BOC-1962, clauses 3.2, 3.10, 3.11, 3.12 and, clause 8 stipulates
the minimum design requirements that must be met for all deliverables.

Contractor will provide the below deliverables as per the project requirements.

ANRD-INF-MFC-CI-4018-0001 Key and Location Plan for SGTF Access Road


ANRD-INF-MFC-CI-4018-0002 Road Layout Plan for SGTF Access Road
Horizontal and Vertical Alignment Plan for SGTF Access
ANRD-INF-MFC-CI-4018-0003 Road
ANRD-INF-MFC-CI-4018-0004 Road Typical Cross Sections for SGTF Access Road
ANRD-INF-MFC-CI-4018-0005 Setting out Listings Plan for SGTF Access Road
ANRD-INF-MFC-CI-4018-0006 Traffic Signs Road Markings Layout for SGTF Access Road
ANRD-INF-MFC-CI-4018-0006 Traffic Signs Road Markings Layout for SGTF Access Road
Traffic Management Plan including Detouring for SGTF
ANRD-INF-MFC-CI-4018-0007 Access Road

11.0 CONSTRUCTION PHASE


Once the construction design has been approved, the construction scope shall include, but not be
limited to, the following:

o Provide Traffic Impact Assessment as stated in Scope of Work - Section V of


CONTRACT BOC-1962, clause 3.5.
o The CONTRACTOR will submit a Traffic Management Plan prior to the
commencement of construction to ensure that all traffic is rerouted to alternate
routes.
o Complete the mobilization of site camp facilities as stated in Scope of Work - Section
V of CONTRACT BOC-1962, clauses 3.7 to 3.9 inc.
o Ploughing existing road surface.
o Levelling and grading of existing road surface.
o Topographical survey, setting out and compaction tests.
o Widening the existing road as per the AFC drawings
o Asphalting including prime coat, base course, tack coat and surface course.
o Construction of road shoulders, and side slopes.
o Supply of road signs and sign boards with foundation and installation.
o Supply of Road Markings.

BOC-1962-AA-9002-0001 Page 11 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

11.1 Construction Sequence

ID Activity Name

Civil Construction Works


Traffic Management
Civ-Tem-1 Establishing Alternative Road in South Gate
Survey Works
Civ-Suv-1 Projection The Road Coordinates
Civ-Suv-2 Check Out the G.L.
Earth Works
Civ-Ear-1 Compcat Sub Grade to 95% MDD
Civ-Ear-2 Compaction Test for Sub Garde
Civ-Ear-3 Lay Geotextile
Civ-Ear-4 1st Layer Structural Backfilling Class A 20cm
Civ-Ear-5 Compact 1st Layer
Civ-Ear-6 Compaction Test for 1st Layer
Civ-Ear-7 2nd Layer Structural backfilling Calss A 15cm
Civ-Ear-8 Compact 2st Layer
Civ-Ear-9 Compaction Test for 2nd Layer
Civ-Ear-10 Lay Geogrid
Road Surface Works
Civ-Sfac-1 Lay Road Base 15cm
Civ-Sfac-2 Prime Coat Gride MC70
Civ-Sfac-3 Lay Binder Course 10cm
Civ-Sfac-11 Compcat Binder Course
Civ-Sfac-4 Tack Coat
Civ-Sfac-5 Surface Course 50 mm
Civ-Sfac-15 Compact Surface Course
Road Shoulders
Civ-Shoul-1 Structural Backfilling Class A 15cm For Shoulders
Civ-Shoul-2 Compact Shoulders Layer
Civ-Shoul-3 Compaction Test for Shoulders
Road Marking
Civ-Mrk-1 Surface Road Marking
Civ-Mrk-2 Install Traffic Signs
Civ-Mrk-3 Touch-Up painting

12.0 TRAFFIC MANAGEMENT PLAN


The proposed Traffic Management Plan which should be based on the following:

Utilizing the southern access which involves the Reinstatement of the south side access road.

BOC-1962-AA-9002-0001 Page 12 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

1. Supply & Install New security 12mx3m cabin and (Existing Cabin need to be operate during
change of Access from SGTF North side to SGTF South side)
2. Re Locate 3mx3m Guard Rest Cabin
3. Supply and install 50 Number T-Walls
4. Provide Electric Power From located Steel Guard Tower (if possible) which is at 75m from
Southern Gate.
5. If Electrical Power from existing Guard not possible; that mean checking for another electrical
power sources.
6. Relocated one of Existing Drop arm Barrier.
7. Relocate existing 14 No. Jersy Barriers
8. Construct 50mx30m Car Park area which includes Grading; Backfilling 0.2m thick Gatch B
Materials
9. Backfilling existing Security Ditch Infront of Gate so Traffic will be smoothly.
10. Construct new road from Southern Gate to the existing Gatch road (Length 150m and width
20m Thick 1m)
11. Supply and Install New Pedestrian Gate.
12. Relocate 2 Lighting poles including Electrical wiring.

SGTF NORTHSIDE REQUIREMENTS:

1. Move the existing 14 Jersey Barriers to the Southern Gate.


2. Transfer 1 steel drop arm barrier to the Southern Gate.
3. Eliminate one lighting pole.
4. Shift the 3mx3m Guard Rest Cabin to the Southern Gate.
5. The suggested position for the Concrete Gate will be to the north before the Security Ditch,
with coordinates as follows:
X: 751959.734, Y: 3443372.742
X: 751973.734, Y: 3443372.742

SGTF NORTHSIDE REQUIREMENTS:

1. Grading Access service Road


2. Removal surplus Graded Materials out site to suitable dumping area
3. Backfilling one Layer Gatch B Materials

13.0 TEMPORORY SITE FAICILITY


The Site Office facilities for CONTRACTOR will be constructed as part of the initial infrastructure
development. CONTRACTOR will manage this construction through its Construction Management
team office as per the COMPANY standards and norms for the entire duration of the CONTRACT.

All facilities shall meet all applicable health, safety, security, environment, and social performance
regulations and fully conform to the requirements of the CONTRACT and Section VIII – HSSE & SP and
Section XV - Contract Reference Documents in particular.

BOC-1962-AA-9002-0001 Page 13 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

14.0 EXECLUSION
The contractor has removed landscaping and irrigation from the work order proposal, as these
elements will be addressed in a separate work order proposal associated with BOC-1962-AA-9002-
0001-SGTF and MCPP External Infrastructure Arrangement.

15.0 COMMERCIAL
Please see Anexure-1

16.0 SCHEDULE
Please see Anexure-2

17.0 CONTRACT PRICING TABLE


Please see Anexure-3

BOC-1962-AA-9002-0001 Page 14 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Anexure-1

BOC-1962-AA-9002-0001 Page 15 of 17 Rev.:001


Uncontrolled when printed or stored locally
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Work Order Proposal For Traffic Management


( Material & Manpower )
Summery
Location : Majnoon Oil field Contract ref:
Project Title : Ancillary Roads and Infrastructure BOC-1962
Date : 03 Jan 2024
SL# Work Description Total Price
1 Design and Construction of SGTF North Access Road $ 347,130.48
2 Diversion of Traffic from North to South Gate $ 135,601.00
3 Diversion of Traffic from North to South Gate (Supply & Manpower) $ 38,225.00
Total $ 520,956.48

BOC-1962-AA-9002-0001 Rev.:001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Work Order Proposal for SGTF Road

Location : Majnoon Oil field Contract ref: BOC-1962


Project Title : Ancillary Roads and Infrastructure Date : 03 Jan 2024
Rate (US$)
Number Discription
Unit QTY Unit Price Total Price Ref. Doc Remark
PRICING TABLE 1: LUMP SUM RATE FOR MOBILISATION
1 Mobilisation sum 1 15000 15000
PRICING TABLE 2: LUMP SUM RATE FOR DEMOBILISATION
1 Demobilisation sum 1 15000 15000
PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES
A GENERAL ITEMS
A1 Design Works
A1.2 Design Works for SGTF ACCESS ROAD sum 1 3000 3000
E EARTHWORKS
All earthworks shall be performed in accordance with MGP1-GEN-KBR-CX-7880-0022, Specification for
E1
Earthworks

E1.1
Site preparation (following ERW clearance) including levelling, rolling and MGP1-PP2-KBR-CI-4018-0001-003
m2 4880 2 9760
compacting sub-grade for Well Pad and General Areas MGP1-PP2-KBR-CI-4018-0001-004

Excavation in material other than topsoil, rock or artificial hard material including
ACAD_RSK-182680-TOPO-SGTF ACCESS
E1.3 trimming of surfaces and disposal of excavated material to on-site disposal area M3 20 2.5 50
ROAD-R1-Model-Model
distance <15km, depth <5m.
R ROADS AND PAVINGS - Within Well Pad Limits
Road construction as per drawings MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Light & Heavy
R1 Duty Roads, MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Temporary & Patrol Roads and in
accordance with MGP1-GEN-KBR-CX-7880-0023, Specification for Roads and Paving

Sub-bases, flexible road bases and surfacing. Granular material Class A Road 1010.16 28.00
MGP1-PP2-KBR-CI-4018-0001-002
R1.1 m3 28284.48
Base. MGP1-PP2-KBR-CI-4018-0001-004

Geotextile. Supply and installation of nonwoven geotextile, UV stabilised, tensile


strenght minimum 12.5 kN/m, tensile elongation maximum 60%, CBR punture 4880.00 5.00
MGP1-PP2-KBR-CI-4018-0001-002
R1.4 m2 24400
resistance minimum 2250 N and permeability 65 l/m2s. Terram 1500 or similar. MGP1-PP2-KBR-CI-4018-0001-004
The area of additional geotextile in laps shall not be measured.

Geogrid. Max Tensile Strength ≥40 / ≥40 kN/m. Elongation at nominal strength,
md/cmd ≤8 / ≤8 %. Tensile strength at 2% elongation, md/cmd ≥13 / ≥13 kN/m.
Tensile strength at 5% elongation, md/cmd ≥26 / ≥26 kN/m, all to DIN EN ISO MGP1-PP2-KBR-CI-4018-0001-002
R1.5 10319 UV-resistance (remaining tensile strength) BS EN 12224 96.3 %. Weather m2 4880.00 5.50 26840
MGP1-PP2-KBR-CI-4018-0001-004
resistance, FGSV, Class, high.

MGP1-PP2-KBR-CI-4018-0001-002
R1.8 Surfacing. Hot rolled asphalt base course. Depth: 100 mm. m3 3904.00 22.00 85888
MGP1-PP2-KBR-CI-4018-0001-004

MGP1-PP2-KBR-CI-4018-0001-002
R1.9 Surfacing. Hot rolled asphalt wearing course. Depth: 50 mm m2 3904.00 11.00 42944
MGP1-PP2-KBR-CI-4018-0001-004

Sub-bases, flexible road bases and surfacing. Bituminous spray. Prime coat grade 3904.00 3.50
MGP1-PP2-KBR-CI-4018-0001-002
R1.11 m2 13664
MC70. MGP1-PP2-KBR-CI-4018-0001-004

Ancillaries. Traffic Signs (inclusive of all foundation, supporting posts, excavation, etc. as per rule C9) and
surface markings as per drawings MFD-GEN-FWK-CX-7880-0013-001-001 to 004, MFD Road Marking &
R3
Signage Typical Details and MFD-GEN-FWK-CX-7880-0014-001&2-001, MFD Sign Board Mountaing
Foundation & Structural Details

Non illuminated. Regulatory sign type R1 to R6, R13 to R 18 and R 20. Warning 3.00 500.00 1500 MGP1-PP2-KBR-CI-4018-0001-002
R3.1 nr. MGP1-PP2-KBR-CI-4018-0001-004
Sign type W1 to W 14
500.00 1000 MGP1-PP2-KBR-CI-4018-0001-002
R3.3 Non illuminated. Regulatory sign type R7 & R8 nr. 2 MGP1-PP2-KBR-CI-4018-0001-004

Ancillaries. Surface markings. Road Paint. White or yellow reflective road marking paint DFT 0.3 mm with
R4
surface applied glass beads 400 g/m2

R4.1
MGP1-PP2-KBR-CI-4018-0001-002
Ancillaries. Surface markings. Reflective road studs nr. 220.00 23.00 5060
MGP1-PP2-KBR-CI-4018-0001-004

R4.2
Ancillaries. Surface markings. Letters and shapes RM1 to RM4 nr. 4.00 39.00 156

R4.6
Ancillaries. Surface markings. Continuous lines. Yellow edge of carriageway line 976.00 12.00
MGP1-PP2-KBR-CI-4018-0001-002
m 11712
wide 150 mm RM7 MGP1-PP2-KBR-CI-4018-0001-004

R4.7
Ancillaries. Surface markings. Continuous lines. White center of carriageway line 976.00 12.00
MGP1-PP2-KBR-CI-4018-0001-002
m 11712
wide 150 mm RM8 MGP1-PP2-KBR-CI-4018-0001-004

R4.8
Ancillaries. Surface markings. Intermittent lines. White center of carriageway line 58.00 20.00
MGP1-PP2-KBR-CI-4018-0001-002
m 1160
wide 150 mm RM8 MGP1-PP2-KBR-CI-4018-0001-004

A2 Temporary Works Requirements


A2.4
Traffic diversions work per location, include establishment and removal of traffic
signs (5x), warning signs (5x), directional signs (5x) to direct all traffic during the 6.00 3300.00
wk 19800 ANRD-INF-MFC-CI-4018-0007
period of work as required by Company. Includes for supply of 2 each trained
flagman.

A4 Method Related Charges: Plant


A4.1
Cranes Mobilisation of all craneage required to execute the Contract including
telescopic mobile cranes, crawler cranes and truck mounted mobile cranes in sum 1.00 5000.00 5000
capacities from 20t to 250t as required to perform the works.
A4.2
Cranes Demobilisation of all craneage required to execute the Contract including
telescopic mobile cranes, crawler cranes and truck mounted mobile cranes in sum 1.00 5000.00 5000
capacities from 20t to 250t as required to perform the works.

A4.3 Asphalting. Mobilisation of Asphalt Paving plant, Caterpillar AP500E, spreading


sum 1.00 5000.00 5000
width 3.5 m.
A4.4 Asphalting. Demobilisation of Asphalt Paving plant, Caterpillar AP500E,
sum 1.00 5000.00 5000
spreading width 3.5 m.
A4.5
Earthmoving. Mobilisation of all Earthmoving Equipment as required for the
Contract, including but not limited to, Excavators, Bulldozers, Loaders, Graders, sum 1.00 4500.00 4500
Vibratory Soil Compactors, Wheel Loaders, Asphalt Cutting Machines etc..

A4.6
Earthmoving. Demobilisation of all Earthmoving Equipment as required for the
Contract, including but not limited to, Excavators, Bulldozers, Loaders, Graders, sum 1.00 4500.00 4500
Vibratory Soil Compactors, Wheel Loaders, Asphalt Cutting Machines, etc.

B2 Laboratory testing

Samples. From the surface, or from trial pits or trenches. Sample size 10 kg.
B2.1 nr 10.00 120.00 1200
Class 3 to BS 5930
Total $ 347,130.48

BOC-1962-AA-9002-0001 Rev.:001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Work Order Proposal For Traffic Management (1-2)


Location : Majnoon Oil field Contract ref: BOC-1962
Project Title : Ancillary Roads and Infrastructure Date : 03 Jan 2024
Sr. No Ref Number Item Description Unit QTY Unit Price Total Price Ref. Remark

Service Road Fron SGTF North side to SGTF South Side ( 360m)
PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

1 E EARTHWORKS

2 E1 All earthworks shall be performed in accordance with MGP1-GEN-KBR-CX-7880-0022, Specification for Earthworks

3 E1.1
Site preparation (following ERW clearance) including levelling, rolling and 7,200.00
m2 3600 2 ANRD-INF-MFC-CI-4018-0007
compacting sub-grade for Well Pad and General Areas

Excavation in material other than topsoil, rock or artificial hard material


4 E1.3 including trimming of surfaces and disposal of excavated material to on-site m3 180 2.5 450.00 ANRD-INF-MFC-CI-4018-0007
disposal area distance <15km, depth <5m.
5 E1.19 Filling using imported granular material Type B m3 720.00 22.00 15,840.00 ANRD-INF-MFC-CI-4018-0007
SGTF South Gate
6 E EARTHWORKS
All earthworks shall be performed in accordance with MGP1-GEN-KBR-CX-7880-0022, Specification
7 E1
for Earthworks

Site preparation (following ERW clearance) including levelling, rolling and 1500.00 2.00 3,000.00
8 E 1.1 m2 ANRD-INF-MFC-CI-4018-0007
compacting sub-grade for Well Pad and General Areas

Filling to embankments using selected excavated material, structural fill,


9 E1.16 from Company provided borrow pit or other excavations. Distance not m3 225.00 8.00 1,800.00 ANRD-INF-MFC-CI-4018-0007
exceeding 5 km.
10 E1.19 Filling using imported granular material Type B m3 720.00 22.00 15,840.00 ANRD-INF-MFC-CI-4018-0007
11 E1.19 Filling using imported granular material Type B m3 2888.00 22.00 63,536.00 ANRD-INF-MFC-CI-4018-0007
12 H PRECAST CONCRETE
Precast concrete elements are typically pipe supports/sleeper, light pole foundations, CCTV
13 H foundations, instrument foundations, T-walls, Jersey barriers and various foundation & pavement
slabs.

Supply Precast 3m high T-walls as per MGP1-GEN-KBR-CG-4017-1037- 50.00 385.00 19,250.00


14 H1.5 no ANRD-INF-MFC-CI-4018-0007
001 Typical T-wall & Stelcon slab GA & RC details
1. Place, remove or re-
position T-walls
Place, remove or re-position T-walls& Jersey Barriers within Well Pad 117.00 55.00 6,435.00 (50X1.5=75mtr)
15 H1.10 mtr. ANRD-INF-MFC-CI-4018-0007
footprint (to separate phased quadrant works) 2. Relocate of Jersey
Barrier (14*3=42 m)
16 X MISCELLANEOUS WORK

Fences to BS 1722-10:2006. Zinc coated mesh wire, mesh size 40-50 mm, zinc coated wire, diameter
3.0 mm. Zinc coated line wire, diameter 4.00 mm. Zinc coated stirrup wire, diameter 2.5 mm. Zinc
17 X1
coated tying wire, diameter 1.60 mm. Inclusive of all fittings. Other details as per MGP1-GEN-KBR-
CX-7880-0007 , Standard Detail for Single Chain link Fence

Supply & Install 10 meter steel light pole c/w required electrical connection 1.00 1500.00 1,500.00
18 X2.31 no ANRD-INF-MFC-CI-4018-0007
and junction boxes

19 F IN SITU CONCRETE

Concrete, formwork and reinforcement steel supply and installation shall be in accordance with
20 F MGP1-GEN-KBR-CX-7880-0021, Specification for Concrete Works and MGP1-GEN-KBR-CX-7880-
0002, Standard Drawing General Notes for Civil Works Abbreviations and Legends.

Supply, place, compact, level, cure Grade C16 blinding concrete with A252
21.0 F1.1 m3 3.00 250.00 750.00 ANRD-INF-MFC-CI-4018-0007 For Pedestain Gate
mesh < 100mm thick

Total $ 135,601.00

BOC-1962-AA-9002-0001 Rev.:001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Work Order Proposal For Traffic Management (2-2)


( Material & Manpower )
Contract ref:
Location : Majnoon Oil field BOC-1962
Project Title : Ancillary Roads and Infrastructure Date : 03 Jan 2024

Sr. No. CATEGORY Total Amount


LS Qty. Remark
(USD)
PRICING TABLE 4: UNIT RATES FOR CONSTRUCTION PERSONNEL

Work Discription

Supply deliver & Installation 40ft Guard Caravan Including Manpower & Equipment
1 20850.00 1 20850.00
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.

Relocate of 3mx3m Guard rest caravan including Manpower & Equipment


2 1800 1 1800
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.

Supply and Install New Lighting Pole including Manpower & Equipment
3 2400 1 2400
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.

Relocate Lighting Pole work including Manpower & Equipmen.


4 1650 1 1650
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.

Supply and Lay 3Core 25mm2 Electrical Cable work including Manpower & Equipment.
5 6750 1 6750 75 Mtr length
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.

Relocate Drop Arm Barrier work including Manpower & Equipment.


6 1750 1 1750
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.

Supply & Installation width Pedestarin Gate work including Manpower & Equipment
7 3025 1 3025
Note : Invoice will be claimed based on Pricing Table 4 and Pricing Table 6.

Grand Total $ 38,225.00

BOC-1962-AA-9002-0001 Rev.:001
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Anexure-2

BOC-1962-AA-9002-0001 Page 16 of 17 Rev.:001


Uncontrolled when printed or stored locally
PROJECT CODE:ANRD
PROJECT NAME: BOC 1962 - Ancillary Roads and
Infrastructure
Activity ID Activity Name Planned Duration Start Finish Total Float PredecessorsSuccessors Activity Check 2024
Jan Feb Mar Apr May
109 10-Jan-24 06-May-24 0 06-May-24, B
BOC-1962 SGTF Access Road Traffic
109 10-Jan-24 06-May-24 0 06-May-24, B
BOC-1962.1 key Milestones
BOC-1962.1.1 WO1 (SGTF Road) 109 10-Jan-24 06-May-24 0 06-May-24, B
Kmil-1 Call off Effective Date (WO1) 0 10-Jan-24* 0 Kmil-3, Kmil-26, Kmil-36 Call off Effective Date (WO1), 10-Jan-24*
Kmil-3 Mobilization Start 0 10-Jan-24 3 Kmil-1 A1370, A1380 Mobilization Start, 10-Jan-24
Kmil-26 Start of Engineering 0 10-Jan-24 84 Kmil-1 Eng-14 Start of Engineering, 10-Jan-24
Kmil-36 Start of Procurement 0 10-Jan-24 0 Kmil-1 A1000, A1070, A1140, A1210, A1280
Start of Procurement, 10-Jan-24
Kmil-46 End of Engineering 0 03-Feb-24 84 Eng-64 Kmil-6 End of Engineering,
Kmil-56 End of Procurement 0 06-Feb-24 81 A1060, A1130,
Kmil-6
A1200, A1270, A1340 End of Procurement,
Kmil-16 Mobilization Finish 0 13-Feb-24 0 A1450, Mob-3
Kmil-2 Mobilization Finish,
Kmil-2 Start of Construction 0 14-Feb-24 0 Kmil-16 A1350 Start of Construction, 14-Feb-24
Kmil-4 End of Construction 0 24-Apr-24 0 Civ-Mrk-2 Kmil-6, Hovr-2 End of Constructi
Kmil-6 Call off Finish 0 06-May-24 0 Kmil-46, Kmil-56, Kmil-4, Hovr-1 Call off Finis
25 10-Jan-24 03-Feb-24 84 03-Feb-24, BOC-1962.2 Engineering
BOC-1962.2 Engineering
BOC-1962.2.2 WO1 SGTF Road 25 10-Jan-24 03-Feb-24 84 03-Feb-24, BOC-1962.2.2 WO1 SGTF Road
BOC-1962.2.2.1 Design Drawings 25 10-Jan-24 03-Feb-24 84 03-Feb-24, BOC-1962.2.2.1 Design Drawings
Eng-14 Issue for IDC 1 10-Jan-24 10-Jan-24 84 Kmil-26 Eng-24 Issue for IDC
Eng-24 Issue for Review (IFR) 7 11-Jan-24 17-Jan-24 84 Eng-14 Eng-34 Issue for Review (IFR)
Eng-34 Recieve Comments 5 18-Jan-24 22-Jan-24 84 Eng-24 Eng-44 Recieve Comments
Eng-44 Issue for Approval (IFA) 5 23-Jan-24 27-Jan-24 84 Eng-34 Eng-54 Issue for Approval (IFA)
Eng-54 Recieve Approval 5 28-Jan-24 01-Feb-24 84 Eng-44 Eng-64 Recieve Approval
Eng-64 AFC 2 02-Feb-24 03-Feb-24 84 Eng-54 Kmil-46 AFC
28 10-Jan-24 06-Feb-24 68 06-Feb-24, BOC-1962.3 Procurement
BOC-1962.3 Procurement
BOC-1962.3.6 WO1 SGTF Road 28 10-Jan-24 06-Feb-24 68 06-Feb-24, BOC-1962.3.6 WO1 SGTF Road
BOC-1962.3.6.2 Procurement of Thermoplastic paint 28 10-Jan-24 06-Feb-24 64 06-Feb-24, BOC-1962.3.6.2 Procurement of The
A1070 Material Requesition 5 10-Jan-24 14-Jan-24 64 Kmil-36 A1080 Material Requesition
A1080 RFQ 5 15-Jan-24 19-Jan-24 64 A1070 A1090 RFQ
A1090 TBE 2 20-Jan-24 21-Jan-24 64 A1080 A1100 TBE
A1100 PO Placement 2 22-Jan-24 23-Jan-24 64 A1090 A1110 PO Placement
A1110 Manufacturing 5 24-Jan-24 28-Jan-24 64 A1100 A1120 Manufacturing
A1120 Inspection & Packing 2 29-Jan-24 30-Jan-24 64 A1110 A1130 Inspection & Packing
A1130 ETA 7 31-Jan-24 06-Feb-24 64 A1120 Kmil-56, Civ-Mrk-1 ETA
BOC-1962.3.6.1 Procurement of Traffic Signs 28 10-Jan-24 06-Feb-24 68 06-Feb-24, BOC-1962.3.6.1 Procurement of Traff
A1000 Material Requesition 5 10-Jan-24 14-Jan-24 68 Kmil-36 A1010 Material Requesition
A1010 RFQ 5 15-Jan-24 19-Jan-24 68 A1000 A1020 RFQ
A1020 TBE 2 20-Jan-24 21-Jan-24 68 A1010 A1030 TBE
A1030 PO Placement 2 22-Jan-24 23-Jan-24 68 A1020 A1040 PO Placement
A1040 Manufacturing 5 24-Jan-24 28-Jan-24 68 A1030 A1050 Manufacturing
A1050 Inspection & Packing 2 29-Jan-24 30-Jan-24 68 A1040 A1060 Inspection & Packing
A1060 ETA 7 31-Jan-24 06-Feb-24 68 A1050 Kmil-56, Civ-Mrk-2 ETA
BOC-1962.3.6.3 Procurement of Geotextile 28 10-Jan-24 06-Feb-24 14 06-Feb-24, BOC-1962.3.6.3 Procurement of Geo
A1140 Material Requesition 5 10-Jan-24 14-Jan-24 14 Kmil-36 A1150 Material Requesition
A1150 RFQ 5 15-Jan-24 19-Jan-24 14 A1140 A1160 RFQ
A1160 TBE 2 20-Jan-24 21-Jan-24 14 A1150 A1170 TBE
A1170 PO Placement 2 22-Jan-24 23-Jan-24 14 A1160 A1180 PO Placement
A1180 Manufacturing 5 24-Jan-24 28-Jan-24 14 A1170 A1190 Manufacturing

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 3 Date Revision Checked Approved

Primary Baseline Remaining Work Baseline Milestone TASK filter: All Activities
PROJECT CODE:ANRD
PROJECT NAME: BOC 1962 - Ancillary Roads and
Infrastructure
Activity ID Activity Name Planned Duration Start Finish Total Float PredecessorsSuccessors Activity Check 2024
Jan Feb Mar Apr May
A1190 Inspection & Packing 2 29-Jan-24 30-Jan-24 14 A1180 A1200 Inspection & Packing
A1200 ETA 7 31-Jan-24 06-Feb-24 14 A1190 Kmil-56, Civ-Ear-3 ETA
BOC-1962.3.6.4 Procurement of Geogrid 28 10-Jan-24 06-Feb-24 14 06-Feb-24, BOC-1962.3.6.4 Procurement of Geo
A1210 Material Requesition 5 10-Jan-24 14-Jan-24 14 Kmil-36 A1220 Material Requesition
A1220 RFQ 5 15-Jan-24 19-Jan-24 14 A1210 A1230 RFQ
A1230 TBE 2 20-Jan-24 21-Jan-24 14 A1220 A1240 TBE
A1240 PO Placement 2 22-Jan-24 23-Jan-24 14 A1230 A1250 PO Placement
A1250 Manufacturing 5 24-Jan-24 28-Jan-24 14 A1240 A1260 Manufacturing
A1260 Inspection & Packing 2 29-Jan-24 30-Jan-24 14 A1250 A1270 Inspection & Packing
A1270 ETA 7 31-Jan-24 06-Feb-24 14 A1260 Kmil-56, Civ-Ear-3 ETA
BOC-1962.3.6.5 Procurement of Camp 28 10-Jan-24 06-Feb-24 0 06-Feb-24, BOC-1962.3.6.5 Procurement of Cam
A1280 Material Requesition 5 10-Jan-24 14-Jan-24 0 Kmil-36 A1290 Material Requesition
A1290 RFQ 5 15-Jan-24 19-Jan-24 0 A1280 A1300 RFQ
A1300 TBE 2 20-Jan-24 21-Jan-24 0 A1290 A1310 TBE
A1310 PO Placement 2 22-Jan-24 23-Jan-24 0 A1300 A1320 PO Placement
A1320 Manufacturing 5 24-Jan-24 28-Jan-24 0 A1310 A1330 Manufacturing
A1330 Inspection & Packing 2 29-Jan-24 30-Jan-24 0 A1320 A1340 Inspection & Packing
A1340 ETA 7 31-Jan-24 06-Feb-24 0 A1330 Kmil-56, A1400 ETA
109 10-Jan-24 06-May-24 0 06-May-24, B
BOC-1962.5 Construction
BOC-1962.5.7 Mobilization 35 10-Jan-24 13-Feb-24 0 13-Feb-24, BOC-1962.5.7 Mobilization
BOC-1962.5.7.1 Camp & Resources Mob. 35 10-Jan-24 13-Feb-24 0 13-Feb-24, BOC-1962.5.7.1 Camp & Resourc
A1370 Manpower Mobilization to site 2 10-Jan-24 11-Jan-24 3 Kmil-3 A1390, A1460, A1470 Manpower Mobilization to site
A1380 Equipment Mobilization to site 2 10-Jan-24 11-Jan-24 3 Kmil-3 A1390, A1460, A1470 Equipment Mobilization to site
A1390 Site Preparation & Grading 3 12-Jan-24 14-Jan-24 23 A1380, A1370
A1400 Site Preparation & Grading
A1400 Caravans Erection 2 07-Feb-24 08-Feb-24 0 A1390, A1340
A1410, A1430, Mob-3 Caravans Erection
A1410 Generator installation 1 09-Feb-24 09-Feb-24 2 A1400 A1420 Generator installation
A1430 Installation of Septic Tank 1 09-Feb-24 09-Feb-24 1 A1400 A1440 Installation of Septic Tank
A1420 Utility electrical works 1 10-Feb-24 10-Feb-24 2 A1410 A1450 Utility electrical works
A1440 Plumping Works 2 10-Feb-24 11-Feb-24 1 A1430 A1450 Plumping Works
A1450 Furniture supply & Installation 1 12-Feb-24 12-Feb-24 1 A1420, A1440
Kmil-16 Furniture supply & Installation
Mob-3 Fenceing Works 5 09-Feb-24 13-Feb-24 0 A1400 Kmil-16 Fenceing Works
BOC-1962.5.2 SGTF traffic Diversion Arrangements 32 12-Jan-24 12-Feb-24 3 12-Feb-24, BOC-1962.5.2 SGTF traffic Diversio
BOC-1962.5.2.1 Service Road From SGTF North side to SGTF South Side 8 12-Jan-24 19-Jan-24 27 19-Jan-24, BOC-1962.5.2.1 Service Road From SGTF N
A1480 Excavation in material other than topsoil 1 12-Jan-24 12-Jan-24 30 A1460 A1490 Excavation in material other than topsoil
A1460 Site preparation 4 12-Jan-24 15-Jan-24 27 A1370, A1380
A1480, A1490 Site preparation
A1490 Back filling 20mm thick Class B 4 16-Jan-24 19-Jan-24 27 A1460, A1480
A1360 Back filling 20mm thick Class B
BOC-1962.5.2.2 SGTF South Gate 32 12-Jan-24 12-Feb-24 3 12-Feb-24, BOC-1962.5.2.2 SGTF South Gate
A1500 Trench Fill in g to embankments usin g selected Borrow Pit material 1 12-Jan-24 12-Jan-24 19 A1470 A1520 Trench Fill in g to embankments usin g selected Borrow Pit ma
A1470 Site preparation Parking Area and Existing Road 2 12-Jan-24 13-Jan-24 3 A1380, A1370
A1500, A1510, A1520, A1550 Site preparation Parking Area and Existing Road
A1550 Electrical Power 5 12-Jan-24 16-Jan-24 26 A1470 A1590 Electrical Power
A1590 Relcoate 1 Light Pole 2 17-Jan-24 18-Jan-24 26 A1550 A1600 Relcoate 1 Light Pole
A1600 Supply and Install 1 Light Pole 2 19-Jan-24 20-Jan-24 26 A1590 A1360 Supply and Install 1 Light Pole
A1510 Class B Extend Existing road to southren Gate&Car Park 17 12-Jan-24 28-Jan-24 3 A1470 A1520 Class B Extend Existing road to southren Gate&Car P
A1520 Supply and Install Pedestarin Gate 2 29-Jan-24 30-Jan-24 3 A1510, A1470,
A1530
A1500 Supply and Install Pedestarin Gate
A1530 Relocate of Jersey Barrier 2 31-Jan-24 01-Feb-24 3 A1520 A1540 Relocate of Jersey Barrier
A1540 Relocate Drop Arm Barrier 1 02-Feb-24 02-Feb-24 3 A1530 A1560 Relocate Drop Arm Barrier
A1560 Supply and Install 12mx3m Guard Cabin 3 03-Feb-24 05-Feb-24 3 A1540 A1570 Supply and Install 12mx3m Guard Cabin

Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 3 Date Revision Checked Approved

Primary Baseline Remaining Work Baseline Milestone TASK filter: All Activities
PROJECT CODE:ANRD
PROJECT NAME: BOC 1962 - Ancillary Roads and
Infrastructure
Activity ID Activity Name Planned Duration Start Finish Total Float PredecessorsSuccessors Activity Check 2024
Jan Feb Mar Apr May
A1570 Supply and Install 50 T-Wall 5 06-Feb-24 10-Feb-24 3 A1560 A1580 Supply and Install 50 T-Wall
A1580 Relocate 3x3 Guard Cabin Rest 2 11-Feb-24 12-Feb-24 3 A1570 A1360 Relocate 3x3 Guard Cabin Rest
BOC-1962.5.9 WO1 SGTF Road 74 14-Feb-24 06-May-24 0 06-May-24, B
BOC-1962.5.9.1 Civil Works 55 14-Feb-24 12-Apr-24 0 12-Apr-24, BOC-1962.
BOC-1962.5.9.1.1 Earth Works 7 14-Feb-24 20-Feb-24 0 20-Feb-24, BOC-1962.5.9.1.1 Earth Works
BOC-1962.5.9.1.1.1 Site Preparations 3 14-Feb-24 16-Feb-24 0 16-Feb-24, BOC-1962.5.9.1.1.1 Site Prepara
A1350 Project the road coordinates 2 14-Feb-24 15-Feb-24 0 Kmil-2 A1360 Project the road coordinates
A1360 Area preparations 1 16-Feb-24 16-Feb-24 0 A1350, A1580,
Civ-Ear-1
A1600, A1490 Area preparations
BOC-1962.5.9.1.1.2 Sub-Grade 4 17-Feb-24 20-Feb-24 0 20-Feb-24, BOC-1962.5.9.1.1.2 Sub-Grade
Civ-Ear-1 Compact Sub Grade to 95% MDD 4 17-Feb-24 20-Feb-24 0 A1360 Civ-Ear-3, Civ-Ear-2 Compact Sub Grade to 95% MDD
BOC-1962.5.9.1.2 Sub Base 12 20-Feb-24 03-Mar-24 1 03-Mar-24, BOC-1962.5.9.1.2 Sub Ba
Civ-Ear-3 Lay Geotextile 2 20-Feb-24 22-Feb-24 0 A1270, A1200,
Civ-Ear-13
Civ-Ear-1 Lay Geotextile
Civ-Ear-13 Lay Geogrid 2 22-Feb-24 24-Feb-24 0 Civ-Ear-3 Civ-Ear-4 Lay Geogrid
Civ-Ear-4 1st Layer Structural Backfilling of Class A 20cm 2 24-Feb-24 26-Feb-24 0 Civ-Ear-2, Civ-Ear-13
Civ-Ear-6, Civ-Ear-14 1st Layer Structural Backfilling of Class A
Civ-Ear-14 1st Layer Compaction 2 26-Feb-24 28-Feb-24 0 Civ-Ear-4 Civ-Ear-7 1st Layer Compaction
Civ-Ear-7 2nd Layer Structural backfilling & Compaction of Calss A 15cm 2 28-Feb-24 01-Mar-24 0 Civ-Ear-6, Civ-Ear-14
Civ-Ear-9, Civ-Ear-17 2nd Layer Structural backfilling & Comp
Civ-Ear-17 2nd Layer Compaction 2 01-Mar-24 03-Mar-24 1 Civ-Ear-7 Civ-Shoul-1 2nd Layer Compaction
BOC-1962.5.9.1.3 Road Base 15 25-Feb-24 11-Mar-24 0 11-Mar-24, BOC-1962.5.9.1.3 Roa
Civ-Sfac-1 Lay Road Base 15cm 8 25-Feb-24 04-Mar-24 0 Civ-Ear-9 Civ-Sfac-2 Lay Road Base 15cm
Civ-Sfac-2 Prime Coat Application 3 08-Mar-24 11-Mar-24 0 Civ-Sfac-1 Civ-Sfac-3 Prime Coat Application
BOC-1962.5.9.1.4 Base Course 3 11-Mar-24 14-Mar-24 0 14-Mar-24, BOC-1962.5.9.1.4 Ba
Civ-Sfac-3 Lay & Compact Binder Course 10cm 3 11-Mar-24 14-Mar-24 0 Civ-Sfac-2, Civ-Shoul-3
Civ-Sfac-4 Lay & Compact Binder Course 10c
BOC-1962.5.9.1.5 Surface Course (Asphalting) 26 14-Mar-24 12-Apr-24 0 12-Apr-24, BOC-1962.
Civ-Sfac-4 Tack Coat Application 3 14-Mar-24 17-Mar-24 0 Civ-Sfac-3 Civ-Sfac-5 Tack Coat Application
Civ-Sfac-5 Place & Compacr Surface Course 50 mm 25 15-Mar-24 12-Apr-24 0 Civ-Sfac-4 Civ-Mrk-3 Place & Compacr Surf
BOC-1962.5.9.13 Road Finishing 44 03-Mar-24 24-Apr-24 0 24-Apr-24, BOC-1
BOC-1962.5.9.13.5 Road Shoulders 5 03-Mar-24 08-Mar-24 1 08-Mar-24, BOC-1962.5.9.13.5 Roa
Civ-Shoul-1 Structural Backfilling Class A 15cm For Shoulders 3 03-Mar-24 06-Mar-24 1 Civ-Ear-17 Civ-Shoul-2 Structural Backfilling Class A 15cm Fo
Civ-Shoul-2 Compact Shoulders Layer 3 06-Mar-24 08-Mar-24 1 Civ-Shoul-1 Civ-Shoul-3 Compact Shoulders Layer
BOC-1962.5.9.13.4 Road Marking 7 13-Apr-24 24-Apr-24 0 24-Apr-24, BOC-1
Civ-Mrk-3 Touch-Up painting 1 13-Apr-24 14-Apr-24 0 Civ-Sfac-5 Civ-Mrk-1 Touch-Up painting
Civ-Mrk-1 Surface Road Marking 4 14-Apr-24 18-Apr-24 0 A1130, Civ-Mrk-3
Civ-Mrk-2 Surface Road Marki
Civ-Mrk-2 Install Traffic Signs 2 19-Apr-24 24-Apr-24 0 A1060, Civ-Mrk-1
Kmil-4 Install Traffic Sign
BOC-1962.5.9.14 Testing Phase 18 20-Feb-24 09-Mar-24 1 09-Mar-24, BOC-1962.5.9.14 Testin
Civ-Ear-2 Compaction Test for Sub Garde 1 20-Feb-24 21-Feb-24 3 Civ-Ear-1 Civ-Ear-4 Compaction Test for Sub Garde
Civ-Ear-6 Compaction Test for 1st Layer 3 26-Feb-24 29-Feb-24 2 Civ-Ear-4 Civ-Ear-7 Compaction Test for 1st Layer
Civ-Ear-9 Compaction Test for 2nd Layer 3 01-Mar-24 04-Mar-24 0 Civ-Ear-7 Civ-Sfac-1 Compaction Test for 2nd Layer
Civ-Shoul-3 Compcation Test for Shoulders 1 08-Mar-24 09-Mar-24 1 Civ-Shoul-2 Civ-Sfac-3 Compcation Test for Shoulders
BOC-1962.5.9.8 Call off Handover 11 24-Apr-24 06-May-24 0 06-May-24, B
Hovr-2 Punch List Closure 4 24-Apr-24 27-Apr-24 0 Kmil-4 Hovr-3 Punch List Closu
Hovr-3 ITRs Closure 6 28-Apr-24 05-May-24 0 Hovr-2 Hovr-1 ITRs Closure
Hovr-1 Walk-down 1 05-May-24 06-May-24 0 Hovr-3 Kmil-6 Walk-down

Actual Level of Effort Actual Work Critical Remaining Work Page 3 of 3 Date Revision Checked Approved

Primary Baseline Remaining Work Baseline Milestone TASK filter: All Activities
WORK ORDER PROPOSAL #001 BOC 1962 - Ancillary Roads and Infrastructure
Design and Construction of SGTF North Access Road

Anexure-2

BOC-1962-AA-9002-0001 Page 17 of 17 Rev.:001


Uncontrolled when printed or stored locally
BOC-1962

Ancillary Roads and Infrastructure

SECTION IVA

SCHEDULE OF PRICES

COMMERCIAL PRODUCTION PROJECT


MAJNOON OIL FIELD DEVELOPMENT, IRAQ

1 of 25
PRICING TABLES
TABLE LIST DESCRIPTION DESCRIPTION
1 PRICING TABLE 1: LUMP SUM RATE FOR MOBILISATION $ 15,000.00
2 PRICING TABLE 2: LUMP SUM RATE FOR DEMOBILISATION $ 15,000.00
3 PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES Unit Rates
4 PRICING TABLE 4: UNIT RATES FOR CONSTRUCTION PERSONNEL Unit Rates
5 PRICING TABLE 5: RATES FOR CONSTRUCTION EQUIPMENT Unit Rates
6 PRICING TABLE 6: MATERIALS AND THIRD PARTY SERVICES Mark up and fee

2 of 25
Contract BOC-1962 - Ancillary Roads and Infrastructure
Section IVA - Schedule of Prices
Revision 01

PRICING TABLE 1: LUMP SUM RATE FOR MOBILISATION

LUMP SUM
ITEM NO DESCRIPTION
(US$)

1 Mobilisation $ 15,000.00

Page 3 of 25
Contract BOC-1962-Ancillary Roads and Infrastructure
Section IVA - Schedule of Prices
Revision 01

PRICING TABLE 2: LUMP SUM RATE FOR DEMOBILISATION

LUMP SUM
ITEM NO. DESCRIPTION
(US$)

1 Demobilisation $ 15,000.00

Page 4 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


A GENERAL ITEMS
A1 Design Works
A1.1 Design Works for SAQR (FALCON) ROAD – CPF2 ACCESS ROAD sum $ 3,000.00
A1.2 Design Works for SGTF ACCESS ROAD sum $ 3,000.00
A1.3 Design Works for MCPP ACCESS ROAD sum $ 3,000.00
A1.4 Design Works for APPRAISAL WELL PAD ACCESS ROAD sum $ 3,000.00

A1.5 Design Works for Landscaping and Irrigation for SAQR (FALCON) ROAD – CPF2 ACCESS ROAD sum $ 3,000.00

A1.6 Design Works for Landscaping and Irrigation for SGTF ACCESS ROAD sum $ 3,000.00
A1.7 Design Works for Landscaping and Irrigation for MCPP ACCESS ROAD sum $ 3,000.00
A2 Temporary Works Requirements
Fencing. Supply, erect, maintain for the duration of the works and dismantle upon completion 2m high
galvanised chainlink fence, mesh wire diameter 3.55 mm, line wire 2.55 mm, tying wire 1.6 mm,
A2.1 m $ 145.00
intemediate posts and struts CHS 48.3 x 3.2 mm, straining posts CHS 60.3 x 4 mm , in accordance with
BS 1722:10 2006 Spec. for anti-intruder fences in chainlink & welded mesh.
Specified requirements. Temporary works. Fencing. Supply, erect, maintain for the duration of the works
and dismantle upon completion galvanised double leaf gate and gate posts, clear opening 6 m. Gate
A2.2 nr $ 7,200.00
posts 1=CHS 168.3 x 5 mm. Gate in accordance with MGP1-GEN-KBR-CS-7880-0007 Standard Details
for Gates

Fencing. Take down N/S section of fencing & gate (items A279.1 & A279.2) and re-erect between
A2.3 m $ 70.00
Quadrants 1 & 3
Traffic diversions work per location, include establishment and removal of traffic signs (5x), warning
A2.4 signs (5x), directional signs (5x) to direct all traffic during the period of work as required by Company. wk $ 3,300.00
Includes for supply of 2 each trained flagman.
A3 Testing of the Works
Water Retaining structure testing where necessary in accordance with the technical requirements of the
A3.1 m3 $ 16.00
applicable design codes

Hydro testing of pipes of all materials where so required by Company. Maximum pressure 25 bar.
A3.2 m3 $ 115.00
Including water supply, saturation, pressurising, emptying, purging and disposal of testing water.

A4 Method Related Charges: Plant

Cranes Mobilisation of all craneage required to execute the Contract including telescopic mobile cranes,
A4.1 crawler cranes and truck mounted mobile cranes in capacities from 20t to 250t as required to perform sum $ 5,000.00
the works.

Cranes Demobilisation of all craneage required to execute the Contract including telescopic mobile
A4.2 cranes, crawler cranes and truck mounted mobile cranes in capacities from 20t to 250t as required to sum $ 5,000.00
perform the works.
A4.3 Asphalting. Mobilisation of Asphalt Paving plant, Caterpillar AP500E, spreading width 3.5 m. sum $ 5,000.00

A4.4 Asphalting. Demobilisation of Asphalt Paving plant, Caterpillar AP500E, spreading width 3.5 m. sum $ 5,000.00

Earthmoving. Mobilisation of all Earthmoving Equipment as required for the Contract, including but not
A4.5 limited to, Excavators, Bulldozers, Loaders, Graders, Vibratory Soil Compactors, Wheel Loaders, sum $ 4,500.00
Asphalt Cutting Machines etc..
Earthmoving. Demobilisation of all Earthmoving Equipment as required for the Contract, including but
A4.6 not limited to, Excavators, Bulldozers, Loaders, Graders, Vibratory Soil Compactors, Wheel Loaders, sum $ 4,500.00
Asphalt Cutting Machines, etc.
Concrete Batching Plant. Mobilisation and erection of 100m3/hr Plant including all required silos,
A4.7 sum $ 10,000.00
aggregate bins, testing laboratory, loading bay, washing facilities, etc.
Concrete Batching Plant. Mobilisation and erection of 50m3/hr Plant including all required silos,
A4.8 sum $ 8,000.00
aggregate bins, testing laboratory, loading bay, washing facilities, etc.
Concrete Batching Plant. Dismantle & De-mobilisation of 100m3/hr Plant including all required silos,
A4.9 sum $ 8,000.00
aggregate bins, testing laboratory, loading bay, washing facilities etc. Reinstate site
Concrete Batching Plant. Dismantle & De-mobilisation of 50m3/hr Plant including all required silos,
A4.10 sum $ 6,000.00
aggregate bins, testing laboratory, loading bay, washing facilities etc. Reinstate site
Precast Piles. Mobilisation of pile driving plant, crew, lifting and other equipment incl. all accesories,
temporary site offices, rest facilities, toilets, etc. Delmag MH 6204, Banut 655 pile driver or similar with
A4.11 Fixed Leader Mast suitable for driving precast concrete piles, up to 8 m long, maximum size 450 x 450 sum $ 10,000.00
mm. Diesel Pile Hammer Delmag D62-22 / D80-23-32, Berminghammer B-64, APE D62-52 or similar.
(Alternative foundation for manifolds)

5 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Precast Piles. Demobilisation of pile driving plant, plant crew, lifting and other equipment and all
A4.12 sum $ 10,000.00
accesories, temporary site offices, rest facilities, toilets, etc. (Alternative foundation for manifolds)

Precast Piles. Relocation of pile driving and all associated equipment within the Majnoon Field, distance
A4.13 sum $ 8,000.00
not exceeding 15 km. (Alternative foundation for manifolds)

Steel Tubular Piles. Mobilisation of crawler crane and pile driving plant, crew & equipment required to
A4.14 install max 18m long, 600dia tubular piles including pile guides gates and All ancilliaries. (Alternative sum $ 10,000.00
foundation for manifolds)
Steel Tubular Piles. Demobilisation of crawler crane and pile driving plant, crew & equipment required
A4.15 to install max 18m long, 600 dia tubular piles including pile guides gates and All ancilliaries. (Alternative sum $ 10,000.00
foundation for manifolds)
Steel Tubular Piles. Relocation of crawler crane and pile driving plant & equipment within the Majnoon
A4.16 sum $ 8,000.00
Field, distance not exceeding 15 km. (Alternative foundation for manifolds)
B GROUND INVESTIGATION
B1 Trial Pits and Trenches
Machine Excavation in material other than rock, width 0.6 m, maximum depth 1.2 m including
B1.1 m $ 6.00
reinstatement on completion of inspection/sampling or pipe/cable laying operations
Hand Excavation in material other than rock, width 0.6 m, maximum depth 1.2 m including reinstatement
B1.2 m $ 20.00
on completion of inspection/sampling or pipe/cable laying operations
Machine Excavation in material other than rock, width 0.6 m, maximum depth 2.4m. Supported including
B1.3 m $ 7.00
reinstatement on completion of inspection/sampling or pipe/cable laying operations

Hand Excavation in material other than rock, width 0.6 m, maximum depth 2.4m. Supported including
B1.4 m $ 40.00
reinstatement on completion of inspection/sampling or pipe/cable laying operations
B2 Laboratory testing
B2.1 Samples. From the surface, or from trial pits or trenches. Sample size 10 kg. Class 3 to BS 5930 nr $ 120.00
B2.2 Classification, Moisture content according to BS 1377 nr $ 120.00
B2.3 Classification, Atterberg limits according to BS 1377 nr $ 120.00
B2.4 Classification, Specific gravity according to BS 1377 nr $ 120.00
B2.5 Classification, Particle size analysis according to BS 1377 nr $ 120.00
B2.6 Compaction, standard Proctor test for compaction according to BS 1377 nr $ 180.00
B2.7 California Bearing Ratio Test CBR nr $ 180.00
D DEMOLITION AND SITE CLEARANCE
General site clearance. Removal of all vegetation, foreign objects and waste including disposal at
D1.1 m2 $ 6.00
Company appointed area <5km.
Other Structures Demolition of Brickwork (Volume not Exceeding 50m3) Includes volumes above and
D1.2 below existing ground elevation. Excavation is deemed to be included. m3 $ 12.00
Fill required for reinstatement of voids left by demolition shall be measured under item E.
Demolition of Reinforced Concrete (or orther artificial hard material) structures.
3
D1.3 Excavation is deemed to be included. m $ 15.00
Fill required for reinstatement of voids left by demolition shall be measured under item E.
D1.4 Demolition of Steel structures. t $ 500.00
Demolition/Removal of Pipelines. Nominal bore: 100-300 mm. Pipeline removal from trenches and
D1.5 above ground inclusive of any supports, bedding/protection layers and disposal at Company appointed m $ 15.00
area <5km. Includes for backfill and reinstatement.
Removal of Internal fences. Metal post and wire. Height upto 2.00 m. Includes for galvanised top and
D1.6 m $ 5.00
bottom rail diameter 42 mm.
Removal of Security fences. Metal post and wire. Height 2.50 m. Includes for double extension arms, 6
D1.7 m $ 7.00
rows of barbed wire and razor wire top.
E EARTHWORKS
All earthworks shall be performed in accordance with MGP1-GEN-KBR-CX-7880-0022,
E1
Specification for Earthworks
Site preparation (following ERW clearance) including levelling, rolling and compacting sub-grade for
E1.1 m2 $ 2.00
Well Pad and General Areas
Excavation in material other than topsoil, rock or artificial hard material including trimming of surfaces
E1.2 m3 $ 2.00
and disposal of excavated material to on-site disposal area, depth <2m.
Excavation in material other than topsoil, rock or artificial hard material including trimming of surfaces
E1.3 m3 $ 2.50
and disposal of excavated material to on-site disposal area distance <15km, depth <5m.
Excavation in material other than topsoil, rock or artificial hard material including trimming of surfaces
E1.4 and disposal of excavated material to on-site disposal area adjacent to Well Pad, depth <2m. (Access m3 $ 2.00
Rd Drains & Security ditch)
Excavation in material other than topsoil, rock or artificial hard material including trimming of surfaces
3
E1.5 and disposal of excavated material to on-site disposal area distance <5km, depth <5m. ( Culverts, m $ 2.50
cellars, drains & ditches)

6 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


General Excavation (within borrow pits); Material other than topsoil, rock or artificial hard material; max
E1.6 m3 $ 2.00
depth 2-5m; for volumes >10,000 m3
General Excavation (within borrow pits); Material other than topsoil, rock or artificial hard material; max
E1.7 m3 $ 2.00
depth 2-5m; for volumes <10,000 m3
Excavation for foundations. Material other than topsoil, rock or artificial hard material including trimming
E1.8 m3 $ 3.00
of surfaces and disposal of excavated material to disposal area adjacent to Well Pad,

7 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Hand excavation for foundations. (blocks, in-situ concrete pavement, interlocking conc. blocks etc)
E1.9 Material other than topsoil, rock, or artificial hard material including trimming of surfaces and disposal of m3 $ 20.00
excavated material to on-site disposal area distance adjacent to Well Pad,.
Excavation of PITS. Material other than topsoil, rock or artificial hard material including trimming of
E1.10 m3 $ 2.00
surfaces and disposal of excavated material to on-site disposal area distance <5km, Depth <5m
Filling to structures using approved selected excavated material, structural fill, from stockpile not
E1.11 m3 $ 2.00
exceeding 5km from excavation
General fill using approved selected excavated material, structural fill, from Company provided borrow
E1.12 m3 $ 8.00
pit or other excavations. Distance not exceeding 5km. (Raising of wellpad area and roads)
General fill using approved selected excavated material, structural fill, from Company provided borrow
E1.13 m3 $ 12.00
pit or other excavations. Distance not exceeding 5km.
Filling to structures using approved selected excavated material, structural fill, from Company provided 3
E1.14 m $ 8.00
borrow pit or other excavations. Distance not exceeding 5km. (Culverts + Cellars)
Filling to embankments using selected excavated material, structural fill, from stockpile not exceeding
E1.15 m3 $ 7.00
100 m from excavation
Filling to embankments using selected excavated material, structural fill, from Company provided borrow
E1.16 m3 $ 8.00
pit or other excavations. Distance not exceeding 5 km.
Filling. General. Imported natural material. Well graded medium sand for backfill around direct buried
E1.17 cables shall be in accordance with MGP1-GEN-KBR-CX-7880-0022, Specification for Earthworks, m3 $ 20.00
Section 12.3.4 Backfill around Direct Buried Cables and Table 4
Filling. General. Imported natural material. Gravel nominal size 25 mm. Percentage retained on sieve
3
E1.18 C31.5: min 0%-max 10%, sieve C22.4: min 50%-max 100%, sieve C16.0: min 97%-max 100%, 2 mm: m $ 25.00
min 98%-max 100% and through sieve 63 μm ≤1%.
E1.19 Filling using imported granular material Type B m3 $ 22.00
E1.20 Trimming side slopes to pits @30% maximum depth 4m (Pit/Ditch side slopes) m2 $ 3.00
Excavation for soft spot repair less than 10 m3. Includes for excavation soft spots and other voids,
E1.21 directed to be excavated. Saw cutting of asphalt, excavation, of acceptable material, excavation of m3 $ 12.00
unacceptable material, disposal of excavated material and trimming back of cutting faces. (road repairs)
Supply and application of soil improvement chemical polymer mixed 300mm deep then seal coat applied
2
E1.22 in accordance with manufacturer's instructions: "Top-Seal, by Bellestar Eco-Tec" or equivalent including m $ 10.00
seal coat and curing. (Alternative foundation material)
6% by volume Cement stabilisation of existing in-situ soils including cement supply, mixing to 300mm
E1.23 m3 $ 35.00
depth, roll & compact to achieve minimum CBR of 30%. (Alternative foundation material)
E2 Geomembrane

Geomembrane supply and installation shall comply with the requirements of the Geosynthetic
Research Institute, particular Geomembrane Specification GM10 revision 3 The Stress Crack
Resistance of HDPE Geomembrane Sheet, Test Method GM13 revision 10 Test Properties Testing
E2 Frequency and Recommended Warranty for Geomembrane and Test Method GM19 revision 6
Seam Strength and Related Properties. Installation in accordance with IAGI, HDPE & LLDPE
Geomembrane Installation Specification 2007 and GRI, Geomembrane Specification GM29, Field
Integrity Evaluation of Geomembrane Seams.

Supply and installation of smooth black HDPE geomembrane thick 1 mm. The area of additional
E2.1 m2 $ 9.00
geomembrane in laps shall not be measured. Rate includes for all welding, testing and test records.

Supply and installation of smooth black HDPE geomembrane thick 1.5 mm. The area of additional
E2.2 m2 $ 11.00
geomembrane in laps shall not be measured. Rate includes for all welding, testing and test records.

Supply and installation of smooth black HDPE geomembrane thick 2 mm. The area of additional 2
E2.3 m $ 13.00
geomembrane in laps shall not be measured. Rate includes for all welding, testing and test records.
E3 Geotextile

Geotextile. Supply and installation of nonwoven geotextile. Geotextile shall be in accordance


with MGP1-GEN-KBR-CX-7880-0022, Specification for Earthworks, Appendix 3 Material, Table 7
E3 Geotextiles to separate soil replacement laters from existing weak soils at base of foundation
excavations (at locations shown on the drawings) Terram 1000 or similar. The area of additional
geotextile in laps shall not be measured.
Supply and installation of nonwoven geotextile, UV stabilised, min wt 125g/m2, tensile strength minimum
E3.1 8 kN/m, tensile elongation maximum 60%, permeability 90 l/m2s. Terram 1000 or similar. The area of m2 $ 5.00
additional geotextile in laps shall not be measured.
Supply and installation of nonwoven geotextile, UV stabilised, min wt 175g/m2, tensile strenght minimum
E3.2 12.5 kN/m, tensile elongation maximum 60%, permeability 65 l/m2s. Terram 1500 or similar. The area of m2 $ 6.00
additional geotextile in laps shall not be measured.

8 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Installation of Company Supplied nonwoven geotextile, UV stabilised, min wt 125g/m2, tensile strength
E3.3 minimum 8 kN/m, tensile elongation maximum 60%, permeability 90 l/m2s. Terram 1000 or similar. The m2 $ 3.00
area of additional geotextile in laps shall not be measured.
Installation of Company Supplied nonwoven geotextile, UV stabilised, min wt 175g/m2, tensile strenght
E3.4 minimum 12.5 kN/m, tensile elongation maximum 60%, permeability 65 l/m2s. Terram 1500 or similar. m2 $ 3.00
The area of additional geotextile in laps shall not be measured.
Supply and Installation of Cellular confinement system (geocells) for slope protection of Majnoon Oilfield
water retaining dykes. Envirogrid EGA406PT or similar. Cell depth upto 200mm. Nominal expanded cell
size 500 mm wide by 475 mm long. Nominal expanded section 2.56 wide by 13.72 m long or bigger.
Panels shall be staples together to form continuous geocell dyke protection. Nominal expanded section
E3.5 m2 $ 20.00
area > 35 m2. Material HDPE, minimum carbon content 1.5%. Cell wall perforated; hole size 10 mm
max., perforations 12-15%. Includes for J-hooks for geocell anchoring; 16 mm steel reinforcing bars,
long 450 mm (without hook), 1 J-hook/m2. Infill material measured seperately. Installation as per
Envirogrid Design and Installation Guidelines for Erosion Control
Supply and installation of geogrid. Geogrid shall be in accordance with MGP1-GEN-KBR-CX-7880-0023,
E3.6 Specification for Roads and Paving, Section10.4 Geotextile and Geogrid Table 3 Geogrid requirements. m2 $ 20.00
NAUE Secugrid 40-40 Q1 or similar.
F IN SITU CONCRETE

Concrete, formwork and reinforcement steel supply and installation shall be in accordance with
F MGP1-GEN-KBR-CX-7880-0021, Specification for Concrete Works and MGP1-GEN-KBR-CX-7880-
0002, Standard Drawing General Notes for Civil Works Abbreviations and Legends.
3
F1.1 Supply, place, compact, level, cure Grade C16 blinding concrete with A252 mesh < 100mm thick m $ 250.00

Supply, place, compact, finish, strip and cure Grade C35 reinforced concrete to foundations (pad, strip,
3
F1.2 raft, ground beams, pipe supports rig tracks etc) including all required formwork, reinforcement, tie wire, m $ 750.00
etc all as shown on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C35 reinforced concrete to ground level slabs,
F1.3 paving, work area etc including all required formwork, reinforcement, tie wire, spacers, etc all as shown m3 $ 500.00
on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C35 reinforced concrete to pit walls, berms
3
F1.4 foundations (pad, strip, raft, ground beams, pipe supports rig tracks etc) including all required formwork, m $ 750.00
reinforcement, tie wire, etc all as shown on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C25 reinforced concrete to foundations (pad, strip,
F1.5 raft, ground beams, pipe supports rig tracks etc) including all required formwork, reinforcement, tie wire, m3 $ 650.00
etc all as shown on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C25 reinforced concrete to ground level slabs,
F1.6 paving, work area etc including all required formwork, reinforcement, tie wire, spacers, etc all as shown m3 $ 450.00
on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C25 reinforced concrete to pit walls, berms
F1.7 foundations (pad, strip, raft, ground beams, pipe supports rig tracks etc) including all required formwork, m3 $ 650.00
reinforcement, tie wire, etc all as shown on the Construction drawings
Supply, place, compact, finish, strip and cure Grade C37 reinforced concrete to foundations (pad, strip,
F1.8 raft, ground beams, pipe supports rig tracks etc) including all required formwork, reinforcement, tie wire, m3 $ 800.00
etc all as shown on the Construction drawings
F1.9 Supply and installation of 1000 gauge (250 μm) polythene m2 $ 5.00
F1.10 Supply and install plastic or rubber centre-bulb waterstops at concrete joints. Width: 150 - 200 mm m $ 25.00

F1.11 Supply and install plastic or rubber back-stop waterstops at concrete joints. Width: 150 - 200 mm m $ 25.00

G Grouting
Grouting. Non-shrink cement based grout type G2 in accordance with MGP1-GEN-KBR-CX-7880-
G
0021, Specification for Concrete Works Section 22 Grouting
Concrete accessories. Grouting under plates. Area: not exceeding 0.1 m2, thickness not exceeding 50
G1.1 nr $ 50.00
mm. Cement based non-shrink grout type G2.
Concrete accessories. Grouting under plates. Area: not exceeding 0.1 m2, thickness not exceeding 50
G1.2 nr $ 80.00
mm. Epoxy based non-shrink grout type G3
Concrete accessories. Grouting under plates. Area: 0.1 - 0.5 m2, thickness not exceeding 50 mm.
G1.3 nr $ 110.00
Cement based non-shrink grout type G2
Concrete accessories. Grouting under plates. Area: 0.1 - 0.5 m2, thickness not exceeding 50 mm.
G1.4 nr $ 200.00
Epoxy based non-shrink grout type G3
G1.5 Cement Sand grout 1:3 m3 $ 1,800.00
H PRECAST CONCRETE
Precast concrete elements are typically pipe supports/sleeper, light pole foundations, CCTV
H foundations, instrument foundations, T-walls, Jersey barriers and various foundation &
pavement slabs.

9 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Supply Precast beams/sleepers, columns including all reinforcement, ancillaries, lifting hooks & eyes
H1.1 m3 $ 495.00
etc.
Supply Precast slabs, manhole & culvert lids, pipeline protection etc including all reinforcement,
H1.2 m3 $ 495.00
ancillaries, lifting hooks & eyes etc.
Supply general precast items such as foundation blocks, kentledge etc nominally less than 1m3
H1.3 m3 $ 495.00
including all reinforcement, ancillaries, lifting hooks & eyes etc
Supply precast elements such as culverts, ducts, Well Pad cellars, manholes & pits on 100mm sand bed
H1.4 m3 $ 495.00
on well compacted sub-base. Notional Cross sectional area around 1m2
Supply Precast 3m high T-walls as per MGP1-GEN-KBR-CG-4017-1037-001 Typical T-wall & Stelcon
H1.5 nr $ 385.00
slab GA & RC details
H1.6 Supply Precast 5m high T-walls as per Drawing No.9, T-Wall & Other Miscellaneous Details of Air Lock nr $ 770.00
H1.7 Supply Precast Jersey Barriers 3m long, T-Wall & Other Miscellaneous Details of Air Lock nr $ 330.00
Install precast elements below ground such as culverts, ducts, Well Pad cellars, manholes & pits on
H1.8 m3 $ 165.00
100mm sand bed on well compacted sub-base. Notional Cross sectional area around 1m2
Install precast elements at grade such as drainage channels, sumps, manhole & pit cover slabs,
H1.9 m3 $ 165.00
spreader beams, rig tracks etc
Place, remove or re-position T-walls& Jersey Barriers within Well Pad footprint (to separate phased
H1.10 m $ 55.00
quadrant works)
Remove from installed position, transport and install in position T-walls & Jersey Barriers to other areas
H1.11 m $ 55.00
within Majnoon Field
H1.12 Manufacture, supply, tranport and install in position 3m high T-walls to Well Pads within Majnoon Field m $ 440.00
H1.13 Installation of concrete splash blocks (600 x 600 x 150mm) nr $ 55.00
H1.14 Installation of Company supplied precast foundations (weight upto 0.2T) nr $ 55.00
H1.15 Installation of Company supplied precast foundations (weight 0.2T to 1T) nr $ 110.00
H1.16 Installation of Company supplied precast foundations (weight 1T to 5T) nr $ 165.00
I PIPEWORK - PIPES
Carbon steel pipe. Schedule 80 to ANSI/ASME B36.10. Provision of pipes only, for use in pipe
I1
jacking. Pipe jacking activities priced in items L231 and L232
I1.1 Steel pipes. Nominal bore 100 mm (4"). Not in trenches for pipe jacking. m $ 75.00
I1.2 Steel pipes. Nominal bore 150 mm (6"). Not in trenches for pipe jacking. m $ 115.00
I1.3 Steel pipes. Nominal bore 250 mm (10"). Not in trenches for pipe jacking. m $ 200.00
uPVC pipes. Waste water pipe and fittings shall comply with EN 1401-1;2009, -2 & -3 and EN
I2 13476-2:2007 & -3:2007. Installation shall comply with MGP1-GEN-KBR-CX-7880-0025, Material &
Workmanship for Drainage & Underground Services. Stiffness SN4 minimum.
uPVC corrugated and perforated drain pipes. Outside diameter: 160 mm. In trenches, depth: 1.5 m.
I2.1 Dual (two each) perforated drain pipes side by side in common trench. Trench width 600 mm. Inclusive m $ 116.00
of non-woven geotextile surround
I2.2 uPVC pipes. Outside diameter: 50 mm. In trenches, depth: not exceeding 1.5 m. m $ 50.00
I2.3 uPVC pipes. Outside diameter: 75 mm. In trenches, depth: not exceeding 1.5 m. m $ 49.00
I2.4 uPVC pipes. Outside diameter: 110 mm. In trenches, depth: not exceeding 1.5 m. m $ 62.00
I2.5 uPVC pipes. Outside diameter: 160 mm. In trenches, depth: not exceeding 1.5 m. m $ 67.00
I2.6 uPVC pipes. Outside diameter: 160 mm. In trenches, depth: 1.5 - 2.0 m. m $ 68.00
I2.7 uPVC pipes. Outside diameter: 200 mm. In trenches, depth: not exceeding 1.5 m. m $ 73.00
I2.8 uPVC pipes. Outside diameter: 200 mm. In trenches, depth: 1.5 - 2.0 m. m $ 81.00
I2.9 uPVC pipes. Outside diameter: 315 mm. In trenches, depth: not exceeding 1.5 m. m $ 86.00
I2.10 uPVC pipes. Outside diameter: 315 mm. In trenches, depth: 1.5 - 2.0 m. m $ 93.00
Glass reinforced plastic pipes. Pressure rating 10 bar. Rubber gasket connections. Pipe and
I3
fittings to BS EN 14364:2013
I3.1 Glass reinforced plastic pipes. Nominal bore: 600 - 900 mm. In trenches, depth: not exceeding 1.5 m. m $ 345.00
I3.2 Glass reinforced plastic pipes. Nominal bore: 600 - 900 mm. In trenches, depth: 1.5 - 2.0 m. m $ 365.00
I3.3 Glass reinforced plastic pipes. Nominal bore: 600 - 900 mm. In trenches, depth: 2.0 - 2.5 m. m $ 360.00
I3.4 Glass reinforced plastic pipes. Nominal bore: 600 - 900 mm. In trenches, depth: 2.5 - 3.0 m. m $ 400.00
I3.5 Glass reinforced plastic pipes. Nominal bore: 900 - 1200 mm. In trenches, depth: not exceeding 1.5 m. m $ 450.00
I3.6 Glass reinforced plastic pipes. Nominal bore: 900 - 1200 mm. In trenches, depth: 1.5 - 2.0 m. m $ 510.00
I3.7 Glass reinforced plastic pipes. Nominal bore: 900 - 1200 mm. In trenches, depth: 2.0 - 2.5 m. m $ 560.00
I3.8 Glass reinforced plastic pipes. Nominal bore: 900 - 1200 mm. In trenches, depth: 2.5 - 3.0 m. m $ 600.00
High Density Polyethylene pipes (PE100). Pressure rating 16 bar. Fusion welded. Pipes to BS EN
I4
12201-2:2011+A1:2013 and fittings to BS EN 12201-3:2011+A1:2012
I4.1 PE100 pipes. Outside diameter: 50 mm. In trenches, depth: not exceeding 1.5 m. m $ 30.00
I4.2 PE100 pipes. Outside diameter: 63 mm. In trenches, depth: not exceeding 1.5 m. m $ 32.00
I4.3 PE100 pipes. Outside diameter: 90 mm. In trenches, depth: not exceeding 1.5 m. m $ 41.00
I4.4 PE100 pipes. Outside diameter: 110 mm. In trenches, depth: not exceeding 1.5 m. m $ 58.00
I4.5 PE100 pipes. Outside diameter: 125 mm. In trenches, depth: not exceeding 1.5 m. m $ 67.00

10 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


I4.6 PE100 pipes. Outside diameter: 160 mm. In trenches, depth: not exceeding 1.5 m. m $ 92.00
I4.7 PE100 pipes. Outside diameter: 225 mm. In trenches, depth: not exceeding 1.5 m. m $ 164.00
I4.8 PE100 pipes. Outside diameter: 63 mm. In trenches, depth: 1.5 - 2.0 m. m $ 45.00
I4.9 PE100 pipes. Outside diameter: 90 mm. In trenches, depth: 1.5 - 2.0 m. m $ 65.00
I4.10 PE100 pipes. Outside diameter: 110 mm. In trenches, depth: 1.5 - 2.0 m. m $ 68.00
I4.11 PE100 pipes. Outside diameter: 125 mm. In trenches, depth: 1.5 - 2.0 m. m $ 75.00
I4.12 PE100 pipes. Outside diameter: 160 mm. In trenches, depth: 1.5 - 2.0 m. m $ 112.00
I4.13 PE100 pipes. Outside diameter: 225 mm. In trenches, depth: 1.5 - 2.0 m. m $ 201.00
J PIPEWORK - FITTINGS AND VALVES - Supply & Installation
Polyvinyl chloride (PVC-U) pipe fittings. Bends. Nominal bore: not exceeding 200 mm. In trenches,
J.1 depth not exceeding 1.5 m. Wastewater pipe fittings, outside diameter 110 mm, stiffness SN4. Bend 90° nr $ 46.00
for connection from buildings to wastewater outlet.
Polyvinyl chloride (PVC-U) pipe fittings. Tapers. Nominal bore: not exceeding 200 mm. In trenches,
J.2 depth not exceeding 1.5 m. Wastewater pipe fittings, outside diameter 110 mm, stiffness SN4. Reducer nr $ 24.00
OD 160/110 mm for connection from buildings to manhole outlet.
Polyvinyl chloride (PVC-U) pipe fittings. End caps. Nominal bore: not exceeding 200 mm. In trenches,
J.3 depth not exceeding 1.5 m. Wastewater pipe fittings, outside diameter 110 or 160 mm, stiffness SN4. nr $ 17.00
End cap OD 110 or 160 mm.
High density polyethylene pipe fittings (PE100). Bends. Nominal bore: not exceeding 200 mm. In
J.4 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar, outside nr $ 17.00
diameter 25 mm. Electrofusion coupling 45° or 90°.
High density polyethylene pipe fittings (PE100). Bends. Nominal bore: not exceeding 200 mm. In
J.5 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar, outside nr $ 18.00
diameter 50 mm. Electrofusion coupling 45° or 90°.
High density polyethylene pipe fittings (PE100). Bends. Nominal bore: not exceeding 200 mm. In
J.6 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar, outside nr $ 31.00
diameter 63 mm. Electrofusion coupling 45° or 90°.
High density polyethylene pipe fittings (PE100). Bends. Nominal bore: not exceeding 200 mm. In
J.7 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar, outside nr $ 58.00
diameter 90 mm. Electrofusion coupling 45° or 90°.
High density polyethylene pipe fittings (PE100). Bends. Nominal bore: not exceeding 200 mm. In
J.8 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar, outside nr $ 73.00
diameter 110 mm. Electrofusion coupling 45° or 90°.
High density polyethylene pipe fittings (PE100). Bends. Nominal bore: not exceeding 200 mm. In
J.9 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar, outside nr $ 105.00
diameter 125 mm. Electrofusion coupling 45° or 90°.
High density polyethylene pipe fittings (PE100). Bends. Nominal bore: not exceeding 200 mm. In
J.10 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar, outside nr $ 114.00
diameter 160 mm. Electrofusion coupling 45° or 90°.
High density polyethylene pipe fittings (PE100). Bends. Nominal bore: 225 mm. In trenches, depth not
J.11 exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar, outside diameter 225 mm. nr $ 158.00
Electrofusion coupling 45° or 90°.
High density polyethylene pipe fittings (PE100). Junctions and branches. Nominal bore: not exceeding
J.12 200 mm. In trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 nr $ 32.00
bar. Electrofusion saddle or tee 50 - 25 mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). Junctions and branches. Nominal bore: not exceeding
J.13 200 mm. In trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 nr $ 48.00
bar. Electrofusion saddle 90 or 110 - 50 mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). Junctions and branches. Nominal bore: not exceeding
J.14 200 mm. In trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 nr $ 61.00
bar. Electrofusion saddle 160 - 110 mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). Junctions and branches. Nominal bore: 225 mm. In
J.15 trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. nr $ 117.00
Electrofusion saddle 225 - 160 mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). Adapters. Nominal bore: not exceeding 200 mm. In
J.16 trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. Flange nr $ 51.00
adaptor 50 mm outside pipe diameter, inclusive of backing ring and galvanised nuts, bolts and washers.

High density polyethylene pipe fittings (PE100). Adapters. Nominal bore: not exceeding 200 mm. In
J.17 trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. Flange nr $ 78.00
adaptor 63 mm outside pipe diameter, inclusive of backing ring and galvanised nuts, bolts and washers.

High density polyethylene pipe fittings (PE100). Adapters. Nominal bore: not exceeding 200 mm. In
J.18 trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. Flange nr $ 78.00
adaptor 90 mm outside pipe diameter, inclusive of backing ring and galvanised nuts, bolts and washers.

11 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


High density polyethylene pipe fittings (PE100). Adapters. Nominal bore: not exceeding 200 mm. In
trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. Flange
J.19 nr $ 149.00
adaptor 110 mm outside pipe diameter, inclusive of backing ring and galvanised nuts, bolts and
washers.
High density polyethylene pipe fittings (PE100). Adapters. Nominal bore: not exceeding 200 mm. In
trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. Flange
J.20 nr $ 216.00
adaptor 160 mm outside pipe diameter, inclusive of backing ring and galvanised nuts, bolts and
washers.
High density polyethylene pipe fittings (PE100). Adapters. Nominal bore: not exceeding 200 mm. In
trenches, depth: not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. Flange
J.21 nr $ 256.00
adaptor 225 mm outside pipe diameter, inclusive of backing ring and galvanised nuts, bolts and
washers.
High density polyethylene pipe fittings (PE100). End caps. Nominal bore: not exceeding 200 mm. In
J.22 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. End cap 50 nr $ 11.00
mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). End caps. Nominal bore: not exceeding 200 mm. In
J.23 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. End cap 63 nr $ 17.00
mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). End caps. Nominal bore: not exceeding 200 mm. In
J.24 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. End cap 90 nr $ 21.00
mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). End caps. Nominal bore: not exceeding 200 mm. In
J.25 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. End cap nr $ 32.00
110 mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). End caps. Nominal bore: not exceeding 200 mm. In
J.26 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. End cap nr $ 53.00
160 mm outside pipe diameter.
High density polyethylene pipe fittings (PE100). End caps. Nominal bore: not exceeding 200 mm. In
J.27 trenches, depth not exceeding 1.5 m. Potable water piping PE100, nominal pressure 16 bar. End cap nr $ 69.00
225 mm outside pipe diameter.
Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.28 nr $ 76.00
water gate valve, DN 50, flanged, nominal pressure 16 bar. AWWA approved or similar.

Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.29 nr $ 86.00
water gate valve, DN 63, flanged, nominal pressure 16 bar. AWWA approved or similar.

Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.30 nr $ 215.00
water gate valve, DN 100, flanged, nominal pressure 16 bar. AWWA approved or similar.

Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.31 nr $ 401.00
water gate valve, DN 125, flanged, nominal pressure 16 bar. AWWA approved or similar.

Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.32 nr $ 502.00
water gate valve, DN 150, flanged, nominal pressure 16 bar. AWWA approved or similar.

Valves and penstocks. Gate valves: hand operated. Nominal bore: not exceeding 200 mm. Potable
J.33 nr $ 612.00
water gate valve, DN 200, flanged, nominal pressure 16 bar. AWWA approved or similar.
K PIPEWORK - MANHOLES AND PIPEWORK ANCILLARIES
Manholes. Polyvinyl chloride (PVC-U) manholes and inspection chambers compliant with EN
13598 -2 & -3, EN 124 and DS 2379. Polyethelyne (PE) waste water manholes shall comply with
K1
EN 13598 -2, & -3, EN 124 and DS 2379. Installation shall comply with Specification ref 45C1 Rev
2, Specification For Drainage Material and Workmanship.
Manholes. Polyvinyl chloride (PVC-U) or polyethylene (PE) . Depth: not exceeding 1.5 m. Wavin Tegra
425 or similar. DN 160 mm, double junction (left and right inlet) type X or similar. Inclusive of
K1.1 nr $ 250.00
polypropylene cover of A14 class, pipe sealing ring and 425 PP corrugated shaft extension pipe 1 m
long.
Manholes. Polyethylene. Depth: not exceeding 1.5 m. Wavin Tegra 600 or similar. DN 160 mm, double
K1.2 junction (left and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring nr $ 280.00
and 600 PP corrugated shaft extension pipe 1 m long.
Manholes. Polyethylene. Depth: 1.5 -2 m. Wavin Tegra 600 or similar. DN 160 mm, double junction (left
K1.3 and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring and 600 PP nr $ 360.00
corrugated shaft extension pipe 1 m long.
Manholes. Polyethylene. Depth: not exceeding 1.5 m. Wavin Tegra 800 or similar. DN 200 mm, double
K1.4 junction (left and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring nr $ 390.00
and 600 PP corrugated shaft extension pipe 1 m long.
Manholes. Polyethylene. Depth: 1.5 - 2 m. Wavin Tegra 800 or similar. DN 200 mm, double junction (left
K1.5 and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring and 600 PP nr $ 440.00
corrugated shaft extension pipe 1 m long.

12 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Manholes. Polyethylene. Depth: 1.5 - 2 m. Wavin Tegra 1000 or similar. DN 200 mm, double junction
K1.6 (left and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring and 600 nr $ 650.00
PP corrugated shaft extension pipe 1 m long.
Manholes. Polyethylene. Depth: 2 - 2.5 m. Wavin Tegra 1000 or similar. DN 200 mm, double junction
K1.7 (left and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring and 600 nr $ 620.00
PP corrugated shaft extension pipe 1 m long.
Manholes. Polyethylene. Depth: 2.5 -3 m. Wavin Tegra 1000 or similar. DN 200 mm, double junction
K1.8 (left and right inlet) type X or similar. Inclusive of ductile iron cover class D400, pipe sealing ring and 600 nr $ 620.00
PP corrugated shaft extension pipe 1 m long.
Other stated chambers. Polyethylene. Depth not exceeding 1.5 m. Wavin Tegra 600 empty base or
K1.9 similar. Inclusive of ductile iron cover class D400, pipe sealing ring and 600 PP corrugated shaft nr $ 310.00
extension pipe 1 m long.
Other stated chambers. Polyvinyl chloride (PVC-U). Depth not exceeding 1.5 m. PVC-U chamber 450 x
K1.10 nr $ 320.00
450 x 450 mm with PVC-U cover.
K2 Supply & Installation of Concrete Cable Tiles and Warning Tape as per Engineering drawings

K2.1 Supply & Installation of Concrete Cable Tiles m2 $ 25.00


K2.2 Supply & Installation of Pipe/Cable Trench Warning Tape m $ 3.00
Ducts and metal culverts. Cable ducts. Reinforced concrete cable duct banks. Includes for PVC
pipe(s) 160 mm, pressure rating 10 bar, formwork, reinforcement and concrete as per drawing
MGP1-GEN-KBR-CX-7880-0011, Typical Details of Duct Bank Road Crossing. Includes
K3
excavation, upholding of sides, etc. as per CESMM4 Coverage Rule C1. Also includes for
concrete protection as per MGP1-GEN-KBR-CX-7880-0004-001_002, Standard Details for
Concrete Protection
K3.1 Ducts. Cable ducts: 1 way. In trenches: depth: not exceeding 1.5 m. Duct Bank Type I (1 Layer) m $ 145.00
K3.2 Ducts. Cable ducts: 1 way. In trenches: depth: 1.5-2 m. Duct Bank Type 1 (1 Layer) m $ 153.00
K3.3 Ducts. Cable Ducts: 2 way. In trenches, depth: not exceeding 1.5 m. Duct Bank Type I (1 Layer) m $ 170.00
K3.4 Ducts. Cable Ducts: 2 way. In trenches, depth: 1.5-2 m. Duct Bank Type - I (1 layer) m $ 205.00
K3.5 Ducts. Cable Ducts: 3 way. In trenches, depth: not exceeding 1.5 m. Duct Bank Type I (1 Layer) m $ 265.00
K3.6 Ducts. Cable Ducts: 3 way. In trenches, depth: 1.5-2 m. Duct Bank Type - I (1 layer) m $ 295.00
K3.7 Ducts. Cable Ducts: 4 way. In trenches, depth: not exceeding 1.5 m. Duct Bank Type I (1 Layer) m $ 343.00
Ducts. Cable Ducts: 4 way (2 wide x 2 high). In trenches, depth: not exceeding 1.5 m. Duct Bank Type II
K3.8 m $ 293.00
(2 Layer)
Ducts. Cable Ducts: 6 way (3 wide x 2 high). In trenches, depth: not exceeding 1.5 m. Duct Bank Type II
K3.9 m $ 410.00
(2 Layer)
Ducts. Cable Ducts: 8 way (4 wide x 2 high). In trenches, depth: not exceeding 1.5 m. Duct Bank Type II
K3.10 m $ 530.00
(2 Layer)
Ducts. Cable Ducts: 10 way (5 wide x 2 high). In trenches, depth: not exceeding 1.5 m. Duct Bank Type
K3.11 m $ 580.00
II (3 Layer)
K3.12 Ducts. Cable Ducts: 4 way. In trenches, depth: 1.5-2 m. Duct Bank Type I (1 Layer) m $ 380.00
K3.13 Ducts. Cable Ducts: 6 way (2 wide x 3 high). In trenches, depth: 1.5-2 m. Duct Bank Type III (3 Layer) m $ 430.00

K3.14 Ducts. Cable Ducts: 9 way (3 wide x 3 high). In trenches, depth: 1.5-2 m. Duct Bank Type III (3 Layer) m $ 526.00

K3.15 Ducts. Cable Ducts: 12 way (4 wide x 3 high). In trenches, depth: 1.5-2 m. Duct Bank Type III (3 Layer) m $ 670.00

K3.16 Ducts. Cable Ducts: 15 way (5 wide x 3 high). In trenches, depth: 1.5-2 m. Duct Bank Type III (3 Layer) m $ 670.00
K3.17 Crossing. T-Wall. Pipe bore: not exceeding 300 mm nr $ 320.00
K3.18 Crossing. T-Wall. Pipe bore: 300 - 900 mm nr $ 520.00
K3.19 Crossing. Fence. Pipe bore: not exceeding 300 mm nr $ 320.00
K3.20 Crossing. Fence. Pipe bore: 300 - 900 mm nr $ 520.00
K3.21 Crossing. Sewer or drain. Pipe bore: not exceeding 300 mm nr $ 320.00
K3.22 Crossing. Sewer or drain. Pipe bore: 300 - 900 mm nr $ 520.00
K3.23 Crossing. Security berm. Pipe bore: not exceeding 300 mm m $ 370.00
K3.24 Crossing. Security berm. Pipe bore: 300 - 900 mm m $ 590.00
Reinstatement. Breaking up, temporary and permanent reinstatement of roads. Pipe bore: not
K3.25 nr $ 670.00
exceeding 300 mm
Reinstatement. Breaking up, temporary and permanent reinstatement of roads. Pipe bore: 300 - 900
K3.26 nr $ 920.00
mm
Reinstatement. Breaking up, temporary and permanent reinstatement of in-situ cast footpaths. Pipe
K3.27 nr $ 663.00
bore: not exceeding 300 mm.
Other pipework ancillaries. Connection to existing manholes and other chambers. Pipe bore: not
K3.28 nr $ 215.00
exceeding 200 mm

13 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Other pipework ancillaries. Connection to existing manholes and other chambers. Pipe bore: 200 - 300
K3.29 nr $ 325.00
mm
Other pipework ancillaries. Connection to existing manholes and other chambers. Pipe bore: 300 - 600
K3.30 nr $ 615.00
mm
Other pipework ancillaries. Connection to existing manholes and other chambers. Pipe bore: 600 - 900
K3.31 nr $ 963.00
mm
Other pipework ancillaries. Connection to existing pipes, ducts and culverts. Pipe bore: not exceeding
K3.32 nr $ 215.00
200 mm
K3.33 Other pipework ancillaries. Connection to existing pipes, ducts and culverts. Pipe bore: 200 - 300 mm nr $ 325.00

K3.34 Other pipework ancillaries. Connection to existing pipes, ducts and culverts. Pipe bore: 300 - 600 mm nr $ 625.00

K3.35 Other pipework ancillaries. Connection to existing pipes, ducts and culverts. Pipe bore: 600 - 900 mm nr $ 965.00

L PIPEWORK - SUPPORTS AND PROTECTION, ANCILLARIES TO LAYING AND EXCAVATION

L1 PIPEWORK - SUPPORTS AND PROTECTION, ANCILLARIES TO LAYING AND EXCAVATION

L1.1 Special pipe laying methods. Pipe jacking. Nominal bore: 6" schedule 40 pipe. Minimum length 8 m. m $ 120.00

L1.2 Special pipe laying methods. Pipe jacking. Nominal bore: 10" schedule 40 pipe. Minimum length 8 m. m $ 185.00

Surrounds. Bed thickness 100 mm, cover 100 mm. Nominal trench width as per rule L-D1: 500
L2
mm greater than the maximum nominal distance between the inside faces of the outer pipe wall.
L2.1 Surrounds. Sand. Nominal bore: not exceeding 110 mm m $ 10.00
L2.2 Surrounds. Sand. Nominal bore: not exceeding 200 mm m $ 12.00
L2.3 Surrounds. Sand. Nominal bore: 200 - 300 mm m $ 15.00
L2.4 Surrounds. Sand. Nominal bore: 300 - 600 mm m $ 20.00
L2.5 Surrounds. Sand. Nominal bore: 600 - 900 mm m $ 22.00
L2.6 Surrounds. Sand. Nominal bore: 900 - 1200 mm m $ 25.00
L2.7 Surrounds. Imported granular material. Nominal bore: 160 mm m $ 15.00
L2.8 Surrounds. Reinforced concrete. Nominal bore: not exceeding 110 mm m $ 153.00
L2.9 Surrounds. Reinforced concrete. Nominal bore: not exceeding 200 mm m $ 183.00
L2.10 Surrounds. Reinforced concrete. Nominal bore: 200 - 300 mm m $ 256.00
L2.11 Surrounds. Reinforced concrete. Nominal bore: 300 - 600 mm m $ 356.00
L2.12 Surrounds. Reinforced concrete. Nominal bore: 600 - 900 mm m $ 658.00
L2.13 Surrounds. Reinforced concrete. Nominal bore: 900 - 1200 mm m $ 865.00
M STRUCTURAL STEELWORK
Structural metal to comply with MGP1-GEN-KBR-CS-7880-0021, Specification for Steel Works,
M1 MGP1-GEN-KBR-CS-7880-0002, Structural Steel Work General Notes
Rates do not include for painting.
M1.1 Fabrication of frames. Columns. Straight on plan. Not exceeding 3 t t $ 3,600.00
M1.2 Fabrication of frames. Columns. Straight on plan. Exceeding 3 t t $ 3,600.00
M1.3 Fabrication of frames. Beams. Straight on plan. Not exceeding 3 t t $ 3,600.00
M1.4 Fabrication of frames. Beams. Straight on plan. Exceeding 3 t t $ 3,600.00
M1.5 Fabrication of frames. Braces, purlins and cladding rails. Straight on plan. Not exceeding 3 t t $ 3,600.00
M1.6 Fabrication of frames. Braces, purlins and cladding rails. Straight on plan. Exceeding 3 t t $ 3,600.00
M1.7 Supply, Fabrication and Installation of Cladding 50mm thick m2 $ 150.00
2
M1.8 Fabrication and installation of heavy duty galvanised steel grating over cellars (41 to 90mm THK) m $ 200.00

M1.9 Fabrication and installation of heavy duty galvanised steel grating over cellars (upto to 40mm THK) m2 $ 200.00
M1.10 Fabrication and installation of heavy duty galvanised steel frames, 3.6m x 2.9m (atop cellars) t $ 4,000.00
Anchor bolts to comply with, MGP1-GEN-KBR-CX-7880-0003, MFD Anchor Bolt Details. Rate
includes for supply and installation of anchor bolts, nuts and washers, sleeves and post
M2
installation removal of sleeve and grout installation for anchor bolt hole. Grout between base
plate and concrete foundation covered in items G1.1 and G1.2
M2.1 Anchorages and holding down bolts. Straight on plan. Anchor bolt size M16 nr $ 50.00
M2.2 Anchorages and holding down bolts. Straight on plan. Anchor bolt size M20 nr $ 60.00
M2.3 Anchorages and holding down bolts. Straight on plan. Anchor bolt size M24 nr $ 75.00
M2.4 Anchorages and holding down bolts. Straight on plan. Anchor bolt size M30 nr $ 90.00
M2.5 Erection of members for frames including all bolted & welded connections. Permanent erection. t $ 2,000.00

All painting and painting preparation works shall be done in accordance with MGP1-GEN-KBR-
M3
RA-7754-0002, External Painting Specification for Equipment, Structural Steel & Piping
2
M3.1 Off site surface treatment. Blast cleaning. m $ 43.00

14 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


M3.2 Off site surface treatment. Painting. m2 $ 71.00
2
M3.3 Surface treatment- fireproofing paints to structural members m $ 56.00
M4 Reinforcement. Cut, bend to length and installed. Inclusive of all spacers and supports
Reinforcement. Deformed high yield steel bars to BS 4449:2005+A2:2009, Grade B500B. Nominal size
M4.1 t $ 500.00
6 mm
Reinforcement. Deformed high yield steel bars to BS 4449:2005+A2:2009, Grade B500B. Nominal size
M4.2 t $ 500.00
8 mm
Reinforcement. Deformed high yield steel bars to BS 4449:2005+A2:2009, Grade B500B. Nominal size
M4.3 t $ 500.00
10 mm
Reinforcement. Deformed high yield steel bars to BS 4449:2005+A2:2009, Grade B500B. Nominal size
M4.4 t $ 500.00
12 mm
Reinforcement. Deformed high yield steel bars to BS 4449:2005+A2:2009, Grade B500B. Nominal size
M4.5 t $ 500.00
16 mm
Reinforcement. Deformed high yield steel bars to BS 4449:2005+A2:2009, Grade B500B. Nominal size
M4.6 t $ 500.00
20 mm
Reinforcement. Deformed high yield steel bars to BS 4449:2005+A2:2009, Grade B500B. Nominal size
M4.7 t $ 500.00
25 mm
Reinforcement. Deformed high yield steel bars to BS 4449:2005+A2:2009, Grade B500B. Nominal size
M4.8 t $ 500.00
32 mm or greater
N MISCELLANEOUS METALWORK
Stairway, walkways, ladders, framing and flooring in accordance with:
MGP1-GEN-KBR-CS-7880-0003 Steelwork Standard Details of Handrail
N1 MGP1-GEN-KBR-CS-7880-0004 Steelwork Standard Details of Grating and Stair Treads
MGP1-GEN-KBR-CS-7880-0005 Steelwork Standard Details of Stairs
MGP1-GEN-KBR-CS-7880-0006 Steelwork Standard Details of Ladder
N1.1 Stairways and landings t $ 3,050.00
N1.2 Installation of Company Supplied Stair Pads nr $ 200.00
N1.3 Walkways and platforms t $ 3,050.00
N1.4 Ladders m $ 400.00
N1.5 Supply and Installation of Ladder rungs nr $ 10.00
N1.6 Handrail m $ 340.00
N1.7 Installation of Company Supplied Handrail m $ 100.00
N1.8 Supply, Fabrication and Installation of Handrail post pocket 1.5" nr $ 250.00
Miscellaneous framing. Angle section. Angle section L100 X 100 X 10 inclusive of tangs 30 x 6 x 300
N1.9 m $ 40.00
mm split up at end @ 300 mm CtC.Hot dipped galvanised post fabrication.
Miscellaneous framing. Angle section. Angle section L50 X 50 X 6 inclusive of tangs 30 x 6 x 300 mm
N1.10 m $ 26.00
split up at end @ 300 mm CtC.Hot dipped galvanised post fabrication.
Miscellaneous framing. Insert steel plates for concrete sleepers 12 mm thick, inclusive of tangs 30 x 6 x
N1.11 m2 $ 300.00
300 mm split up at end @ 200 mm CtC both ways. Hot dipped galvanised post fabrication.
Open grid flooring. Open steel flooring panels (grating) single span, pressed intermediate bars,
galvanised, anti-slip, mesh width 33 x 33 mm, bearing bars 35 x 5 mm, transverse bars 15 x 5 mm. Size
N1.12 m2 $ 650.00
as per drawings. Open steel flooring inclusive of frames, positioners, banding where appropriate and
fastener devices minimum 4 each/m2
N1.13 Installation of Company Supplied Safety Shower including fixing accessories nr $ 150.00
P PILES
Preformed reinforced concrete piles. Cross-sectional area 0.016 m2 (400 x 400 mm), length 23 m.
P2 Pile installation in accordance with MGP1-GEN-KBR-CG-7880-0011, Specification for Concrete
Piles.
P2.1 Supply only of 400x400 Precast piles inclusive of Mild Steel heads & shoes. 12m long nr $ 3,300.00
P2.2 Supply only of 400x400 Precast pile extensions inclusive of MS heads & shoes. 8m long nr $ 2,600.00
P2.3 Supply only of 400x400 Precast pile extensions inclusive of MS heads & shoes. 4m long nr $ 1,800.00
Pitching and driving Precast piles including splicing extensions, cut to level and preparation of heads for
P2.4 m $ 180.00
testing and/of pile-cap installation. Typical length 21m
Pitch and drive Company supplied 600mmm diameter tubular steel, closed-end bearing piles to set or
P2.5 level. Includes splicing lengths (full penetration butt welds & painting) cutting to level and preparing ends m $ 155.00
for testing and/or pile-caps
Q PILING ANCILLARIES
Pile tests. Maintained loading with various reactions. Test load 200-300 t to refusal. Testing in
Q1.1 accordance with MGP1-GEN-KBR-CG-7880-0012, Specification for Pile Testing. Test pile to nr $ 12,000.00
failure
R ROADS AND PAVINGS - Within Well Pad Limits
Road construction as per drawings MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Light
& Heavy Duty Roads, MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Temporary & Patrol
R1
Roads and in accordance with MGP1-GEN-KBR-CX-7880-0023, Specification for Roads and
Paving
R1.1 Sub-bases, flexible road bases and surfacing. Granular material Class A Road Base. m3 $ 28.00
R1.2 Sub-bases, flexible road bases and surfacing. Granular material Class B Road Base. m3 $ 30.00

15 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


R1.3 Sub-bases, flexible road bases and surfacing. Granular material Class C Road Base. m3 $ 18.50
Geotextile. Supply and installation of nonwoven geotextile, UV stabilised, tensile strenght minimum 12.5
R1.4 kN/m, tensile elongation maximum 60%, CBR punture resistance minimum 2250 N and permeability 65 m2 $ 5.00
l/m2s. Terram 1500 or similar. The area of additional geotextile in laps shall not be measured.
Geogrid. Max Tensile Strength ≥40 / ≥40 kN/m. Elongation at nominal strength, md/cmd ≤8 / ≤8 %.
Tensile strength at 2% elongation, md/cmd ≥13 / ≥13 kN/m. Tensile strength at 5% elongation, md/cmd
R1.5 m2 $ 5.50
≥26 / ≥26 kN/m, all to DIN EN ISO 10319 UV-resistance (remaining tensile strength) BS EN 12224 96.3
%. Weather resistance, FGSV, Class, high.
Double bituminous bitumen dressing in accordance with "Section R8 of Standard Specification for
R1.6 m2 $ 10.00
Roads & Bridges, Dept of Design & Studies, 1983-Republic of Iraq"
R1.7 Surfacing. Hot rolled asphalt base course. Depth: 60 mm. m2 $ 13.00
R1.8 Surfacing. Hot rolled asphalt base course. Depth: 100 mm. m3 $ 22.00
2
R1.9 Surfacing. Hot rolled asphalt wearing course. Depth: 50 mm m $ 11.00
Spot Hot rolled asphalt surface/wearing course for road repair area, inclusive of Tack Coat, all as per
R1.10 m2 $ 20.00
Specification Clause 9.3 and 10.4. Total layer thickness 100 mm.
R1.11 Sub-bases, flexible road bases and surfacing. Bituminous spray. Prime coat grade MC70. m2 $ 3.50
Supply and application of soil improvement chemical polymer through and atop internal and access
roads in accordance with manufacturer's instructions: "Top-Seal, by Bellestar Eco-Tec" or equivalent
R1.12 m3 $ 15.00
including seal coat and curing. (Alternative method of road construction. Mixed with existing soil then
seal coat applied)
6% by volume Cement stabilisation of existing in-situ soils including cement supply, mixing to 300mm
R1.13 m3 $ 35.00
depth, roll & compact to achieve minimum CBR of 30%. (As above)
R ROADS AND PAVINGS
Road construction as per drawings MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Light
& Heavy Duty Roads, MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Temporary & Patrol
R2
Roads and in accordance with MGP1-GEN-KBR-CX-7880-0023, Specification for Roads and
Paving
3
R2.1 Sub-bases, flexible road bases and surfacing. Granular material Class A Road Base. m $ 28.00
R2.2 Sub-bases, flexible road bases and surfacing. Granular material Class B Road Base. m3 $ 30.00
R2.3 Sub-bases, flexible road bases and surfacing. Granular material Class C Road Base. m3 $ 18.50
Geotextile. Supply and installation of nonwoven geotextile, UV stabilised, tensile strenght minimum 12.5
R2.5 kN/m, tensile elongation maximum 60%, CBR punture resistance minimum 2250 N and permeability 65 m2 $ 5.00
l/m2s. Terram 1500 or similar. The area of additional geotextile in laps shall not be measured.
Geogrid. Max Tensile Strength ≥40 / ≥40 kN/m. Elongation at nominal strength, md/cmd ≤8 / ≤8 %.
Tensile strength at 2% elongation, md/cmd ≥13 / ≥13 kN/m. Tensile strength at 5% elongation, md/cmd
R2.6 m2 $ 5.50
≥26 / ≥26 kN/m, all to DIN EN ISO 10319 UV-resistance (remaining tensile strength) BS EN 12224 96.3
%. Weather resistance, FGSV, Class, high.
Double bituminous bitumen dressing in accordance with "Section R8 of Standard Specification for
R2.7 m2 $ 10.00
Roads & Bridges, Dept of Design & Studies, 1983-Republic of Iraq"
R2.8 Surfacing. Hot rolled asphalt base course. Depth: 100 mm. m2 $ 22.00
R2.9 Surfacing. Hot rolled asphalt wearing course. Depth: 50 mm m2 $ 11.00
R2.10 Sub-bases, flexible road bases and surfacing. Bituminous spray. Prime coat grade MC70. m2 $ 3.50
Supply and application of soil improvement chemical polymer through and atop internal and access
R2.11 roads in accordance with manufacturer's instructions: "Top-Seal, by Bellestar Eco-Tec" or equivalent m3 $ 15.00
including seal coat and curing. (Alternative method of road construction)
6% by volume Cement stabilisation of existing in-situ soils including cement supply, mixing to 300mm
R2.12 m3 $ 35.00
depth, roll & compact to achieve minimum CBR of 30%. (As above)
Concrete pavement. In-situ sidewalks slabs with B503 steel mesh reinforcement. 2
R2.13 m $ 20.00
Depth 150 mm on 75mm sand bedding on levelled, compacted sub-base
Kerbs. Precast concrete kerbs to BS 7263: Half Batter 2 (HB2), 255 x 125 mm. Straight or curved to
R2.14 m $ 50.00
radius exceeding 12 m on 35mm lean-mix concrete blinding layer
Kerbs. Precast concrete edgings to BS 7263: 150 x 50 mm. Straight or curved to radius exceeding 12 m
R2.15 m $ 35.00
on 25mm lean-mix concrete blinding layer.
Light duty pavements. Precast concrete interlocking flags to BS 6717. Depth: 60 mm on 50mm sand
R2.16 m2 $ 35.00
bedding
R2.17 Install precast Jersey Barriers as detailed in item H1.6 nr $ 300.00
Ancillaries. Traffic Signs (inclusive of all foundation, supporting posts, excavation, etc. as per
rule C9) and surface markings as per drawings MFD-GEN-FWK-CX-7880-0013-001-001 to 004,
R3
MFD Road Marking & Signage Typical Details and MFD-GEN-FWK-CX-7880-0014-001&2-001, MFD
Sign Board Mountaing Foundation & Structural Details
R3.1 Non illuminated. Regulatory sign type R1 to R6, R13 to R 18 and R 20. Warning Sign type W1 to W 14 nr $ 500.00
R3.2 Non illuminated. Regulatory sign type R9, R10, R21. Place identification sign D2 nr $ 500.00
R3.3 Non illuminated. Regulatory sign type R7 & R8 nr $ 500.00
R3.4 Non illuminated. Distance sign D1A, D1B, D3,D3B nr $ 500.00

16 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


R3.5 Non illuminated. Warning sign W15, 16 & 17 nr $ 500.00
R3.6 Non illuminated. Information sign IF nr $ 500.00
Ancillaries. Surface markings. Road Paint. White or yellow reflective road marking paint DFT 0.3
R4 2
mm with surface applied glass beads 400 g/m
R4.1 Ancillaries. Surface markings. Reflective road studs nr $ 23.00
R4.2 Ancillaries. Surface markings. Letters and shapes RM1 to RM4 nr $ 39.00
R4.3 Ancillaries. Surface markings. Continuous lines. White parking separation line wide 100 mm RM5 m $ 7.00
R4.4 Ancillaries. Surface markings. Continuous lines. White stop line wide 300 mm RM7 m $ 15.00
R4.5 Ancillaries. Surface markings. Continuous lines. White zebra line wide 500 mm RM7 m $ 20.00
R4.6 Ancillaries. Surface markings. Continuous lines. Yellow edge of carriageway line wide 150 mm RM7 m $ 12.00

R4.7 Ancillaries. Surface markings. Continuous lines. White center of carriageway line wide 150 mm RM8 m $ 12.00

R4.8 Ancillaries. Surface markings. Intermittent lines. White center of carriageway line wide 150 mm RM8 m $ 20.00
Fences. Road restraint system. Bollards and crash barriers in accordance with MGP1-GEN-KBR-
R5 CX-7880-0008, Typical Details of Crash Barriers & Bollards. Includes for all associated
earthworks, concrete works, support steel and painting.
R5.1 Bollards. nr $ 75.00
R5.2 Crash barriers. Galvanised m $ 100.00
V PAINTING

All painting and painting preparation works shall be done in accordance with All painting and
V1 painting preparation works shall be done in accordance with MGP1-GEN-KBR-RA-7754-0002,
External Painting Specification for Equipment, Structural Steel & Piping;
Coating System CS-1; zinc rich epoxy primer, epoxy MIO and polyurethane. Metal, other than metal 2
V1.1 m $ 121.00
sections and pipework.
2
V1.2 Coating System CS-1; zinc rich epoxy primer, epoxy MIO and polyurethane. Metal sections & pipework m $ 128.00
Epoxy or polyurethane paint. Smooth concrete. Exposed concrete surfaces protection as per
MGP1-GEN-KBR-CX-7880-0004, MFD Concrete Protection Standard Details Standard Details
V2
Concrete Protection. Two coats of light grey colour Fosroc® Nitocoat EP403 Epoxy Resin or
similar
V2.1 Epoxy paint to all underground Precast concrete elements. m2 $ 32.00
W WATERPROOFING
All painting and painting preparation works shall be done in accordance with MGP1-GEN-KBR-
W1 CX-7880-0021, Technical Specification for Concrete Works Section10, Concrete Protection item
b. Modified bitumen.
Waterproofing. Waterproof coating. Upper surfaces inclined at an angle not exceeding 30° to the
W1.1 m2 $ 81.00
horizontal.
W1.2 Waterproofing. Waterproof coating. Upper surfaces inclined at an angle exceeding 60° to the horizontal. m2 $ 81.00
W680 Supply and installation of 1000 gauge (250 μm) polythene m2 $ 1.50
Protective layers. Sand and cement screed. Mix: sand 4, cement 1. Inclusive of construction
W2
mesh A142 to BS 4483:2005. Nominal mass 2.22 kg/m2.
Protective layers. Sand and cement screed. Upper surfaces inclined at an angle not exceeding 30° to
W2.1 m2 $ 75.00
the horizontal.
2
W2.2 Waterproofing. Sand and cement screed. Upper surfaces inclined at 30° - 60° to the horizontal. m $ 90.00
Waterproofing. Sand and cement screed. Upper surfaces inclined at an angle exceeding 60° to the
W2.3 m2 $ 90.00
horizontal.
X MISCELLANEOUS WORK

Fences to BS 1722-10:2006. Zinc coated mesh wire, mesh size 40-50 mm, zinc coated wire,
diameter 3.0 mm. Zinc coated line wire, diameter 4.00 mm. Zinc coated stirrup wire, diameter 2.5
X1
mm. Zinc coated tying wire, diameter 1.60 mm. Inclusive of all fittings. Other details as per MGP1-
GEN-KBR-CX-7880-0007 , Standard Detail for Single Chain link Fence
Internal fences. Metal post and wire. Height 1.00 m. Includes for galvanised top and bottom rail diameter
X1.1 m $ 25.00
42 mm.
Internal fences. Metal post and wire. Height 2.00 m. Includes for galvanised top and bottom rail diameter
X1.2 m $ 35.00
42 mm.
Security fences. Metal post and wire. Height 2.50 m. Includes for double extension arms, 6 rows of
X1.3 m $ 45.00
barbed wire and razor wire top.

17 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Installation only of Company Supplied HERAS M500 anti-climb temporary security fencing. Metal post
X1.4 and welded mesh. Inclusive of concrete foundation block, connection clamp,intermediate strut and anti- m $ 15.00
lift device. Installation as per Heras Assembly Manual Mobile Fence.

X1.5 Installation only of Company Supplied HERAS gates. Installation as per HERAS installation manual. nr $ 200.00
X2 Additional Miscellaneous Rates as per COMPANY requirements
Concrete accessories. Inserts. Other inserts. Halfen Cast-in Channels HTA-CE 50/30, inclusive of 6
X2.1 m $ 150.00
each M20 GVs 8.8 x 60 mm anchor bolts.
Concrete accessories. Inserts. Other inserts. Halfen Frimeda Plate Anchor, Load Group 2.5 t, TPA-FP
X2.2 2,5- 8 FV hot dipped galvanized. Inclusive of 1 each recess former TPA-A1 2,5 per 25 Plate Anchors nr $ 100.00
and 1 each Ring Clutch TPA-R1 2,5 per 250 Plate Anchors.
Light duty pavements. Precast concrete interlocking flags to BS 6717. Depth: 60 mm on 50 mm sand
X2.3 m² $ 100.00
bedding
X2.4 Supply and installation of pre cast speed humps nr $ 500.00
X2.5 Supply and install New Precast jersey barriers nr $ 300.00
Supply & Installation of windsock pole c/w foundation, grouting and anchor bolts in accordance with
X2.6 MGP1-GEN-KBR-CG-4017-1029-001_002. Refer to General Arrangment Drawinig contained under nr $ 1,250.00
Vendor Document Review Sheet Doc No. MGP1-POMJOH0142-C08-0018_004
X2.7 Supply, Install Windsock (Cloth only) nr $ 150.00
X2.8 Supply, fabircation & Installation of Steel Checkered Plate 6mm thick m² $ 200.00
X2.9 Supply, fabircation & Installation of Steel Checkered Plate 8mm thick m² $ 250.00
X2.10 Supply, fabircation & Installation of Steel Checkered Plate 10mm thick m² $ 275.00
Supply and Installation of bitumen paint Sika® Igolflex-205 (coating thickness 1000microns) Two
X2.11 component, cement and bitumen rubber based waterproofing coating. Waterproofing and damp-proofing m² $ 10.00
of below ground concrete structures.
X2.12 Take up and relocate existing precast cover slabs to COMPANY stores within Majnoon concession. nr $ 50.00
Installation of COMPANY provided precast cover slabs.
X2.13 nr $ 150.00
CONTRACTOR shall transport COMPANY provided precast cover slabs from Majnoon stores to the
WORKSITE including loading and unloading.
Installation of COMPANY provided Stelcon slabs.
X2.14 nr $ 150.00
CONTRACTOR shall transport COMPANY provided precast Stelcon slabs from Majnoon stores to the
WORKSITE including loading and unloading.
X2.15 Take up and relocate existing Stelcon slabs to COMPANY stores within Majnoon concession. nr $ 150.00

18 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Installation of COMPANY provided precast foundation (weight not exceeding 5 t)
X2.16 nr $ 250.00
CONTRACTOR shall transport COMPANY provided precast foundation from Majnoon stores to the
WORKSITE including loading and unloading.
X2.17 Installation of perforated HDPE pipe 100 mm m $ 15.00
X2.18 Installation of perforated HDPE pipe 160 mm m $ 20.00
X2.19 Installation of perforated HDPE pipe 200 mm m $ 25.00
X2.20 Installation of Company Supplied Handrail m $ 150.00
Road construction as per drawings MGP1-GEN-KBR-CX-7880-0012 , Typical Road Sections Light &
Heavy Duty Roads, MGP1-GEN-KBR-CX-7880-0012 , MFD Typical Road Sections Temporary & Patrol
X2.21 Roads and in accordance with MGP1-GEN-KBR-CX-7880-0023, Specification for Roads and Paving. m $ 2,000.00
Rate shall include subgrade preperation, applicable Tests, Subbase Type - A, geogrid, Geotextile,
asphalt layers and both sides shoulders (unpaved) as per typical Cross section details
X2.22 Relocation of existing T-Walls within Majnoon concession nr $ 100.00
Installation of safety signs with all associated items including bolts,nuts,washers in accordance with
X2.23 nr $ 200.00
safety seign specification MGP1-GEN-KBR-HX-7880-0002
X2.24 Installation of windsock with associated items (i. e. bolts, plates, nuts and etc.) nr $ 250.00
X2.25 Concrete repair works (surface cracks using suitable repair material to be approved by COMPANY) m² $ 75.00
Supply, laying, compaction and Testing of sub-base filling material of Class E type in accordance with
X2.26 specification for earthworks (MGP1-GEN-KBR-CX-7880-0022) and road works (MGP1-GEN-KBR-CX- m3 $ 8.00
7880-0023)
3
X2.27 Filling. General. Imported natural material. Hard limestone rock nominal size 50 to100 mm m $ 45.00
X2.28 Filling. General. Imported natural material. Hard limestone rock nominal size 100 to150 mm m3 $ 45.00
X2.29 Filling. General. Imported natural material. Hard limestone rock nominal size150 to 200 mm m3 $ 50.00
X2.30 Filling. General. Imported natural material Class A. m3 $ 25.00
X2.31 Supply & Install 10 meter steel light pole c/w required electrical connection and junction boxes nr $ 1,500.00
Supply and Installation of safety sign foundation pole - Type A as per MGP1-GEN-KBR-CG-4017-1041-
X2.32 nr $ 300.00
001
Supply and Installation of safety sign foundation pole - Type B as per MGP1-GEN-KBR-CG-4017-1041-
X2.33 nr $ 350.00
001
Take up and relocate existing HERAS M500 anti-climb temporary security fencing to COMPANY stores
within Majnoon concession. Take up shall include all posts and welded mesh, concrete foundation
X2.34 m $ 15.00
blocks, connection clamps, intermediate strut and anti-lift device shall be in accordance with applicable
Heras Assembly Manual Mobile Fence procedures
Z Landscaping
Z1 Conocarpus lanceolins, Common name Stem -Damas nr $ 6.00
Z2 Terminalia catalpa, Common name Indian almond nr $ 18.00
Z3 Pennisetum secateur - Common name - Fountain grass nr $ 12.00
Z3 Acacia Redolens - adaptive G. Cover plants nr $ 18.00
Z4 Organic Filtalizer Tonne $ 120.00
Z5 Adentative Soil Berlight Ltr $ 1.80
Z6 Getoxile Protective Layer (1m wide) m $ 2.40
Y Irrigation
Y1 Tank GRP - Volume 400 cu.m nr $ 94,000.00
Y2 Set Pump - Head Flow 24 cu.m/hr , Head 7 Bar (1set of 2 Pumps) lot $ 24,000.00
Y3 Sleeve for Crossing Irrigation Pipes 3inch Dia, Length 8m m $ 90.00
Y4 Sleeve for Crossing Electric cable 1.5 inch Dia, Length 8m m $ 60.00
Y5 Electric Solid/ Solenoid 2" Valve nr $ 90.00
Y6 Brass Gate Valve 2 inches nr $ 90.00
Y7 Iron Union 2inches nr $ 18.00
Y8 Pressure regulator nr $ 180.00
Y9 Valve Box HDEP nr $ 60.00
Y10 Elbow 90 Digree nr $ 12.00
Y11 Solvent Cement Cans 500g nr $ 24.00
Y12 uPVC Pipe 3 inches class 10 m $ 19.00
Y13 uPVC Pipe 2 inches class 10 m $ 14.00
Y14 Dripline Pipe LDEP Rolls, 400m each, Distance 30m, Flow 2 .72 L/Hr nr $ 90.00
Y15 16mm LDEP Pipe Rolls, 400m each, Distance 30cm, Flow 3.42 L/Hr nr $ 90.00
Y16 Flashing Pole Valve 1.5 inch nr $ 36.00

19 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 3: ALL INCLUSIVE WORKS UNIT RATES

Number Item Description Unit Unit Rate(USD)


Y17 Irrigation (Conditional)
Y18 Valve Box 12 Inches nr $ 36.00
Y19 Warning Tape m $ 1.00
Y20 Drainage Pipe 1.5m length m $ 6.00
Y21 Drainage Pipe Elbow 1.5m nr $ 12.00
Y22 Drainage Pipe Valve 1.5m. nr $ 30.00
Y23 Drainage T 3inch x 2inch nr $ 18.00
Y24 Drainage T 2inch x 1.5inch nr $ 14.00
Y25 Adapter 1.5x16mm LDP nr $ 12.00
Y26 Role 16mm Blank nr $ 90.00
Y27 Incapp 16mm 8 Form LDP nr $ 12.00
Y28 End Capp 3inch nr $ 18.00
Y29 Solvent Clearance Can 200g nr $ 24.00
Y30 Irrigation cables including Auto. system controller ls $ 40.00

20 of 25
Section IVA - Schedule of Prices Contract BOC-1962 Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 4: UNIT RATES FOR CONSTRUCTION PERSONNEL

Rate (US$)
ITEM NO. CATEGORY OVERTIME HOURLY STANDBY HOURLY
DAY RATE WEEKLY RATE MONTHLY RATE
RATE RATE
1 Blacksmith $ 100.00 $ 600.00 $ 2,700.00 $ 15.63 $ 12.50
2 Carpenter $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
3 Certified Painter $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
4 Chainman $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
5 Civil Labourer $ 40.00 $ 240.00 $ 1,080.00 $ 6.25 $ 5.00
6 Concrete Labourer $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
7 Crane Operator $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
8 Crane Rigger $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
9 Crane Truck Driver $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
10 Draughtsman $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
11 Dump Truck Driver $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
12 Earthworks Equipment Operator $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
13 Electrician $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
14 Fencing erector $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
15 Flagman (Local) $ 40.00 $ 240.00 $ 1,080.00 $ 6.25 $ 5.00
16 Flatbed Driver (40 ft) $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
17 Foreman Concrete $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
18 Foreman Earthworks $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
19 Foreman General $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
20 Foreman Pavement Works $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
21 Formwork Carpenter $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
22 Gas Testers $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
23 General Labourer/Unskilled Operative (Local) $ 40.00 $ 240.00 $ 1,080.00 $ 6.25 $ 5.00
24 GRP jointer $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
25 HSE Officer $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
26 Light Duty Driver $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
27 Bus Driver (bus capacity 30 - 50 persons) $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
28 Mason $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
29 Permit to Work Holder $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
30 Pipelayers (drains/ducts) $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
31 Plasterer $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
32 Paver $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
33 QA/QC Officer $ 100.00 $ 600.00 $ 2,700.00 $ 15.63 $ 12.50
34 Rebarman $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
35 Sandblaster $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
36 Scaffolder $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
37 Structural Steel Erector $ 60.00 $ 360.00 $ 1,620.00 $ 9.38 $ 7.50
38 Structural Steel Welder $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
39 Warehouse Assistant $ 50.00 $ 300.00 $ 1,350.00 $ 7.81 $ 6.25
40 Welder $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38
41 Certified First Aider $ 75.00 $ 450.00 $ 2,025.00 $ 11.72 $ 9.38

*** NOTES ***


Note 1 Day Rate is applicable to twelve (12) hours/day (inclusive of lunch & coffee breaks)
Note 2 Weekly Rate is applicable to twelve (12) hours/day (inclusive of lunch & coffee breaks) & six (6) days/week (from Saturday to Thursday)
Note 3 Monthly Rate is applicable to twelve (12) hours/day (inclusive of lunch & coffee breaks) & six (6) days/week per calendar month
Note 4 Overtime Hourly Rate is applicable to all hours worked in excess of twelve (12) hours per day (Saturday through Thursday), Friday working & public holidays
Note 5 Standby Hourly Rate is to be applied to Standby Time, subject to notification and substantiation in accordance with the CONTRACT
Note 6 The above rates shall be all-inclusive rates that include, but not limited to, all costs as outlined in Article 3.0. of Section IV - Schedule of Prices and are applicable per individual.
Note 7 The above rates are all-inclusive rates which shall be in compliance with all APPLICABLE LAWS
Note 8 The above rates shall include provision of small tools. Small tools are defined as tools costing an amount that is equivalent of US Dollar $1500.00 and below
Note 9 The above rates are inclusive of personnel mobilisation to and demobilisation from the WORKSITE, provision of food, drinking water, PPE & the like

Note 10 The above rates shall allow for all indirect supervision including, but not limited to, all HSE personnel, QA/ QC personnel, Permit to Work Applicants / Holders and First Aiders. CONTRACTOR shall not be
separately compensated for indirect supervision, unless COMPANY expressly requests these

Page 21 of 25
Section IVA - Schedule of Prices Contract BOC-1962 - Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 5: RATES FOR CONSTRUCTION EQUIPMENT

Rate (US$)

ITEM NO. CATEGORY MOBILIZATION DEMOBILIZATION STANDBY RATE


HOURLY RATE DAILY RATE WEEKLY RATE MONTHLY RATE
RATE RATE PER HOUR

1 Bobcat with bucket and brush attachment $ 250.00 $ 250.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50

2 JCB 3C Excavator or equivalent $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75

3 Cat 225 Excavator or equivalent, bucket capacity 1 m3 $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50

4 Cat 225 Excavator or equivalent with rock breaker $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50

5 Cat 235 Excavator or equivalent, bucket capacity 2 m3 $ 350.00 $ 350.00 $ 40.63 $ 325.00 $ 1,950.00 $ 8,027.50 $ 40.63

6 Cat 235 Excavator or equivalent with rock breaker $ 350.00 $ 350.00 $ 56.25 $ 450.00 $ 2,700.00 $ 11,115.00 $ 56.25

7 Cat D6 track-type Tractor or equivalent, 150 hp, blade capacity >3 m3 $ 350.00 $ 350.00 $ 50.00 $ 400.00 $ 2,400.00 $ 9,880.00 $ 50.00

8 Cat D8 track-type Tractor or equivalent, 300 hp, blade capacity >8 m3 $ 350.00 $ 350.00 $ 75.00 $ 600.00 $ 3,600.00 $ 14,820.00 $ 75.00

9 Cat 950 wheel type Loader or equivalent, 130 hp, bucket capacity >1.5 m3 $ 350.00 $ 350.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

10 Cat 960 wheel type Loader or equivalent, 210 hp, bucket capacity >3.5 m3 $ 350.00 $ 350.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

11 Cat 12H Grader or equivalent, 150 hp, blade width 3.6 m, height 0.6 m $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50

12 Cat 14H Grader or equivalent, 215 hp, blade width 4.3 m, height 0.7 m $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50

13 10 ton Vibratory Soil Compactor (Roller) $ 350.00 $ 350.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

14 18 ton Vibratory Soil Compactor (Roller) $ 350.00 $ 350.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50

15 2 ton Utility Roller (Tandem Roller), Caterpillar CB 22 or similar $ 350.00 $ 350.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

16 10 ton Tandem Vibratory Roller, Caterpillar CB 54 or similar $ 350.00 $ 350.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

17 Vibratory Rammer WackerNeuson BS 50 or equal $ 200.00 $ 200.00 $ 15.63 $ 125.00 $ 750.00 $ 3,087.50 $ 15.63

18 Single Direction Vibratory Plate Compactor, impact >18 kN $ 100.00 $ 100.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.00 $ 9.38

19 Reversible Vibratory Plate Compactor, impact >35 kN $ 100.00 $ 100.00 $ 12.50 $ 100.00 $ 600.00 $ 2,470.00 $ 12.50

20 Auger pole hole (>400 mm diameter) drilling machine or equivalent $ 500.00 $ 500.00 $ 187.50 $ 1,500.00 $ 9,000.00 $ 37,050.00 $ 187.50

21 20 ton All Terrain Crane $ 250.00 $ 250.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75

22 60 ton All Terrain Crane $ 350.00 $ 350.00 $ 62.50 $ 500.00 $ 3,000.00 $ 12,350.00 $ 62.50

23 100 ton All Terrain Crane $ 500.00 $ 500.00 $ 125.00 $ 1,000.00 $ 6,000.00 $ 24,700.00 $ 125.00

24 10 ton Truck with Telescopic Crane 3 t (HIAB) $ 250.00 $ 250.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75

25 10 ton Truck with Telescopic Crane 5 t (HIAB) $ 250.00 $ 250.00 $ 50.00 $ 400.00 $ 2,400.00 $ 9,880.00 $ 50.00

26 20 ton Truck with Telescopic Crane 10 t (HIAB) $ 350.00 $ 350.00 $ 62.50 $ 500.00 $ 3,000.00 $ 12,350.00 $ 62.50

27 5 ton Flat Bed Truck $ 150.00 $ 150.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

Page 22 of 25
Section IVA - Schedule of Prices Contract BOC-1962 - Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 5: RATES FOR CONSTRUCTION EQUIPMENT

Rate (US$)

ITEM NO. CATEGORY MOBILIZATION DEMOBILIZATION STANDBY RATE


HOURLY RATE DAILY RATE WEEKLY RATE MONTHLY RATE
RATE RATE PER HOUR

28 7.5 ton Flat Bed Truck $ 150.00 $ 150.00 $ 28.13 $ 225.00 $ 1,350.00 $ 5,557.50 $ 28.13

29 20 ton Flat Bed Truck $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

30 40 ton Flat Bed Truck $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75

31 5 ton Tipper Truck $ 150.00 $ 150.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75

32 20 ton Tipper Truck $ 200.00 $ 200.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

33 40 ton Tipper Truck $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75

34 20 000 litre Water Bowser $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

35 40 000 litre Water Bowser $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75

36 Vacuum Tanker 9 000 litres $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

37 Vacuum Tanker 20 000 litres $ 250.00 $ 250.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50

38 2 ton Pick up Truck 4 x 4 single/double cabin $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38

39 3 ton Pick up Truck 4 x 4 single/double cabin $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38

40 Passenger bus 15 seater $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38

41 Passenger Bus 26 / 30 Seater $ 150.00 $ 150.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75

42 Passenger Bus 50 Seater $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

43 TOYOTA Land Cruiser $ 150.00 $ 150.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75

44 140 cfm Compressor $ 250.00 $ 250.00 $ 37.50 $ 300.00 $ 1,800.00 $ 7,410.00 $ 37.50

45 250 cfm Compressor $ 250.00 $ 250.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75

46 4.5 kVA Diesel Generator $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38

47 100 kVA Diesel Generator $ 250.00 $ 250.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75

Trash pump 4 inch, trailer mounted, inclusive of 10 m suction hose and 50 m


48 $ 250.00 $ 250.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75
discharge hose
Trash pump 6 inch, trailer mounted, inclusive of 10 m suction hose and 50 m
49 $ 250.00 $ 2,450.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00
discharge hose

50 Submersible pump $ 150.00 $ 150.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38

51 Poker Vibrator for Concrete, shaft diameter >60 mm $ 250.00 $ 250.00 $ 93.75 $ 750.00 $ 4,500.00 $ 18,525.00 $ 93.75

52 Jack hammer / Rock Drill >60 J impact $ 250.00 $ 250.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

53 Rebar cutter, maximum diameter 30 mm $ 250.00 $ 250.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75

54 Rebar bending machine, maximum diameter 30 mm $ 250.00 $ 250.00 $ 18.75 $ 150.00 $ 900.00 $ 3,705.00 $ 18.75

Page 23 of 25
Section IVA - Schedule of Prices Contract BOC-1962 - Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 5: RATES FOR CONSTRUCTION EQUIPMENT

Rate (US$)

ITEM NO. CATEGORY MOBILIZATION DEMOBILIZATION STANDBY RATE


HOURLY RATE DAILY RATE WEEKLY RATE MONTHLY RATE
RATE RATE PER HOUR

55 Chain blocks, up to 6.1m lift; 3 t $ 250.00 $ 250.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

56 Chain blocks, up to 6.1m lift; 4 t $ 250.00 $ 250.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

57 Pull lift (Tirfor type); 1.5 t $ 250.00 $ 250.00 $ 28.13 $ 225.00 $ 1,350.00 $ 5,557.50 $ 28.13

58 Pull lift (Tirfor type); 3 t $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

Articulated Boom Lift (manlift). Working height >20 m, lift capacity >225 kg,
59 horizontal reach >18 m, Up & Over Clearance >8.5 m. Genie (Terex) Z-80/60 or $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
equal
Slab Scissor Lift. Working height >8 m, lift capacity >350 kg, gradeability 30%.
60 $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
Genie (Terex) GS 2032 or equal

61 Total Station Leica TS 30 with all accessories $ 75.00 $ 75.00 $ 9.38 $ 75.00 $ 450.00 $ 1,852.50 $ 9.38

62 Level, automatic, inclusive of staff Leica NA 700 $ 50.00 $ 50.00 $ 6.25 $ 50.00 $ 300.00 $ 1,235.00 $ 6.25

63 Survey equipment- pipe and cable locator, Radio detection RD 7000 $ 50.00 $ 50.00 $ 6.25 $ 50.00 $ 300.00 $ 1,235.00 $ 6.25

64 Communication set - 2 way Radio reach 2 km $ 50.00 $ 50.00 $ 6.25 $ 50.00 $ 300.00 $ 1,235.00 $ 6.25

65 Hydrotest equipment. High pressure test pump (30 bar) for piping $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

Confined Space Ventilator 12' diameter. Free air flow >70 m3/min. Inclusive of 8
66 $ 250.00 $ 250.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25
m duct hoses. Schaefer VAF 3000B or similar.
67 Hydraulic jack 30 t $ 350.00 $ 350.00 $ 43.75 $ 350.00 $ 2,100.00 $ 8,645.00 $ 43.75

68 Paint spraying equipment $ 150.00 $ 150.00 $ 31.25 $ 250.00 $ 1,500.00 $ 6,175.00 $ 31.25

69 Blasting equipment $ 150.00 $ 150.00 $ 25.00 $ 200.00 $ 1,200.00 $ 4,940.00 $ 25.00

*** NOTES ***

Note 1 Mobilisation & Demobilisation Rates will only be applicable if Construction Equipment is not already located at site
Note 2 The above rates exclude the cost of operators or drivers
Note 3 The above rates are all-inclusive rates which shall be in compliance with all APPLICABLE LAWS
Note 4 The above rates are inclusive of Construction Equipment maintenance, repair, rental, insurance, taxes, etc. and any necessary consumables including, but not being limited to, fuel, lubricants, spare parts, etc
Note 5 COMPANY will compensate the lesser of the hourly, daily, weekly and monthly rate. At no time will COMPANY compensate CONTRACTOR in excess of the total monthly rate.
Note 6 Mobilisation & demobilisation will not be compensated under any cicumstances where N/A is marked by COMPANY in the appropriate column.

Page 24 of 25
Section IVA - Schedule of Prices Contract BOC-1962 - Ancillary Roads and Infrastructure
Revision 01

PRICING TABLE 6: MATERIALS AND THIRD PARTY SERVICES

DIRECT MATERIALS

Note: CONTRACTOR shall be compensated for the net quantity and net invoiced cost of Materials delivered
to the Site in the performance of additional Work, supported by Vendor's invoice showing the actual
purchase price net, including any cash or trade discounts.

1.0 Mark-up including all cost for taking delivery, handling, storing and issuing of Materials delivered to the
Site in the performance of additional Works, including any allowances, overhead costs and profit or
any mark-up whatsoever. 18% (Mark up)

SUBCONTRACTORS / THIRD PARTY SERVICES

Note: CONTRACTOR shall be compensated for the provision of SUBCONTRACTOR/ Third Party Services for additional Works
as instructed by COMPANY either on or off-site for the net invoiced cost to CONTRACTOR by
the Third Party.

2.0 Mark-up including all costs for the provision of SUBCONTRACTOR/THIRD Party Services for additional Works,
including all overheads and profit, and any other margin or mark-up whatsoever. 18 % (Mark up)

COMPANY ARRANGED IMPORTED MATERIALS

Mark-up including all cost for taking delivery, handling, storing and issuing of Materials delivered to the
Site in the performance of additional Works, including any allowances, overhead costs and profit or
any mark-up whatsoever.

3.0 Mark-up including all cost for taking delivery, handling, storing and issuing of Materials delivered to the
Site in the performance of additional Works, including any allowances, overhead costs and profit or
any mark-up whatsoever. 18% (Mark up)

DEMOBILISATION & REMOBILISATION FEE (ref Section IV, Article 8.2) (Lump Sum, US$) $ 15,000.00

Page 25 of 25