BOC-1962 Ancillary Roads

and Infrastructure

BOC-1962

DAILY PROGRESS REPORT NO. 249


DATED 23-5-2024

001 Issued for Information 23-May-24 Ali Hussein Monthir S Sudeep D

Rev. Reason for Issue Date Author Reviewer Approver

Rev.
ANRD-INF-MFC-AA-6944-0249
ANRD-INF-MFC-AA-6944-0249
001
DAILY PROGRESS REPORT
BOC-1962 Ancillary Roads and
Infrastructure
Work Order Title Contract No. Project Manager

Majnoon Oil Field Development Work Order-03 (MCPP Road) BOC-1962 Monthir Saleh
Sequence Report Date Weather Temperature (°C)
23/May/2024 ✘ Sunny ✘ Normal Max/Day 37°C
ANRD-INF-MFC-AA-6944-249 Progress Date Cloudy Foggy Min/Night 28°C
23/May/2024 Rainy Windy
HSSE observations:
No HSE Observations

Resources Deployed:
Manpower Equipment/Vehicles Material Received for this day
Category Nos. Category Nos. Description Unit Qty
A. Indirect Manpower Direct Equipment
BOC-1962-AA-9003-0001-Design and Construction of SGTF North BOC-1962-AA-9003-0001-Design and
27
Access Road Construction of SGTF North Access Road
BOC-1962-AA-9003-0003- Design and Construction of MCPP North BOC-1962-AA-9003-0003- Design and
0
Access Road 19 Construction of MCPP North Access Road

BOC-1962-AA-9003-0004-Design and Construction of Shams North BOC-1962-AA-9003-0004-Design and


0
Access Road Construction of Shams North Access Road
B. Direct Manpower (Site) Work Shop Equipment
BOC-1962-AA-9003-0001-Design and Construction of SGTF North BOC-1962-AA-9003-0001-Design and
11 0
Access Road Construction of SGTF North Access Road
BOC-1962-AA-9003-0003- Design and Construction of MCPP North BOC-1962-AA-9003-0003- Design and
11 0
Access Road Construction of MCPP North Access Road
BOC-1962-AA-9003-0004-Design and Construction of Shams North BOC-1962-AA-9003-0004-Design and
0 0
Access Road Construction of Shams North Access Road

Total 41 Total 27

Activities of the Day Next Day Activities


Today's Accu.
Item
Progress Progress

BOC-1962-AA-9003-0001-Design and Construction of SGTF North Access Road


Wating the approval for the new drawing ( new
1- 0% 0% 1-
coordinates )

2- Geogrid and Geotextile available and storage at camp 0% 0% 2-

BOC-1962-AA-9003-0003- Design and Construction of MCPP North Access Road


preparing sub-grade layer for mcpp road involving ( grading ,
1- 0% 63% 1- Taking sand replacement test for sub-grade layer for the mcpp road
leveling )

2- compacting the sub-garde layer 0% 60% 2-

3- excavating the 3 berms at mcpp road 0% 75% 3-

4- taking rsk for sub grade layer 0% 50% 4-

5- stacking sub-base type A for the mcpp road 0% 50% 5-

6- processing swelling soil for the Mcpp road 0% 60% 6-

taking sand replacement test for sub-grade layer for the


7- 100% 100% 7-
mcpp road from st + 1400 to + 1480

BOC-1962-AA-9003-0004-Design and Construction of Shams North Access Road

1- Still Under Design Stage

Concerns/Remarks

Page 3 of 12
Resources Deployed: Manpower
Manpower
BOC-1962-AA-9003-0001-Design and BOC-1962-AA-9003-0003- Design and
Construction of SGTF North Access Construction of MCPP North Access
Road Road
Category

Expat Iraqi Expat Iraqi

A. Indirect Manpower 2 16 1
Project Manager 1
Planning Engineer 1
Document Controller 1
C&P Engineer 1
HSE Manager 1
Quality Manager 1
Security Manager 1
First Aider 1
Road Design Engineer 1
HSE Supervisor 1
Constrcution Supervisor 1
Lifting Supervisor 1
Permit Applicant 1
Quality Inspector 1
Journey Manager 1
Permit Holder 1 1
construction manager 1
Civil superintendent 1
B. Direct Manpower 0 11 11
Surveyor 1 1
Flag man 2 2
Driver 5 5
HouseKeeper 1 1
Electrician 1 1
Mechanical 1 1

Total 2 27 0 12

Page 4 of 12
Resources Deployed: Equipment/Vehicles
Equipment/Vehicles

BOC-1962-AA-9003-0001-Design and Construction BOC-1962-AA-9003-0003- Design and BOC-1962-AA-9003-0004-Design and


of SGTF North Access Road Construction of MCPP North Access Road Construction of Shams North Access Road
Category

Nos. Nos. Nos.

Direct Equipment 27 0 0
Pickups (Own) 3
Pickups (Supplied to BOC) 4
Pickups (Supplied to KBR) 5
wheel loader 2
Grader 2
Sheep foot compaction 2
water tanker 1
excavator 2
dump truck 4
tire roller compaction 2

Page 5 of 12
Photographs Wo No.BOC-1962-AA-9003-0001-Design and Construction of SGTF North Access Road

Page 6 of 12
Photographs WO No : BOC-1962-AA-9003-0003- Design and Construction of MCPP North Access Road

Page 7 of 12
Photographs WO No : BOC-1962-AA-9003-0004-Design and Construction of Shams North Access Road

Page 8 of 12
AL YAMAMA DAILY
PROGRESS REPORT

Project Contract Title Contract No. Manager/Engineer


Majnoon Oil Field Development Snagging works @ MJE-22,24& SIPD-976 Syed Zaki
20
Date Weather Temperature (°C)
31 Oct, 2013 Sunny Normal ✘ 27
Cloudy ✘ Foggy
Rainy Heavy wind
Daily Report No.11
PTW No : N/A
HSSE observations:
All employees must have Shell HSE passport. Also machinery using at site must have Shell approved sticker
Control measures:

Manpower Equipment/Vehicles Material Received


Category Nos. Category Nos. Description Unit Qty
Labors 3 Excavator 0 Bolts Nos 51
Foreman 1 Shovel 0
Engineers 1 Crane 0
HSE supervisor 0 Welding Machine 0
Surveyor 1 Vaccum truck 0
Driver 1 Sheep Foot Roller 0
First Aider 0 Concrete Mixer 0
Flag man 0 Water Tanker 0
Permit Holder 1 Steel compacter 0
Supervisor 0 Manual compacter 0
Banksman 0 Crane 50 T 0
Sub- Contractor Labou 0 Buldozer 0
Riggers 0 Mini Bus 0
Electrician 1 Pick up (Y007) 1 4 Hours
operator 2 Hiab (Y240) 1 8 Hours
Helper 0 JCB (Y163) 1 8 hours
Welder 0 HIAB 0
Pipe Fitter 0 Basket 0
Supervisor 0 BobCat 0
Grinder man 0 Hydraulic Crimping tool 0
Tools Kit 0
Total 11 Total 3

Activities of the Day


1. Arranging of jersy barriers around the water tank and septic tank @ MJE-24
2.Levelling of the Ground around security cabins @ MJE-24
3.Level the electric pump and bolted down @ MJE-24 & 22
4.Security cabins are earthed together with stairs @ MJE-22& 24
5. Levelling the gound with JCB around the water tank & Septic Tank Area.

Plant & Material required for next day

SITE ISSUES

QA-QC INSPECTIONS / OBSERVATIONS

HSE ISSUES
None to report
Name: Management office
None to report
Signature:

PHOTOGRAPHS

Page 9 of 12
AL YAMAMA DAILY
PROGRESS REPORT

Page 10 of 12
AL YAMAMA DAILY
PROGRESS REPORT

Project Contract Title Contract No. Manager/Engineer


Majnoon Oil Field Development Snagging works @ MJE-22,24& SIPD-976 Syed Zaki
20
Date Weather Temperature (°C)
31 Oct, 2013 Sunny Normal ✘ 27
Cloudy ✘ Foggy
Rainy Heavy wind
Daily Report No.11
PTW No : N/A
HSSE observations:
All employees must have Shell HSE passport. Also machinery using at site must have Shell approved sticker
Control measures:

Manpower Equipment/Vehicles Material Received


Category Nos. Category Nos. Description Unit Qty
Labors 3 Excavator 0 Bolts Nos 51
Foreman 1 Shovel 0
Engineers 1 Crane 0
HSE supervisor 0 Welding Machine 0
Surveyor 1 Vaccum truck 0
Driver 1 Sheep Foot Roller 0
First Aider 0 Concrete Mixer 0
Flag man 0 Water Tanker 0
Permit Holder 1 Steel compacter 0
Supervisor 0 Manual compacter 0
Banksman 0 Crane 50 T 0
Sub- Contractor Labou 0 Buldozer 0
Riggers 0 Mini Bus 0
Electrician 1 Pick up (Y007) 1 4 Hours
operator 2 Hiab (Y240) 1 8 Hours
Helper 0 JCB (Y163) 1 8 hours
Welder 0 HIAB 0
Pipe Fitter 0 Basket 0
Supervisor 0 BobCat 0
Grinder man 0 Hydraulic Crimping tool 0
Tools Kit 0
Total 11 Total 3

Activities of the Day


1. Arranging of jersy barriers around the water tank and septic tank @ MJE-24
2.Levelling of the Ground around security cabins @ MJE-24
3.Level the electric pump and bolted down @ MJE-24 & 22
4.Security cabins are earthed together with stairs @ MJE-22& 24
5. Levelling the gound with JCB around the water tank & Septic Tank Area.

Plant & Material required for next day

SITE ISSUES

QA-QC INSPECTIONS / OBSERVATIONS

HSE ISSUES
None to report
Name: Management office
None to report
Signature:

PHOTOGRAPHS

Page 11 of 12
AL YAMAMA DAILY
PROGRESS REPORT

Page 12 of 12