Professional Documents
Culture Documents
Tunneling With Low Rock Cover Within Tight Geometr
Tunneling With Low Rock Cover Within Tight Geometr
Tunneling With Low Rock Cover Within Tight Geometr
C. Cátedra
Cowi, Copenhagen Denamrk (Former Rambøll during current project)
ABSTRACT: The case studied in this article covers a mined twin track railway tunnel
within Scandinavia. Where due to weakness zones and uncertainty on the rock levels, the usu
ally drill and blast solution had to be replaced by soft ground tunneling.
A local lowering in the top of rock was identified in the existing geological information,
resulting in very low rock cover (or potentially no rock cover). The soil above the rock con
sists of high permeable ground with more than 10m of water pressure.
The lowering is located below existing pile founded buildings and under a public road with
a range of utilities. This high congestion of both the surface and underground space made it
impossible to perform ground investigations prior to construction, to confirm the rock level
above the tunnel.
This led to a temporary solution comprising of ground freezing, pipe umbrellas, heavy sup
port frames and a redesigned underpinning of the building immediately above the tunnel.
The current paper summarizes the design process and the chosen design, and the consider
ations for dealing with uncertain geological conditions within a congested areas with high
water pressure.
1 INTRODUCTION
A section of a twin-track rail tunnel is passing over two parallel tunnels with less than 1m
rock in-between, and the crown of the tunnel is entering a zone of rock where several faults
are crossing and where there is a significant depression in the rock surface. The rock is over
layed by 14m of water-bearing quaternary deposits. A building, founded on piles extending
into the soil pocket, is located immediately above the tunnel section.
The design of the tunnel section was developed in phases where the risk, opportunities, and
buildability formed the route to the final design. The process is now continuing into the execu
tion phase where specialist contractor inputs are being implemented in the design to smoothen
the execution phase.
Throughout this article, the tunnel in design is referred as “TD” while the tunnels places
below are referred by “TB”
2 GEOMETRIC CONSTRAINTS
The main geometric constraints of the existing tunnel below and the pile foundations above.
DOI: 10.1201/9781003348030-204
1705
Figure 1. Initial proposed solution. a) longitudinal section.; b) Cross section.
1706
3 INITIAL KNOWLEDGE OF GEOLOGY AND HYDROGEOLOGY
Due to the crowded upper ground, the possibility for ground investigations is limited, and the
existing information on geology is only based on previous existing ground investigations and
information on the building foundation.
Based on the existing information along this stretch of the tunnel, it was expected to have 3
sets of fault zones in conjunction with a “soil pocket”, reducing drastically the rock cover.
However, at the feasibility stage of the design, the depth of the “soil pocket” was unknown,
meaning that the rock level could have been above the TD, protruding in the TD alignment or
even extending all the way to the bench of the TD, and no additional ground information was
seen possible until the start of excavation works.
The sketch below summarizes the uncertainties on the rock level and the fault zones along
the TD.
The approximately 18m of soil above the tunnel is primarily consisting of silty sand, sand
and gravels and is water-bearing with the aquifer a few meters below the ground surface,
lowering of the groundwater in the area is not allowed. For the structural design, the water
level has been conservatively assumed at the surface.
Figure 3. Existing information on the geology. a) Uncertainty of the rock level; b) expected fault zones.
Based on the knowledge of the ground and the rock a range of primary risks was identified
and used to define the base structural solution, described in the section below.
The list below summarizes the principal risks and the initial possible mitigations.
1. Control of ground water – grouting, jet-grouting, freezing
2. Risk of further settlements of building – minimizing excavation steps to reduce volume loss
and avoiding inflow of soil and water
3. Uncertainty of condition of the surrounding rock – forming of tunneling method that can
span the two tunnels below
4. Uncertainty of the composition of the soils above the rock – include a vault that can sup
port the soil if it extends into the tunnel cross section
5. Risk of collision with building piles when executing grouting and spiling – Probing and
vibration monitoring in building
6. Risk of building piles extending into the crown of the tunnel – considering new pile support
regime to allow cutting and undermining of piles
5 DESIGN PROCESS
Below it is described how the structural solution has evolved during the different stages of the
design based on the existing and new information.
1707
5.1 Feasibility solution
The initial design approach was based on a worst-case scenario where the tunnel needed to
carry all loads from above to the areas between and next to the tunnels below, the structure
consisted of two longitudinal beams along the sides of the rail tunnel, forming the base for the
vault supporting the soil, water and the building above.
The beam solution was initially formed as two parallel beams spanning over the tunnel
below and supporting soil, water pressure and building loading on the full length of the
beams. However, it was quickly acknowledged that the magnitude of load was too big for this
approach and the area of the arch had to be reduced to only covering the zone where the
depression of the rock was most prominent. Secondary vaults next to the weak zone included
support on the rock next to the beams.
It can be observed that the feasibility solution did not cover risk 1, 2, 5 and 6, presented in
section 4
1708
Figure 5. TD cross section without beams (Feasibility study).
Figure 6. TD longitudinal profile, with pipe umbrella supported on steel ribs. (Feasibility study).
Left was the issue with the treatment of the soil and the risk of clashes with building piles.
A range of solutions was kept open, such as high-pressure soil grouting, jet grouting, compen
sation grouting, and soil freezing.
However, jet grouting was considered risky due to shading from piles and boulders, there were
also concerns about heave/settlements. There was no space available for a compensation grouting
scheme. Experience with the soils showed it to be hardly groutable while still water-bearing. And
finally, there were concerns about heave/settlement in connection with a freezing scheme.
Risk 1, 2, 5 and 6, presented in section 4, remained unsolved at the end of the preliminary
design phase, while the handling risk 3 and 4 still relied on late confirmation of rock quality.
The table below summarizes the evolution of the design throughout the different design
phases
1709
Table 1. Evolution of the design trough the different design phases.
Ground freezing experts and grouting experts were once again approached to back
a decision on the type of ground treatment, and soil samples were recovered during the execu
tion of a recharge well, these soil samples were sent for testing of frozen properties.
While the borehole from TB provided additional information on the rock between the TB
and the TD, it did not provide any clarification on the level of the rock above TD.
This uncertainty on the rock level led to a scenario-based design. Where the different rock
levels, described in section 3, were considered as design scenarios, and for each scenario,
a temporary solution has been designed. The final temporary support is then chosen on-site,
during construction, based on the results from probing performed at the face excavation.
Regardless of the scenario, the temporary ling is performed by pipe umbrellas; ground
freezing, and steel ribs, as described below.
Figure 7. Boreholes performed form the tunnel below, confirming the presence of a rock shelf.
1710
the installation of the 2nd pipe umbrella. Along the second stretch, the pipe umbrella is placed
horizontally, reducing the probability of hitting the existing pile foundations.
The drilling of the pipe umbrella is also used as preliminary probing, confirming if there is
a protrusion of ground in the excavation face.
Figure 8. Longitudinal alignment of TD, divided in stretches with respective temporary support solution.
Figure 9. Structural verification of the frozen ground along the free span.
1711
Figure 10. Ground freezing scheme.
Along stretch 1 of the excavation, where there is a higher rock cover, HEM280 is con
sidered, whereas, for stretch 2, the area with higher uncertainties on the existence of a rock
cover, HEM 320 is used.
Regardless of the scenarios or stretches, all the steel ribs are connected by a stiffener to help
to support and arch the forces during each advance, while only one side of the steel rib is filled
with concrete.
Figure 11. Representative sketch of the steel rib for temporary lining.
6 CONCLUSIONS
A range of risks/problems were identified at the feasibility level by a thorough risk assessment
and formed the basis for taking decisions during the design process.
The risk of hitting foundation piles and by that harming the building above was not closed
by the end of the detailed design, this led to the final decision of underpinning the building to
make sure that even if piles are hit the building above is still safe.
Working with a focus on risks leads to finding solutions that interact and solve more than
one design problem rather than solving one issue at a time.
1712