Professional Documents
Culture Documents
DBR Phase1 DESIGN PHILOSOPHY
DBR Phase1 DESIGN PHILOSOPHY
DBR Phase1 DESIGN PHILOSOPHY
SECTION-E
HVAC
Contents
8.1 TIER-4 & TIER-3 DATA CENTER – WATER COOLED CHILLER PLANT E-8
1 & AIR COOLED CHILLER PLANT 2
2. DESIGN OBJECTIVES
A) Data Center building is a G + 4 building with a pump room in the partial
basement. The ground and first floor consists of the services rooms such as HVAC The aim is to provide an eco-friendly & energy efficient design keeping in mind the
chiller plant room, Transformer rooms, HT panel rooms, APFC and LT panel rooms, stringent requirements of Tier IV data center. The design will take cognizance of
UPS and Battery rooms that support the Data server modules/halls. The 2nd, 3rd & easy installation & maintenance requirements.
4th floor of the DC building are typical, each floor comprising of four Data server The Key design objectives are:
modules/halls (for rack details refer Table no: 8 & 9), along with supporting rooms
Maintain specified design temperature & dew point temperature in server halls.
like PAHU rooms, Electrical rooms and MDF rooms.
Maintain design temperature and indoor air quality in all occupied areas.
The DC building shall be occupied in three phases as per the details provided
Ensure adherence to Uptime Institute and ASHRAE TC 9.9 standards for server
below:
halls.
600 server racks per phase.
Maintain feasible condition for safe evacuation of occupants during fire / smoke
The Tier IV server halls shall be occupied in the 2nd, 3rd floor and 4th floor of the
alarm conditions.
building.
The server halls will be designed keeping in view the recommendations of Uptime
B) 30 seater office space shall be provided at the 4th floor of the building during
Institute and ASHRAE TC 9.9 standards for Tier IV data center.
phase 1, which will be demolished during the next phase.
The following are the salient features:
C) Office Building is a G + 3 building to the east side of Data Center Building. The
Design to be fully redundant & fully tolerant
Ground floor includes Reception areas, Board rooms, Training rooms and some
Facilitate concurrent maintainability
technical rooms such as BMS and UPS rooms. The first and second floors are
Compartmentalization (physical isolation) of complementary systems and Smoke Purging system in Server halls.
distribution paths.
Chilled water system to have two simultaneously active distribution paths, each 4. CODES, STANDARDS & REFERENCES
capable of meeting full load requirements. The system design, material equipment shall in general comply with the following
Enable planned maintenance activity without adverse impact on the system. requirements of the standards, codes and statutory regulations issued by the relevant
Tolerate single unplanned failure event without adverse impact on the system Authorities and Institutions:
Continuous Cooling
ASHRAE – TC 9.9 (2015) Thermal Guidelines for Data Processing Environments.
Uptime Institute standards
3. HVAC SCOPE OF WORK
ASHRAE – 62.1 (2016) Ventilation for acceptable indoor air quantity
3.1. Air conditioning systems
ASHRAE – 90.1 (2016) Energy standard for buildings except low-rise residential
Chilled water Dual Coil PAHU’s for serving the Tier- IV racks in the Data center buildings (Applicable for chillers)
server modules/halls to suit the Cold Aisle Containment system. IS : 277 (2003) Galvanized Steel Sheets (Plain & Corrugated)
Chilled water Dual Coil PAHU’s for server racks in MDF rooms serving Tier IV IS: 325 (2007) Three Phase induction Motors
server halls. IS: 659 (2001) Safety codes for Air Conditioning
Chilled water Single Coil PAHU’s for UPS rooms & BMS rooms. IS: 1239 (2004) Specification for Mild Steel and Tubular
Conventional Chilled water system for air-conditioning of: IS: 3589 (2001) Specification for Steel pipes
Transformer rooms IS: 3588 (1999) Specification for Electric Axial fans
APFC, LT & HT Panel rooms & Electrical rooms IS: 4894 (1999) Centrifugal Fans
Corridors, Reception areas and Lift lobbies AHRI standards for Cooling Coil ratings and Chiller Rating
3.2 Ventilation Systems Air Movement and Control Association (AMCA) standards for Axial & Centrifugal fans
SMACNA – 2005 HVAC Duct construction standards
Battery room Hydrogen exhaust system (Emergency Mode Only)
National Building Code of India – 2016
Toilet and Pantry
Air filters as per ASHRAE standard 52.1-1992
GIS panel room, and Pump room.
National Fire Protection Association – 1 (NFPA-1)(2005)
3.3 Life Safety Systems
Fire strategy as approved by local authority
Lift well and Staircase Pressurization system ASHRAE Applications Handbook – Data Processing & Electronic office areas
ANSI/ASHRAE 127 – Testing standards for Computer Room Air-conditioners (CRAC) The Extreme Annual Design conditions mentioned in Table: 2 is taken from ASHRAE
5. BASIS OF DESIGN Handbook-Fundamentals 2005 as per the Uptime Institute recommendations and is
used for cooling load calculations and equipment sizing for data center server areas.
The Air Conditioning system shall be designed based on the following design
parameters * - An ambient design temperature of 42 Deg C DBT has been considered for cooling
load calculation and equipment sizing.
5.1 OUTSIDE DESIGN CONDITIONS
Project location : Pune, Mumbai 5.2 INDOOR DESIGN CONDITIONS
Latitude : 18.3 Degree North The indoor air quality and thermal environment for air-conditioning areas are
Altitude : 559 m above mean sea level considered based on the following conditions.
Daily Range : 31 Degree F
22 ± 2 (*) °C (inlet to racks) ; 5.5 °C - 15 °C
Data Centre Server Rooms (Cold aisle)
Dew Point
Seasons DBT °C WBT °C RH %
Data Centre Server Rooms (other areas-Hot
Summer 40.0 24.4 28 Not exceeding 35 °C
aisle)
Monsoon 28.3 26.1 82 Electrical Rooms 30 °C Max DBT ; No RH control
Extreme annual design The outdoor air requirements for office spaces shall be 30% more than recommended in
41.94 ( * ) 29
condition for N = 20 years ASHRAE 62.1 – 2016 standard. Minimum air flow of 170 CFM/rack kW including leakages
Table 2– Outdoor Design Conditions-Data center server areas is considered in server halls and positive pressure ranging in between 5-15 pa will be
maintained to prevent contaminant ingress.
For Floor grilles serving server halls 154 CFM / Rack kW Table 7– Design parameters-HVAC equipment
For Transformer, electrical rooms and
As per the inside conditions
other supporting areas
Air conditioning in Battery rooms: Condenser Water Pumps 3125 USGPM – 2 3125 USGPM – 2 3125 USGPM – 1 5 Nos.
for Water Cooled chillers Nos. Nos. Nos.
The Battery room in DC building shall be air-conditioned using conventional
3125 USGPM – 2 3125 USGPM – 2 3125 USGPM – 1
ceiling suspended chilled water AHU with 4/6 row cooling coil. These CAHU’s Cooling Towers
Nos.
5 Nos.
Nos. Nos.
are with and mixing box. The return air from battery rooms are ducted.
48 TR / 25500CFM 48TR / 25500CFM 48 TR / 25500CFM
PAHU’s for Server Rooms 144 Nos.
48 Nos. 48 Nos. 48 Nos.
Tempered Air cooling in Electrical room, Transformer room, Panel rooms:
Tempered cooling shall be used in areas such as Electrical Room, Transformer
Room & Panel Room to ensure that the space temperatures do not exceed Table 8– Chiller Configurations for Tier 4 Data center
30˚C. This shall be achieved by using chilled water vertical AHUs with 4/6 row
cooling coil. These AHUs are with VFD and mixing box.
HVAC plant 2: Air-cooled chiller plant (Circuit 1) From the chiller plants, 2 separate chilled water circuit (simultaneously active) has been
proposed which runs through the building vertical risers (Riser 1 & Riser 2) and gets
HVAC plant 1 shall be planned at ground floor and HVAC plant 2 shall be planned at the
connected to PAHUs, AHU’s, CAHU’s & VAHU’s.
terrace level of main Data Center building respectively as per capacities and
configuration mentioned in Table 8. PAHUs shall have dual coil and Coil 1 of each unit shall be connected to active circuit 1
and coil 2 of each unit shall be connected to active circuit 2. This scheme is proposed to
Hybrid system with Air cooled chillers & Water cooled chillers has been sized for 100%
ensure that there is always 50% water flow availability in both the chilled water coils in
load to meet N+N redundancy requirements,
PAHU during normal mode operation. During failure of any one cooling coil, the other
(A) If 100% Air cooled chiller works, all the water cooled chillers are standby, coil shall receive 100% flow and ensures that there is no impact on cold air distribution
(B) If all the water cooled chillers will work 100%, then all the Air cooled chillers are to the racks.
standby In addition to the above, there are two standby PAHU’s for each server hall and the EC
(C) If 50% of the total chillers work, remaining 50% shall be standby. fans of all PAHU’s including standby shall ensure that all fans ramp up and ramp down
the speed uniformly depending on the cooling requirements and ensures that sufficient
The Air cooled chillers serving the Tier IV Data Center shall be with variable speed drive
cold air is available at the server rack inlet.
and the water cooled chillers shall be of HT type without VFD.
The chilled water flow through the cooling coil is modulated based on the supply air
temperature sensor and the EC fan speed is modulated based on the average reading
measured by the cold aisle temperature sensors.
8.3 PUMPING STRATEGY AND PIPING The chilled water shall be generated at 13.0°C temperature by a set of air cooled &
water cooled chillers in HVAC plant 1 & HVAC plant 2.
The HVAC Plant 1 & Plant 2 shall have Variable speed chilled water circulation primary
Chilled water generated by the air cooled chillers shall be pumped into a separate
pumps and its associated piping connected with the respective plants comprising of
circuit and chilled water generated by the water cooled chiller plant shall be pumped
air cooled chillers & water cooled chillers.
into a separate circuit.
Variable speed Chilled water pumps shall be insulated with insulation of same
From the main chilled water pipe line, the chilled water shall be distributed through
material & thickness as the connected pipe. GI powder coated sheet cladding shall be
the vertical shafts to the AHUs, CAHUs, FCUs & PAHU’s
provided for the insulation.
All Chilled water pumps shall be connected to its respective chiller and there is no
8.4 AIR DISTRIBUTION SYSTEM
common header pumping system.
The Chilled water pipes (running in vertical shafts & floor level) shall be served by Grills shall be provided as air distribution terminal units.
means of site-insulated Chilled water Mild steel pipes with all necessary fittings like Floor grills with dampers are proposed for supply air for server halls.
bends, elbows, tees, reducers, hanger, supports, etc. and shall be Class C as per IS Thermal insulation for false flooring using Nitrile rubber (19 mm thick).
1239 (2004) up to 150mm dia. and as per IS 3589 (2001) for 200mm dia. & above. The
Air Distribution system for common areas:
Pipes shall be rated for 10 bar working pressure.
Chilled water pipes running in Terrace level, vertical shafts and floor level shall be Air conditioned air shall be provided with GI ducting (with 120 GSM coating). The
insulated with closed cell elastomeric aluminum foiled nitrile rubber insulation and galvanized sheet metal duct shall be as per SMACNA. The Galvanized steel sheet shall
with density of 40-60 kg/m3 and thermal conductivity not exceeding 0.038 W/m 0K. be confirmed to IS 277.
The insulation material shall be fire rated for Class 0 as per BS 476 Part 6: 1989 for fire Diffusers / Grills shall be provided as air distribution terminal units.
propagation test and for Class 1 as per BS 476 Part 7, 1987 for surface spread of flame Fusible link fire dampers shall be provided in fire zone crossings. Dampers shall be as
test. The chilled water piping insulation shall be covered with 26G Aluminum cladding per UL-555, 1995 certified by CBRI Roorkee
as mechanical protection.
The duct Thermal insulation shall with 13 mm thick closed cell Self Adhesive Nitrile
Drain water shall be taken through insulated UPVC pipes to the nearest drain point Rubber / Polyoleifin meeting Class 0 as per BS 476 Part 7.
located in the AHU room / PAHU room. Drain pipe shall be insulated with 9mm thick
8.5 Cold Aisle Containment system for server halls:
nitrile rubber. For drain pipes running in PAHU rooms there shall be two drain headers
A cold-aisle containment system encloses the cold aisle, allowing the rest of the data
each connected to its respective drain point to ensure that there is proper drain flow
center to become a large hot-air return plenum.
from the PAHU’s to satisfy the redundancy requirements.
By containing the cold aisle, the hot and cold air streams are separated. Sl.no. Space Design basis System type Equipment locations
The containment method requires that the rows of racks be set up in a consistent
1 Toilets 10 ACPH Propeller fan Respective floor level
cold-aisle arrangement and hence the same needs to be ensured.
Each cold aisle containment has temperature sensors at the aisle high level to As per heat
2 Pump Room Vane Axial fan Underground level
dissipation
ensure that the set temperature is always available in the cold aisle. These sensors
are connected to the EC fans of PAHU’s which helps to ramp up / down the speed of Spark proof Ducted
Battery
3 1 cfm / sq. ft. inline fan with Respective floor level
EC fans depending on the load requirements. room
Hydrogen sensor
Lift wells shall be pressurized using tube axial type and shall be located at the terrace.
Lift well shall be pressurized from terrace directly pumping to the well.
9. VENTILATION SYSTEMS Staircase pressurization for internal staircase shall be distributed through a vertical
Ventilation will be provided for areas like toilets, pantry, and Battery rooms. The masonry shaft from terrace & grilles shall be fixed in the masonry wall every three
landings.
ventilation system will be sized based on the air change rates or equipment heat
dissipation as per below table 9.
Smoke Purging system for Server halls shall be through smoke spill type tube axial fan
at floor level.
The Air cooled chiller should be approved as per ARI standard 550/590-2011 (Latest) and
Eurovent certified. Proposed Air cooled chiller characteristics are listed below.
2 Chilled water outlet temperature 13°C The Quick start feature for Air cooled chillers enables it to get back to pre-power failure
operating capacity within 3 minutes to 6 minutes with respect to each chiller
3 Chilled water flow rate / chiller 1.9 USGPM / TR
manufacturer. Benefits of quick start air cooled chiller are as below:
4 Evaporator Fouling Resistance 0.0001 FPS units
Reduces the time for chiller restart after a power failure.
5 Load / Chiller As Per Table 11-12
Rapidly brings the chiller back to pre-power failure operating capacity.
Table 11–Air Cooled Chiller Characteristics
Keeps critical space and equipment cooled.
Reduces the risk of expensive downtime.
3 Condenser water inlet temperature 32.89°C MS pipes of Heavy class (Class C) shall be provided for condenser water piping.
4 Condenser water outlet temperature 39.56°C The condenser water pumps are proposed to be located in the ground floor HVAC
plant room of the DC building.
5 Chilled water flow rate / chiller 1.9 USGPM / TR
8 Condenser Fouling Resistance 0.00025 FPS units The cooling tower shall be open type with counter flow construction.
9 Load / Chiller As Per Table 11-12 Cooling tower fans shall be belt driven / direct driven / Gear reducer driven with
variable speed drives (VFD) for optimized operation of fans during part load
10 Design Wet Bulb Temperature 29 deg C
conditions and favorable ambient wet bulb conditions.
Table 12–Water Cooled Chiller Characteristics
The cooling tower shall be proposed to be located in the terrace of the DC building.
11.3 Chilled Water Pumps Make up water shall be supplied from Terrace Water tank to maintain constant
Variable Primary Flow pumping system will be installed; broadly comprises of vertical amount of water in the condenser water circuit. The cooling tower sizing and make
split case pumps with factory fitted motor suitable for variable speed application. up water calculation are shown in the below tables:
11.6 Buffer Tank All PAHUs shall have EC fans with EFF1 motors.
It is proposed to provide Chilled water back up to meet the required capacities for 10
11.8 Air Handling Units (AHU)
minutes for Tier 4 rack system which is sufficient to meet the pre-power failure
The Air handling units (AHU) will be selected based on cooling load calculations and to
operating capacity.
meet the peak load from each zone. Proposed AHU will be double skinned
Buffer tank is used to balance cooling energy demand between day time & night time. It
construction. AHU will comprise mixing box section, filter section, chilled water
is also used to store cool energy for use as a buffer during emergency/shut down in
cooling coil section and a fan section.
critical applications.
The cooling coils will be sized for a velocity of 2.5 m/s and the filters will be sized for a
For Phase 1 cooling requirements, we need to have a total volume of 130 Cu.m. to cater face velocity of less than 2.5 m/s.
the building load for 10 minutes during power failure. As the Chilled water pipe volume All floor mounted AHUs will have backward / forward curved centrifugal fans and coil
available during phase 1 is about 150 Cu.m. and will be sufficient to supply the required section with 4/ 6 Row copper tube (as per heat load) cooling coil with Aluminum fins
chilled water for a period of 10 minutes during power failure to chillers. Hence there are & 22 G SS drain tray. All AHU will have single stage (MERV-8-EU4) filters. Also each
no buffer tanks envisaged for Phase 1. floor mounted AHUs will be provided with Neoprene vibration pads.
AHU shall have a lamp with a switch for the maintenance. Sound level at 1.5m
For Phase 1& 2 cooling requirements, we need a buffer tank volume of 195 Cu.m. to
distance shall be less than 75 dBA. Limit switch with internal wiring shall be provided
cater to the building load for 10 minutes during power failure. Hence 1Nos of 65 Cu.m.
for the safety purpose. Each AHU shall have switch arrangement at the outside so that
buffer tanks shall be installed during Phase 2.
the user shall control the lighting from outside.
For Phase 1,2& 3 cooling requirements, we need a buffer tank volume of 260 Cu.m. to
AHU shall be provided with VFD.
cater to the building load for 10 minutes during power failure. Hence additional 1 Nos of
AHU coil shall be certified by AHRI.
65 Cu.m. buffer tanks shall be installed during Phase 3.
CAHUs are without VFD.
11.7 Precision Air handling units (PAHU) 11.9 Fan Coil Units (FCU)
Precision Air Conditioning shall be floor discharge type Dual Coil (chilled water + Chilled water type horizontal Fan Coil Units (FCU) shall be blow through type with 3
chilled water) unit for all server halls. Whereas for serving UPS rooms shall be served row cooling coil, cleanable fabric filter, main condensate extended insulated SS drain
by Single Coil PAHU’s. pan, completed with factory fitted modulating type PICBV valve, ball valve with
The dual coil machines shall have inbuilt PIBCV / 2 way valves on both circuit. strainer, ball valve without strainer, balancing valve, drain pipe provision and
The unit shall have the provision for dual power supply. necessary supports.
The FCU shall have forward curved centrifugal fan. Electrical rooms
12. SALIENT FEATURES OF DESIGN 5. Single coil PAHU’s for UPS room NA NA
Fault Tolerant system for Data server hall 7. Conventional CAHU’s for corridor areas NA NA
Redundant chilled water plant 8. Horizontal piping network NA NA
Concurrently Maintainable system for Data server hall. 9. Individual pipe connections to the equipment’s
Quick start featured air cooled chillers with VFD
10. Drain Piping NA NA
HT Water cooled chillers.
11. All Toilets NA NA
Inbuilt Harmonic filters/free standing in Air cooled chiller Panel.
12. Battery room Ventilation NA NA
High ∆T chillers.
The COP of chillers as per ASHRAE 90.1 – 2016. DC Building – First Floor
Variable primary chilled water pumping system Conventional AHU’s / VAHU’s / CAHU’s for LT
1.
panel rooms, Battery rooms, Corridors
Redundancy chilled water piping.
VFD for cooling tower fan motors. 2. Single coil PAHU’s for UPS room NA
Buffer tank for energy storage. ( 10 minutes backup) 4. Horizontal piping network
High static (ESP 10 mm) PAHUs with dual coil 5. Individual pipe connections to the equipment’s
Hydrogen Sensor operated Hydrogen exhaust fans for Battery rooms 5. Drain Piping NA NA
6. All Toilets X X
13. SCOPE MATRIX
7. Battery room Ventilation NA
Sl.No, Description Phase 1 Phase 2 Phase 3
DC Building – Second floor
DC Building – Ground Floor
1. PAHU – Server Halls 1 - 4 (Tier-4) X NA
1. Water cooled chillers
2. PAHU – MDF Rooms NA NA
2. Primary chilled water pumps
3. TFA’s for Server Halls 1 - 4 NA NA
3. Foundation for chillers & pumps NA NA
4. Conventional CAHU’s for corridor areas NA NA
4. Conventional AHU’s / VAHU’s for Transformer 5. Horizontal piping network NA NA
rooms, HT panel rooms, Battery rooms,
4. Conventional CAHU’s for corridor areas X NA 5. Life safety system (Lift well Pressurization) NA NA
8. All Toilets X NA
6. Drain Piping X X