Duration Weight %

No Description
(Hours) (%) Complete
I Install Diesel Engine Include Accessories
1 Crew Change & Preparation WCC 40
2 Preparation Material & Tools 16
Special Tools & standard tools 8
Lifting tools 8
3 Menaikan ADG B dari kapal ke main Deck Zulq 14
Mengangkat Skid Base 2
Mengangkat Engine 2
Mengangkat Generator 2
Mengangkat Radiator 2
Mengangkat Daily tank 2
Mengangkat Silencer 2
Mengangkat PCC 2
4 Cleaning New Generator Area (ADG B) 2
5 Transfer and Reposition New Skid Base from Main Deck to sub cellar deck 8
6 Install New Skid Base 24
Alignment New Skid Base 12
Install Vibration Damper 12
7 Transfer and Reposition Engine Block from Main Deck to sub cellar deck 48
Transfer Engine Block Set to Skid Base 12
Install Engine Block to skid base 12
Re-Alignment Engine Block to Skid Base 12
Install Bolt & Nut at Engine & Skid Bse 12
8 Transfer and Reposition Generator from Main Deck to sub cellar deck 12
Transfer Generator Set to Skid Base 12
9 Install Generator to skid base 24
Re-Alignment Generator to Skid Base 12
Install Bolt & Nut at Engine & Skid Bse 12
10 Transfer and Reposition Radiator from Main Deck to sub cellar deck 12
Transfer Radiator to Skid Base 12
11 Install Radiator to skid base 24
Re-Alignment Radiator to Skid Base 12
Install Bolt & Nut at Engine & Skid Bse 12
12 Transfer and Reposition Fuel tank from Main Deck to sub cellar deck 12
13 Install Fuel tank to skid base 24
14 Install Cable Power 48
Glanding & Termination 48
15 Install Engine attachment 84
Install Fuel Filter Base 12
Install Exhaust Manifold 12
Install Water Line 12
Install Fuel Line 24
Install Air Supply Line for starting system 24
16 Install Cable Power & Cable Control (Engine Set) 36
Install Cable Power 12
Make Hole Penetration Cable Power 12
Install Cable Control 12

II Pulling Cable and Insulation Test from LCP to RCP 168


1 Pulling Cable Speed Control 6
2 Pulling Cable AVR 6
3 Pulling Cable Common Signal From PC 3.3 to Comap 6
4 Pulling Cable From Heater Genarator to Swgr 6
5 Pulling Cable LV 3C x 500 CM 48
6 Pulling Cable HV 3C x 2/O 48
7 Install Cable Tray Form Generator to Switchgear 48

III Dressing, Glanding And termination (RCP & LCP) 156


1 Glanding and Termination Cable Speed Control at JB Generator 12
2 Glanding and Termination Cable AVR at JB Generator 12
Glanding and Termination Cable Common Signal From PC 3.3 to Comap at JB
3
Generator 12
4 Glanding and Termination Cable LV 3C x 500 CM at JB Generator 36
5 Glanding and Termination Cable LV 3C x 500 CM at JB Transformer 36
6 Glanding and Termination Cable HV 3C x 2/O at JB Transformer 24
7 Glanding and Termination Cable HV 3C x 2/O at Switchgear 24

IV Pre Commissioning Continuity, Commissioning and Functional Test 32


1 Check All termination cable control and cable power 16
2 Continuity all connection cable 8
3 Function Test 8

V Internal Test 112


1 Test Run Engine 24
2 Setting Safety Device 8
3 Install Load Bank 40
4 Performance Test & Monitoring 40

VI SAT 18
1 Run Engine 8
2 Setting Safety Device 8
3 Performance Test 8

VI TEST PARALEL & SYNCHRONIZING 8


VII REPORTING 8