REF DESIGNATION No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
LABOR
1 FOREMAN 1 8 ₱ 103.50 ₱ 828.00
2 SKILLED LABORER 1 8 ₱ 69.00 ₱ 552.00
A.1
3 UNSKILLED LABORER 2 8 ₱ 57.50 ₱ 920.00
REF NAME AND SPECIFICATION Unit Quantity Unit Cost Amount (PhP)
MATERIALS
0 0 - -
F.1
Sub-Total for F.1 - As Submitted
F.2
Sub-Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted ₱ 743.80
H.1 Overhead, Contigencies & Miscellaneous (OCM) - As Submitted 8.00% of G.1 ₱ 59.50
I.1 Contracto'rs Profit (CP) - As Submitted 8.00% of G.1 ₱ 59.50
J.1 Value Added Tax (VAT) - As Submitted 5.00% of (G.1 + H.1 + I.1) ₱ 43.14
K.1 Total Unit Cost - As Submiited G.1 + H.1 + I.1 + J.1 ₱ 905.95
LABOR RATES
LABOR COST HOURLY RATE
MINIMUM WAGE: 460 DOLE (Pangasinan) CATEGORY DAILY WAGE
INDEX (8 hours)
REF DESIGNATION No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
LABOR
1 FOREMAN 1 8 ₱ 103.50 ₱ 828.00
A.1 2 UNSKILLED LABORER 2 8 ₱ 57.50 ₱ 920.00
REF NAME AND SPECIFICATION Unit Quantity Unit Cost Amount (PhP)
MATERIALS
1 D-FENCE SOIL TERMITICIDE L 1 ₱ 325.00 ₱ 325.00
F.1
Sub-Total for F.1 - As Submitted ₱ 325.00
F.2
Sub-Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted ₱ 418.23
H.1 Overhead, Contigencies & Miscellaneous (OCM) - As Submitted 8.00% of G.1 ₱ 33.46
I.1 Contractoer's Profit (CP) - As Submitted 8.00% of G.1 ₱ 33.46
J.1 Value Added Tax (VAT) - As Submitted 5.00% of (G.1 + H.1 + I.1) ₱ 24.26
K.1 Total Unit Cost - As Submiited G.1 + H.1 + I.1 + J.1 ₱ 509.40
LABOR RATES
LABOR COST HOURLY RATE
MINIMUM WAGE: 460 DOLE (Pangasinan) CATEGORY DAILY WAGE
INDEX (8 hours)
REF DESIGNATION No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
LABOR
1 FOREMAN 1 8 ₱ 103.50 ₱ 828.00
A.1 2 SKILLED LABORER 3 8 ₱ 69.00 ₱ 1,656.00
REF NAME AND SPECIFICATION Unit Quantity Unit Cost Amount (PhP)
MATERIALS
0 0 - -
F.1
Sub-Total for F.1 - As Submitted
F.2
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted ₱ 1,086.80
H.1 Overhead, Contigencies & Miscellaneous (OCM) - As Submitted 8.00% of G.1 ₱ 86.94
I.1 Contracto's Profit (CP) - As Submitted 8.00% of G.1 ₱ 86.94
J.1 Value Added Tax (VAT) - As Submitted 5.00% of (G.1 + H.1 + I.1) ₱ 63.03
K.1 Total Unit Cost - As Submiited G.1 + H.1 + I.1 + J.1 ₱ 1,323.72
LABOR RATES
LABOR COST HOURLY RATE
MINIMUM WAGE: 460 DOLE (Pangasinan) CATEGORY DAILY WAGE
INDEX (8 hours)
REF DESIGNATION No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
LABOR
1 FOREMAN 1 8 ₱ 103.50 ₱ 828.00
A.1 2 UNSKILLED LABORER 2 8 ₱ 57.50 ₱ 920.00
REF NAME AND SPECIFICATION Unit Quantity Unit Cost Amount (PhP)
MATERIALS
1 3/4" GRAVEL cu.m. 1 ₱ 1,320.00 ₱ 1,320.00
F.1
Sub-Total for F.1 - As Submitted ₱ 1,320.00
F.2
Sub-Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted ₱ 1,669.60
H.1 Overhead, Contigencies & Miscellaneous (OCM) - As Submitted 8.00% of G.1 ₱ 133.57
I.1 Contracto's Profit (CP) - As Submitted 8.00% of G.1 ₱ 133.57
J.1 Value Added Tax (VAT) - As Submitted 5.00% of (G.1 + H.1 + I.1) ₱ 96.84
K.1 Total Unit Cost - As Submiited G.1 + H.1 + I.1 + J.1 ₱ 2,033.57
LABOR RATES
LABOR COST HOURLY RATE
MINIMUM WAGE: 460 DOLE (Pangasinan) CATEGORY DAILY WAGE
INDEX (8 hours)
REF DESIGNATION No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
LABOR
1 FOREMAN 1 8 ₱ 103.50 ₱ 828.00
A.1 2 SKILLED LABORER 2 8 ₱ 69.00 ₱ 1,104.00
REF NAME AND SPECIFICATION Unit Quantity Unit Cost Amount (PhP)
MATERIALS
0 0 - -
F.1
Sub-Total for F.1 - As Submitted
F.2
Sub-Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted ₱ 367.37
H.1 Overhead, Contigencies & Miscellaneous (OCM) - As Submitted 8.00% of G.1 ₱ 29.39
I.1 Contracto's Profit (CP) - As Submitted 8.00% of G.1 ₱ 29.39
J.1 Value Added Tax (VAT) - As Submitted 5.00% of (G.1 + H.1 + I.1) ₱ 21.31
K.1 Total Unit Cost - As Submiited G.1 + H.1 + I.1 + J.1 ₱ 447.46
LABOR RATES
LABOR COST HOURLY RATE
MINIMUM WAGE: 460 DOLE (Pangasinan) CATEGORY DAILY WAGE
INDEX (8 hours)
REF DESIGNATION No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
LABOR
1 FOREMAN 1 8 ₱ 103.50 ₱ 828.00
A.1 2 SKILLED LABORER 5 8 ₱ 69.00 ₱ 2,760.00
REF NAME AND SPECIFICATION Unit Quantity Unit Cost Amount (PhP)
MATERIALS
1 10MM DEFORMED BAR kg 1695.12 ₱ 40.00 ₱ 40.00
2 12MM DEFORMED BAR kg 280.99 ₱ 40.00 ₱ 40.00
F.1
3 16MM DEFORMED BAR kg 662.15 ₱ 40.00 ₱ 40.00
F.2
Sub-Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted ₱ 200.51
H.1 Overhead, Contigencies & Miscellaneous (OCM) - As Submitted 8.00% of G.1 ₱ 16.04
I.1 Contracto's Profit (CP) - As Submitted 8.00% of G.1 ₱ 16.04
J.1 Value Added Tax (VAT) - As Submitted 5.00% of (G.1 + H.1 + I.1) ₱ 11.63
K.1 Total Unit Cost - As Submiited G.1 + H.1 + I.1 + J.1 ₱ 244.22
LABOR RATES
LABOR COST HOURLY RATE
MINIMUM WAGE: 460 DOLE (Pangasinan) CATEGORY DAILY WAGE
INDEX (8 hours)
REF DESIGNATION No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
LABOR
1 FOREMAN 1 8 ₱ 103.50 ₱ 828.00
A.1 2 SKILLED LABORER 4 8 ₱ 69.00 ₱ 2,208.00
REF NAME AND SPECIFICATION Unit Quantity Unit Cost Amount (PhP)
MATERIALS
1 CEMENT (40 kg) kg 9 ₱ 259.00 ₱ 2,331.00
2 SAND cu.m. 0.5 ₱ 465.00 ₱ 232.50
F.1
3 GRAVEL cu.m. 1 ₱ 1,320.00 ₱ 1,320.00
F.2
Sub-Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted ₱ 5,431.95
H.1 Overhead, Contigencies & Miscellaneous (OCM) - As Submitted 8.00% of G.1 ₱ 434.56
I.1 Contracto's Profit (CP) - As Submitted 8.00% of G.1 ₱ 434.56
J.1 Value Added Tax (VAT) - As Submitted 5.00% of (G.1 + H.1 + I.1) ₱ 315.05
K.1 Total Unit Cost - As Submiited G.1 + H.1 + I.1 + J.1 ₱ 6,616.11
LABOR RATES
LABOR COST HOURLY RATE
MINIMUM WAGE: 460 DOLE (Pangasinan) CATEGORY DAILY WAGE
INDEX (8 hours)
REF DESIGNATION No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)
LABOR
1 FOREMAN 1 8 ₱ 103.50 ₱ 828.00
A.1 2 SKILLED LABORER 3 8 ₱ 69.00 ₱ 1,656.00
REF NAME AND SPECIFICATION Unit Quantity Unit Cost Amount (PhP)
MATERIALS
1 0.8mm (2" x 4" x 6m) C-PURLINS pcs 5 ₱ 415.00 ₱ 2,075.00
2 40mm x 40mm x 6mm thick ANGLE BAR pcs 18 ₱ 896.00 ₱ 16,128.00
F.1
3 0.90m x 10' x 0.5mm GI SHEET pcs 39 ₱ 460.00 ₱ 17,940.00
F.2
Sub-Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted ₱ 36,584.60
H.1 Overhead, Contigencies & Miscellaneous (OCM) - As Submitted 8.00% of G.1 ₱ 2,926.77
I.1 Contracto's Profit (CP) - As Submitted 8.00% of G.1 ₱ 2,926.77
J.1 Value Added Tax (VAT) - As Submitted 5.00% of (G.1 + H.1 + I.1) ₱ 2,121.91
K.1 Total Unit Cost - As Submiited G.1 + H.1 + I.1 + J.1 ₱ 44,560.04
LABOR RATES
LABOR COST HOURLY RATE
MINIMUM WAGE: 460 DOLE (Pangasinan) CATEGORY DAILY WAGE
INDEX (8 hours)
CONSTRUCTION OF S-CURVE
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
PROJECT NAME : REINFORCED CONCRETE BUNGALOW HOUSE
PROJECT LOCATION : POBLACION MAPANDAN PANGASINAN
CONSTRUCTION OF S-CURVE