Pkg 4 OHE Works – UPDATED STATUS

DOWN LINE ROCS WORK CMPLETION PLAN AND PROGRESS STATUS dated 18.06.24

Expected date for


completion and
Si.No Activity Line.Ref UOM Total Completed Balance accepted by IRCON Reason for Delay
1 Drilling DN Nos 756 746 10 25.06.24
2 Anchor Fixing DN Nos 756 746 10 25.06.24
3 Drop Tube Erection DN Nos 756 727 29 25.06.24
4 Bracket Erection DN Nos 730 707 23 25.06.24
5 Mid point Anchor Erection DN Nos 26 7 19 25.06.24
6 Conductor Rail Erection DN Nos 503 484 19 25.06.24
7 Contact Wire Erection DN Mtr 5875 3500 2375 25.06.24
8 Bracket Adjustment DN Nos 721 0 721 30.06.24
9 SED Checking DN Nos 726 0 726 30.06.24
10 OPC wiring DN KM 5.9 4.6 1.3 25.06.24
11 RC wiring DN KM 5.9 4.25 1.65 25.06.24
12 TEW wiring DN KM 5.9 2.3 3.6 25.06.24

UP LINE ROCS WORK CMPLETION PLAN AND PROGRESS STATUS dated 18.06.24

Expected date for


completion and
Si.No Activity Line.Ref UOM Total Completed Balance accepted by IRCON Reason for Delay
1 Drilling DN Nos 747 599 148 15.07.24
2 Anchor Fixing DN Nos 747 575 172 15.07.24
3 Drop Tube Erection DN Nos 747 420 327 15.07.24
4 Bracket Erection DN Nos 720 182 538 15.07.24
5 Mid point Anchor Erection DN Nos 22 0 22 15.07.24
6 Conductor Rail Erection DN Nos 443 24 419 18.07.24 Target fixed as per Civil work progress (Track
7 Contact Wire Erection DN Mtr 5875 0 5875 20.07.24 handing over by 21.06.24)
8 Bracket Adjustment DN Nos 720 0 720 25.07.24
9 SED Checking DN Nos 720 0 720 25.07.24
10 OPC wiring DN KM 5.9 0 5.9 15.07.24
11 RC wiring DN KM 5.9 0 5.9 15.07.24
12 TEW wiring DN KM 5.9 0 5.9 15.07.24