Professional Documents
Culture Documents
31.+2021-020+RC+CEPALCO+Application-Rate+Schedule+True-up
31.+2021-020+RC+CEPALCO+Application-Rate+Schedule+True-up
31.+2021-020+RC+CEPALCO+Application-Rate+Schedule+True-up
APPLICATION
Applicant Cagayan Electric Power and Light Company, Inc. (“CEPALCO”),
thru counsel and unto this Honorable Commission, respectfully states that:
3) Pursuant to the Position Paper and the Rules for Setting Distribution
Wheeling Rates for Privately-owned Electricity Distribution Utilities
Operating under Performance Based Regulation (First Entry Group:
Third Regulatory Period) dated 01 December 2009 (“3rd RP RDWR”),
the First Entry Group completed the Regulatory Reset Process for
the Third Regulatory Period (“3rd RP”) covering the period from 01
July 2011 to 30 June 2015. In the decision dated 06 June 2011 in ERC
Case No. 2010-064 RC, the Commission set out its final
determination of the price control arrangements that applied to
CEPALCO for the 3rd RP.
6) To date, the reset for the 4th RP for CEPALCO and other private DUs
under PBR has not commenced and is not expected to commence
pending issuance by the Commission of the relevant rules.
7) On 20 January 2016, while the regulatory reset for the 4th RP
remained on hold, CEPALCO filed before the Commission an
Application for an Interim Average Rate adjustment and its
Corresponding Translation into Distribution Charges for each Rate
Schedule. This was docketed as ERC Case No. 2016-007 RC.
12) Due to the absence of a regulatory reset when the 3rd RP ended on 30
June 2015, CEPALCO continued to implement its last approved
distribution charges for Regulatory Year (RY) 2015, until these
charges were adjusted on October 2019, in accordance with the
Decision issued in ERC Case No. 2016-007 RC, and the Interim Rate
Adjustment in the 138 kV Kirahon Substation Rate Adjustment case,
provisionally authorized in ERC Case No. 2016-029RC.
15) The actual weighted average rate varies depending on the sales mix
and load factor of customers whose rate design consist of a demand
charge billed on a P/kW and energy charge billed on a P/kWh. In fact,
the Commission, in its Decision dated 04 August 2014 in ERC Case
No. 2014-028RC (CEPALCO’s Rate Translation for RY 2015),
acknowledged the effect of sales mix to the actual average rate, to
wit:
16) Due to the absence of the annual rates translation during the lapsed
RYs, CEPALCO proposes to true-up its rates on a per customer class.
The proposed True-Up Calculations of the Actual Average Rate
against the ERC-approved Average Rates by Rate Schedule during
the lapsed period is submitted to be the most fair and reasonable
approach. This ensures that the customers are fairly billed with the
Distribution, Supply and Metering Charges equivalent to the ERC
approved average rates by Rate Schedule during the lapsed period,
starting with the approved rate for RY 2015, which was the lowest
rate in the 3rd RP.
17) Due to the absence of the annual rates translation, the true-up
calculations proposed herein fairly and reasonably captures the
changes in customers’ sales mix and load factor. This normalizes the
impact to the actual average rate during the lapsed period against
the last approved average rate by Rate Schedule translated in RY
2015. This is particularly significant to customer classes whose rates
are designed to include a demand charge (in P/kW) and an energy
charge (in P/kWh).
PRAYER
RY 2020 Refund
Allocated Monthly (24
Rate Sked kWh Sales Rate,
Revenue kWh Sales Rev Mix Refund, Peso Months), Peso
P/kWh
Streetlight 10,688,096 9,156,934 0.70% (230,512) - 9,604.67 763,078 (0.0126)
Residential 751,874,603 292,368,999 49.08% (16,215,814) - 675,658.92 24,364,083 (0.0277)
Commercial 385,199,434 228,534,890 25.14% (8,307,665) - 346,152.71 19,044,574 (0.0182)
Big Industrial 108,519,448 130,030,165 7.08% (2,340,458) - 97,519.10 10,835,847 (0.0090)
Small Industrial 107,481,094 104,650,281 7.02% (2,318,064) - 96,586.00 8,720,857 (0.0111)
High Voltage 69KV 136,128,776 225,931,787 8.89% (2,935,914) - 122,329.74 18,827,649 (0.0065)
High Voltage 138KV 32,130,743 240,381,757 2.10% (692,969) - 28,873.73 20,031,813 (0.0014)
Total 1,532,022,194 1,231,054,813 100.00% (33,041,397) - 1,376,724.86 102,587,901 (0.0134)
CEPALCO also prays for such other relief or remedy as may be just and
equitable under the circumstances.
Ranulfo M. Ocampo
Counsel for CEPALCO
PTR No. 8668356 | 04 January 2021 | Marikina City
IBP Lifetime No. 014284 | 18 January 2016 | RSM
IBP Roll No. 33872 | MCLE Compliance No. VI-0023649 valid until 22 April 2022
7/F STRATA 100 Bldg. | F. Ortigas Jr. Road | Ortigas Center | Pasig City
Smart: 0920-938-4470 / Globe: 0917-301-2455 | Email: ranulfoocampo@outlook.com