Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

REFERENCE DOCUMENTS

DOCUMENT TITLE DOCUMENT NR


MST-Method of statement for HDPE-50mm Duct Installation
GRP-08-TS000-SGC-ELE-MST-00001

KEYMAP

00 29-04-2024 FOR APPROVAL HBM HBM MOHSEN

REV. DATE ISSUE, SCOPE OF REVISION PREP. CHECKED APPR.


CLIENT:
ROYAL COMMISSION FOR RIYADH CITY
ENVIRONMENT & INFRASTRUCTURE PLANNING DEPARTMENT
Roundabout No. 3, Al-Kindy Square, Diplomatic Quarter, Riyadh, Saudi Arabia
PROJECT:
Construction of TSE Network for Green Riyadh Program –
Group Five A
PROJECT MANAGEMENT CONSULTANT:

ILF CONSULTING ENGINEERS SAUDI ARABIA


PRINCE MUHAMMAD BIN ABDULAZIZ ROAD, OLAYA
DISTRICT, BUILDING NO. 3074 OLAYA TOWERS,
TOWER B, 11TH FLOOR. RIYADH 11433, SAUDI
ENGINEERING CONTRACTOR
Abdullah Ibrahim Al Sayegh & Sons for Trade &
Contracting
Al Qadisiyah, Alyasmin, Riyadh 11564, Saudi Arabia
DOCUMENT TITLE: MST-Method of statement for HDPE-50mm Duct Installation

SCALE: PROJECT DOCUMENT NUMBER: REV: SHEET


NO:
12021G5 A GRP-08-TS000-SGC-ELE-MST-00001 00 1 OF 23
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

Method Statement for HDPE


50MM DUCT Installation

1
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

Table of Content
S. No. Content Page
1. Objectives 03

2. Purpose 03

3. Scope 03

4. References 03

5. Definitions and Abbreviations 04

6. Responsibilities 05

7. Site Planning and Preparation 08

8. Installation Procedures / Methodology 08

9. Recourses 11

10. Quality Control 11

11. PPE Requirements 12

12. Health, Safety, and Environment 13

2
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

1. Objective: The objective of this method is to describe the required standards and performance
criteria to be followed for HDPE 50MM DUCT Installation.

2. Purpose: The purpose of this method statement is to create awareness and communicate the
tasks involved in executing the procedures for HDPE 50MM DUCT Installation and to ensure
the compliance of these activities with the contract specifications, IFC drawings and with HSE
requirements. It is to guide and take precautionary measures and to safeguard traffic within the
area of work and possible environmental impact.

3. Scope: This method statement outlines the procedures for HDPE 50mm Duct Installation in
accordance with project specifications and approved drawings. It encompasses preparations
involved in the installation of HDPE 50mm Duct for underground electrical wiring.

4. Reference:
The latest revision of the referred codes and standards shall be used wherever applicable. In
case of conflict, the Contractor shall propose equipment conforming to one group of codes and
standards.
4.1 – SBC Saudi Building Code:
4.1.1 SBC 401 - Electrical

4.2 SASO – Saudi Arabian Standard Organization:


4.2.1 SASO-IEC-60918 - PVC Insulated ribbon cable with a pitch of 1.27 mm suitable
for insulation displacement termination

4.3 – IEC - International Electro-Technical Commission:


4.3.1 IEC 60227 - Thermoplastic Insulated Wires and Cables.
4.3.2 IEC 60364 - Electrical Installations for Buildings.
4.3.3 IEC 60445 - Basic and safety principles for man-machine interface, marking and
identification - Identification of equipment terminals, conductor terminations and
conductors.
4.3.4 IEC 60454-3 - Pressure-sensitive adhesive tapes for electrical purposes.
4.3.5 IEC 60502-1 -Power cables with extruded insulation and their accessories for rated
voltages from 1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV)
4.3.6 IEC 61238-1-1 - Compression and mechanical connectors for power cables - Part
1-1: Test methods and requirements for compression and mechanical connectors
for power cables for rated voltages up to 1 kV (Um = 1,2 kV) tested on non-
insulated conductors.
4.3.7 IEC 60811 - Common Test Methods for Insulating and Sheathing Materials of
Electric Cables 8. IEC 61386 - Conduit Systems for Electrical Installations.

3
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

4.4 Reference Documents:


4.4.1 Section 26 05 19 – Low-Voltage Electrical Power Conductors and Cables.
4.4.2 Section 26 05 26 – Grounding and Bonding for Electrical Systems.
4.4.3 Section 26 05 43 – Underground Ducts and Raceways for Electrical Systems.
4.4.4 Section 26 06 20 – Schedule for Low voltage Electrical Distribution.
4.4.5 Contract Drawings.
4.4.6 Section 03 20 00 - Concrete Reinforcing
4.4.7 Section 03 30 00 - Cast-in-Place Concrete
4.4.8 Section 03 41 00 - Precast Structural Concrete.
5. Definitions and Abbreviations:

5.1 Raceways: Raceways include, but are not limited to, uPVC conduit, rigid metal conduit,
rigid non-metallic conduit, intermediate metal conduit, liquid-tight flexible conduit,
flexible metallic tubing, flexible metal conduit, electrical non-metallic tubing, metallic
electrical tubing, underfloor raceways, cellular concrete floor raceways, cellular metal
floor raceways, surface raceways, wire ways, and busways.

5.2 Cable: Conductor with insulation or a stranded conductor with or without insulation
covering (single conductor cable), or a combination of conductors insulated from one
another conductor cable).

5.3 Conductor: Any carrier of electric current. In practical terms, a wire or cable is designed
to carry electric current. A conductor can be insulated or uninsulated, depending on the
application. Examples include wire, cable and bus bar.

5.4 Concentric Neutral Cable: A two-conductor cable consisting of an insulated wrapped in


a copper neutral conductor.

5.5 Duct Bank: A group of ducts or conduit usually encased in concrete in a trench.

5.6 Direct Buried: Also referred to as URD or underground distribution. Cable is laid in a
trench and directed to specific locations through the use of pad-mount transformers,
switchgear, centres, riser poles.

5.7 Insulation: Non-conductive material that is applied over a conductor (e.g. cable, wire) to
insulate a conductor from other conductors or ground.

5.8 Jacket (the outer covering of a cable): A tough plastic material that provides physical
protection for the cable. Jacketed cable protects against physical damage and corrosion,
thus reducing the risk of damage to the primary neutral.

4
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

5.9 Handhole: A subsurface enclosure which personnel may enter; handholes are for installing,
operating and maintaining underground cable systems.

5.10 Splice: The joining of two or more cables by connecting the conductor’s pair to pair.
5.11 Shield (Screen): A metallic layer usually in the form of a braid of foil surrounding one or
more electrical conductors to insulate them from electromagnetic interference.

5.12 Overcurrent: Any current in excess of the rated current of equipment or the ampacity of
a conductor. It may result from overload, short circuit, or ground fault.

5.13 Overload: Operation of equipment in excess of normal, full-load rating, or of a conductor


in excess of rated ampacity that, when it persists for a sufficient length of time, would cause
damage or dangerous overheating. A fault, such as a short circuit or ground fault, is not an
overload.

5.14 Abbreviations:
5.15.1 MS - Method Statement
5.15.2 QCP - Quality Control Procedure
5.15.3 ITP - Inspection and Test Plan
5.15.4 RA - Risk Assessment
5.15.5 CM - Construction Manager
5.15.6 HSE - Health Safety and Environment
5.15.7 MEP - Mechanical Electrical Plumbing
5.15.8 PPE - Personal Protection Equipment
5.15.9 PQP - Project Quality Plan
5.15.10 QA/QC - Quality Assurance / Quality Control
5.15.11 SE - Site Engineer
5.15.12 WIR - Work Inspection Request
5.15.13 MIR - Material Inspection Request
5.15.14 RFI - Request for Information
5.15.15 PVC - Polyvinyl Chloride
5.15.16 UPVC - Un-Plasticized Polyvinyl Chloride

6. Responsibilities:

6.1 Project Manager: Will have the overall responsibility of the project for execution, quality
and safety. Also, he will maintain the planning progress and coordination of works with
main contractor.

5
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

6.2 Construction Manager: The Construction manager has overall responsibility of the
implementation of the method statement and to ensure that his team of engineers and
foreman are aware of this method statement and that all resources – human, material and
equipment’s are available to carry out the work as planned and without any delay.

6.3 Project Engineer: Become familiar with the method statement and quality & safety
requirements for the activity. Convey all technical data to the site engineer & to ensure
sufficient understanding of activities to be executed. Control productivity & quality of
work. Attend risk assessment meeting and follow up implementation of requirements.
Arrange the required resources to execute the work.

6.4 Site Engineer: The Site Engineer is responsible for carrying out the work as per the
approved shop drawings, method statements and for co-ordination with MEP sub-
contractor and to ensure that all MEP embedded items are in place, are adequate and that
all necessary inspection and testing have been carried out.

6.5 QA/QC:
6.5.1 Quality Control (QC) & Quality Assurance (QA) personnel will be assigned to
ensure to the quality control and quality assurance requirement of the works.
6.5.2 QA/QC personnel will inspect the work & produce all the documents attesting to
the acceptability of the works.
6.5.3 Contractor shall ensure to protect of ongoing & completed work from damage all
the time during construction work.
6.5.4 Conduct site quality awareness training periodically & prior to start of any new
activity. Training records shall be maintained.
6.5.5 The QA/QC Engineer is responsible to make sure the delivered materials are as per
approved material submittal.
6.5.6 Ensure that the work has been done as per the specification and approved drawings.
6.5.7 Ensure that the inspections are done as per approved PQP and ITP and offer works
for consultants’ inspection.

6.6 HSE Officer: HSE Officer is responsible to ensure that all safety precautions are in place,
and that all personnel on site are using the required PPE like Helmet, Gloves, Shoes and
Coveralls. All relevant permissions are will be ensured for the works.

6
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

6.7 Foreman: Follow up scope of work given by the Engineer. Understand approved shop
drawing, method statement and HSE requirements before execute the work. Assign
manpower, material and machinery for the scheduled work. Complete the work in the
planned/scheduled time period. Conduct the toolbox meetings regularly to the workers
before start the work.

6.8 First Aider:


6.8.1 To provide on-site first-aid treatment to employees at work upon incidents resulting
from minor injuries which would otherwise receive minimal or no treatment, or
which do not need treatment by a medical practitioner.
6.8.2 Ensure that the First Aid Box assigned is safe guarded and box kept at conspicuous
location.
6.8.3 Ensure that First Aid Box content is maintained and stock usage is recorded and
reported to supervisor.

6.9 Skilled/Unskilled workers:


6.9.1 Skilled workers:
6.9.1.1 Understand the work from foreman, study IFC drawing.
6.9.1.2 Arrange required tools, equipment and materials to complete the assigned
job.
6.9.1.3 Make sure all PPE has been worn and approved material is used.
6.9.1.4 Attend tool box talk to understand the scope of work and to know the risk
and hazards involved the job.
6.9.1.5 Complete the wok in given time period.

6.9.2 Unskilled Workers/helpers:


6.9.2.1 Assist the skilled workers to complete the work within the given time
schedule.
6.9.2.2 Attend tool box talk to understand the scope of work and to know the risk
and hazards involved the job.
6.9.2.3 Make sure all PPE has been worn.

7
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

6.10 Contact Details with Designation:

No. Designation Names Contact Details


1. Project Manager Mohsen Ahmed +966549593920
2. Technical Manager Mohamed Khaled +966558288765
3. QA/QC Manager
4. HSE Manager Mohamed Gouda +966570432542
5. QC Engineer Haggag Abouelkhair +966572065229
6. Site Engineer Ahmed Abouelftouh +966534001391
7. Chief Surveyor Mohamed Ali +966598879977
7. Site planning and preparation:

7.1 Ensure All the Employees Attend Site-Specific Induction Covering Safety, Environment,
And Quality.
7.2 Acquire approvals and inspection for plant & machinery to enter inside the site locations
if any.
7.3 Any PTW for General works will be applied and obtained prior to works on site.
7.4 All environmental control will be established in accordance with the site environmental
plan.
7.5 Ensure that all the necessary clearances from the construction team are obtained prior to
start the work.
7.6 Check that the drawings and material submittals are approved and verify that the materials
are as per the approved by the engineer.
7.7 Check that HDPE 50MM DUCT are delivered pre-packed in standard quantities.
7.8 Inspect the HDPE 50MM DUCT stored on a reasonably flat surface free from any type of
damage.
7.9 Loading and unloading of HDPE 50MM DUCT should be carried out by proper tools and
equipment, to ensure safety and avoid damage of equipment.
7.10 Extra care should be exercised in handling HDPE 50MM DUCT to avoid damages.
7.11 Check work area is clean and safe to proceed for the installation of uPVC Ducts.
8. EXECUTION:
8.1 GENERAL:
8.1.1 SGC shall provide all materials, equipment and labor as deemed necessary to show
proper execution of the Work

8
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

8.1.2 Enclosures, equipment shall be protected during installation against entry of foreign matter
8.1.3 The aforementioned shall be vacuum cleaned both inside and outside before testing and
operating, as well as before repainting if required by the Royal Commission
8.1.4 All the Work shall be performed in a first-class workmanlike manner, in conformance with
the applicable codes and standards, the best electrical engineering practices and as per the
manufacturer’s instruction. Work shall be performed by skilled workers equipped to produce
satisfactory results in a safe and substantial manner so as to avoid undue stresses
8.1.5 Damaged equipment, as determined by the Royal Commission, shall be placed in first-
class operating condition or be returned to the source of supply for repair or replacement
8.1.6 SGC shall be responsible for the proper coordination of all phases of the Work and
equipment as specified herein, with the Work to be performed and equipment to be furnished
under the other Sections of the Specifications, in order to assure a complete and satisfactory
installation
8.1.7 SGC shall furnish and install all temporary electrical facilities, including lamps, required for
construction and safety operation. All such equipment shall remain the property of the
Contractor and shall be removed when permanent connections have been completed. If it is
determined during construction that the temporary facilities, as installed, interfere with other
construction operations, the Contractor shall relocate said facilities in an approved manner to an
approved location
8.1.8 No wire, bus or electrical equipment which is part of any of the permanent electrical
systems may be used for temporary electrical service during the construction operations.
Temporary connections shall be safe and in accordance with accepted practices
8.1.9 SGC shall be responsible for any damage to equipment, materials, or injury to personnel
caused by improperly protected temporary installations
8.1.10 All costs for materials and installation for temporary electrical facilities and energy for
their operation shall be at the expense of SGC
8.1.11 Electrical welders used in the erection and fabrication of the building and its equipment
shall be provided with an independent grounding cable connected directly to the structure on
which the weld is being made rather than to an adjacent conduit
8.1.12 After the installation is complete and properly adjusted, SGC shall conduct operating
tests. The various equipment and systems shall be demonstrated to operate in accordance with
the requirements of the specifications. Tests shall be performed in the presence of the Royal
Commission’s representative. The Contractor shall provide electric power, instruments and
personnel necessary for performing the various tests.

8.2 INSTALLATION OF ELECTRICAL CONDUITS:

9
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

8.2.1 Below Grade Conduit


1. The installation of below-grade conduit should not be avoided

» The direct buried conduits installed directly on earth shall be hot-dip galvanized rigid steel
conduits. Conduits encased in the concrete shall be UPVC conduits
» The minimum size for the below-grade conduit shall be 50 mm. Below grade conduits shall be
sized one size larger than required by the Code maximum wire fill
» Below grade bends shall be of the long radius type
» The minimum depth for low voltage system UPVC conduit installation shall be 560 mm below
grade. For rigid steel conduit, the minimum depth for a low voltage system shall be 310 mm
» Minimum depth for low voltage system EB UPVC conduits encased in concrete shall be 880
mm
» There shall be no more than three 90° bends in a below or above grade conduit run
» Below grade conduits shall have red tiles or concrete cover

» Spare conduits shall be provided with pull, terminated with plugged couplings and installed
flush with the finished floor in buildings, or 18.75 mm above the finished surface in other areas
» Upon completion of a duct run, a test mandrel (6 mm less in diameter than the inside diameter
of the duct) and wire brush cleaner (slightly larger than the duct) shall be pulled through each
duct. The testing and cleaning of a concrete encased duct shall be done on the day after the
concrete has been poured into, removing any concrete splash of spalls in the ducts
8.2.2 Above Grade Conduit
» Above grade conduit shall be rigid, Rigid PVC conduit shall be allowed for use, where
applicable, as per IEC 61386
» The minimum conduit size shall be 18.75 mm. Conduit used behind control boards or other
types of panels shall be 12.5 mm
» The separation of the conduit shall be horizontal, vertical, and on the crossing by a minimum
of 150 mm from piping or equipment with surface temperatures in excess of 45°C
» When conduit is terminated to equipment where vibration or movement is a concern, a
flexible, liquid tight conduit shall be installed between the rigid conduit and the equipment
» Conduit fitting in the above grade conduit system shall be manufactured from copper-free
aluminum. Cover screws shall be stainless steel
» Fittings shall be approved for the area classification and be suitable for the environment in
which they are installed.
» When PVC coated rigid galvanized steel conduit is used, it shall consist of galvanized steel
fitting with a 1.02 mm (40 mm) PVC exterior coating and epoxy interior coating. Cover screws
shall be stainless steel. Fittings shall be approved for the area classification and be suitable for

10
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

the environment in which they are installed. PVC coated rigid steel conduit shall be used in
exposed areas subject to mechanical damages and also used below grade.
» PVC coated clamps shall be used to fasten the aluminum conduit to ungalvanized steel or
concrete surfaces. Where the aluminum conduit comes in direct contact with ungalvanized steel
or concrete, the conduit shall be wrapped with insulating tape.
» At transition points between aluminum and steel conduit, an anti-oxidizing compound specially
made for this application shall be applied to the threads.
» Straight runs of conduit in excess of 45 m shall be provided with an approved expansion
fitting.
» Where conduit runs exceed the equivalent of a 45 m run or more than the equivalent of three
90° bends, expansion joint fittings shall be installed. One 90° bend shall be considered the
equivalent of 15 m of straight run conduit.
» Conduit entry into enclosures or devices shall be besides, bottom or top entry. For outdoor
installation, the top entry is not allowed, without exception.
8.2.3 Conduit Seals, Breathers and Drains
» Breathers and drains shall be installed at all low points in conduit systems and as required to
prevent the accumulation of moisture in the conduit and equipment enclosures.

8.2.4 Conduit Elbows and Tees


» Installation and construction of elbow and tee fittings shall be compatible with the above
Specifications.
8.3 INSTALLATION OF DUCT BANKS AND MANHOLES
8.3.1 Duct Banks
» Duct banks shall be constructed of UPVC conduit, encased in reinforced concrete
» In the assembly of a duct bank, the conduits are supported by spacers that hold the conduits
in place during the backfilling of inter-conduit space with sand or cement. The spacer shall be of
polypropylene plastic
» Spacers for supporting conduits shall be installed at intervals not exceeding 1.5 m. Spacers
shall be with interlocking lugs and matching holes for field assembly and into multiple units
» Conduit runs in duct banks shall be made continuous by the use of couplings
» Duct banks shall be provided with 20% spare capacity
» Structural concrete shall be used in duct banks constructed with PVC conduits under areas
that are subjected to vehicular traffic, for example, under roadways

11
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

» The concrete encasement shall extend a minimum of 75 mm from any conduit in the bank to
the outside surface
» The minimum distance from grade to the top of the duct bank shall be 600 mm
» Conduit stubs from duct bank to above grade shall be rigid steel. Where PVC conduit is used,
a transition to rigid steel conduit shall be made below grade
8.3.2 Handholes
» Handholes shall be installed in the locations as shown on the Contract Drawings and as
necessary to meet cable pulling requirements
» Manholes shall have a minimum inside dimensions of 800 x 800 mm by 800 mm deep
» Handhole cover plates shale be completely sealed against water ingress.
» Handhole cover plates shall be heavy duty
» Adequate space shall be allowed for :
• Making and supporting splices
• Supporting cables
• Clearance between low voltage control, power cables
• Bending and training cables for offsets and changes in the horizontal and vertical direction
• Providing adequate working clearance required as per IEC 60364 pulling, terminating and
splicing cables
» Handholes required for the duct bank system shall be located in non-hazardous classified
areas. Manholes shall be provided with cable pulling irons embedded in the concrete sidewalls
of the duct bank.
9. Resources:

9.1 Material and Tools:


9.1.1 uPVC Duct
9.1.2 uPVC Pipe & Fittings.
9.1.3 Hand Saw.
9.1.4 Pipe Cutters.
9.1.5 Various Hand Tools.

9.2 Manpower:
9.2.1 Foreman
9.2.2 Electrician

12
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

9.2.3 General Labor

10. Quality Control:

10.1 Documentation: The following input and output documents are needed in order to ensure
quality and comply with this method statement.
10.1.1 Input Documents:
10.1.1.1 IFC Drawings
10.1.1.2 Risk assessment / job safety analysis.
10.1.2 Output Documents:
10.1.2.1 Work inspection request (WIR)
10.1.2.2 Inspection records

10.2 Inspection: In order to ensure the quality assurance and quality control, the following
documents will be reviewed to ensure that all quality requirements have been met before
execution of any method statement works:
10.2.1 Approved Shop Drawings and Specifications.
10.2.2 Approved associated/linked Method Statements.
10.2.3 Approved Material Submittals.
10.2.4 All delivered uPVC Ducts shall be subject to inspection and approval of the
Engineer/ Consultant in line with the approved material submittal.
10.2.5 All uPVC Ducts installations shall be inspected in accordance with the approved
drawings.
10.2.6 Approved inspection test plan (ITP) and check lists will be used during inspection.
10.2.7 Work inspection request shall be issued to contractor / company project inspector
in advance.
10.2.8 Inspection shall be done in accordance with the QC Plan.
10.2.9 During Inspection, all exposed areas of uPVC Ducts shall be carefully examined
for leakage.
10.2.10 Initial mandrel test will be conducted for uPVC installed in duct bank prior to
concrete pouring and a final mandrel test after concrete pouring.
10.2.11 There will be red color painted on the top surface of duct bank after surface
preparation of concrete.

11. PPE Requirements: The PPE (Personal Protective Equipment) requirements for the
installation of uPVC (un-plasticized polyvinyl chloride) ducts may vary depending on the
specific regulations and guidelines set by local authorities, industry standards, and the nature
of the installation project. However, there are some common PPE recommendations that can
be followed to ensure the safety of workers during the installation process of uPVC Ducts.

13
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

11.1 Safety Glasses or Goggles: Safety glasses or goggles should be worn to protect the eyes
from potential hazards such as flying debris, dust, or chemical splashes. They should
provide adequate coverage and have impact-resistant lenses.

11.2 Protective Gloves: It is important to wear protective gloves to safeguard hands from cuts,
abrasions, chemical exposure, or other potential risks. The type of gloves required may vary
depending on the specific tasks involved in the installation process. For example, cut-
resistant gloves may be necessary when handling sharp tools or equipment.

11.3 Respiratory Protection: Depending on the nature of the installation project and the
potential for airborne contaminants, respiratory protection may be required. This can
include dust masks, respirators, or other appropriate respiratory protective equipment. It is
essential to select respiratory protection that is suitable for the specific hazards present in
the work environment.

11.4 Protective Clothing: Workers should wear appropriate protective clothing to minimize
exposure to potential hazards. This may include coveralls, long-sleeved shirts, long pants,
or other garments that provide adequate coverage and protection against physical or
chemical hazards.

11.5 Safety Footwear: Safety footwear with slip-resistant soles and toe protection should be
worn to prevent foot injuries from falling objects or accidental contact with sharp objects.

11.6 Head Protection: In situations where there is a risk of head injury from falling objects or
overhead hazards, wearing a hard hat or helmet is recommended.

11.7 Ear Protection: If the installation process involves loud noise levels exceeding
permissible exposure limits, hearing protection such as earplugs or earmuffs should be worn
to prevent hearing damage.

11.8 Fall Protection: If working at heights is involved during the installation process,
appropriate fall protection equipment such as harnesses, lanyards, and anchor points should
be used to prevent falls and ensure worker safety.

11.9 Skin Protection: Depending on the specific tasks involved, skin protection measures may
be necessary. This can include wearing chemical-resistant gloves, aprons, or other
protective clothing to prevent contact with hazardous substances.

11.10 First Aid Kit: It is essential to have a well-stocked first aid kit readily available on-site to
provide immediate medical attention in case of injuries or accidents.

14
Project: Construction of TSE Network for Green Method Statement for Installation of uPVC Ducts.
Riyadh Program – Group 5A
The Contractor: Abdullah Ibrahim Al Sayegh &
Date: Contract No: G5A
Sons Company.

It is important to note that the above PPE requirements are general recommendations and may
need to be adjusted based on the specific circumstances of the installation project. It is crucial to
consult local regulations, industry standards, and any specific guidelines provided by
manufacturers or relevant authorities for comprehensive and up-to-date information on PPE
requirements for uPVC duct installation.

12. Health, Safety and Environment:


12.1 All Waste will be collected and disposed as per Site requirement (CESMP).
12.2 The precautionary work will be made as per RA.
12.3 Make sure that all workers have PPE and PPE requirements are met as per RA.
12.4 Ensure that the powered tools are inspected and only used by a competent personal.
12.5 More environmental risk and mitigation measures are included in RA.
12.6 Contractor Water Tanker will be used to control the dust in the site where backfilling
executed in site.
12.7 All the concern employees will be provided with an ear plug to prevent noise hazard.
12.8 HSE and RA for the installation of uPVC Ducts as also including hazards associated with
the installation work shall be submitted separately in provided format for review and
approval..

15
Construction of TSE Network For
Green Riyadh Program – Group 5A

Hazard Identification and Risk Assessment – HIRA

Contractor Name Abdullah Ibrahim Al Sayegh & sons. Co Group No. 5A Related Documentation/ Legislation Method statement

 Routine Non-Routine Task/Activity: Risk Assessment Installation of HDPE 50MM Ducts. RA No: REVISION 00

RISK ASSESSMENT RISK CONTROLS


Residual Risk
Original Risk Original Risk with
with Additional
Without Controls Present Control
Additional Control Measures Control
SN Activity Hazards Impact Control Measure Already in Use
Needed
L S L S Rat L S
Rate Rate
(1-5) (1-5) (1-5) (1-5) e (1-5) (1-5)
• Load the HDPE duct thinking about the
burden supporting capacity of trailer.
Loss of
Transportation of Roll/ fall of HDPE duct • HDPE duct to be organized and tightened
1 equipment. 2 3 6 1 2 2
uPVC Ducts. street site visitors chance well within the trailer. Warning flag, sign
People’s injury.
to be displayed.
• observe the traffic regulations
shocked due to
underground electrical
• Work to be carryout under competent
cable (if any) Falling of
Burn supervisor.
Excavation & item on head or body
2 Electric shock. 3 4 12 • Use of PPE’s like protection shoe, hardhat 1 2 2
Trenching collapse of trench traffic
Fatality etc. Trench to be excavated in V shape.
hazards / car movement
Car visitors to be diverted if required.
Fall of character in the
trench

REV-0 Page 1 of 7
 Routine Non-Routine Task/Activity: Risk Assessment Installation of HDPE 50MM Ducts. RA No: REVISION 00

RISK ASSESSMENT RISK CONTROLS


Residual Risk
Original Risk Original Risk with
with Additional
Without Controls Present Control
Additional Control Measures Control
SN Activity Hazards Impact Control Measure Already in Use
Needed
L S L S Rat L S
Rate Rate
(1-5) (1-5) (1-5) (1-5) e (1-5) (1-5)

• Vehicles should never be overloaded. Loads


should be evenly distributed.
• Reverse beeper and flashing beacon fitted.
• All guards and covers to be in position and
secured
Windows, lights, mirrors and camera lens to be
kept clean at all times.
• The cab floor to be kept clean and free from any
obstacles which may affect the safe operation of
the Machine.
• Ground workers to wear hi visibility vests at all
times and hard-Hats.
• Warning signs will be erected to alert
Total loss of pedestrians of Unloading/Loading Operations.
equipment or • Ground workers to keep clear of plant at all times
Loading & Unloading • Falls from height not working and not to approach until signaled to do so by the ● Periodical Inspections for all
3 4 4 16 3 4 12 2 4 8
Of HDPE duct • Crushing properly and trained Operator while loading/unloading lifting accessories
the people’s operations are underway.
injury • All lifting equipment must be certified for its use
and have proof of such inspections available to all
supervisory staff.
• Loads to be tipped only on suitably level ground
to prevent overturning.
• All plant and equipment will be equipped with a
Fire extinguisher.
• Competent Garage Mechanics carry out servicing
to plant as per the manufacturer’s instructions.
• The use of mobile phones will be prohibited
during lifting operations.

REV-01 Page 2 of 7
 Routine Non-Routine Task/Activity: Risk Assessment Installation of HDPE 50MM Ducts. RA No: REVISION 00

RISK ASSESSMENT RISK CONTROLS


Residual Risk
Original Risk Original Risk with
with Additional
Without Controls Present Control
Additional Control Measures Control
SN Activity Hazards Impact Control Measure Already in Use
Needed
L S L S Rat L S
Rate Rate
(1-5) (1-5) (1-5) (1-5) e (1-5) (1-5)
Always check the equipment before using.
Performs periodic inspection and maintenance
Entrapment due to fall/ tasks.
HDPE 50MM duct. Ensure your training is up to date.
• Operators direct field The weight of the load must fit the equipment.
of vision obscured by Use high-quality monitoring and overload
load leading to contact protection systems.
with other persons or Vehicles should never be overloaded.
plant. Loads should be evenly distributed, secured and not
• Failure of lifting protruding beyond the sides or back of the vehicle.
equipment. Reverse beeper, flashing beacon and mirrors fitted
Defective skids removed immediately from the line.
• Inadequate supervision.
Injury to the Heavy duty gloves to be worn by operatives
• Untrained Operatives
working people handling skids.
4 Laying of HDPE duct • Use of mobile phones 3 4 12 1 2 2
and visitors. All engines guards and covers to be in position and
by operators.
Fatality secured.
• Displacement of load
Windows, lights, mirrors and camera lens to be
• Person being struck by kept clean at all times
suspended HDPE 50MM The cab floor to be kept clean and free from any
duct causing serious obstacles which may affect the safe operation of the
injury of harm. Machine.
• Defective and broken Ground workers to wear Hi Visibility Vests at all
skids causing crushing of times and Hard-Hats.
limbs of entrapment of Warning signs will be erected to alert pedestrians of
body parts. • Manual Unloading/Loading Operations.
Handling. Traffic management must be in place where
loading/unloading is being carried out on public
roads.
●Time Delays
Dropped objects resulting ●Financial loss ●Lifting control by ‘appointed person’/ rigger
in personnel being struck ●Property ●Barrier lift and laydown areas ●Equipment’s Operators Training
5 Crane Operation 4 5 20 ●Inspection of equipment 3 5 15 2 5 10
or other equipment or damage ●TUV equipment’s Inspection
materials being damaged ●Injury for ●Strictly following the lifting plan (If needed)
involved

REV-01 Page 3 of 7
 Routine Non-Routine Task/Activity: Risk Assessment Installation of HDPE 50MM Ducts. RA No: REVISION 00

RISK ASSESSMENT RISK CONTROLS


Residual Risk
Original Risk Original Risk with
with Additional
Without Controls Present Control
Additional Control Measures Control
SN Activity Hazards Impact Control Measure Already in Use
Needed
L S L S Rat L S
Rate Rate
(1-5) (1-5) (1-5) (1-5) e (1-5) (1-5)
●Electric fault error
happened from ●Provide spare part in stock
●No progress
electric cards, ●Standby, well training maintenance team
electronic device ●The people's ● Improving lubrication at tunnel face and
Operation/ Tunneling and equipment injury throughout the HDPE duct line by injecting
6 breakdown 3 4 12 bentonite and installation of benchmark and 2 4 8
work ●Financial loss
●Soil Collapse due to ●Property counter checking the asphalt level.
backfilled area or ● Conduct soil investigation and provide
damage
nonhomogeneous ground comprehensive soil data
●Collapse of ●Observe confined space controls and permit
personnel due ● Trained watcher to monitoring
to fumes or lack conditions
●Asphyxia the exit of confined space
7 Confined spaces of oxygen 4 4 16 ●Emergency arrangements in place and 3 4 12 2 4 8
●Hazardous atmosphere ● Fire devices to be near of
●Fire and communicated
location in case of emergency
explosion ●Gas monitoring by gas detector
Using safety helmet and height gauging at site
Serious injury
8 Overhead obstructions Not using safety helmet 3 4 12 entrance and in front of any other height 2 4 8
and damage
restriction.
●Regular checks on cable, connector and service
●Death ●Cable protection and careful routing
9 Electric fault Electricity 4 4 16 1 4 4
●shock ●Examination by electrician of all tools brought to
site before authorization for use
●Fatality
Lack of competent gas Ensure that the testing devices are calibrated &
10 Gas testing ●Injury 2 4 8 1 4 4
testers certified
●Reputation
• Work at height must be adequately planned and
supervised Collective fall protection measures must
be given priority.
• Fall of a person a • Trench boxes must have guard and mid rails.
distance liable of causing • Inspections on equipment carried out (i.e., crowd
personal injury ●Serious injury control barriers, harnesses, fall arrest devices etc.)
11 Work at height 4 5 20 2 5 10
• Falls of persons off the ●Death • Safe means of access to the work location
edge of structures provided using ladders
●wearing safety harnesses
●take precautions when working on or near fragile
surfaces
●provide protection from falling objects

REV-01 Page 4 of 7
 Routine Non-Routine Task/Activity: Risk Assessment Installation of HDPE 50MM Ducts. RA No: REVISION 00

RISK ASSESSMENT RISK CONTROLS


Residual Risk
Original Risk Original Risk with
with Additional
Without Controls Present Control
Additional Control Measures Control
SN Activity Hazards Impact Control Measure Already in Use
Needed
L S L S Rat L S
Rate Rate
(1-5) (1-5) (1-5) (1-5) e (1-5) (1-5)
Collision with plant or
traffic
• Traffic Accidents.
• Inadequate Traffic • Correct signing/coning/barriers in place for all
Management roadwork’s and path works; including site entrance
Arrangements signage
• Misleading signs • Employees operating stop/go batten or
• Close proximity of the ●Moderate maintaining the system to have safety at
Working on or near public. injury to skin roadwork’s training.
12 3 4 12 2 4 8
roads, • Collision with plant or ●Serious eye • Longitudinal & size safety zones in place
traffic injuries • Safe access and egress for vehicles, plant and
Traffic Accidents. person's.
• Inadequate Traffic • Safe crossing of traffic lanes.
Management • Traffic management equipment maintained
Arrangements clean.
• Misleading signs
• Close proximity of the
public
●Care MUST be taken to ensure that all hand tools
Incorrect use of hand ●Fatality used are in good condition and fit for purpose
13 Hand tools 3 3 9 1 3 3
tools ●Injury ●No homemade hand tools are allowed on work
site
Access/egress points are checked regularly including
Injury to the
condition of floor , steps, handrails, doors, and
working people
14. Access / egress Unsafe access/ egress 2 3 6 handles Actions are in place to deal with hazardous 1 3 3
and visitors.
weather conditions which could affect access/
Fatality
egress
Untrained, incompetent,
unprofessional, and Permit to work lifting procedure and its
Injury to the
uncertified crane requirements shall be followed. All crane operators
HDPE Ducts lifting working people
15. operators can lead to 4 3 12 must be trained by an Accredited Institution and 1 3 3
procedure and visitors.
incidents causing injuries certified. Operators of Mobile Lifting Equipment
Fatality
and property damage. must be appointed as per the HSE Procedure.
Working without permit

REV-01 Page 5 of 7
 Routine Non-Routine Task/Activity: Risk Assessment Installation of HDPE 50MM Ducts. RA No: REVISION 00

RISK ASSESSMENT RISK CONTROLS


Residual Risk
Original Risk Original Risk with
with Additional
Without Controls Present Control
Additional Control Measures Control
SN Activity Hazards Impact Control Measure Already in Use
Needed
L S L S Rat L S
Rate Rate
(1-5) (1-5) (1-5) (1-5) e (1-5) (1-5)

Untrained and uncertified


Riggers carrying out lifts
that require a qualified Injury to the All Riggers must be trained by an Accredited
Rigger as per the working people Institution and certified. All Certified Riggers are to
4 3 12 1 3 3
Company SHE Procedure and visitors. wear RED hard hats for identification purposes.
Manual can lead to Fatality Qualified Riggers must be appointed.
incidents causing injuries
and property damage.
Incorrect cranes for the The right tool for the right job is the golden rule.
task on hand can lead to Site Managers and Supervisors are to ensure that
crane failure, injuries, this rule is applied at all times. A lifting checklist is to
Injury to the
and property damage. be used as set out in the Company’s SHE Procedure
working people
An uncertified crane is 4 3 12 Manual. All Lifting Equipment is to be tested and 1 3 3
and visitors.
used which could lead to certified by an Authorized Inspection Authority once
Fatality
equipment failure and a year or when repaired or modified. This includes
subsequent injuries all integral parts of the said Lifting equipment e.g.
and/or property damage. hooks, crane rope, etc.
Personnel
PTW not PTW system shall be Implemented and complied.
injury
implemented and 3 4 12 No resting, eating or smoking shall be allowed inside 2 2 4
Property
complied the site.
damages

Legend: S →Severity and L→Likelihood:


Risk Assessment Team
HSE Manager Construction Manager Project Manager:

Signature Signature Signature

Reviewed by Approved by

REV-01 Page 6 of 7
Risk Heat Map Mitigation Strategy

Health and Safety Impact scale Likelihood Criteria

REV-01 Page 7 of 7

You might also like