WINEP Phase 2_ L1 Project Engineering Schedule

Activity ID Activity Name Planned Duration


W2 W4 W6 W8 W10 W12 W14 W16 M9
JI-WINEP Phase 2 Project 90d

JI-2023.1
1 Process Process
55d
A1000 PFD's & Philosophies PFD's & Philosophies
A1010 Line Sizing Line Sizing
A1020 P&ID and Datasheets P&ID and Datasheets
JI-2023.2 Pipeline & Piping 80d
A1030 Valves & Misc. datasheets Valves & Misc. datasheets
A1040 Layout drawings Layout drawings
A1050 GAD's GAD's
A1060 Stress Calculation Stress Calculation
A1070 Support drawings Support drawings
A1080 Isometrics Isometrics
A1090 MTO MTO

JI
JI--2023.3 Civil & Mechanical
202 75d
A1110 Calculations Calculations
A1120 Datasheets Datasheets
A1130 MTO MTO
A1140 Drawings Drawings

JI
JI--2023.4 Electrical & Instumentation
202 85d
A1150 Calculations Calculations
A1160 Datasheets Datasheets
A1170 MTO MTO
A1180 Drawings Drawings

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities