U Method Statement For Penstock Installation (20220918 - 0462)
U Method Statement For Penstock Installation (20220918 - 0462)
Rev.2
September 2022
Method statement for penstock installation
Table of Contents
1. Engineering Overview.......................................................................................................... 1
2. Basis of Compilation ............................................................................................................ 1
3. Overall Construction Planning ........................................................................................... 1
3.1 Steel Pipe Installation Sequence................................................................................ 1
3.2 Installer Access ........................................................................................................... 8
3.3 Construction Water Planning.................................................................................... 8
3.4 Construction Ventilation Planning ........................................................................... 8
3.5 Construction Communication Planning................................................................... 9
3.6 Electricity Consumption Planning for Construction .............................................. 9
4. Installation Schedule ............................................................................................................ 9
5. Resource Input Plan ........................................................................................................... 10
5.1 People Configuration Plan....................................................................................... 10
5.2 Equipment Configuration Plan ............................................................................... 11
5.3 Self-Made Tooling Plan ............................................................................................ 13
6. Preparation before Installation ......................................................................................... 13
6.1 Site transportation of penstock ............................................................................ 13
6.2 Transportation Track Layout .................................................................................. 13
6.3 Preparation of Transport Trolley ............................................................................ 14
6.4 Preparation of In-Pipe Construction Platform...................................................... 15
7. Installation Process Measures ........................................................................................... 15
7.1 Installation Process Flow ......................................................................................... 15
7.2 Transportation Method of penstock ....................................................................... 15
7.3 Penstock Installation Adjustment ........................................................................... 16
8. Circumferential Seam Welding and Inspection ............................................................... 16
8.1 Preparation before Welding .................................................................................... 16
8.2 Welding Requirements ............................................................................................. 17
8.3 Welding Technology ................................................................................................. 18
8.4 Nondestructive Testing ............................................................................................. 19
8.5 Deficiency Treatment ............................................................................................... 20
9. Anticorrosive Coating Process .......................................................................................... 20
10. Quality Control Measures ............................................................................................... 21
11. Special Safety and Civilized Measures ........................................................................... 22
11.1 Special Safety Measures ......................................................................................... 22
11.2 Civilized Construction Measures .......................................................................... 23
Method statement for penstock installation
1. Engineering Overview
Steel Penstock to pass the rated water 50.0 m3/s for two (2) water turbine units in each
15.55 MW shall consist of embedded type steel penstock starting from 7.2 m downstream of
the datum line of the surge tank gate up to the powerhouse.
The steel penstock starts from 7.2 m downstream of the datum line for the surge tank gate
to the Contract boundary at 7.5 m upstream side from the centerline of the water turbines. The
line profile consists of an upper horizontal portion, an inclined portion, a lower horizontal
portion, a bifurcation and two (2) branched pipe portions.
The steel penstock shall be of the embedded type and complete with straight pipes, bend
pipes, reducing pipes, bifurcation, branch pipes, seepage rings, stiffener rings, thrust rings,
grout holes and plugs and all other necessary components.
2. Basis of Compilation
According to the specification mentioned in the contract.
1
Method statement for penstock installation
2
Method statement for penstock installation
1:The anchors are at the top of the cave and are used to fix the fixed pulley.
2:The anchors are on the floor and are used to fix the 1T winch.
3:The anchors are on the floor and are used to fix the fixed pulley.
4:The anchors are on the floor and are used to fix the 10T winch.
All the anchors should be installed by Lot A2 contractor.
Figure 3 Using the Motor hoist to transport the pipe section in the inclined shaft
(2) Second phase
The first pipe section of IP6 should be the position joint. The pipes will be installed from
the position joint to IP7. The joint section of IP7 will be reserved and not installed at this phase.
The pipe sections will be transported through Adit No.3. 10T forklift will be used to move the
pipes in the lower horizontal portion. Every time the length of the penstock transported by the
forklift is 2m.
Note:The installation of first phase and second phase will be carried out alternately.
3
Method statement for penstock installation
4
Method statement for penstock installation
5
Method statement for penstock installation
We will use 16# I-beam and 10# channel steel as the bracket for bifurcation and conduct the
water pressure test with this bracket. The 16# I-beam is used as the column and beam of the
bracket, and the 10# channel steel is arranged around it to assist in fixing the bifurcation. The
specific arrangement is shown in Figure 8 and Figure 9.
(4) Forth phase
Two branch pipes installation will be started from the joint section with the bifurcation to
the downstream powerhouse. For the transportation of the branch pipes, the powerhouse OHT
crane will be used to unload the pipes to the platform at EL. 469.400. Trolley with the rail
system will be arranged in the two branch channels. The branch sections will be transported by
the trolley in the two branch pipes portion.
6
Method statement for penstock installation
7
Method statement for penstock installation
4. Installation Schedule
Table 4-1 Installation Schedule of Penstock
Duration
No. Process Name Start Time Finish Time Remarks
(days)
9
Method statement for penstock installation
Bifurcation
3 Installation of bifurcation T3 T4 90
T4=T3+90
branch pipe
4 Installation of branch pipe T4 T5 60
T5=T4+60
Final joint
5 Installation of IP8 to IP7 T6 T7 30 T6=T4+1
T7=T6+30
Final joint
6 Installation of IP0 to 2#-2 T8 T9 30 T8=T7+1
T9=T8+30
Note: T1 is the time for the handover of the Inclined shaft steel pipe and upper flat pipe
working face from Lot A2 to Lot B.
2 Technician 1
3 Security guard 1
5 Measuring worker 1
10
Method statement for penstock installation
Number of
No. Type of Work Persons Remarks
(Persons)
6 Crane man 2
7 Rigger 4
9 Electrician 1
Qualified to conduct UT
10 Flaw detection 1
and RT tests
11 Auxiliary worker 4
Total 24
1 set
4 Winch 1t, 10t
For each
5 Forklift 10t 1 set Lease
11
Method statement for penstock installation
1 set
20 RT flaw detection equipment
1台
12
Method statement for penstock installation
13
Method statement for penstock installation
work is completed by lot A2.
14
Method statement for penstock installation
6.4 Preparation of In-Pipe Construction Platform
14# and 10# I-beams are used for welding the steel structure skeleton, Φ48×3.5mm steel
pipes are used for welding, and the top surface is paved with 3mm thick patterned steel plates.
4 groups of lifting lugs are set on the top surface of the construction platform. The lifting lugs
are 65mm in diameter and 30mm in thickness and welded on both sides. The lifting lugs are
connected with 4 cable hinges, of which 2 are short hinges and the other 2 are long hinges,
which can be switched when the platform needs to shift and change hooks. Each cable hinge
bears 3t, and the other end of the cable hinge is connected with a one-way inclined opening
hook.
After the construction platform is in place, hang the free end of the short hinge at the
penstock nozzle and slowly slip out the steel wire rope until the two iron cable hinges are
fully stressed. After the short hinge is stressed, hang the free end of the long hinge at the
penstock nozzle as a backup. After the comprehensive inspection, the short hinge can be
released from slipping out. When the construction platform needs to be displaced, connect the
slip wire rope shackle with the long hinge hook and slowly lift it upwards. After meeting the
short hinge release condition, release the short hinge. After the construction platform is
displaced to the required position, hang the short hinge according to the above steps.
welding → Weld non-destructive testing →Apply respective coats at welding seam locations
Preparatory Work includes the fabrication of the trolley and platform outside of the
penstock tunnel and the installation of guide rails after taking over the tunnel from Lot A2.
With a 10T forklift, transport the penstock to the installation position. Inclined section and
15
Method statement for penstock installation
After the steel pipe is transported to the installation position, use 4 screw jacks to jack up
the steel pipe to the installation elevation. Adjusting the butt joint of the bottom of the steel pipe
to meet the specification requirements, weld 2~3 positioning plates of the same material at the
bottom of the steel pipe. Tie the steel pipe section and the previous section with a chain block
at the top and side. After confirming that the steel pipe has been reliably fixed at the installation
position, move the trolley out of the bottom of the steel pipe. Pull the trolley to the starting point
of transportation with the inclined slip rope to prepare for the next section of the steel pipe.
The riveter can press and adjust the circumferential seam of the steel pipe. The butt joint
device (Including the screw jack) is arranged on the pipe construction platform to adjust the
circumferential joint and adjust the roundness, misalignment, gap and other dimensions of the
(1) Welders engaged in welding of penstock shall pass the examination as required and
with the welder certificate issued by the corresponding competent department and submit the
certificate.
(2) Check the quality certificate and certificate of welding materials, and confirm that
(3) Welding seam preheating and post-heating equipment mainly includes temperature
control cabinet, heating block and its auxiliary power cord, welding material heating equipment
mainly includes the oven and its auxiliary power cord, and welding material storage equipment
mainly includes welding material heat preservation box, heat preservation barrel, etc.
(5) In case of the following situations happen in the welding environment, protective
16
Method statement for penstock installation
① Wind Speed: Gas shielded welding is more than 2m/s, and other welding methods are
③ The ambient temperature is lower than: Low alloy steel below -10℃;
(8) Before welding, remove rust, slag, grease and water marks within 50mm of the groove
and both sides. Check the installation size, groove size and positioning welding quality.
The penstock is made of Q345R, and the circumferential seam of the penstock is welded
by SMAW.
The welding material used for girth welding is 507, and the diameter of the electrode is
Ф3.2mm and Ф4.0mm, the diameter of carbon is Ф8mm and Ф10mm. Electrode and carbon
rods for carbon arc gouging shall meet the requirements of relevant standards. Welding
materials shall be sealed and moisture-proof during storage and transportation. The warehouse
shall be well ventilated, with room temperature not lower than 5℃ and relative humidity not
higher than 60%, and the room temperature and relative humidity shall be recorded regularly.
Electrodes shall be stored on shelves with a height distance of not less than 300mm from the
Heating temperature and time during the use of welding materials shall be implemented
according to the specifications of welding materials manufacturers. After drying, the electrode
should be kept in a constant temperature box at 100~150℃, and the coating of the electrode
should be free from falling off and obvious cracks. When in use, the welding rod is loaded into
the heat preservation cylinder. The number of thermal insulation cylinders filled each time shall
In the welding process, the welding heat input is strictly controlled to reduce the weld line
17
Method statement for penstock installation
energy, thus reducing the welding stress. Parameters of Q345R steel electrode arc welding: The
current type is DC reverse connection, the welding current is 110~170 A, the arc voltage is
24~28 V, the welding speed is 4.5cm~12cm/min, and multi-layer and multi-channel welding is
performed.
grooved with an angle of 60°, a blunt edge of 2mm and an assembly clearance of 2mm.
The wall thickness of the bifurcation is 20mm, and the circumferential joint of the tile butt
joint is a single V-grooved with an angle of 60°, a blunt edge of 2mm and an assembly
clearance of 2mm. The thickness of the crescent rib is 40mm, and the combined weld at the
The welding seam of the lifting lug is a T-shaped fillet weld, and the groove form is the
unilateral V-shaped groove, the groove angle is 45°, and the blunt edge is 2mm.
The welding materials and welding requirements for fixed welds are the same as those for
formal welds. Spot welding shall be firm, reliable and free from defects; The locating weld shall
have a thickness of not less than 15mm, a length of not less than 100mm and an interval of not
less than 600mm. The locating weld shall be welded on the root cleaning side, and the locating
In order to ensure the welding quality and deformation control, the parts above the center
line of the steel pipe should be welded on the outer side first, and the root should be cleaned on
the inner side. The parts below the center line shall be welded on the inner side first, and the
welding of the penstock, and multi-layer, multi-channel, symmetrical, segmented and backward
welding method is adopted for welding of bifurcation. The indirect joints of each weld layer
18
Method statement for penstock installation
should be staggered. After each weld is welded, it should be cleaned by the wire brush or slag
remover, and the next welding can be carried out after the cleaning inspection.
Class-I Weld: Main stress welds, such as all the welds in the bifurcation, longitudinal seam
of the pipe wall and closed circumferential seam of the make-up joint.
Class-II Welds: Secondary stress welds, such as circumferential seam of pipe wall, butt
Class-III Welds: Other welds that do not belong to Class-I and Class-II welds.
Non-destructive testing personnel shall receive professional training and hold technical
qualification certificates issued by relevant departments and suitable for their work. Internal
quality inspection can be carried out after the appearance quality inspection is qualified.
Ultrasonic flaw detection or RT flaw detection method can be selected for internal flaw
detection of welds. When one of the flaw detection methods is in doubt, another flaw detection
method should be adopted for reexamination. The proportion of NDT for weld interior shall be
(%) (%)
Type of Steel
Class-I Class-II Class-I Class-II
Q345R 100 50 25 10
Remarks: 1. After ultrasonic flaw detection is adopted for Class-I welds, ray or RT flaw detection shall
19
Method statement for penstock installation
be used for re-inspection. The re-inspection length shall not be less than 5% of the total weld length, and
each weld shall not be less than one film.2. In case of the suspicious waveform of Class-II weld after
ultrasonic inspection, which cannot be accurately judged, RT inspection shall be applied for re-inspection.
3. According to the contract, 100% UT and 20% RT shall be carried out for welded joints of pressure steel
pipes.
(1) The protrusions on the pipe wall surface should be polished and removed. When cracks
and other dangerous defects are found inside or on the surface of the weld, the contractor shall
analyze them, put forward the defective repair parts and repair measures, and repair them by
(2) The internal defects of welds shall be removed by carbon arc gouging or grinding
wheel and shall be ground into grooves convenient for welding by grinding wheel, which shall
be checked before welding repair. If the defect is a crack, it shall be tested according to relevant
specifications, and the welding repair can only be carried out after confirming that the crack
Both sides of the installation weld of penstock and bifurcation and the surface of the weld
shall be de-rusted manually by using a grinder wire wheel (Grinder with wire wheel).
Coatings used for penstock shall be produced by manufacturers with production licenses
issued by relevant departments, and the product specifications and quality shall conform to
documents.
20
Method statement for penstock installation
ensure the construction progress by organizing technical disclosure, clarifying the process and
(2) Adhere to the system of pre-shift meetings and strengthen the skills training of
employees. Before the daily construction, a pre-shift meeting shall be held, and the operation
team leader and on-site technical person in charge shall specify the construction tasks and
construction quality control points of the day and make technical disclosure to avoid quality
accidents and hidden dangers caused by unclear technical and quality requirements of
construction personnel.
(3) The construction procedures, methods and techniques shall be strictly implemented
according to the requirements, and the construction technicians and quality management
departments shall strictly inspect and control the construction process. If it is found that the
construction fails to comply with the plan, the barbaric construction and the operation fails to
comply with the specifications, it must be resolutely stopped, and the relevant responsible
(4) After the construction of a single process is completed, the quality management
department will conduct a comprehensive inspection of the construction quality and resolutely
(5) In the construction process, the quality control inspection plan shall be carefully
implemented. Strengthen the stand-by system for the whole construction process, and correct
the potential quality and safety hazards if found on the spot to eliminate the potential quality
(6) The construction process is strictly based on construction measures, design drawings,
technical clauses and quality standards of relevant specifications, and construction personnel
are strictly required to comply with them. After each working procedure is up to standard, the
construction of the next working procedure can be carried out to ensure that the construction of
each working procedure meets the requirements of specifications and design quality standards
21
Method statement for penstock installation
(7) Regularly check the running status of machines and tools and handle abnormal sounds
and other abnormal phenomena in time to avoid quality and safety accidents.
(8) Strengthen the inspection of weld appearance quality. The welding appearance quality
shall conform to the welding appearance quality standard. The weld shall be full and the
(9) In order to ensure the welding quality, the welding materials shall be managed by
designated personnel, and the heating temperature, holding time, distribution and recycling of
(10) When welding, the heated electrode should be placed in the heat preservation
cylinder and covered in time after taking the electrode to prevent it from being affected by
dampness.
(11) The locating solder joints, spacing, length and thickness should be appropriate to
avoid tearing during welding, and the locating electrode should be the same as the formal
welding electrode.
(12) Each working procedure shall be carried out in strict accordance with the three-
inspection system, and the original records shall be made, and the acceptance form shall be
filled in time. The three-inspection system refers to the system of initial inspection by the team,
re-inspection by the operation team, and final inspection by the quality management department.
(1) Before all construction personnel enters the site, they shall carry out safety production
(2) Enter the construction site, wear safety helmets and other labor protection articles,
(4) The lighting is sufficient, and the mobile lighting shall use safe traveling lights with
22
Method statement for penstock installation
a voltage below 36 V.
(5) Scaffolding is safe and stable with reasonable structure, which is convenient for
(6) When working at height, the construction personnel shall fasten their safety belts and
(7) Pedestrians are forbidden to walk or stay in the lifting area when lifting the split
(8) Lifting command and operation shall be carried out by certified and skilled lifting
personnel.
(9) Keep the distance between the oxygen cylinder and acetylene cylinder > 5m, keep the
cylinder stable, check whether the pressure gauge is in good condition at any time, and close
the valve in time when not in use, and flashback arrestors shall be installed at cylinder end
(10) With the remaining electrode, the abandoned electrode head back in time for
safekeeping.
(12) Construction personnel should count tools and instruments to avoid loss.
(13) Personnel irrelevant to operation are prohibited from entering the construction site.
(14) Safety protection and construction measures must be taken to coordinate and arrange
all the work in time, and crossover operations should be avoided as far as possible.
(1) Educate the construction personnel to abide by the rules and regulations of the
construction site, take good care of the environment, put into construction production with a
good mental outlook, and conduct friendly coordination and communication with other
23
Method statement for penstock installation
participating units.
(2) All construction personnel on site must wear labor uniforms and identification cards
(3) Strictly control the safe and civilized construction on the construction site and ensure
that the materials are sorted and placed in order. When the work is finished, the materials are
exhausted, and the site is cleared. The team leader shall check the clean-up of the working area
(4) Maintain the environmental sanitation of the construction site. After the completion
of the work, arrange for the personnel on duty to clean the construction surface and keep the
(5) The wastes and waste residues of various operations shall be removed at any time,
and the wastes, waste residues and other wastes shall be transported to the designated waste
disposal area to ensure the cleanness and neatness of the working area and do a good job in
24