(2) Importing/Updating S-63 Chart

Start

Is importing SA Certificate file


Yes
(e.g.primar.crt) already completed?

No

Import SA Certificate file(3.1)

Select SA Certificate file(3.2)

Is a cell permit already Yes


imported in the unit?

No Yes have we received a new


cell permit?
Import Cell permit(3.3)
No

What is the type of Chart Update CD


CD-ROM?

Base CD

Import Chart(3.4) Update Chart(3.5)

Yes Is there still other CD?

No

Completed

・Importing of SA Certificate file and Cell permit is available in either Sequence.

3 Chart Portfolio
Import/Update of S-63 Chart
Note:
• ECDIS can use the charts published by more than one data server (PRIMAR STAVANGER, UKHO,
Hydrographic and Oceanographic Department of Japan Coast Guard, etc.). It is necessary, however, to
import and select SA Certificate file to the system each time charts provided by a new data server are
used. Before importing the charts, for certification of ENC, import and select SA Certificate file con-
tained in Chart CD-ROM provided by the data server.

3.1 Import of SA Certificate file (if this is already imported skip this step)
1) Start Chart Portfolio.
2) Select [Tool] - [Option] in that order.
The “Option” panel opens.

3) Left-click the [S-63] tab, and then, the [Import of Certificate...] button.
The “Find file” panel opens.

8 Chart Portfolio 8-32


4) Insert S-63 Chart CD-ROM into the CD-ROM drive, and wait until it is ready to be read.
5) Select [D:] (D drive) from the “Drive” combo box (a) as shown below.
(c) (b)

(a)
6) Double-click [D:] in the “Directory” list box (b).
7) Double-click the file name of SA Certificate (such as “primar.crt”) in the “File name” list box (c).
8) Check the file name, and left-click the [OK] button.
The “Import of SA Certificate” panel opens.

Check the file name you have selected.


8

8-33 8 Chart Portfolio


9) Check the SA Certificate information, and left-click the [OK] button.
Check the SA Certificate information.

10) As the message box appears, left-click the [OK] button to close the box.
Import procedure is completed.
“1” in “[1:primar.crt]” indicates the order of adding CRT file.
“primar.crt” indicates the file name.

8 Chart Portfolio 8-34


3.2 Selection of SA Certificate file (Select Certificate According to chart Provider)
1) Start Chart Portfolio.
2) Select [Tool] - [Option] in that order.
The “Option” panel opens.
3) Left-click the [S-63] tab, and then, the [Select of Certificate...] button.
The “Select of SA Certificate” panel opens.

8
4) Select an SA Certificate as the system SA Certificate.

8-35 8 Chart Portfolio


5) Check the information of SA Certificate, and left-click the [OK] button.

Check the information of SA Certificate.

6) Check the file name of SA Certificate (such as [1:primar.crt]), and left-click the [OK] button to close the
panel.

“1” in “[1:primar.crt]” indicates the order of adding CRT file.


“primar.crt” indicates the file name.

3.3 Import of Cell Permit (If no new cell permit is received skip this step)
1) Start Chart Portfolio.
2) Select [Tool] - [Option] in that order.
The “Option” panel opens.

8 Chart Portfolio 8-36


1. Deleting old permit file (Do it when a pop up message appears on Navigation and Planning stating
that licence for a number of charts has expired. If not skip this step and go to 2. Registration/update of permit file)
NOTE:
z Only the permit files are deleted. The already imported charts will not be deleted.
z Make sure to reregister the new permit file. If leaving the permit file deleted and not reregistered,
importing/updating the charts will be impossible.
z When subscribing from multiple data servers (PRIMAR STAVENGER, UKHO, Hydrographic and
Oceanographic Department of Japan Coast Guard), all the permit files will be deleted after executing the
deletion. Make sure to reregister the new permit files of all the data servers.

pay attention in case you are not using


charts supplied solely from one source
(only from Primar or only from UKHO etc.)
(3) Click the [S-63] tab and then [Delete Cell Permit].

Click [Delete Cell Permit…]

2. Registration/update of permit file


The new permit has to be inputed by the following steps.

3
1) Left-click the [S-63] tab, and then, the [Import Cell Permit...] button.
The “Find file” panel opens.

2) Insert Cell Permit CD-ROM into the CD-ROM drive, and wait until it is ready to be read.
3) Select [D:] (D drive) from the “Drive” combo box (a) as shown below. 8
(c) (b)

-When Cell Permit is


supplied in FD,
insert it into the FD
(a)
drive, and select [A:]
4) Double-click [D:] in the “Directory” list box (b).
(A drive).
5) Double-click the file name of Cell Permit (such as “PERMIT.TXT”) in the “Filen ame” list box (c).

8-37 8 Chart Portfolio


6) Check the file name, and left-click the [OK] button.

Check the file name you have selected.

7) As the “Completed” panel appears, left-click the [OK] button.


The display returns to the “Option” panel.

8) Check the number of chart license, and left-click the [OK] button to close the panel.
Import procedure of S-63 Cell Permit is completed.

Check the number of chart license.

8 Chart Portfolio 8-38


3.4 Import of S-63 Chart
1) Insert S-63 Chart CD-ROM into the CD-ROM drive.
2) Select [Sort] - [S-63(Offline)] in that order.
S-63 chart list will appear in several minutes.

Note:
• Decoding of chart and checking of permission start.
This processing takes several minutes or more (30 minutes, for example) depending on the num-
ber of chart license.

3) Left-click the [Import/Update] button.


The “Import Condition” panel opens.

[Import/Update] button
8

S-63 chart list

8-39 8 Chart Portfolio


4) Left-click the [OK] button.
The “S-57/S-63 Import/Update” panel opens.

5) Left-click the [OK] button.


Import of S-63 chart is started.

Structure, format and validity of the chart are checked.

8 Chart Portfolio 8-40


Left-clicking the [Log] button will show the import result.

[Log] button

8
Import result

Number of charts imported Total number of charts to be imported excluding invalid ones
(Charts updated previously are counted in.)

Progress meter shows the progress of the import processing according to the capacity
of the chart files already processed.

8-41 8 Chart Portfolio


6) Check that the import is completed, and then, left-click the [Exit] button to exit Chart Portfolio.

(2) Left-click the [Exit] button.

(1) Check that the import is completed.

3.5 Update of S-63 Chart (Same procedure as 3.4 Import of S-63 Chart)
1) Insert S-63 Chart CD-ROM into the CD-ROM drive.
2) Select [Sort] - [S-63(Offline)] in that order.
S-63 chart list will appear in several minutes.

Note:
• Decoding of chart and checking of permission start.
This processing takes several minutes or more (30 minutes, for example) depending on the num-
ber of chart license.