MRP Matrics For B & C


Item : B LLC : 1 Period
Lot size : 100 LT : 2 PD 0 1
Gross requirements
Scheduled receipts
Projected on hand 50 50 50
Net requirements
Planned order receipts
Planned order release

Item : C LLC : 1 Period


Lot size : 500 LT : 3 PD 0 1
Gross requirements
Scheduled receipts
Projected on hand 500 500 500
Net requirements
Planned order receipts
Planned order release
TUGAS MATERIAL REQUIRE

M
Period Item : B.1
2 3 4 5 6 Lot size : 50
0 Gross requirements
Scheduled receipts
50 50 50 0 0 Projected on hand
-50 Net requirements
-50 Planned order receipts
-50 Planned order release

Period M
2 3 4 5 6 Item : B.1
0 Lot size : 50
Gross requirements
500 500 500 500 500 Scheduled receipts
Projected on hand
Net requirements
Planned order receipts
Planned order release
TUGAS MATERIAL REQUIREMENT PLANNING

MRP Matrics For B.1 & B.2


LLC : 2 Period
LT : 3 PD 0 1 2 3 4 5 6
Gross requirements 200
Scheduled receipts
Projected on hand 10 10 10 10 10 10 10
Net requirements 190
Planned order receipts 190
Planned order release 190

MRP Matrics For B.1 & B.2


LLC : 2 Period
LT : 3 PD 0 1 2 3 4 5 6
Gross requirements 180
Scheduled receipts 50
Projected on hand 25 25 25 25 75 25 25 25
Net requirements 1720
Planned order receipts 1750
Planned order release 1750
Item : B.2 LLC : 2 Period
Lot size : 1000 LT : 2 PD 0 1 2
Gross requirements
Scheduled receipts
Projected on hand 1000 1000 1000 1000
Net requirements
Planned order receipts
Planned order release 3000
Period
3 4 5 6
0

4000 4000 4000 4000


-1000
3000