Professional Documents
Culture Documents
435.8R 85
435.8R 85
8R-85
(Reapproved 1991) (Reapproved 1997)
D. R. Buettner* S. K. Ghosh*
Chairman Chairman, Subcommittee on Field
Measurements
1
2 ACI Committee 435
Contents:
Part I
--IL-
Slab Systems and Large Deflections 3
Part II
Part I
INVESTIGATION A
Summary
Structure Mark II had 9-ft spans over two bays in one direc-
tion and three bays in the other. Cantilevers 3 ft long extended
in the two-span direction. The slab was of expanded shale con-
crete and was intended to be 4-in. thick, but because of distor-
tion of the formwork it was much thicker in some places. The
concrete, supplied by an outside contractor, contained in error
some dense basalt in addition to the expanded shale aggregate.
These two factors combined to make the slab much stiffer than was
intended and useless for studies of deformation. No attempt,
therefore, was made to examine its deflection under imposed load-
ing, and it was tested directly to destruction.
References
INVESTIGATION B
Summary
Reference
INVESTIGATION C
Summary
Reference
INVESTIGATION D
Summary
one of the radial beams. The measurements showed that the con-
struction loading increased very rapidly after the props were
removed from under the test floor and reached a peak of 121 psf
when it was supporting three floors above together with the
associated formwork.
References
INVESTIGATION E
Summary
was carried out soon after; Later on, levels were taken at
increasing intervals. In test series 1, span 2O ft 2 in., the
measurements continued over about three months, while the meas-
urements in test series 2, span 22 ft 4 in., covered a period of
about two years. In order to check the concrete quality the
compressive strength was measured on 6 in. standard cubes, and
by rebound hammer on the floors. Shrinkage and creep deforma-
tions were measured on special prisms. All the test specimens
were stored at the building site to have the same climatic
conditions as the slabs.
Reference
INVESTIGATION F
Summary
when the slab above was stripped and repropped. When all
the props were removed, the center of panel deflection was
O.181 in., more than twice the initial deflection, only 75
days after the slab had been poured.
iii. The bricks which were to form the brickwork partitions were
left in piles on the slab for two weeks to act as preload.
By the time the bricklaying had commenced, the mid-point
deflection was 0.2O1 in.
iv. After one year, the deflection of the center of the panel
due to dead load was 0.311 in. - a factor of four increase
on the initial deflection and equal to span/99O.
V. Fourteen months later when live load was applied (25 psf to
the southern half of the test panel, and adjacent panels to
the south side of the test panel), the mid-point deflection
was O.339 in. After another 12 months with some additional
live load (approximately 5 psf), the mid-panel deflection
was O.461 in. The loading was due to library books, and at
this stage the shelves were about 6O% full. Thus, it was
unlikely that the permanent live load would exceed 6O psf.
vi. A method of deflection prediction proposed by Taylor
(Refs. D.l and D.3) was used to estimate deflections.
Figure 7c shows the comparison of measured and predicted
deflections for the slab after 12 months under dead load.
The approximate method of long-term deflection prediction
gave excellent agreement with the experimental results.
Reference
INVESTIGATION G
Summary
STRUCTURE
Center-to-center span, !i = 22 ft
Clear span, IIn = O.9%
Slab thickness, t = 1 l/4 in., standard deviation =
l/4 and l/3 in.
Reinforcement, At columns, As, = 5.O sq in./strip
Elsewhere, A, = 1.8 sq In. strip
CONCRETE
LOADS
References
MISCELLANEOUS ITEM
Summary
Reference
Engineering News Record, Vol. 187, No. 25, Dec. 16, 1971, p. 19.
22 ACI Committee 435
Part II
REFERENCES
8eresford8 2.2 (n = 4)
1.5A AObserved
m=
= number of levels of shoring used
n = time in days for removal of lowest levels of shores after
concreting top floor
Slab Systems and Large Deflections 31
Load Ratio 1.00 at 5 days 11O 1.OO at 5 days 11O Total (after 28 days) 185
1.34 at 7 days 147 1.OO at 7 days 11O
1.45 at 12 days 160 1.5O at 12 days+ 765
1.78 at 14 days 196 1.83 at 14 days 201
2.03 at 19 days 223' 1.OO at 19 days 110
2.36 at 21 days 26O
1.OO at 26 days 11O
c2 -_---
fN
I I
c22 C27;
c29 23.24.25
1
2 C24
F
= -
%
I
=g C2!
0 -Location of plug
m\
c2z (a)
2 0.30-
5
5 0.40-
Y
h 0.50.
0
0.60.
0.30 -
0.40-
0.50-
0.60-
0.70-
STRUCTURE I FLAT PLATE w
0.80’
--_-
0.60
(a)
0 - Location of plug
0 100 200 300 400 500 600 700 600 900 1000 1100 1200 1300
I I
2.7 ,_ 5 -.-.
4 _-_--- 3 - - - -
6 .___...... I -x-x
-.-.v _, -
---__ --- _
O?O-
oeo-
090-
I oo-
STRUCTURE II- FLAT SLAB (b)
I IO-
POINT NO 2.7
0.16-
0.24 -
0.32 -
0.40-
0.46-
0.56-
0 6 4 -
0 72-
0 80-
0 m-
S T R U C T U R E II - FLAT SLAB
0.96-
24’-9” Typ
Slab on ground
G
Shale
23’- IO”
b)
I
Slab Systems and Large Deflections 37
TIME FROM CASTING (DAYS)
50 100 150 2DO 250 300 350, 400 450 500 550 600
,.“~1~11’1~1’111.~‘1ll”~.““‘1’.~~”~’~”~’l~”~”””’
Graph Pomt
type “0.
- . - . 5
II Time from
----_ ,7 ConstructIon
Mark casting (days)
090 1
TIME FROM CASTING (DAYS)
0 50 I00 150 200 250 300 350, 400 450
500 550 600
rr,.II,11.1,‘,1’,““““““.“““““r,
LEGEND I year
Graph Point
type no.
_. -. 8
A
B Refer to
C Fig. 3(C)
D
0.70
(d)
0.60i
POINT NO. II
20th Floor
B 20 (measured)
0.04
n
0.08 t
7 0.12
g 0.16
F 0.20
8
J 0.24
0.32
0.36
STRUCTURE V
0.40 :_
8 I
I -
SECTION I
E 0 30 60 90 120
av AGE (DAYS)
I.-. -. e’-
3
are denoted xy=.
41.5’-6’ x refer. to the .p=n.
y refera to the floor.
SECTION I -I z refers to the point.
I
x
4 0: 0 30 I 60 I 90 I I20 1
ti AGE (DAYS)
z
Service
0 n n ” d (a)
TIME (DAYS)
0 50 loo 150 200 250 300 350 400 456
1 I I I I I I
Adjacent Panel Stripped
- Floor Above Stripped
Props Removed
Test Conducted
%
z o.zo-
Tiles Laid And Ceiling Added
x
2 0.24”
x
0.28 -
I
N
0.19 027
(0.18) +(0:26) +,o”:& 0.16
‘co. 16)
0.29
-t
(0.31)
\
1
I I I II II I I
90 70 50 30 IO 5
PROBABILITY (PERCENT)
4 6 8 IO 12 14
Computed values of w’.‘& ~10~
Fig. 9--Measured and computed modulii of elasticity of concrete13.
0 Nor. Wt. y
a Sand-Lt. ht.
0 All-Lt. Wt.
- Eq. (2)
I I I 1 I I
100 150 200 250 300 350
Age of concrete in days
IO3 -
t
w
IO2 -
IO’ -
1Y A- I 1 I I 1
0.1 0 . 5 1.0 5 IO 50 N/mm2
f ct (I N/mm2=145psi)
2.5 r
lower bound
Ot , I I II I I I
Instantaneous recovery
On. Residual .
200 - /-- loading deformation
‘0 20 I * 40 I 60 I 80 I 100 I 120 I 140 I 160 I 180 IW 200 I
-.--__
0 0 @ -*~--TF--@j--s[
Column
\
2'x40'
strip 8etwem - f Canter
Fnrr
strip
I