Professional Documents
Culture Documents
Project Schedule Management
Project Schedule Management
Project Schedule Management
PROJECT SCHEDULE
MANAGEMENT INCLUDES THE
PROCESSES REQUIRED TO MANAGE
2
Dependency Relationships in the Precedence Diagramming Method (PDM)
4
LEADS AND LAGS
A LEAD
ALLOWS AN ACCELERATION OF THE SUCCESSOR ACTIVITY.
A LAG
DIRECTS A DELAY IN THE SUCCESSOR ACTIVITY 5
• DEPENDENCY DETERMINATION
.
4 TYPES OF DEPENDENCIES ARE USED TO DEFINE THE
SEQUENCE AMONG THE ACTIVITIES
Start
H F FS +15
End
G
SS +10
I J
K
FF
Start 0 -------------
A 2 Start
B 12 A
C 5 B&D
D 6 Start
E 7 D
F 3 E
Finish 0 C&F
NETWORK DIAGRAMMING ANALYSIS
A network diagrams is a schematic display of project’s activities
and dependencies
A B C
Finish
Start
D E F
NETWORK DIAGRAM ANALYSIS
The Forward Pass …
0 A
0
Start 6 Days
0 6
D
CRITICAL PATH METHOD (PDM), FORWARD PATH
Early Start = Highest of predecessor’s
Early Finish Times
0 2 2 14 14 19
A B C
2 Days 12 Days 5 Days 19 19
0 0
Start Finish
0 6 6 13 13 16
D E F
6 Days 7 Days 3 Days
NETWORK DIAGRAM ANALYSIS
The Backward Path …
5 Days
14 19
C 19 19
14 19 Finish
3 Days 19 19
13 16
F
Late Start 16 19 Late Finish
Box Box
CRITICAL PATH METHOD (PDM), BACKWARD PATH
Late Finish =
Lowest of successor’s Late Start Times
0 2 2 14 14 19
A B C
0 2 2 14 14 19
0 0 19 19
Start Finish
6 Days 7 Days 3 Days 19 19
0 0
0 6 6 13 13 16
D E F
3 9 9 16 16 19
Network calculations
HOW MUCH THE FREE FLOAT FOR ACTIVITY D?
0 8 8 20 20 25
A B C
0 8 8 20 20 25
0 0 25 25
(0) (0) (0) Finish
Start
6 Days 7 Days 3 Days 25 25
0 0
0 6 8 15 15 18 (0)
Float = (0)
D E F
9 15 15 22 22 25
15
10 1 4
C D E
6 7 9 8 4 6 3
A B F G H J K
11
C D E
6 7 9 8 4 6 3
A B F G H J K
11
18
YOU ARE THE PROJECT MANAGER FOR PROJECT WITH
THE FOLLOWING NETWORK DIAGRAM
Task Preceding Estimate in
DRAW THE NETWORK DIAGRAM ? Activity months
Start 0
CALCULATE ALL OF THE PATHS IN THIS NETWORK 1 Start 2
DIAGRAM? 2 Start 3
3 1 7
WHAT IS THE DURATION OF THE CRITICAL PATH OF 4 1,2 9
THIS NETWORK DIAGRAM? 5 2 3
WHAT IS THE FLOAT OF TASK 3? 6 3 2
WHAT IS THE FLOAT OF TASK 5? 7 4 8
WHAT IS THE FLOAT OF TASK 1? End 5,6,7 0
WHAT IS THE SLACK OF TASK 7?
7 2
2 9 9 11
2
3 6
11 18 18 20
0 2
1
1 3 9 8
3 12 12 20
start 3 4 7 Finish
3 12 12 20
0 3
2 3
0 3
3 6
5
17 20
1) 1 - 3 - 6 : 2 + 7 + 2 = 11 MONTHS
.
2) 1 - 4 - 7 : 2 + 9 + 8 = 19MONTHS
3) 2 - 4 - 7 : 3 + 9 + 8 = 20MONTHS
4) 2 - 5 : 3 + 3 = 6 MONTHS
Activity Normal duration Crash Normal cost $ Crash cost $ Crash cost / day
duration
A) P
Activity Normal time Crash Time Normal Cost Crash Cost
B) S P 7 5 7000 9000
Q 4 3 7000 7500
C) T
R 5 2 8000 14000
D) Q
S 4 2 4000 4800
T 8 7 4000 5500
ESTIMATE ACTIVITY DURATIONS
EXPERT JUDGMENT
EXPERT JUDGMENT CAN BE USED TO DETERMINE WHETHER TO COMBINE METHODS OF ESTIMATING AND HOW TO RECONCILE DIFFERENCES
BETWEEN THEM.
ANALOGOUS ESTIMATING
ANALOGOUS ESTIMATING IS A TECHNIQUE FOR ESTIMATING THE DURATION OR COST OF AN ACTIVITY OR A PROJECT USING HISTORICAL
DATA FROM A SIMILAR ACTIVITY OR PROJECT.
ANALOGOUS DURATION ESTIMATING IS FREQUENTLY USED TO ESTIMATE PROJECT DURATION WHEN THERE IS A LIMITED AMOUNT OF
DETAILED INFORMATION ABOUT THE PROJECT.
ESTIMATING IS GENERALLY LESS COSTLY AND TIME CONSUMING THAN OTHER TECHNIQUES, BUT IT IS ALSO GENERALLY LESS ACCURATE.
THREE-POINT ESTIMATES
PERT USES THREE ESTIMATES TO DEFINE AN APPROXIMATE RANGE FOR AN ACTIVITY’S DURATION
MOST LIKELY: THE DURATION OF THE ACTIVITY, GIVEN THE RESOURCES LIKELY TO BE ASSIGNED, THEIR PRODUCTIVITY, REALISTIC
EXPECTATIONS OF AVAILABILITY FOR THE ACTIVITY, DEPENDENCIES ON OTHER PARTICIPANTS, AND INTERRUPTIONS.
OPTIMISTIC: THE ACTIVITY DURATION IS BASED ON ANALYSIS OF THE BEST-CASE SCENARIO FOR THE ACTIVITY.
PESSIMISTIC: THE ACTIVITY DURATION IS BASED ON ANALYSIS OF THE WORST-CASE SCENARIO FOR THE ACTIVITY
TE = (TO + TM*4 +T P) / 6.
CALCULATION OF PERT PROBABILITIES
σ =P– O
V = σ2
6
O = OPTIMISTIC
P = PESSIMISTIC
28
4 5
A B
7 5
start D Finish
C
A 2 4 6 4 0.67 0.44
B 3 5 7 5 0.67 0.44
C 4 7 10 7 1 1
D 4 5 6 5 0.33 0.11
-1s
• +1•s
-2•s +2•s
-3s
• Te, Project• +3•s
Duration•
68.26%•
95.46%•
99.73%•
LCL• UCL•
PERT Calculations
-1 s +1 s
Project
Start
Date
-2 s +2s
50%
84.13%
97.73%
99.86%
Normal Distribution:
50% chance - using expected time durations (Te, )
84% chance - (Te, ) + 1 s , etc
FACTORS FOR CONSIDERATION WHEN ESTIMATING DURATION
INCLUDE:
NUMBER OF RESOURCES.
ADVANCES IN TECHNOLOGY
MOTIVATION OF STAFF.
TRENDS AND EMERGING PRACTICES
ITERATIVE SCHEDULING WITH A BACKLOG. THIS SCHEDULING METHOD IS APPROPRIATE FOR MANY PROJECTS
THE BENEFIT OF THIS APPROACH IS THAT IT WELCOMES CHANGES THROUGHOUT THE DEVELOPMENT LIFE
CYCLE.
RESOURCE AVAILABILITY
PROJECT DIMENSIONS
TECHNOLOGY SUPPORT
CONSIDERATIONS FOR AGILE/ADAPTIVE ENVIRONMENTS
SOME LARGE ORGANIZATIONS MAY NEED TO COMBINE PRACTICES FROM SEVERAL CORE
METHODS BECAUSE OF DIFFERENT PROJECT TYPES.
36
Project Management Process Groups
Knowledge Areas
Monitoring and Controlling Closing Process
Initiating Process Group Planning Process Group Executing Process Group
Process Group Group
4- Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project 4.5 Monitor and Control Project 4.7 Close Project
Work Work or phase
4.4 Manage Project Knowledge 4.6 Perform Integrated Change
Control
5- Project Scope Management 5.1 Plan Scope Management 5.5 Validate Scope
5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
6- Project Schedule Management 6.1 Plan Schedule Management 6.6 Control Schedule
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
7- Project Cost Management 7.1 Plan Cost Management 7.4 Control Costs
7.2 Estimate Costs
7.3 Determine Budget
8- Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9- Project Resource Management 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
10- Project Communications 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications
Management
11- Project Risk Management 11.1 Plan Risk Management 11.6 Implement Risk Responses 11.7 Monitor Risks
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12- Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 37
13- Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder
Engagement Engagement
PLAN SCHEDULE MANAGEMENT
Inputs Tools & Techniques Outputs
1. Project charter 1. Expert Judgment 1. Schedule
Management Plan
2. Project manage. Plan 2. Data Analysis
•Scope manage. Plan .Alternatives analysis
•Development approach
The schedule management plan includes :
1. Meetings
Project schedule model development.
3. Enterprise environmental Release and iteration length.
factors (EEF) Level of accuracy.
Units of measure.
4. Organizational process Organizational procedures links.
assets (OPA) Project schedule model maintenance.
Control thresholds.
Rules of performance measurement.
Reporting formats
Accuracy Estimates
•Rough order of magnitude : Made during initiation process
ROM is -25% to 75%
39
DEFINE ACTIVITIES
4. OPA
ESTIMATE ACTIVITY DURATIONS
Inputs Tools & Techniques Outputs
1.Project manage. Plan 1. Expert Judgment 1. Duration estimates
•Schedule manage. plan 2. Analogous estimating
•Scope baseline 3. Parametric estimating 2. Basis of estimates
2. Project documents 4. Three-point estimating
•Activity list 5. Bottom-up estimating 3. Project documents
•Activity attributes 6. Data analysis updates
•Assumption log •Alternative analysis • Activity attributes
•Lessons learned register •Reserve analysis • Assumption log
•Milestone list 7. Decision making • Lessons learned
•Project team assignments 8. Meetings register
•Resource breakdown structure
•Recourse calendars
•Resource requirements
•Risk register
3. EEF
4. OPA
DEVELOP SCHEDULE
Inputs Tools & Techniques Outputs
1. Project manage. Plan 1.Schedule network analysis 1. Schedule baseline
•Schedule manage. plan 2.Critical path method 2. Project schedule
•Scope baseline 3.Resource optimization 3. Schedule data
2. Project documents 4.Data analysis 4. Project calendars
•Activity list •What-if scenarios 5. Change requests
•Activity attributes •Simulation 6. Project manage Plan updates
•Assumption log 5. Leads & lags Schedule manage Plan
•Basis of estimates 6. Schedule compression Cost baseline
•Duration estimates 7. Project management 7. Project documents updates
•Lessons learned register information system • Activity attributes
•Milestone list 8. Agile release planning • Assumption log
•Project schedule network diagram • Duration estimates
•Project team assignments • Lessons learned register
•Recourse calendars • Resource requirements
•Resource requirements • Risk register
•Risk register
3. Agreements
4. EEF
5. OPA
GANTT CHART
Activity
Task A
Task B
Task C
Task D
June July Aug sep Oct.
Time
45
MILESTONE CHART
46
RESOURCE LEVELING.
RESOURCE SMOOTHING.
AGILE RELEASE PLANNING
AGILE RELEASE PLANNING PROVIDES A HIGH-LEVEL SUMMARY TIMELINE OF THE RELEASE SCHEDULE
(TYPICALLY 3 TO 6 MONTHS) BASED ON THE PRODUCT ROADMAP AND THE PRODUCT VISION FOR THE
PRODUCT’S EVOLUTION.
AGILE RELEASE PLANNING ALSO DETERMINES THE NUMBER OF ITERATIONS OR SPRINTS IN THE RELEASE, AND
ALLOWS THE PRODUCT OWNER AND TEAM TO DECIDE HOW MUCH NEEDS TO BE DEVELOPED AND HOW
LONG IT WILL TAKE TO HAVE A RELEASABLE PRODUCT BASED ON BUSINESS GOALS, DEPENDENCIES, AND
IMPEDIMENTS.
SINCE FEATURES REPRESENT VALUE TO THE CUSTOMER, THE TIMELINE PROVIDES A MORE EASILY UNDERSTOOD
PROJECT SCHEDULE AS IT DEFINES WHICH FEATURE WILL BE AVAILABLE AT THE END OF EACH ITERATION,
WHICH IS EXACTLY THE DEPTH OF INFORMATION THE CUSTOMER IS LOOKING FOR.
PROJECT SCHEDULE
51
CONTROL SCHEDULE
Inputs Tools & Techniques Outputs
1. Project manage. Plan 1.Data analysis 1. Work performance Info.
•Schedule manage. plan •Earned value analysis 2. Schedule forecasts
•Schedule baseline •Iteration burndown chart 3. Change requests
•Scope baseline •Performance reviews 4. Project manage. Plan updates
•Performance measurement •Trend analysis •Schedule manage. Plan
baseline •Variance analysis •Schedule baseline
2. Project documents •What-if scenario analysis •Cost baseline
•Lessons learned register 2. Critical path method •Performance measurement baseline
•Project calendars 3. Project management information 5. Project documents updates
•Project schedule system • Assumption log
•Recourse calendars 4. Resource optimization • Basis of estimates
•Schedule data 5.Leads & lags • Lessons learned register
3. Work performance data 6. Schedule compression • Project schedule
4. OPA • Recourse calendars
• Risk register
• Schedule data
ITERATION BURNDOWN CHART
54
1- WHICH OF THE FOLLOWING IS THE BEST TO DO TO TRY TO
COMPLETE YOUR PROJECT TWO MONTHS EARLIER?
A ) TELL SENIOR MANAGEMENT THAT THE PROJECT’S CRITICAL PATH DOES NOT ALLOW THE
PROJECT TO BE FINISHED EARLIER.
C ) MEET WITH THE TEAM AND LOOK FOR OPTIONS FOR CRASHING OR FAST TRACKING THE
CRITICAL PATH.
D ) WORK HARD AND SEE WHAT THE PROJECT STATUS IS NEXT MONTH.
55
2- A PROBLEM OCCURS ON AN ACTIVITY WITH FREE FLOAT AND THE
PROJECT MANAGER HAS EXTENDED ITS DURATION. WHAT IS MOST
LIKELY TO BE AFFECTED?
A) PROJECT DURATION
B) RESOURCE SCHEDULES
56
3- AN ACTIVITY HAS AN EARLY START (ES) OF DAY 3, A LATE START (LS)
OF DAY 13, AN EARLY FINISH (EF) OF DAY 9 AND A LATE FINISH (LF) OF
DAY 19. WHAT IS THE ACTIVITY FLOAT?
A) 10
B) 6
C) 3
D) 19
57
4-WHICH OF THE FOLLOWING PROCESSES INCLUDE ASKING TEAM
MEMBERS ABOUT THE TIME ESTIMATES FOR THEIR ACTIVITIES
AND REACHING AGREEMENT ON THE calendar DATE FOR EACH
ACTIVITY?
A ) SEQUENCE ACTIVITY.
B ) DEVELOP SCHEDULE.
C ) DEFINE SCOPE.
end G
6.WHAT TERM IS DEFINED AS THE PRACTICE OF PLANNING ACTIVITIES BASED ON
HOW SOON THE TASKS ARE SCHEDULED TO START, SUCH THAT ACTIVITIES
THAT ARE CLOSE TO THEIR START DATE ARE PLANNED AT A MORE DETAILED
LEVEL THAN THOSE FARTHER IN THE FUTURE? THIS TERM ALSO IMPLIES THAT
AS ACTIVITIES NEAR THEIR START DATE MORE DETAILED PLANS WILL BE
REQUIRED.
A. PROGRESSIVE ELABORATION
60
7- TOTAL FLOAT IS THE AMOUNT OF TIME AN ACTIVITY CAN
BE DELAYED WITHOUT DELAYING THE :
A ) PROJECT.
61
8- YOUR BOSS TELLS YOU THAT ONE OF YOUR RESOURCES IS NEEDED ON ANOTHER
PROJECT. ALL THE ACTIVITIES IN THE CHART ARE OCCURRING AT THE SAME TIME.
ASSUMING THAT ALL THE RESOURCES WORKING ON WHICH ACTIVITY WOULD YOU
PICK TO MOVE TO THE OTHER PROJECT?
activity Float
A ) ACTIVITY D (month)
Start
B 2
B ) ACTIVITY C
C 1
D 0
C ) ACTIVITY H F 1
G 0
H 4
D ) ACTIVITY B I 0
62
E 3
End
9- LAG MEANS:
A ) THE AMOUNT OF TIME AN ACTIVITY CAN BE DELAYED WITHOUT DELAYING THE PROJECT FINISH
DATE.
B ) THE AMOUNT OF TIME AN ACTIVITY CAN BE DELAYED WITHOUT DELAYING THE EARLY START
DATE OF ITS SUCCESSOR.
C ) WAITING TIME
A ) LOGICAL RELATIONSHIPS.
B ) CRITICAL PATHS.
C ) RESOURCE TRADE-OFFS.
D ) PROGRESS OR STATUS.
64