Professional Documents
Culture Documents
Report For Sourcing RE Power by GAIL Vijaipur For Green Hydrogen
Report For Sourcing RE Power by GAIL Vijaipur For Green Hydrogen
This report has been prepared by PTC India Limited in accordance with the requirement of LOA
No. GAIL/VL/C23251/5300039993/ELECT/NY dated 20.11.2023 of PTC India Limited. The
information contained herein is for the sole benefit of GAIL and may not be relied upon by any
other person. PTC has taken due regard of data available; and has performed the services in
accordance with standards of care and diligence currently practiced by consulting firms
performing services of a similar nature. Notwithstanding the foregoing, neither PTC nor any
person acting on its behalf makes any representation or warranty whatsoever, express or
implied, (i) regarding the truth, accuracy, or adequacy of any information contained or referred
to herein developed by or obtained from third parties. Accordingly, PTC does not assume any
responsibility whatsoever for any damages or other liability (including any consequential
damages) arising from or related to the application, by the client, of the information, results,
findings or analysis contained in this report.
This report has been prepared for the use of the client named in the report for the specific
purpose identified in the report. Any other party should not rely upon this report for any other
purpose. This report is not be used, circulated, quoted or referred to, in whole or in part, for any
other purpose without the prior written consent of PTC.
Table of Contents
Table 3: Tentative landed cost for sourcing of RE power through RE-RTC mode under third
party mode................................................................................................................................................................ 13
Table 4: Tentative landed cost for sourcing of RE power through hybrid project under third
party mode................................................................................................................................................................ 13
Table 6: Tentative landed cost for sourcing of Hybrid RE power under third party mode...... 14
Table 7: Tentative landed cost for sourcing of Bagasse based RE power under third party
mode............................................................................................................................................................................ 14
Table 11: Typical charges & losses payable under Open Access ....................................................... 31
Table 14: Deviation Charges for Sale of Power within the State ........................................................ 53
Table 18: Open Access Charges as per prevailing Tariff Order by MPERC ................................... 65
Table 20: Deviation Charges for Sale of Power within the State ........................................................ 67
Table 21: Tentative landed cost for sourcing of RE power through RE-RTC mode under third
party mode................................................................................................................................................................ 72
Table 22: Tentative landed cost for sourcing of RE power through hybrid project under third
party mode................................................................................................................................................................ 73
Table 24: Tentative landed cost for sourcing of Hybrid RE power under third party mode ... 75
Table 25: Tentative landed cost for sourcing of Bagasse RE power under third party mode 75
Table 26: Tentative landed cost for sourcing of RE power through PX ........................................... 76
Table 27: Tentative landed cost for sourcing of RE power through hybrid project under third
party mode................................................................................................................................................................ 83
List of Figures
Figure 1: Probable options available for procurement of Renewable Energy by GAIL Vijaipur
....................................................................................................................................................................................... 12
Figure 7: All India Installed Capacity Resource wise, Source CEA ................................................... 28
Figure 14: Growth in volume and trend of average prices in bilateral & Exchange segment 34
Figure 18: Sector wise installed capacity, Source National Power Portal ...................................... 39
°C : Degree Centigrade
ABT : Availability Based Tariff
AC : Alternating Current
AM : Anti Meridiem
AMC : Annual Maintenance Contract
APPC : Average Annual Power Purchase Cost
APTEL : Appellate Tribunal for Electricity
ASTM : American Society for Testing and Materials
BIS : Bureau of Indian Standard
CAPEX : Capital expenditures
CD : Contract Demand
CEA : Central Electricity Authority
CERC : Central Electricity Regulatory Commission
CNG : Compressed Natural Gas
CSP : Concentrated Solar Power
CU : Cubic Meter
CUF : Capacity Utilization Factor
DC : Direct Current
DG : Diesel Generator
DIFG : Double Fed Induction Generator
DIN : German Institute for Standardization
DISCOM : Distribution Company
DNI : Direct Normal Irradiation
EOI : Expression of Interest
ESCOM : Electricity Supply Companies
GSS : Grid Sub Station
GW : Giga Watt
Hr / hr : Hours
IEA : International Energy Agency
IEC : International Electro technical Commission
IRR : Internal rate of return
Kg : Kilogram
KV : Kilo Volt
KVA : Kilo Volt Ampere
KW : Kilo Watt
kWh : Kilo Watt Hour
KWp : Kilo Watt Hour Peak
m/s : Meter per Second
MD : Maximum Demand
MEDA : Maharashtra Energy Development Agency
MERC : Maharashtra Electricity Regulatory Commission
MNRE : Ministry of New & Renewable Energy
MPERC : Madhya Pradesh Electricity Regulatory Commission
MPPGCL : Madhya Pradesh Power Generation Company Limited
MPPMCL : Madhya Pradesh Power Management Company Limited
MPPTCL : Madhya Pradesh Power Transmission Company Limited
MPUVNL : Madhya Pradesh Urja Vikas Nigam Limited
MSEB : Maharashtra State Electricity Board
MSEDCL : Maharashtra State Electricity Distribution Company Limited
MSETCL : Maharashtra State Electricity Transmission Company Limited
MSPGCL : Maharashtra State Power Generation Company Limited
MSL : Mean Sea Level
MT : Metric Ton
MU : Million Units
MVA : Mega Volt Ampere
MW : Mega Watt
MWHr : Mega Watt Hour
MWp : Mega Watt Hour Peak
NASA : National Aeronautics and Space Administration
NISE : National Institute of Solar Energy
NREL : National Renewable Energy Laboratory
O&M : Operation and Maintenance
OA : Open Access
OAU : Open Access Unit
OPEX : Operational Expenditure
PCU : Power Conditioning Unit
PF : Power Factor
PLF : Plant Load Factor
PM : Post Meridiem
PPA : Power Purchase Agreement
PV : Photovoltaic
RE : Renewable Energy / Green Energy
RECs : Renewable Energy Certificates
ROE : Return on Equity
RPO : Renewable Purchase Obligation
S/s : Sub Station
SECI : Solar Energy Corporation of India
ToD : Time of Day
UI : Unscheduled Interchange
UPERC : Uttar Pradesh Electricity Regulatory Commission
UPNEDA : Uttar Pradesh New & Renewable Energy Development Agency
UPPCL : Uttar Pradesh Power Corporation Limited
UPRVUNL : Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited
UPSEB : Uttar Pradesh State Electricity Board
UPTCL : Uttar Pradesh Power Transmission Corporation Limited
V : Volt
WBA : Wheeling & Banking Agreement
WTG/WEG : Wind Turbine Generator
Glossary
RE Project: RE Project means Solar PV Project or Wind Power Project or Wind-Solar Hybrid
Power Project;
IPPs: Independent power producer: A corporation, person, agency, authority, or other legal
entity or instrumentality that owns or operates facilities for the generation of electricity for
use primarily by the public, and that is not an electric utility;
Captive Plant: “Captive generating plant” means a power plant set up by any person to
generate electricity primarily for his own use and includes a power plant set up by any co-
operative society or association of persons for generating electricity primarily for use of
members of such cooperative society or association;
Group Captive: Group Captive mechanism is the one in which a person or group or persons
set up a power plant for purchase of power from that plant for their own consumption. Such
captive user(s) shall hold at least 26% of the ownership in the generating plant and consume
not less than 51% of the electricity generated, on an annual basis, in proportion to their
shares in ownership of the power plant within a variation not exceeding 10%;
Energy Banking: Banked Energy means the surplus Renewable Energy generated and
credited with the Distribution Licensee after set off with consumption in the same Time of
Day slot, if applicable; Banked Energy means the electric energy held under Banking an
agreement arrangements for later delivery to a Purchaser.
a) Any system for the conveyance of electricity by means of main transmission line from the
territory of one State to another State;
b) The conveyance of electricity across the territory of an intervening State as well as
conveyance within the State which is incidental to such inter-State transmission of
electricity;
c) The transmission of electricity within the territory of a State on a system built, owned,
operated, maintained or controlled by a Central Transmission Utility.
InSTS: Intra-State transmission system” means any system for transmission of electricity
other than an inter-State transmission system;
Open Access: means the non-discriminatory provision for the use of transmission lines or
distribution system or associated facilities with such lines or system by any licensee or
consumer or a person engaged in generation in accordance with the regulations specified by
the Appropriate Commission;
Wheeling: means the operation whereby the distribution system and associated facilities of
a transmission licensee or distribution licensee, as the case may be, are used by another
person for the conveyance of electricity on payment of charges to be determined under section
62;
Executive Summary
1.1 Background
Hon’ble Prime Minister launched the National Hydrogen Mission on India’s 75th
Independence Day (i.e. 15th August, 2021). The Mission aims to aid the government in
meeting its climate targets and making India a green hydrogen hub. This will help in
meeting the target of production of 5 million tonnes of Green hydrogen by 2030 and the
related development of renewable energy capacity.
Various sectors like Refineries, Petrochemical, Steel, Fertilizers uses large quantities of
hydrogen for their operations which releases huge quantities of carbon in the air.
Accordingly, these sectors are identified as one of the major sources of carbon emission.
To curb carbon release from this segment, they will need to set up large-scale
electrolysers to produce green hydrogen from water and thereby decarbonize hydrogen
production. Large-scale electrolyser installations can be powered directly by renewable
electricity, helping to enable the production of the green hydrogen.
1.2 Objective
Aligned with the objectives of the National Hydrogen Mission, GAIL, Vijaipur, is
currently in the process of establishing a Green Hydrogen plant within its premises,
boasting a capacity of 4.3 TPD. The anticipated commissioning date for this plant is
expected to be June 2024.
Aligned with this objective, GAIL has appointed PTC to assist them in sourcing of
renewable power for the operation of the said GHGP. Under this assignment, PTC shall
be assisting GAIL in devising its strategy for sourcing of renewable power through
exploring various options available in the market, developing a portfolio mix of long term
/ short term etc. Besides, PTC shall also be suggesting GAIL implementation strategies
through preparation of RFP and tender documents for operationalization of the contract,
including the management of operational and commercial activities.
It may be noted that, GAIL, Vijaipur is in the process of enhancing its contract
demand which will be increased to 18500 kVA shortly.
As per the data provided by GAIL, the tentative load profile of the electrolyser shall be
as follows:
May-25
Mar-25
Jun-25
Aug-24
Dec-24
Jan-25
Nov-24
Sep-24
Feb-25
Apr-25
Oct-24
Jul-24
(MWh)
1,980
1,980
1,980
1,980
1,980
1,980
1,980
7,920
7,920
7920
7920
7920
10.50
10.50
10.50
10.50
10.50
(MW)
2.66
2.66
2.66
2.66
2.66
2.66
2.66
Initially, the load requirement of Green Hydrogen Plant will be around 2.50 to 3.00 MW
RTC which will increase and stabilize to the tune of 10.50 MW RTC after 7-8 months.
In order to fulfill the energy requirements of Green Hydrogen plant, PTC explored and
analyzed various modes of RE power sourcing alternatives like long term through third
party / group captive, short term arrangement through third party bilateral
arrangements, power exchanges, procurement from incumbent Discom through Green
Tariffs etc. Accordingly, the probable options are evaluated in the subsequent section
under this report.
Under this report, it is deliberated that GAIL has various options and it can make the
portfolio using any of the available alternatives to source renewable energy for
production of the green hydrogen. In this regard, PTC has evaluated the following
potential alternatives:
RE Project
Hence, the analysis was carried out for sourcing of RE-RTC power through ISTS
projects. The tentative landed cost for sourcing of RE-RTC shall be as follows:
Table 3: Tentative landed cost for sourcing of RE power through RE-RTC mode under third party
mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 18 18
Estimated Energy at GAIL’s bus on annual basis MUs 110 113
Tariff in ₹/kWh ₹/kWh 4.50 4.50
Impact of OA charges in ₹/kWh ₹/kWh 0.75 0.62
Landed Cost at GAIL’s bus in ₹/kWh ₹/kWh 5.25 5.12
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kWh 7.10 7.10
Savings in ₹/kWh ₹/kWh 1.85 1.98
Approx. Annual Savings ₹ Crs 20.41 22.40
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
Besides this, as per Ministry of New and Renewable Energy vide its OM dated 18 August
2023, the “Green Hydrogen” shall mean Hydrogen produced using renewable energy,
including, but not limited to, production through electrolysis or conversion of biomass.
Renewable energy also includes such electricity generated from renewable sources which
is stored in an energy storage system or banked with the grid in accordance with
applicable regulations.
Hence, the analysis was carried out for sourcing of hybrid power through ISTS or InSTS
projects under third party route. The financial evaluation of the same is as follows::
Table 4: Tentative landed cost for sourcing of RE power through hybrid project under third party
mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 18 18
Estimated Energy at GAIL’s bus on annual basis @ 50%
MUs ~74 ~75
CUF
Tariff in ₹/kWh ₹/kW 4.20 4.20
h
Impact of OA charges in ₹/kWh ₹/kW 0.88 0.77
h
Landed Cost at GAIL’s bus in ₹/kWh ₹/kW 5.08 4.97
h
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kW 7.10 7.10
h
Savings in ₹/kWh ₹/kW 2.03 2.13
h
Approx. Annual Savings ₹ Crs 14.92 16.05
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
Procurement of Wind Solar Hybrid power through 100% own captive RE Project
Establishing a RE Captive Power Plant is generally beneficial for a state where Cross
subsidy and Additional Surcharge are notably high and applicable under third party
mode / power exchanges. By doing so, the organization can reap numerous benefits
like exemption from payment of cross subsidy and additional surcharge. It may be noted
that the present rate of Cross Subsidy and Additional Surcharge in the state of Madhya
Pradesh is Rs. ₹1.36/kWh and ₹1.28/kWh respectively which are comparatively higher
than the other states.
However, these charges i.e. Cross Subsidy and Additional Surcharge are already
waived-off by MPERC for consumers procuring green energy for the production of green
hydrogen and green ammonia, in line with MPERC Green Energy Open Access
Regulation 2023.
Given that exemptions such as Cross Subsidy and Additional Surcharge have already
been waived by MPERC for green hydrogen, it is not viable for GAIL, Vijaipur, to procure
power through the captive route, as it would entail additional capital expenditure.
A tentative landed costs for sourcing of RE power through Hybrid and bagasse based
source are as follows:
Table 5: Tentative landed cost for sourcing of Hybrid RE power under third party mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 5 5
Estimated Energy at GAIL’s bus on annual basis @ 50%
MUs ~20 ~21
CUF
Tariff in ₹/kWh ₹/kW 4.40 4.40
h
Impact of OA charges in ₹/kWh ₹/kW 0.92 0.69
h
Landed Cost at GAIL’s bus in ₹/kWh ₹/kW 5.32 5.09
h
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kW 7.10 7.10
h
Savings in ₹/kWh ₹/kW 1.78 2.01
h
Approx. Annual Savings ₹ Crs 3.65 4.29
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
Table 6: Tentative landed cost for sourcing of Bagasse based RE power under third party mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 5 5
Estimated Energy at GAIL’s bus on annual basis @
MUs ~41 ~43
100% CUF
Tariff in ₹/kWh ₹/kW 4.55 4.55
h
Impact of OA charges in ₹/kWh ₹/kW 0.70 0.49
h
Landed Cost at GAIL’s bus in ₹/kWh ₹/kW 5.25 5.04
h
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kW 7.10 7.10
h
Savings in ₹/kWh ₹/kW 1.85 2.07
h
Approx. Annual Savings ₹ Crs 7.58 8.81
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
The tentative cost implication for procurement of green power through incumbent
Discom under ‘Green Tariff’ mechanism is as follows:
a. Sourcing of RE-RTC power - The tentative landed cost for sourcing of RE-RTC shall
be as follows:
b. Procurement of Wind Solar Hybrid power - The tentative landed cost for sourcing
of RE-RTC shall be as follows:
2. Sourcing of Renewable Energy under short term - for meeting the power requirement
of up to 20-30% requirement
As studied earlier, GAIL may leverage the opportunity of the short-term market for
catering to balance or contingent power requirement of its green hydrogen plant while
realizing the benefit of the lower cost power. GAIL will always have the option to source
renewable power through sources like wind/solar/hybrid under short-term open
access.
Besides this, GAIL may also explore sourcing of renewable energy from renewable
sources like bagasse and hydro which are the valuable source of renewable energy in
India, particularly for procurers in the agricultural and industrial sectors. Renewable
energy sources, including bagasse-based power and hydropower, offer significant
benefits for procurers in India, contributing to sustainability, energy security, and cost-
effectiveness.
GAIL may enter into an agreement under short-term arrangement with RE
developers for meeting the deficits/shortfall of the energy, if any. The tentative
savings under these short-term arrangements ranges between ₹3.65 Crores/
annum to ₹8.81 Crores/ annum. However, the actual savings will be based upon
the prevailing market conditions at the time of procurement of power.
General Scope
PTC India Limited was engaged by GAIL India Limited vide LOA No.
GAIL/VL/C23251/5300039993/ELECT/NY dated 20.11.2023 undertaking Phase 1 -
Study on sourcing of RE Power. The brief scope of work is given below:
Preparation of DFR:
PTC shall carry out analysis of estimated load requirement, future load growth
considering two nos. of upcoming solar power plants (10MW & 8 MW each) at
Vijaipur for assessing the modalities and the options evaluation for sourcing
RTC renewable energy under Open Access (OA).
PTC shall also carry out assessment of existing metering facility and
requirement of new metering facility (in view of second 132 kV line for GAIL
Vijaipur Complex, expected to be commissioned by December, 2024 essential
for sourcing of Round the clock (RTC) green power and settlement of solar
power in case of export to DISCOM.
PTC shall study and review the Regulatory landscape and Policy framework
pertaining to procurement of renewable power under OA specifically for Green
Hydrogen Generation and suggest GAIL accordingly.
PTC shall study and review the Policies & Regulations to understand the
modalities of sourcing power from renewable energy sources like Standalone
Wind/Solar, Wind Solar Hybrid Project, Small Hydro and their cost implication
and suggest GAIL accordingly.
PTC shall study and review the mapping of Regulations and Policies related to
evacuation of the green power, scheduling & forecasting, must run status RTC,
etc. for such RE Projects and suggest GAIL accordingly.
➢ Techno-commercial viability:
PTC shall carry out analysis covering the cost economics and options evaluation
for meeting the renewable power requirement for GAIL in line with statutory
requirements of SERC/CERC and suggest GAIL Accordingly most economic option.
The analysis shall cover following aspects:
Legal & Regulatory issues w.r.t. The Electricity Act & State electricity
regulatory commission (SERC) regulations.
Investment of funds into equity and loss of captive structure (in case of group
captive mode).
Duties like Electricity Duty (ED), surcharge like Cross Subsidy Surcharge
(CSS), other surcharges, temporary charges / System Marginal Price (SMP) /
Losses / Wheeling charges transmission charges, RPO obligation (solar and
non-solar both) etc.
Any other related issues which is not covered but necessary for the
procurement of RTC renewable power.
Based on the above analysis, power procurement strategy shall be advised by PTC
to GAIL covering the tenure and type of OA contract, quantum of load to be sourced
under OA, and risk mitigation measures for probable identified risks and
recommendations shall be provided accordingly.
➢ Risk Matrix
Based on the analysis carried before, PTC shall prepare a risk matrix identifying
the risks, providing probability of occurrence of relevant events and impact of the
same on returns and likely mitigation measures. The parameters that would be
considered for risk analysis:
Increase in OA charges
Must run status not being honoured by state.
Discontinuing banking facility
While studying the existing power consumption, sources of energy and future
requirements, the following were considered:
GAIL (India) Ltd was incorporated in August 1984 as a Central Public Sector
Undertaking (PSU) under the Ministry of Petroleum & Natural Gas (MoP&NG). GAIL
(India) Limited is India’s leading natural gas company with diversified interests across
the natural gas value chain of trading, transmission, LPG production & transmission,
LNG re-gasification, petrochemicals, city gas, E&P, etc. It owns and operates a network
of around 13,340 km of natural gas pipelines spread across the length and breadth of
country. It is also working concurrently on execution of multiple pipeline projects to
further enhance the spread.
GAIL commands ~70% market share in gas transmission and has a Gas trading share
of over ~ 50% in India. GAIL and its Subsidiaries / JVs also have a formidable market
share in City Gas Distribution. In the Liquefied Natural Gas (LNG) market, GAIL has
significantly large portfolio. GAIL is also expanding its presence in renewable energy like
Solar, Wind and Biofuel.
The company was initially given the responsibility of construction, operation &
maintenance of the Hazira - Vijaypur -Jagdishpur (HVJ) pipeline Project. It was one of
the largest cross-country natural gas pipeline projects in the world. Originally this 1800
Km long pipeline was built at a cost of Rs 1700 Crores and it laid the foundation for
development of market for natural Gas in India.
Figure 3: GAIL OFC Network
Within a very short span of time, GAIL has established themselves as a Global
Maharatna with significant presence in the entire gas value chain. GAIL fast progression
has made us face resultant business complexities, associated confrontation of global
scale competition in all major business verticals. Besides rising competition, GAIL have
also witnessed a pivotal transformation across energy sector in recent years, driven by
various factors such as rising demand, technological innovation, geopolitical shifts and
environmental concerns. Considering the imminent challenges and sectorial
transformation, GAIL have adopted long term strategic plan - “Strategy 2030” to
overcome business challenges and new areas for growth and the way forward.
GAIL is committed to reduce carbon emissions and implement renewable projects. GAIL
has a total installed capacity of 130.26 MW of alternative energy; out of which 118 MW
are wind energy projects and 12.26 MW are solar energy projects. GAIL has installed
India’s 2nd largest solar rooftop of ~6 MW grid-connected captive solar power plant at
Pata Petrochemical complex. Further, roof-top and ground-mounted solar units are also
being installed at various offices/ work centers for captive use. GAIL plans to install 1
gigawatt solar and wind or either together or any other renewable part in the next three
to four year.
GAIL is presently operating 5 Gas Processing Units (GPUs) located at Vijaipur (2 Units),
Pata, Gandhar & Vaghodia for production of LPG and other Liquid Hydrocarbon (LHC)
products. Further, GAIL also operates an integrated petrochemical complex at Pata
(U.P.) for production of Polymer along with associated Liquid products. LPG produced
in GAIL plants is sold exclusively to PSU Oil Marketing Companies (OMCs) while other
LHC products (Propane, Pentane and Naphtha) are sold directly to industrial customers
in Retail segment. By-products from Gas Cracker Unit (GCU) of Petrochemical plant
such as Mixed Fuel Oil (MFO), Propylene & Hydrogenated C4 Mix are also sold directly
to customers in Retail segment.
3.1 About GAIL Vijaipur
In November 1988, GAIL received approval for investment of ₹ 300 crore for setting up
a LPG extraction plant at Vijaipur. The unit, based on HVJ gas was to have a capacity
of over 400,000 TPA to be implemented in two phases of 200,000 TPA capacity each.
By 1990-91 commissioning of the Phase I of the LPG plant at Vijaipur was completed,
eight months ahead of schedule. Following this, Phase-II at Vijaipur was completed in
November/December 1991 and commissioned in February 1992.
GAIL is in the process of building one of India's largest proton exchange membrane
(PEM) electrolyzer at Guna in Madhya Pradesh to produce green hydrogen by the end
of 2023, as it looks to supplement its natural gas business with carbon-free fuel.
GAIL is progressively adopting the state of the art gas producing technologies for making
environment friendly gas. To cater to the Power and Steam requirement of the Plant,
GAIL-Vijaipur has set up its own Captive Plants comprising of 1 X 15 MW STG based
on Natural Gas and 2 X 2.7 MW GTG based on Gas. All the three (3) nos. of said
Turbines are of BHEL make.
Aligned with the objectives of the National Hydrogen Mission, GAIL, Vijaipur, is
currently in the process of establishing a Green Hydrogen plant on its premises,
boasting a capacity of 4.3 TPD. The anticipated commissioning date for this plant is set
for June 2024. Initially, the electrolyser's power demand is estimated to range between
~2.5 – 3.0 MW, with plans to increase it to ~10-11 MW by February 2025. In adherence
to the green hydrogen regulations, hydrogen will be classified as "Green Hydrogen" only
if the power supplied to the electrolyser originates from MNRE-approved Renewable
Energy sources.
As per the data provided by GAIL, the tentative load profile of the electrolyser shall be
as follows:
Capacity Energy Months
May-25
Mar-25
Jun-25
Aug-24
Dec-24
Jan-25
Nov-24
Sep-24
Feb-25
Apr-25
Oct-24
Jul-24
(MWh)
1,980
1,980
1,980
1,980
1,980
1,980
1,980
7,920
7,920
7920
7920
7920
10.50
10.50
10.50
10.50
10.50
(MW)
2.66
2.66
2.66
2.66
2.66
2.66
2.66
Power Scenario in India
The Indian power sector, since independence, was dominated by state and centrally
owned vertically integrated utilities with the prime objective of making “power available
to all”. The opening up of Indian economy in early 1990s and large scale liberalization,
urbanization and industrialization led to a rapid increase in demand for power. The
quantum of investment requirement grew exponentially and Government alone was no
longer able to make adequate investments in the sector. As a result, power generation
was de-licensed and opened to private investment in 1991 to provide a boost to the
sector.
The State-dominated power sector was inefficient, hamstrung by under-maintenance
and inadequate investment. The state utilities were supplying power below the cost of
production to key consumer groups at a huge financial loss. With massive additions to
capacity needed to support growth, private sector participation was seen as a necessary
complement to public investment.
Amendments in 1991 to the Electricity Supply Act opened the sector to private
participation in generation. As the country continued to face crippling power shortages,
States restructured their vertically integrated State Electricity Boards (SEBs) and
established State Electricity Regulatory Commissions (SERCs) under their own reform
legislative initiatives to improve performance.
From 1996 onwards, focus shifted to unbundling of State Electricity Boards (SEBs) with
the broad aims of enhancing function-specific efficiencies and ensuring better returns
to generation and transmission businesses. Starting with Orissa, five more states opted
for unbundling of their SEBs. Soon after in 1998, the Electricity Regulatory Commission
Act was notified, which laid down provisions for establishing independent regulatory
commissions at state and central level to regulate electricity prices. The Electricity
Regulatory Commission Act of 1998 set up the Central Electricity Regulatory
Commission (CERC) and brought regulatory consistency to the States.
This form of market structure was considered as a surrogate for competition in
monopoly markets wherein the independent regulatory commission protects the
interest of consumers and other market participants. However, such a market structure
is only transitional till the establishment of full scale competitive market. Subsequently,
the Electricity Act 2003 was formulated to address the changing needs of the power
market.
India’s power sector is well diversified with market dynamics. Power generation ranges
from conventional sources such as coal, lignite, natural gas, oil, hydro and nuclear
power to non-conventional sources such as wind, solar, and agricultural and domestic
waste. Electricity demand in the country has increased rapidly and is expected to rise
further in the years to come. In order to meet the increasing demand for electricity in
the country, the electricity supply chain consisting of generation, transmission and
distribution has undergone a phase of transformation to competitiveness.
India is a major force in the global energy economy. Energy consumption has more than
doubled since 2000, propelled upwards by a growing population – soon to be the world’s
largest – and a period of rapid economic growth. Near‐universal household access to
electricity was achieved in 2019, meaning that over 900 million citizens have gained an
electrical connection in less than two decades.
India’s continued industrialization and urbanization will make huge demands of its
energy sector and its policy make₹ Energy use on a per capita basis is well under half
the global average, and there are widespread differences in energy use and the quality
of service across states and between rural and urban areas. The affordability and
reliability of energy supply are key concerns for India’s consumer.
India consumes about 7.9% of the world’s commercial energy and is ranked as the third
largest consumer of energy in the world in terms of energy demand. This is despite
having one of the lowest per capita energy consumptions in the world. Continued
economic development and increasing population are pushing up the demand for energy
at a higher rate than additions in generation capacity. India’s incremental energy
demand for the next decade is projected to be among the highest in the world, spurred
by sustained economic growth, rise in income levels and increased availability of goods
and services. With a gross domestic product (GDP) growth target of 8% set for the next
few years, the energy demand is expected to grow at 5.2% annually. This rapid increase
in energy demand has resulted in increasing dependence on foreign sources of energy.
It has been estimated that to support the government’s GDP growth targets, the
electricity sector alone will have to increase supply by 10% annually.
Prior to the Electricity Act 2003, the electricity industry recognized generation,
transmission and supply as three principal activities, and the legal provisions were also
woven around these concepts. Indian power sector was dominated by state owned
companies, while suppliers of electricity had little choice about whom to sell and the
buyers had no alternate choice to purchase power. Bulk purchase and sale is a regular
phenomenon between DISCOMs and licensees that was construed as part of the activity
of supply of electricity.
Electricity is a concurrent subject and both federal and state governments have
jurisdiction in India’s power market structure. Electricity Act 2003 (EA) marked the
transformation of the sector, providing consolidation of laws, promotion of competition,
private participation and delicensing of generation. EA also emphasized tariff-related
policy formulation and setting up of regulatory commissions. Policy developments and
establishment of power markets provided needed stimulus for capacity additions, which
witnessed steep growth over the last decade.
The Electricity Act 2003 focused on two elements: “development of a competitive power
market with transparent market-driven pricing mechanism which gives the consumers
enough options to choose from”, and “providing the right policy, legal and regulatory
platform to the consumers for exercising their choice.” Based on these two core agendas,
the Electricity Act 2003 has six major themes:
Reorganization of the state owned vertically integrated electricity boards;
De licensing of power generation to enable higher investments;
Trading and market development;
Tariff and subsidies;
Consumer interest; and
Open Access
With the new Act, a liberalized market structure was envisaged to be developed by
introducing competition in distribution and supply through Open Access mechanism.
Annual average power generation capacity grew in the range of 9 -10% during FY 08 to
FY 22 vis-à-vis a demand growth of 6 -7% during the same period. This resulted in a
decline in power shortages of 11% during FY 2008 to current deficits of less than 1%.
Since 2000, India has been responsible for more than 10% of the increase in global
energy demand. On a per capita basis, energy demand in India has grown by more than
60% since 2000, although there are widespread differences across different parts of the
country as well as across socio‐economic groups. On a range of economic and energy‐
related indicators, India has been catching up with the rest of the world in recent year
Coal demand per capita increased from 25% of the world average in 1990 to 60% in
2019 and, mainly for this reason, carbon dioxide (CO2) emissions per capita increased
from a little over 15% of the world average to a little under 40% over this period.
150
100
50
0
FY-13 FY-14 FY-15 FY-16 FY-17 FY-18 FY-19 FY-20 FY -21 FY - 22 Till
Nov'23
Thermal Renewable Nuclear Total
Figure 7: All India Installed Capacity Resource wise, Source CEA
Renewable energy capacity has seen a remarkable growth with a 10.2% CAGR,
outpacing other sources at 4.6% CAGR. The total installed generation capacity grew at
6.6% from 2012-13 to 2022-23.
Thermal generation from fossil fuels such as coal, gas and oil, has the dominant share
of total electricity generation in India. While hydro-electricity also has a significant
share, other sources such as nuclear and other renewable energy sources (solar, wind,
biomass, etc.) have relatively small share. In the recent past the Government of India
has put a lot of emphasis on generation from renewable sources.
Over dependence on coal based thermal power plants results in attendant problems of
low plant load factors, coal transportation, coal mining and pollution. It is also being
realized that presently used conventional electricity generation techniques are not likely
to be adequate for meeting all the electricity requirements in the coming year Such
doubts are being expressed due to constraints born out of current social-economic
concerns. The major concern is from environmental point of view. Over the years the
power supply position has also improved with new generation capacities:
1400000
1200000
1000000
800000
600000
400000
200000
Requirement (MU) Availability (MU) Peak Demand (MW) Peak Met (MW)
The transmission sector was opened for private investments in 1998. The Central
Transmission Utility (CTU) is the nodal agency for providing the medium term (3 months
to 5 years) and long-term (exceeding 7 years) access (the right to use the inter-state
transmission system) typically required by a generating station or a trader acting on the
station’s behalf. The PGCIL is responsible for inter-state transmission and development
of the national grid, and it acts as the CTU.
500000 1200000
456716
441821
450000 425071
413407
390970 1104450 1000000
400000 367851 1025468
341551 967893
350000
313437 899663 800000
291336
300000 274588 804458
721265
CKM
100000
200000
50000
0 0
FY-13 FY-14 FY-15 FY-16 FY-17 FY-18 FY-19 FY-20 FY-21 FY-22
Transmission Lines(CKM) Transformation Capacity(MVA)
The bulk transmission (transmission lines 220 KV & above) has increased from
2,74,588 CKM in 2012-13 to 4,56,716 CKM in 2021-22. During the same period, the
transmission capacity of substations has also increased from 4,59,716 MVA to
11,04,450 MVA. This has resulted in lower grid congestion and improved market
activity. The CAGR in the transmission lines and transmission capacity of substations
was 5% and 9% respectively.
The sector is having natural monopoly as there are high sunk costs in investing in the
infrastructure needed to transmit electricity, such as transmission lines. Because of
these characteristics, non-public entities also face entry barriers, and private
investments are allowed in transmission projects only after approval from CERC.
Although the transmission market is largely dominated by the public sector, there are
many lines including High-Voltage Direct Current (HVDC) lines owned by private player.
Bulk electric power supply in India is mainly tied in long-term contracts. The DISCOMs
who have the obligation to provide electricity to their consumers mainly rely on supplies
from these long-term contracts. By identifying electricity trade as a distinct activity, EA
2003 along with pursuant regulations from the CERC, paved the way for a paradigm
shift in the power sector.
The Section 2 (47) of the Electricity Act -2003 defines Open Access as “non-
discriminatory provision for the use of transmission lines or distribution system
or associated facilities with such lines or system by any licensee or consumer or
a person engaged in generation in accordance with the regulations specified by
the Appropriate Commission”
The drivers for this mechanism were uneven distribution of fuel resources and far away
load centers scattered across the country which impeded in the justifiable distribution
and usage of electricity. To achieve the aforementioned objectives, Open Access
mechanism was given statutory force through Section 38, 39, 40 and 42 of the Act.
Open Access accords better choice to consumers on transparent and fair terms,
promotes competition amongst the generators and encourages optimal utilization of
geographically spread diverse energy resources (coal, gas, water, renewables) as it has
been found in most cases to better transport electricity than fuel.
Power Procurement through OA mechanism is growing in India and more than 5000
consumers are procuring power under open access for optimizing their power
procurement costs. Every OA transaction involves some transaction costs viz. network
usage (transmission, wheeling) charges, system operation charges etc. and associated
network losses. Open Access as per Regulation, is categorized hereunder as:
The above-mentioned charges are over & above the negotiated cost of power generation
that the open access customer has to pay for the energy contracted through OA.
It may be noted that, as per the NLDC order, OA users has an option of paying POC
Charges either for the PoI State or PoD State for bilateral transaction, however for power
exchange both side charges are applicable.
I. Bilateral Transactions
“Bilateral transaction” means a transaction for exchange of energy between a specified
buyer and a specified seller, directly or through a trading licensee, from a specified
point of injection to a specified point of drawl for a fixed or varying quantum of power
for any time period during a month. Bilateral market constitutes largest share of power
trading market and has grown at a good rate. A bilateral transaction can be both Inter
State & Intra State.
The cost of power supply under this mode is directly driven by prices of coal, oil
and gas. In the past few months it has been observed that the tariffs of bilateral
power have increased due to shortage of coal and subsequent increase in coal
prices.
Presently, there are three operational power exchanges in India; Indian Energy
Exchange (IEX), Power Exchange of India Limited (PXIL) and Hindustan Power
Exchange (HPX). IEX was initially promoted by FTIL and PTC, it was launched on
27.06.2008 and presently its market share is more than 95%. PXIL, launched on
22.10.2008 & being promoted by NSE and NCDEX, on other hand has a minimal
market share. Hindustan Power Exchange (HPX) is the new age power exchange in
Indian Electricity Market. HPX launched on 06.07.2022 & being promoted by three
leading organization of their respective fields PTC India Limited, BSE Investments
Limited, ICICI Bank Limited
For successful
execution of Collective
Transaction and also to
accommodate any
exigencies of congestion
in intra- regional
transmission system
with the help of market
splitting the Electrical
Regions Namely
Northern, Southern,
Eastern, Western and
North-East of the
country has been
divided further in 13
bid-areas.
Real Time Market has been operationalized across the country w.e.f. 1 June 2020,
following the Hon’ble CERC order. The real time market would help Discom/State
Utilities to meet the gap between demand and supply through procurement and sale of
power, and simultaneously restricting the under drawal and over drawal under DSM
regime. Also, the generators in case of forced outage, can procure the power under RTM
to supply the committed power under various contracts, so as to avoid penalties under
DSM regime while maintaining the Grid discipline.
Similarly, the Procurers may also meet their power demand under Real Time Market
through submission of their purchase bids on Exchange. However, the participation
from the industrial & commercial consumers is observed to be negligible due to various
Regulatory restrictions and constraints like scheduling of power on RTC basis, levy of
SLDC and NLDC charges, etc.
It has also observed that some states have been issuing the NOCs/Standing Clearance
with a directive that the power has to be scheduled on Round the Clock (RTC) basis,
and in such a scenarios, procurement of power under RTM is a challenging activity.
The Green-Term Ahead Market (G-TAM) is a newly introduced market segment for
trading in renewable energy following the CERC approval. It is an alternative new model
introduced for selling off the power by the renewable developers in the open market.
The new market segment features contracts such as Green-Intraday, Green-Day-ahead
Contingency (DAC), Green-Daily and Green-Weekly. The matching mechanism is
continuous/spot trading for Green-Intraday, Green-DAC and Green-Daily contracts
whereas double sided open auction process to be implemented for Green-Weekly.
The operations to be carried out in accordance with the Procedure for Scheduling
Bilateral Transactions through Power Exchange issued by Power System Operation
Corporation Ltd; CERC Power Market Regulations, 2010; CERC Open Access in inter-
State Transmission Regulations, 2008; CERC Indian Electricity Grid Code Regulations,
2010 as amended from time to time and the Bye-Laws, Rules and Business Rules of the
Exchange.
The said G-TAM Market is in its nascent stage, however with the increase in liquidity,
GTAM platform would lessen the burden on RE-rich States and incentivize them to develop
RE capacity beyond their own RPO. This would promote RE merchant capacity addition
and help in achieving RE capacity addition targets of the country.
The growth in volume and trend of average prices in bilateral & Exchange segment for
FY11 to FY21 is as follows:
6 90
4.28
80
5 4.33 4.29 4.11
4.79 4.28 3.53 70
3.59
4.51
4.18
4 60
4.26
3.4750
3.57 3.67
3 3.47 3.50 3.45
3.23 40
2.90 2.98
2.72
2 2.50 30
20
1
10
0 0
FY-11 FY-12 FY-13 FY-14 FY-15 FY-16 FY-17 FY-18 FY-19 FY-20 FY-21
Figure 14: Growth in volume and trend of average prices in bilateral & Exchange segment
III. Captive Transaction
The Section 2 (8) of the Electricity Act -2003 defines Captive generating plant “as a
power plant set up by any person to generate electricity primarily for his own
use and includes a power plant set up by any co-operative society or association
of persons for generating electricity primarily for use of members of such
cooperative society or association”
In addition, the Section 9 of the Act (EA 2003) says a person may construct, maintain
or operate a captive generating plant and dedicated transmission lines:” --
Provided further that no licence shall be required under this Act for supply of electricity
generated from a captive generating plant -- to any consumer subject to the regulations
made under subsection (2) of section 42.
“Every person, who has constructed a captive generating plant and maintains
and operates such plant, shall have the right to open access for the purposes of
carrying electricity from his captive generating plant to the destination of his
use:” --- such open access shall be subject to availability of adequate transmission
facility---”
Further, Ministry of Power empowered by the EA 2003 brought out a Notification on 8th
June 2005 to be called the Electricity Policy 2005. Provisos related to captive
transaction are appended below:
No power plant shall qualify as a ‘captive generating plant’ under section 9 read with
clause (8) of section 2 of the Act unless-
(i) Not less than twenty-six percent of the ownership is held by the captive
user(s), and
(ii) Not less than fifty-one percent of the aggregate electricity generated in such
plant, determined on an annual basis, is consumed for the captive use:
Provided that in case of power plant set up by registered cooperative society, the
conditions mentioned under paragraphs at (i) and (ii) above shall be satisfied collectively
by the members of the cooperative society:
Provided further that in case of association of persons, the captive user(s) shall hold not
less than twenty-six percent of the ownership of the plant in aggregate and such
captive user(s) shall consume not less than fifty-one percent of the electricity
generated, determined on an annual basis, in proportion to their shares in ownership
of the power plant within a variation not exceeding ten percent;
Explanation: -
(1) The electricity required to be consumed by captive users shall be determined with
reference to such generating unit or units in aggregate identified for captive use and
not with reference to generating station as a whole; and
(2) The equity shares to be held by the captive user(s) in the generating station shall not
be less than twenty-six per cent of the proportionate of the equity of the company
related to the generating unit or units identified as the captive generating plant.
▪ As per the provisions under Section 42 of the Electricity Act, 2003, captive
consumers of the group captive plant are exempted from payment of cross-subsidy
charges as applicable under open access.
▪ The group captive consumers have to consume power proportionate to their equity
investment (rule of proportionality).
▪ After the completion of financial year, the documents related to consumption,
generation, equity shareholding (as required by the designated assessment agency)
are required to be submitted to the designated assessment agency (Discom/ SERC) for
according the status of captive generating plant.
▪ Purchase through Captive Mode is a feasible option in states where cross subsidy
charges are very high;
The adoption of the Group Captive model is witnessing an increasing trend amongst
corporates, because the savings per-unit electricity make it a compelling model. The
capital investment is minimal, while per-unit tariffs are at least 25-40% cheaper than
the grid. It is a great way for corporates to ease into energy transition and procuring
from renewables.
Growth of Renewable Energy in India is well ahead on the path to achieve the
Government of India’s target of 175 GW capacity installation by the year 2022. Further,
it is expected to grow up the Renewable Energy capacity to 450 GW by the year 2030
as declared by the Honorable Prime Minister.
The Ministry of New and Renewable Energy (MNRE), Government of India, is the nodal
Ministry for all the matters related to new and renewable energy. The Ministry with the
objective/aim to develop and deploy new and renewable energy to supplement the
energy requirements of the country is issuing various Schemes, Guidelines and Policies
to encourage development Renewable Energy Projects in India.
Generation being a delicensed activity, anyone can set-up its own Renewable Project
with any capacity as per the requirement. However, some of the states have imposed
certain restriction on setting up Captive Wind/Solar Projects limited to contact demand
with incumbent Discom.
Also, as per the MNRE latest guidelines anyone can generate electricity through solar
power system and surplus electricity can be export through net-metering system. The
installation of net-metering at the site will connect it to grid via state electricity board or
distribution companies.
With reduction in costs related to renewable capacities (panels, turbines, etc.) and
various incentives provided by states, many industrial consumers are observed setting
up their own captive renewable power plant to minimize the generation cost.
While this is certainly an option for cost optimization, but one has to be also considerate
(considering same being a non-core business) towards the magnitude of equity
investment, conduct of various responsibilities including 24X7 monitoring, O&M,
forecasting & scheduling etc.
The cost-benefit section, in the later sections of the report, analyses both the equity
investment options for optimization of power procurement costs.
For the last 19 years or so, introduction of competition has been one of the main aims
of reform in the electricity sector in India. One of the key measures to bring about
competition is open access (OA) whereby, mainly, large consumers have access to the
transmission and distribution (T&D) network to obtain electricity from suppliers other
than the local electricity distribution company (Discom).
According to the Standing Committee on Energy, 27 SERCs have issued regulations for
OA and allowed OA for consumers with loads greater than 1 MW. 23 of the 27 SERCs
have specified transmission charges, wheeling charges and cross-subsidy surcharges for
OA.
The renewable energy sector in India is growing rapidly and presents an opportunity for
strong financial returns. Social and economic growth are at the top of the government’s
agenda, and new energy sources to serve this demand are increasingly coming from
renewable energy. The government policy has been supportive, and more recently, a
wider set of actions—incentives, infrastructure and investment promotions were taken
up.
Technology development, larger-scale projects and the learning effect has allowed the
use of efficient designs and have pushed down costs. This makes renewable energy
attractive to power utilities that are contracting new long-term capacity, and in addition,
this avoids them the burden of take-or-pay contracts and fuel risk.
The dependence of renewable energy companies on fiscal support from the government
is minimal in India. This means an investor with a given capital can fund more projects
across regions or asset-classes to diversify resource-based risks. The lower cost
structure also means that an investor who is early or better prepared gains from better
returns. Market creation has not been easy but regulators are acting on this with tighter
compliance standards. Public opinion is positive with the recognition of environmental,
economic and social benefits.
Hydro
Nucl…
Ther…
RES
0.00 50.00 100.00 150.00 200.00 250.00
Figure 18: Sector wise installed capacity, Source National Power Portal
Generation from Renewable Energy Sources (RES) against Non- RES for the financial
years 2010-11 to 2021-22 are given below:
Figures in GW
450
395
400 370
356 382
344
350 327
305
300 275
249 288 289
275 278 283
250 223 270
259
200
236
200 174 214
196
150 175
155
100
106
87 94
50 69 78
57
18 25 28 35 39 46
0
FY-11 FY-12 FY-13 FY-14 FY-15 FY-16 FY-17 FY-18 FY-19 FY-20 FY -21 FY - 22
Non-RES RES
As of 31st May 2022 the installed capacity of wind power in India was 40.7 GW, mainly
spread across Tamil Nadu (9.86 GW), Gujarat (9.34 GW), Karnataka (5.17 GW),
Maharashtra (5.01GW), Rajasthan (4.49 GW), Andhra Pradesh (4.09 GW) and Madhya
Pradesh (2.52 GW). Wind power accounts for 10% of India's total installed power
capacity. India has set an ambitious target to have 500 of electricity from wind power
by 2022. In the past seven years, the installed capacity has increased with CAGR of
7.1%.
Wind Installed Capacity Vs Generation
45000 80000
40353
39243
40000 37689 70000
35626
34046 68640
35000 32280
64646 60000
62036
30000 60150
26777 50000
52666
25000 23354
MUs
MW
46004 40000
20000
33768 30000
15000 33029
20000
10000
5000 10000
0 0
FY-15 FY-16 FY-17 FY-18 FY-19 FY-20 FY-21 FY-22
Setting up of SHP projects normally require about 3-4 years depending upon its size
and location. The national target for SHP is to achieve a cumulative capacity of 5
GW by 2022, under overall targets of achieving a cumulative grid connected
Renewable Energy Power Projects of 1.75 GW. Against this target of achieving an
aggregate capacity of 5.0 GW by the year 2022, an aggregate capacity of 4.67 GW
been achieved by 31st December 2019 through 1127 small hydropower projects. In
addition, 109 projects of about 529.24 MW are in various stages of implementation.
Government of India’s initiatives on Renewable Energy
India is blessed with abundant renewable energy resources like wind & solar and these
energy sources are emerging as an alternative to the conventional sources of energy to
meet the requirements of the country. The estimated solar power potential is 749 GW
and wind power potential of the country is 695 GW at 120 meter above ground level.
Unlike solar resource, wind resource is mainly concentrated in the states of Andhra
Pradesh, Gujarat, Karnataka, Madhya Pradesh, Maharashtra, Rajasthan and Tamil
Nadu.
Growth of Renewable Energy in India is well ahead on the path to achieve the
Government of India’s target of 175 GW capacity installation by the year 2022.
Further, it is expected to grow up to 450 GW by 2030 as declared by the Honorable
Prime Minister.
Wind Solar Hybrid Policy
The Government of India has issued Wind-Solar Hybrid Policy on 14.05.2018 with the
objective to provide a framework for promotion of large grid connected wind-solar PV
hybrid system for optimal and efficient utilization of transmission infrastructure and
land, reducing the variability in renewable power generation and achieving better grid
stability. The Government has adopted transparent competitive bidding process for
such large scale projects and has also issued guidelines for the same.
Subsequently, a scheme for setting-up of 2500 MW wind-solar hybrid power
projects was sanctioned on 25.05.2018 by the Government for procurement of
hybrid power at a tariff discovered through transparent process of bidding by Solar
Energy Corporation of India (SECI). The wind solar hybrid projects of 1.44 GW
capacity have been awarded till date, under the above scheme.
It may please be noted that while the bidding has resulted in competitive tariffs which are
much lower than traditional Feed-in Tariffs, on the other hand a number of projects have
been delayed due to land, NoCs and transmission related issues. These challenges and
uncertainties have raised the concerned of investors in the sector
Development of Wind Park / Wind-Solar Hybrid Park
In order to overcome the above mentioned challenges and to speed up the
commissioning of the projects, the Government has come up with a concept note vide
its office memorandum dated 13.11.2020 for “Development of Wind Park / Wind-
Solar Hybrid Park”. The capacity of each park should generally be 500 MW and more,
however parks of lower capacity, not be less than 50 MW, may also be developed
depending upon the availability of land and resource.
Waiver of ISTS Charges for Projects based on Renewable Sources
As per MOP order dated 23 Nov 2021, CTU Charges shall be waived-off for Wind/Solar
Projects for 25 years for projects commissioned before June 2025.
However, the transmission loss is applicable. As per the present procedure, the
transmission losses are notified by Power System Operation Corporation (POSOCO)
every week.
Ministry of Power notified the Green Hydrogen Policy on 17 February 2022 providing
various benefits to the producer of the green hydrogen.
The salient features of the said Green Hydrogen Policy are as follows:
Electricity (Promoting Renewable Energy through Green Energy OA) Rules, 2022
In order to further accelerate our ambitious renewable energy programmes, with the
end goal of ensuring access to affordable, reliable, sustainable and green energy for all,
Green Open Access Rules, 2022 have been notified on 06.06.22. The notified Rules
enable simplified procedure for the open access to green power. It will enable faster
approval of Green OA, Uniform Banking, Voluntary purchase of RE power by
commercial & industrial consumers, Applicability of OA charges etc.
▪ The Green Open access is allowed to any consumer and the limit of Open Access
Transaction has been reduced from 1 MW to 100 kW for green energy, to enable
small consumers also to purchase renewable power through open access.
▪ Minimum one month RE Banking on payment of banking charges to be allowed.
Respective Commission will fix such charges. No carry forward of banked energy
after a month is allowed.
▪ Additional Surcharge shall not be applicable on Green OA if fixed charges are paid
by consumers
▪ Cross subsidy surcharge and additional surcharge shall not be applicable if green
energy is utilized for production of green hydrogen and green ammonia
Hon'ble Prime Minister launched the National Hydrogen Mission on India's 75th
Independence Day (i.e. 15th August, 2021). The Mission aims to aid the government in
meeting its climate targets and making India a green hydrogen hub.
Government of India, Ministry of New and Renewable Energy has introduced a National
Green Hydrogen Mission January 2023, The National Green Hydrogen Mission aims to
provide a comprehensive action plan for establishing a Green Hydrogen ecosystem and
catalyzing a systemic response to the opportunities and challenges of this sunrise
sector.
The Government of India has been contemplating various policy measures to support
the transition from fossil fuels to Green Hydrogen and Green Ammonia, both as energy
carriers and chemical feedstocks for different industries.
Green Hydrogen policy have several key provisions to encourage the production
of Green Hydrogen and Green Ammonia:
d) Banking shall be permitted for a period of 30 days for Renewable Energy used for
making Green Hydrogen / Green Ammonia.
e) The charges for banking shall be as fixed by the State Commission which shall not
be more than the cost differential between the average tariff of renewable energy
bought by the distribution licensee during the previous year and the average market
clearing price (MCP) in the Day Ahead Market (DAM) during the month in which the
Renewable Energy has been banked.
f) Connectivity, at the generation end and the Green Hydrogen / Green Ammonia
manufacturing end, to the ISTS for Renewable Energy capacity set up for the purpose
of manufacturing Green Hydrogen / Green Ammonia shall be granted on priority
under the Electricity (Transmission system planning, development and recovery of
Inter State Transmission charges) Rules 2021. 7. Land in Renewable Energy Parks
can be allotted for the manufacture of Green Hydrogen / Green Ammonia.
j) Distribution licensees may also procure and supply Renewable Energy to the
manufacturers of Green Hydrogen / Green Ammonia in their States. In such cases,
the Distribution licensee shall only charge the cost of procurement as well as the
wheeling charges and a small margin as determined by the State Commission.
k) Ministry of New and Renewable Energy (MNRE) will establish a single portal for all
statutory clearances and permissions required for manufacture, transportation,
storage and distribution of Green Hydrogen / Green Ammonia. The concerned
agencies/authorities will be requested to provide the clearances and permissions in
a time-bound manner, preferably within a period of 30 days from the date of
application.
l) In order to achieve competitive prices, MNRE may aggregate demand from different
sectors and have consolidated bids conducted for procurement of Green
Hydrogen/Green Ammonia through any of the designated implementing agencies.
Waiver of ISTS Charges: Green Hydrogen and Green Ammonia producers will enjoy a
waiver of Inter-State Transmission System (ISTS) charges for 25 years. This incentive
aims to reduce the operational costs for these producers, making the production of
green hydrogen and green ammonia more economically viable.
Open Access: Green Hydrogen and Green Ammonia plants will be granted Open Access
within 15 days of receiving a complete application. Open Access allows these plants to
efficiently source Renewable Energy for their operations. This expedited process
ensures that producers can readily access the required renewable energy.
As per Ministry of New and Renewable Energy vide its OM dated 18 August 2023, the
“Green Hydrogen” shall mean Hydrogen produced using renewable energy, including,
but not limited to, production through electrolysis or conversion of biomass. Renewable
energy also includes such electricity generated from renewable sources which is stored
in an energy storage system or banked with the grid in accordance with applicable
regulations.
Renewable Energy Policies and Regulations
The Ministry of New and Renewable Energy (MNRE) is the nodal Ministry of the
Government of India for all matters relating to new and renewable energy. MNRE aiming
towards development and deployment of new and renewable energy to supplement the
energy requirements of the country.
Objective
The main objective of the Policy is to provide a framework for promotion of large grid
connected wind-solar PV hybrid system for optimal and efficient utilization of
transmission infrastructure and land, reducing the variability in renewable power
generation and achieving better grid stability.
Policy also aims to encourage new technologies, methods and way-outs involving
combined operation of wind and solar PV plants.
Operative Period
This policy will remain in force unless withdrawn, modified or superseded by the
Government. The Government will undertake a review of this Policy as and when
required.
Hybrid Plant
A wind-solar plant will be recognized as hybrid plant if the rated power capacity of one
resource is at least 25% of the rated power capacity of other resource.
Implementation Strategy
The implementation of wind solar hybrid system will depend on different configurations
and use of technology.
▪ The power procured from the hybrid project may be used for fulfilment of solar
RPO and non-solar RPO in the proportion of rated capacity of solar and wind
power in the hybrid plant respectively.
▪ Government entities may invite bids for new hybrid plants keeping qualifying
criteria such as grid interface point, effective CUF and unit price of electricity,
and the tariff being the main criteria for selection.
▪ In case of AC integration assessment of solar and wind power injected from the
hybrid project into the grid will be worked out by apportioning the reading of
main meter installed at the receiving station on the basis of readings of ABT
meters installed on LT or HT side of the wind and solar PV plant as the case may
be.
▪ In case of DC integration assessment of solar and wind power injected from the
hybrid project into the grid will be worked out by apportioning the reading of
main meter installed at the receiving station on the basis of readings of DC
meters installed at the DC output of the wind and solar PV plant. Till such time
the methodology for DC metering of hybrid systems and standards & regulations
are framed for DC meters, only AC integration will be permitted.
▪ The additional solar/wind power generated from the hybrid project may be used
for
(a) captive purpose.
(b) sale to third party through open access.
(c) sale to the distribution company
Storage
Bidding factors for wind solar hybrid plants with storage may include minimum firm
power output throughout the day or for defined hours during the day, extent of
variability allowed in output power, unit price of electricity, etc.
Incentives
The Government will encourage development of wind-solar hybrid systems through
different schemes and programmes. All fiscal and financial incentives available to wind
and solar power projects will also be made available to hybrid projects.
7.1.2 CERC (Connectivity and General Network Access to the inter-State Transmission
System) Regulations, 2022
Integration of the power transmission system in India was an urgent need for, on one
hand, creating equilibrium in generation and consumption patterns throughout the
country and, on the other, maintaining grid stability. Thus, in October 2021, the
Ministry of Power, Government of India, notified the Transmission Planning Rules,
which introduced the ‘General Network Access’ (GNA), i.e., ‘one-nation one-grid one-
frequency’ regime in India.
Under earlier regulations, open access was categorized as long term, medium term and
short-term open access, based on the term for which it was required. The GNA
Regulations has simplified this categorization as:
Eligibility criteria-
Conceptually GNA does away with pre-determined specific point-to-point access and
allows access or drawl on the entire beltway, thus providing generators and procurers
the choice of injection and drawl.
1 CERC (Connectivity and General Network Access to the ISTS) Regulations 2022
What is the reason for replacing the existing regulations?
These regulations shall be applicable to all grid connected regional entities and other
entities engaged in inter-State purchase and sale of electricity.
Computation of Deviation
Charges for Deviation: Charges for deviation in a time block by a seller shall be payable
by such seller as under:
Charges for deviation in a time block by a buyer shall be payable by such buyer as
under:
▪ The payment of charges for deviation shall have a high priority and the concerned
regional entity shall pay the due amounts within 7 (seven) days of the issue of
statement of charges for deviation by the Regional Power Committee, failing which
late payment surcharge @ 0.04% shall be payable for each day of delay.
▪ Any regional entity which at any time during the previous financial year fails to
make payment of charges for deviation within the time specified in these
regulations, shall be required to open a Letter of Credit (LC) equal to 110% of their
average payable weekly liability for deviations in the previous financial year in
favour of the concerned Regional Load Dispatch Centre within a fortnight from the
start of the current financial year.
▪ In case of failure to pay into the Deviation and Ancillary Service Pool Account within
7 (seven) days from the date of issue of statement of charges for deviation, the
Regional Load Dispatch Centre shall be entitled to encash the LC of the concerned
regional entity to the extent of the default and the concerned regional entity shall
recoup the LC amount within 3 days. MERC (Forecasting, Scheduling And Deviation
Settlement For Solar And Wind Generation) Regulations, 2018.
Eligible Entities
▪ All wind and solar energy generators with individual or combined capacity of 5 MW
and above connected to the state grid independently or through pooling station.
▪ All wind and solar generators of any capacity connected to the state grid through
pooling stations with total capacity of 5 MW and above.
Table 12: Deviation Charges for Sale of Power within the State
Absolute Error in a
Deviation Charges payable to State DSM Pool
15-min. time block
≤15% None.
At ₹0.50 per unit for the shortfall or excess beyond 15% and up
>25% but ≤35% to 25% + ₹1.00 per unit for balance energy beyond 25% and up
to 35%.
At ₹0.50 per unit for the shortfall or excess beyond 15% and up
>35% to 25% + ₹1.00 per unit for balance energy beyond 25% and up
to 35% + ₹1.50 per unit for balance energy beyond 35%.
Payment Mechanism
▪ Deviation charges shall be paid within ten days from date of issue by SLDC.
▪ Late payment will attract surcharge of 1.25 % per month.
Energy Accounting
▪ SLDC shall furnish data on weekly basis through IT enabled system and software.
Metering
▪ Metering to record parameters in every 15-minute time block.
▪ QCA shall furnish weekly meter readings to SLDC by 00:00 hours on Thursday of
the previous week.
▪ Data telemetry shall be adopted at the turbine/inverter or plant level as considered
appropriate by SLDC.
7.2 Madhya Pradesh Renewable Energy Landscape
Madhya Pradesh is a fast developing state and thus there is tremendous need for energy.
The Government of Madhya Pradesh has taken note of the growing recognition of
impacts of climate change and recognizes the need to tackle challenges that arise on
account of these impacts through integrated policy prescriptions and programmes
aimed at mitigation of impacts and adaptation to reduce vulnerability of systems.
Based on this green initiative, by endorsing the essential need to prevent avoidable
erosion of natural carbon – energy resources the state is endowed with, the state is
committed to promote promotion of generation of electricity from Renewable Energy
sources.
Control Period:
The Policy shall remain in operation for a period of five (5) years from the date of
notification in the Madhya Pradesh State Gazette or until a new policy is notified by the
State Government.
Nodal Agency:
The Office of the Commissioner, New and Renewable Energy Department, GoMP
(“NRED”) shall be the Nodal Agency for the implementation of this Policy
Policy Target:
i. Investment of INR 15,000 Crore by 2024 and INR 50,000 Crore by 2027 in the
Renewable Energy generation sector in the state
ii. Investment of INR 4,000 Crore by 2024 and INR 10,000 Crore by 2027 in RE
Equipment Manufacturing sector
iii. Twenty percent (20%) RE in State‟s energy mix by FY2024, thirty percent (30%) by
FY 2027 and fifty percent (50%) by FY 2030
a. Development of Ten thousand (10,000) MW Renewable Energy Technology
based Park/ RE Hybrid Park under GoI/ GoMP Scheme by FY 2027
b. Four thousand (4000) MW Renewable Energy Projects for exporting power
outside the state by 2024 and ten thousand (10,000) MW by FY 2027
iv. Generate more than 10,000 new jobs in Renewable Energy sector by 2024 and
50,000 new jobs by 2030.
CDM:
Carbon credits or any other similar incentives, which are available for such Projects,
can be availed by the Developer, as per the guidelines issued by the concerned
authorities from time to time.
7.2.4 MPERC (Terms and Conditions for Intra-State OA) Regulations, 2021 (Revision-I)
Allotment Priority
The allotment priority for allowing open access shall be decided in the following order
of priority:
▪ Distribution Licensee (irrespective of whether Open Access has been sought for long-
term, Medium-term or Short-term)
▪ Other Long-term Open Access Applicants.
▪ Other Medium-term Open Access Applicants
▪ Other Short-term Open Access Applicants:
Nodal Agency
▪ The nodal agency for arranging all types of long-term access and medium-term
access, such as transmission or distribution or combination of both, shall be the
State Transmission Utility (STU) who shall nominate the officer not below the rank
of Superintending Engineer to process the open access applications.
▪ The Nodal Agencies, i.e., STU and SLDC, shall be responsible for the implementation
of these Regulations and shall act under the supervision and control of the
Commission for the purpose.
Application Procedure
▪ An open access customer shall file an application to the nodal agency in the format
provided with these Regulations. The nodal agency has the right to seek additional
information as may be required. The nodal agency shall acknowledge the receipt of
completed application along with the Fees paid to the party within one working day
of receipt.
▪ A customer intending to avail open access shall also submit a copy of his application
to the Distribution Licensee who is supplying electricity to him or in whose area of
supply, the point of drawal lies.
▪ The nodal agency shall forward a copy of the application to the Transmission
Licensee and to the Distribution Licensee who is supplying electricity or in whose
area of supply, -the point of drawal lies.
▪ Provided, that where the long-term open access or medium-term open access can be
allowed without further system strengthening, this shall be allowed without delay on
entering into commercial agreements.
▪ If, in the opinion of the STU, further system strengthening is essential before
providing long-term open access or medium-term open access, the applicant may
request the STU to carry out the system studies and preliminary investigation for
the purpose of cost estimates and completion schedule for system strengthening.
▪ The applicant shall reimburse the actual expenditure incurred by the STU/
Transmission Licensee and /or Distribution Licensee, as the case may be, for system
strengthening studies: Provided that the fee of rupees one lakh for long-term open
access and rupees fifty thousand for medium-term open access paid by the applicant
shall be adjusted against the actual expenditure to be reimbursed by the applicant.
▪ In cases there is any material change in the location of the Applicant or a change by
more than ten (10) percent in the quantum of power to be interchanged using the
intra-State Transmission System and/or Distribution System, a fresh application
shall be made, which shall be considered in accordance with the provisions of these
Regulations.
Open Access Agreements: An open access customer shall enter into agreements with
the concerned Licensees, generators, traders and others as applicable and fulfil the
conditions as laid down under these Regulations.
Provided that if a Power Purchase and Wheeling Agreement, in accordance with the
applicable Madhya Pradesh Electricity Regulatory Commission (Cogeneration and
Generation of Electricity from Renewable Sources of Energy) Regulations, has been
executed by the long-term and medium-term open access customer using
distribution system with the Distribution Licensee/MPPMCL, then in such case
separate Bulk Power Wheeling Agreement shall not be executed.
Charges for Open Access: The Licensee providing open access shall levy only such fees
or open access charges as may be determined by the Commission from time to time. The
Following Charges are applicable.
▪ Transmission Charges
▪ Wheeling Charges
▪ Operating Charge
▪ Imbalance charges
▪ Reactive Energy Charges
▪ Cross-subsidy Surcharge
▪ Additional Surcharge
▪ Interconnection Expenses
Energy Losses
▪ The open access customers shall bear energy losses of the transmission system and
distribution system as approved by the Commission in accordance with the
Regulations framed by the Commission under section 61 of the Act. The energy
losses in the transmission and distribution systems shall be compensated by
additional injection at the injection point(s).
▪ The information regarding average energy losses for the previous 12 months shall
be posted on the websites of the SLDC and the Transmission and Distribution
Licensees.
In different As per
CTU As per CERC
States CERC
Provided that on achievement of Solar RPO compliance to the extent of 85% and above,
remaining shortfall if any, can be met by excess Non-Solar Energy purchased beyond
specified Non-Solar RPO for that particular year:
• The regulations outline the procedures for the procurement of renewable energy by
Distribution Licensees. If these licensees fulfill the minimum purchase obligation and
receive additional offers from renewable energy generators, either the Distribution
Licensee or the Investor/Developer can seek the Commission's approval for such
additional procurement.
• For Captive Users, the Renewable Purchase Obligation (RPO) is specified based on
the commissioning date of the Captive Generating Plants. If the obligated entities
cannot meet the minimum purchase requirements, they are mandated to purchase
Renewable Energy Certificates.
• The Commission may relax the purchase requirement conditions due to Force
Majeure Conditions. The MP Power Management Company Limited is authorized to
procure energy from all renewable sources on behalf of State-owned Distribution
Licensees, and the allocated energy is distributed based on the previous year's actual
energy input. Power Purchase Agreements (PPAs) are to be signed between the
Renewable Energy Generating company/Developer and the MP Power Management
Company Limited, with back-to-back Power Supply Agreements with Distribution
Licensees. The proposed energy purchase for the ensuing year must be indicated by
Distribution Licensees in tariff determination applications.
ii. Procedure for execution of Power Purchase Agreement(s) {PPAs} and Wheeling
Agreement (s) {WAs}:
• The process for renewable energy project integration in Madhya Pradesh involves
several key steps. Firstly, the Renewable Energy Generating company/Developer is
required to present a proposal for power sale to the MP Power Management
Company Limited, including detailed project information as specified in the
applicable regulations. Simultaneously, the company must approach the
Transmission Licensee and Distribution Licensee to facilitate interconnection
studies. If the studies confirm feasibility, permissions are granted within 30 days,
including cost estimates for required extensions.
• Should the stipulated timelines not be met, the applicant has the option to seek
intervention from the Commission. Additionally, the applicant is obliged to submit
technical details of their Generating Stations to the Commission as per the
Electricity Act, 2003.
• The Power Purchase Agreement period will be of minimum 20 years, if not otherwise
specified in the Tariff Orders, from the date of commissioning of plant. However, the
agreement may be for a shorter period in case the Renewable Energy Generating
company/Developer opts to supply to the Distribution Licensees after consuming
the electricity for self-use/ third party sale for lesser period.
• The Renewable Energy Generating company/Developers are required to get all the
required statutory consents before entering into the Agreement. Such consents shall
have validity for the entire period of the Agreement.
• The regulations outline the connectivity and operational aspects for renewable
energy generation in Madhya Pradesh. Generation and Co-generation from
Renewable Sources, excluding Roof-top Solar PV and Bio-gas Sources, are to be
connected to the State Grid at specified voltage levels determined by the Licensee.
For Roof-top Solar PV sources and Biogas Plants, connectivity may be allowed at
Low Voltage or 11/33 kV, based on technical suitability as determined by the
Distribution Licensee.
• The responsibility for power evacuation facility expenses lies with the Renewable
Energy Generating company/Developer. Infrastructure laid, even if funded by the
developer, becomes the property of the concerned Licensee. The Licensee maintains
it at the developer's cost and retains the right to use it for power evacuation from
other Renewable Energy Generating companies/Developers, ensuring existing
arrangements are not adversely affected.
• For Solar and Wind Energy based Generating Plant, forecasting, scheduling,
deviation settlement, energy accounting and settlement shall be done in 15-minute
time-block as per MPERC (Forecasting, Scheduling, Deviation Settlement
Mechanism and related matters of Wind and Solar generating stations) Regulations,
2018, subject to limits specified in the aforesaid Regulations as amended time to
time. For Renewable Energy based Generating Plants other than Wind and Solar,
Forecasting, Scheduling, Deviation Settlement and Energy Accounting shall be done
in 15-minute time-block as per MPERC Balancing and Settlement Code, 2015 and
MP Electricity Grid Code, 2019, as may be applicable and as amended from time to
time.
• Wheeling charges, Cross subsidy surcharge, additional surcharge and such other
charges, as applicable under Section 42 of the Electricity Act, 2003 shall be
applicable at the rate as decided by the Commission from time to time in its Retail
Supply Tariff Order.
Shall mean any person who has contracted demand or sanctioned load of 100 kW or
more or such other limit as may be specified by Commission from time to time with the
Distribution Licensee, except for captive consumers, who are supplied with electricity
from green energy sources for their own use by a Licensee or the Government or by any
other person engaged in the business of supplying electricity to the public under this
Act or any other law for the time being in force and includes any person whose premises
are for the time being connected for the purpose of receiving green energy with the works
of a Licensee, the Government or such person, as the case may be.
Renewable Energy Sources
Shall mean the hydro, wind, solar, biomass, biofuel, biogas, bagasse, waste including
municipal and solid waste, geothermal, tidal, forms of oceanic energy, or combination
thereof, with or without storage and such other sources as may be notified by the
Central Government from time to time
• Transmission charges;
• Wheeling charges;
• Cross subsidy Surcharge;
Provided further that such cross-subsidy surcharge shall not be levied in case
a person is availing green power from the plant established as captive
generation plant for his own use:
Provided also that cross subsidy surcharge shall not be applicable in case Green
Energy Open Access Consumer is availing power from a non-fossil fuel-based Waste-
to-Energy Plant:
Provided also that the cross-subsidy surcharge shall not be applicable if green
energy drawn through green energy open access is utilised for production of green
hydrogen and green ammonia.
• Additional surcharge;
Provided further that the additional surcharge shall not he applicable for Green
Energy Open Access Consumers, if fixed charges are being paid by such a
consumer;
Provided further that such cross-subsidy surcharge shall not be levied in case a
person is availing green power from the plant established as captive generation
plant for his own use:
Provided also that cross subsidy surcharge shall not be applicable in case Green
Energy Open Access Consumer is availing power from a non-fossil fuel-based
Waste-to-Energy Plant:
Provided also that the cross-subsidy surcharge shall not be applicable if green
energy drawn through green energy open access is utilised for production of green
hydrogen and green ammonia.
Provided also that additional surcharge shall not be applicable in case of green
energy is supplied to the Green Energy Open Access Consumer from offshore wind
projects which are commissioned up to December 2025.
a) The Banking Charges shall be adjusted in each month in kind @ 8% of the total
energy banked.
b) The permitted quantum of banked energy in each month by the Green Energy
Open Access consumers shall be at least thirty percent of the total monthly
consumption of electricity from the Distribution Licensee by the Green Energy
Open Access consumers.
c) Banking shall be permitted at least on a monthly basis on payment of banking
charges to the Distribution Licensee.
Provided that the credit for banked energy shall not be permitted to be carried
forward to subsequent banking cycles and shall be adjusted during the same banking
cycle as per the energy injected in the off-peak period and peak period determined
by the Commission in its Retail Supply Tariff order from time to time:
Provided further that, the energy banked during peak period shall be permitted to
be drawn during peak as well as off-peak period in 15minutes time block and the
energy banked during off-peak period shall be permitted to be drawn only during
off-peak period in 15 minutes time block by paying the banking charges:
Provided also that the Licensee shall reconcile the banking charges recovered as
mentioned in clause 10 (d) above at the end of each financial year on the basis of
actual cost of power purchase arranged by the Licensee to return banked energy and
claim additional expenses, if any, through a separate petition along with truing up
petition of Retail Supply Tariff of subsequent financial year.
d) The unutilized surplus banked energy shall be considered as lapsed at the end
of each banking cycle:
Table 16: Open Access Charges as per prevailing Tariff Order by MPERC
Charges/
Particulars Unit Remarks
Loss
Losses
Transmission
% 2.81% MPSLDC
Loss
Transmission
Rs Transmission MYT Order for FY
Charge (RE 17.11
Lakh/MW/Annum 2019-20 to FY 2023-24
above 132 kV)
Additional
Rs/kWh 1.28 Tariff order for FY 23-24
Surcharge
The Banking of energy is entirely
Banking Charges % 8%
at MPPMCL’s discretion.
Absolute Error
Absolute Error in a 15-min. Deviation Charges payable to
in a 15-min.
time block State DSM Pool
time block
8.2 MPERC (F&S, DSM and Related Matters of Wind and Solar Generating Stations)
Regulations, 2018 (Amended 2019)
Eligible Entities
▪ All solar generators, with individual or combined capacity of 5 MW and above,
connected to the grid independently or through pooling station.
▪ All wind generators, of any capacity, connected to the state grid through pooling
stations, with a total capacity of 10 MW and above.
▪ Inter-state power transmission for solar and wind generators having combined
capacity of 1 MW and above.
Table 18: Deviation Charges for Sale of Power within the State
Absolute Error
in a 15-min. Deviation charges payable to State DSM Pool
time block
≤15% None.
>15% but ≤
₹0.50 per unit.
25%
₹0.50 per unit for the shortfall or excess beyond 15% and up to 25%
>25% but ≤35% +
₹1.00 per unit for balance energy beyond 25% and up to 35%.
₹0.50 per unit for the shortfall or excess beyond 15% and up to 25%
+
>35%
₹1.00 per unit for balance energy beyond 25% and up to 35% +
₹1.50 per unit for balance energy beyond 35%.
Payment Mechanism:
Commercial settlement on account of deviations respective to pooling sub-stations to
be settled on a weekly basis.
Metering:
Metering to record parameters in every 15-minute time block. Data telemetry shall be
adopted at the turbine/inverter or plant level as considered appropriate by SLDC.
Green Hydrogen Standards – Indian perspective vis-à-vis International
Green Hydrogen refers to hydrogen gas produced through a process that utilizes
renewable energy sources, such as wind, solar, or hydropower, to electrolyze water
(H2O) into hydrogen (H2) and oxygen (O2). This production method distinguishes green
hydrogen from conventional methods that often rely on fossil fuels, emitting carbon
dioxide in the process.
• In the Union Budget 2021, GoI announced the National Hydrogen Mission in 2021-
22 for making a hydrogen roadmap for the country.
• The National Hydrogen Energy Mission aims to reduce petroleum use, greenhouse
gas emissions, and air pollution, and contribute to more diverse and efficient
energy infrastructure.
• Green Hydrogen Mission is not only essential to decarbonise heavy industries like
steel and cement, it also holds the key to clean electric mobility that doesn’t depend
on rare minerals.
Ministry of New and Renewable Energy (MNRE) has issued an office memorandum on
18 August 2023 clarifying “Green Hydrogen”.
Bureau of Energy Efficiency (BEE), Ministry of Power shall be the Nodal Authority for
accreditation of agencies for the monitoring, verification and certification for Green
Hydrogen production projects.
European Union (EU) has been actively promoting the production and use of green
hydrogen as part of its broader efforts to achieve carbon neutrality and address climate
change. The EU has outlined its vision for a hydrogen strategy, emphasizing the
importance of green hydrogen in a sustainable energy transition.
On 10 February 2023, in line with the requirements of the Renewable Energy directives,
the EU Commission adopted two delegated regulations: one defining rules on renewable
hydrogen production and clarifying the additionality criteria for renewable electricity,
and another setting out a methodology to calculate lifecycle GHG emissions.
Renewable PPA with contracted
asset built within 36 months
before electrolyzer unit + no
Renewable Energy Sources
OPEX or CAPEX subsidy received.
Green 𝐇𝟐
Standard for in same bidding zone (usually
European Geographical correlation: grid-connected country)
Union electrolyzers must prove that RE asset is
located either
in interconnected bidding zone,
including in another Member State,
if day-ahead market price in this
GHG intensity: approx. 3.4 kgCO2e/kgH2 zone is equal or higher
across the full lifecycle of the fuels
International Standard
Parameters Indian Standard (Europe)
Wind, Solar, Biomass, Hydro Renewable Fuels of Non-
Renewable Energy including banked energy like biological origin e.g. Wind,
Sources Energy Storage System / Solar, Hydro etc. excluding
banking with Discom Biomass
No restrictions Not older than 36 months
Eligible Projects /
Vintage / (*No OPEX or CAPEX subsidy
being received)
Additionality
Electrolysis of Water, Electrolysis of Water,
Technologies Conversion of Bio-mass Conversion of Bio-mass
Certification As per States Energy Monthly (allowed until 2029)
timelines / Banking Provisions One Hour period (2030
Temporal onwards)
correlation
Settlement of No Real-time scheduling, No banking allowed, real-time
Energy / Energy banking of energy is allowed adjustment in 15 min time
Banking blocks
GAIL & PTC officials discussed about the usage/purpose of green hydrogen production
by GAIL. It is understood that, the green hydrogen as produced by GAIL, will be used
within the country, therefore, GAIL may strategize its RE power sourcing for its green
hydrogen plant either through intra-state network wherein banking of energy will be
available or through the inter-state network wherein GAIL will have to adjust the energy
on real time basis i.e. 15 mins block.
Options Evaluation for sourcing of Renewable Energy under Open Access
As detailed above, GAIL has various options for sourcing of RE power to meet the power
requirement of its electrolyers. Potentially, GAIL can make its portfolio using
combination of any of the following available alternatives subject to the techno-
commercial viability:
Wind / Solar /
Long Term
Hybrid
60-70%
RE
Power
Wind / Solar /
Medium Term
Hybrid
Green Day
Ahead Market
Biomass /
Hydro / Hybrid
Green Term
Ahead Market
Power
Short Term
Exchange
Daily Contracts
Green Energy
thru Discom
30-40% Long Duration
RE Contracts (3
Power months)
Accordingly, GAIL may strategize the RE power sourcing for its green hydrogen plant
through sustainable long-term solutions which may cater to the power requirement
significantly e.g. around 70-80% of the requirement.
Under this mode, GAIL Vijaipur may explore the possibility of entering into a long-term
agreement with a specific RE supplier for a defined quantity, tariff, and duration. This
agreement could be established directly with the RE Generator or through a trading
licensee, ensuring the supply of Renewable Energy from a designated injection point to
the specified withdrawal point of GAIL Vijaipur.
Renewable Energy Plant can be located in any of the renewable energy rich states like
Madhya Pradesh, Rajasthan or any other western state and connected to CTU. The
generation from the ISTS (CTU) connected projects is required to be scheduled in 15
minutes time block basis for GAIL Vijaipur as per the LTA capacity approved for each
of the plant.
GAIL Vijaipur will have the option to source Renewable Energy, favorably sourced from
wind-solar based RE project with or without storage, with a 75 % Capacity Utilization
Factor (CUF). This procurement can be executed through Inter-State / Intra-State Open
Access wherein the chosen supplier must have the capability to deliver power
continuously on a round-the-clock basis (RTC) to meet the specific requirements of
GAIL Vijaipur's green hydrogen plant, as detailed earlier.
Generally, RE developers provides the RE-RTC solution through oversizing the project
which is usually 2 to 2.5 times the load requirement which also incurred higher capex
cost by them. Under this oversized RE project, developer may sell the surplus
generation post utilizing the open access capacity in the market on day ahead or real
time basis.
Also, as per the present regulatory scenario, ISTS charges proposed to be waived-off for
RE projects commissioned on or before June 2025. Besides this, MPERC Green Energy
Open Access Regulation 2023 states that there will be no Cross Subsidy Surcharge and
Additional Surcharge applicable when green energy obtained through green energy
open access is used for the production of green hydrogen and green ammonia.
Hence, the analysis was carried out for sourcing of RE-RTC power through ISTS
projects. The tentative landed cost for sourcing of RE-RTC shall be as follows:
Table 19: Tentative landed cost for sourcing of RE power through RE-RTC mode under third party
mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 18 18
Estimated Energy at GAIL’s bus on annual basis MUs 110 113
Tariff in ₹/kWh ₹/kWh 4.50 4.50
Impact of OA charges in ₹/kWh ₹/kWh 0.75 0.62
Landed Cost at GAIL’s bus in ₹/kWh ₹/kWh 5.25 5.12
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kWh 7.10 7.10
Savings in ₹/kWh ₹/kWh 1.85 1.98
Approx. Annual Savings ₹ Crs 20.41 22.40
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
10.1.2 Procurement of Wind Solar Hybrid power under third party route
Under this mode of transaction, GAIL Vijaipur may explore sourcing of renewable
energy from a wind solar hybrid project under long term agreement for a specified
quantum, tariff with a specific RE developer supplying Renewable Energy, directly or
through a trading licensee, from a specified point of injection to the specified drawl
point of GAIL Vijaipur.
Unlike wind projects, which gives CUF of around 30-35%, and 20-22% in case of solar
projects, Wind-solar hybrid projects provides the CUF as high as 50-55% on annual
basis. Wind Solar Hybrid project combine the benefits of both wind and solar energy to
enhance overall energy production and reliability. It can achieve higher capacity factors
compared to standalone wind or solar installations. This is because the complementary
nature of the two sources allows for a more consistent utilization of the available
resources.
This transaction can be structured under Inter-State, as well as under Intra-State Open
Access, as the state of Madhya Pradesh enables developers to put-up projects under
hybrid mode. It may also be noted that, MPERC Green Energy Open Access Regulation
2023 states that there will be no Cross Subsidy Surcharge and Additional Surcharge
applicable when green energy obtained through green energy open access is used for
the production of green hydrogen and green ammonia.
Besides this, as per Ministry of New and Renewable Energy vide its OM dated 18 August
2023, the “Green Hydrogen” shall mean Hydrogen produced using renewable energy,
including, but not limited to, production through electrolysis or conversion of biomass.
Renewable energy also includes such electricity generated from renewable sources which
is stored in an energy storage system or banked with the grid in accordance with
applicable regulations.
Hence, the analysis was carried out for sourcing of hybrid power through ISTS or InSTS
projects under third party route. The financial evaluation of the same is as follows::
Table 20: Tentative landed cost for sourcing of RE power through hybrid project under third party
mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 18 18
Estimated Energy at GAIL’s bus on annual basis @ 50%
MUs ~74 ~75
CUF
Tariff in ₹/kWh ₹/kW 4.20 4.20
h
Impact of OA charges in ₹/kWh ₹/kW 0.88 0.77
h
Landed Cost at GAIL’s bus in ₹/kWh ₹/kW 5.08 4.97
h
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kW 7.10 7.10
h
Savings in ₹/kWh ₹/kW 2.03 2.13
h
Approx. Annual Savings ₹ Crs 14.92 16.05
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
10.1.3 Procurement of Wind Solar Hybrid power under 100% own captive mode
Establishing a RE Captive Power Plant is generally beneficial for a state where Cross
subsidy and Additional Surcharge are notably high and applicable under third party
mode / power exchanges. By doing so, the organization can reap numerous benefits
like exemption from payment of cross subsidy and additional surcharge. It may be noted
that the present rate of Cross Subsidy and Additional Surcharge in the state of Madhya
Pradesh is Rs. ₹1.36/kWh and ₹1.28/kWh respectively which are comparatively higher
than the other states.
However, these charges i.e. Cross Subsidy and Additional Surcharge are already
waived-off by MPERC for consumers procuring green energy for the production of green
hydrogen and green ammonia, in line with MPERC Green Energy Open Access
Regulation 2023.
Given that exemptions such as Cross Subsidy and Additional Surcharge have already
been waived by MPERC for green hydrogen, it is not viable for GAIL, Vijaipur, to procure
power through the captive route, as it would entail additional capital expenditure.
Accordingly, GAIL may leverage the features of the short-term market to make strategic
decisions that align with their cost-saving objectives while catering to the balance or
contingent power requirement of its green hydrogen plant. The same could be done
using any of the following mechanism based on the market prevailing conditions.
As mentioned above, GAIL may strategize its RE sourcing through a sustainable long-
term solution like RE-RTC or Hybrid for meeting the 70-80% or 100% of its power
requirement through long-term contracts. However, given the fact that renewable
energy is intermittent in nature, there might be the scenarios when the generation is
not adequate and GAIL might have to source the balance power through short-term
market.
As per MPERC rules and regulations, GAIL will have the option to source renewable
power through sources like wind/solar/hybrid under short-term open access. Several
developers are offering renewable power based on the surplus power available with their
existing assets. GAIL may enter into an agreement with these developers for meeting
the gaps/shortfall of the energy, if any.
Besides this, GAIL may also explore sourcing of renewable energy from renewable
sources like bagasse and hydro which are the valuable source of renewable energy in
India, particularly for procurers in the agricultural and industrial sectors. Renewable
energy sources, including bagasse-based power and hydropower, offer significant
benefits for procurers in India, contributing to sustainability, energy security, and cost-
effectiveness.
Table 21: Tentative landed cost for sourcing of Hybrid RE power under third party mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 5 5
Estimated Energy at GAIL’s bus on annual basis @ 50%
MUs ~20 ~21
CUF
Tariff in ₹/kWh ₹/kW 4.40 4.40
h
Impact of OA charges in ₹/kWh ₹/kW 0.92 0.69
h
Landed Cost at GAIL’s bus in ₹/kWh ₹/kW 5.32 5.09
h
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kW 7.10 7.10
h
Savings in ₹/kWh ₹/kW 1.78 2.01
h
Approx. Annual Savings ₹ Crs 3.65 4.29
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
Table 22: Tentative landed cost for sourcing of Bagasse RE power under third party mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 5 5
Estimated Energy at GAIL’s bus on annual basis @
MUs ~41 ~43
100% CUF
Tariff in ₹/kWh ₹/kW 4.55 4.55
h
Impact of OA charges in ₹/kWh ₹/kW 0.70 0.49
h
Landed Cost at GAIL’s bus in ₹/kWh ₹/kW 5.25 5.04
h
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kW 7.10 7.10
h
Savings in ₹/kWh ₹/kW 1.85 2.07
h
Approx. Annual Savings ₹ Crs 7.58 8.81
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED.
Power exchanges in India play a crucial role in optimizing costs and enhancing
efficiency in the energy sector. By providing a transparent platform for price discovery
through market forces, power exchanges promote competition, encouraging innovation
and driving down costs.
7 120
6.25
6 4.28
5.85 100
4.29 4.11
5 4.28 3.53 3.59
4.51 80
4 4.69
4.26 3.72
3.47 60
3 3.50 3.45
3.23
2.90 2.98 40
2 2.72
2.50
1 20
0 0
FY-14 FY-15 FY-16 FY-17 FY-18 FY-19 FY-20 FY-21 FY-22 FY-23
GAIL Vijaipur has been optimizing its power procurement costs through sourcing power
from the exchanges as and when required depending upon the prevailing market
conditions.
Since the short term market has been evolving, GAIL may also devise its power portfolio
in such a way that any shortfall or gaps in meeting the power requirement for its
electrolyser could be compensated from the power exchanges. A tentative landed cost
for sourcing of RE power through power exchanges shall be as follows:
Table 23: Tentative landed cost for sourcing of RE power through PX
Particulars Unit ISTS
Open Access Capacity MW 5
Estimated Energy at GAIL’s bus on annual basis MUs ~41
Tariff in ₹/kWh ₹/kWh 4.50
Impact of OA charges in ₹/kWh ₹/kWh 1.47
Landed Cost at GAIL’s bus in ₹/kWh ₹/kWh 5.97
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kWh 7.10
Savings in ₹/kWh ₹/kWh 1.14
Approx. Annual Savings ₹ Crs 4.65
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
Recently, Green Tariffs have been emerged as another option for consumers for
sourcing of power through renewable sources wherein incumbent Discoms are offering
the renewable power at a tariff (Green Tariff) approved by the commission.
Green Tariffs are specialized pricing mechanisms that enable Discoms to purchase
electricity exclusively from renewable sources, such as solar, wind, or hydroelectric
power, thereby encouraging the growth of clean energy infrastructure. By opting for
Green Tariffs, Discoms not only contribute to environmental conservation but also
promote the integration of renewable resources into the mainstream energy grid.
It may be noted that, this mechanism is in the nascent stages and is yet to be widely
accepted by the consumers because of the reason that Green Tariff as approved by the
commission is only over and above their existing energy charges. It means, if a
consumer opting for a Green Tariff from the Discom, then they have to pay the Green
Tariff and the existing grid tariff for each of the units consumed under green energy
from the Discom.
The tentative cost implication for procurement of green power through incumbent
Discom under ‘Green Tariff’ mechanism is as follows:
1. Transmission Charge
2. Wheeling Charge
3. Cross Subsidy Surcharge
4. Additional Surcharge
5. Banking Charge
6. Any other charges as specified by the state regulator
Establishing a RE Captive Power Plant is generally beneficial for a state where Cross
subsidy and Additional Surcharge are notably high and applicable under third party
mode / power exchanges. By doing so, the organization can reap numerous benefits
like exemption from payment of cross subsidy and additional surcharge. It may be noted
that the present rate of Cross Subsidy and Additional Surcharge in the state of Madhya
Pradesh is Rs. ₹1.36/kWh and ₹1.28/kWh respectively which are comparatively higher
than the other states.
However, these charges i.e. Cross Subsidy and Additional Surcharge are already
waived-off by MPERC for consumers procuring green energy for the production of green
hydrogen and green ammonia, in line with MPERC Green Energy Open Access
Regulation 2023.
Considering that the waivers like Cross Subsidy and Additional Surcharge are already
waived-off by MPERC for green hydrogen, therefore, GAIL, Vijaipur may structure its
RE power sourcing under long term arrangement through third party mode.
Risk Associated in Transactions and Risk Mitigation Strategies
This section deals with assessment of various identified business risks and associated
mitigation measures while exploring options under procurement of power through open
access. Various business risks that have been identified, with respect to sourcing of
renewable power, are listed below:
Generation
Economics
Legal &
Change in
regulatory
Regulations
issues
Probable Risks
Verification,
Monitoring Supply/ pay
& or take
Accounting
Exemption of
waivers /
banking
under ISTS
transactions
Based upon the risk type and its severity, risk responses have been prepared for various
identified risks in the subsequent sub-section. Following three types of risk responses
have been proposed:
For mitigating the risks related to change in Incumbent Discom's Energy Charge
and/or any other Retail Tariff Component and/or any other OA Charge, we
propose ‘Treat/ Manage the Risk’, wherein following measures have been
proposed.
a. The tariff, for supplying power under (bilateral or group captive mode), be the
tariff at BUS bar of GAIL Vijaipur all applicable charges and losses, including
the open access charges, transmission and/ or distribution network charges &
losses, banking charges, scheduling & operation charges, application fees, etc.
shall be to the account of the consumer;
b. Provisions corresponding to revision in Tariff shall may be incorporated under
which Tariff shall be revised in such a manner that, the impact of change in any
above said charge will be shared equally between the Generator and the
consumer; subject to a maximum percentage to be defined in the agreement
c. In case, with the revised Tariff (after change), supply of power is not
economically viable for GAIL Vijaipur, then in such condition renegotiating the
Tariff/ PPA conditions, on mutual agreement basis, within a pre-defined period;
We have proposed some measures under ‘Treat/ Manage the Risk’ and ‘Terminate the
Risk’.
a. Treat/ Manage the Risk:
Settlement of issue: Such issues, if they are uncontrollable in nature, could be
settled between GAIL Vijaipur and the Generator. Settlement is proposed only
in conditions, which are agreeable to GAIL Vijaipur.
b. Downward measures:
Appropriate band may be kept as a downward relaxation measure for GAIL
Vijaipur with a corresponding minimum generation & consumption guarantee
of 8% on monthly basis. Any scheduling of less 80% by either GAIL Vijaipur/
consumer shall attract the compensation charges.
Waivers / incentives like open access charges / banking under ISTS transactions
For availing renewable energy under Intra-State Open Access, consumers are entitled
to receive the benefits/waivers/incentives provided by state regulators for projects set-
up within the state. However, it has been generally observed that these
waivers/incentives are uncertain in some cases if a consumer source renewable energy
from the projects located outside of the state through inter-state open access.
For mitigating the risks related to VMA, producers can take a few steps like
pursue the matter with concerned authorities and these authorities may be
pushed for clear and consistent rules that everyone can follow.
It may also be noted that, MNRE vide its OM dated 18 Aug 2023 has nominated
BEE as the Nodal agency for monitoring, verification and certification of green
hydrogen projects.
Change in OA Regulations
There might be event (s) related to change or issuance of certain regulations related to
open access, such as mandatory surrender of contract demand up to the quantum
contracted under open access, removal/ restriction of banking, etc., which could lead
to situations creating OA transaction unviable/ unprofitable for either GAIL Vijaipur or
Consumers.
For mitigating the risks related to change/ issuance of OA related regulations creating
OA transaction unviable/ unprofitable for GAIL Vijaipur / consumers, we propose
‘Treat/ Manage the Risk’, wherein following measures have been proposed.
a. Appropriate clauses to safeguard GAIL Vijaipur interest will be
incorporated in the Power Purchase Agreement;
b. Provisions like renegotiating the Tariff/ PPA conditions, on mutual
agreement basis, within a pre-defined period from the date of notification
of such change/ issuance of OA regulations;
c. If renegotiation is not possible/ agreeable, then it would lead termination
of contract without any liability to either party.
Recommendation
After analysing the requirement of GAIL Vijaipur, policy & options available in the state,
the plan for sourcing renewable energy for electrolyser is recommended to be structured
under the following business cases in the order of priority:
a. Sourcing of RE-RTC power - The tentative landed cost for sourcing of RE-RTC shall
be as follows:
b. Procurement of Wind Solar Hybrid power - The tentative landed cost for sourcing
of RE-RTC shall be as follows:
Table 24: Tentative landed cost for sourcing of RE power through hybrid project under third party
mode
Particulars Unit ISTS InSTS
Open Access Capacity MW 18 18
Estimated Energy at GAIL’s bus on annual basis @ 50%
MUs ~74 ~75
CUF
Tariff in ₹/kWh ₹/kW 4.20 4.20
h
Impact of OA charges in ₹/kWh ₹/kW 0.88 0.77
h
Landed Cost at GAIL’s bus in ₹/kWh ₹/kW 5.08 4.97
h
Tentative Green Tariff through MPMKVVCL in ₹/kWh ₹/kW 7.10 7.10
h
Savings in ₹/kWh ₹/kW 2.03 2.13
h
Approx. Annual Savings ₹ Crs 14.92 16.05
Note: Green Tariff through MPMKVVCL is inclusive of Green Tariff of ₹0.97.kWh & variable charges
of ₹6.13/kWh only, and exclusive of fixed charges like Demand Charges & ED
II. Sourcing of Renewable Energy under short term - for meeting the power requirement
of up to 20-30% requirement
As studied earlier, GAIL may leverage the opportunity of the short-term market for
catering to balance or contingent power requirement of its green hydrogen plant while
realizing the benefit of the lower cost power. GAIL will always have the option to source
renewable power through sources like wind/solar/hybrid under short-term open
access.
Besides this, GAIL may also explore sourcing of renewable energy from renewable
sources like bagasse and hydro which are the valuable source of renewable energy in
India, particularly for procurers in the agricultural and industrial sectors. Renewable
energy sources, including bagasse-based power and hydropower, offer significant
benefits for procurers in India, contributing to sustainability, energy security, and cost-
effectiveness.
GAIL may enter into an agreement under short-term arrangement with RE developers
for meeting the deficits/shortfall of the energy, if any. The tentative savings under these
short-term arrangements ranges between ₹3.65 Crores/annum to ₹8.81
Crores/annum. However, the actual savings will be based upon the prevailing market
conditions at the time of procurement of power.