Professional Documents
Culture Documents
For SAIL CFP - 29.01.2024
For SAIL CFP - 29.01.2024
Particulars Values
CD (MVA) 55 Management of operational & commercial matters
Tentative Daily Requirement (MUs) ~1.1 •Filing of Open Access application, scheduling & Operations
•Billing, Payment, energy reconciliation
Avg. Monthly Requirement (MUs) 32.71 •Compensation, Rebate, Refund etc.
Yearly Requirement (MUs) 392.56
3
Indian Power Market
4
Installed Capacity (GW) - India
Nuclear, 7.5, 2%
Thermal, 240.0, 56%
Wind, 44.7, 10%
Solar, 73.3, 17%
1800
Installed Capacity (GW) Generation (BUs) 1624
1600 1492
428 1376 1389 1382
450
382 399 416 1400 1242
1308 1264
400 356 370 1110
1173
327 344 1200
350 305 928 969 1026
275 1000 852
300 249
223
250 800
200 161
136 600
150
400
100
50 200
0 0
Since FY14, installed RE generation capacity grew at more than 8.3% CAGR
Power generation from renewable energy sources stood at 204 BUs during FY23, which is ~22% of total energy generation 6
The country plans to increase 500 GW of installed renewable energy capacity by 2030, with 50% of requirement to be met from RE sources
Renewable Energy – Probable Options for C&I
consumers
7
Concept of Open Access
“Open access” is a cornerstone of the Electricity Act 2003 which is bringing competition in the distribution sector 8
Inter-State Transaction (RJ – MH) – Third Party
₹ 7.44/kWh at
SAIL-CFP
RE-RTC STU facility
CTU
Generator
CTU Charges
– ₹ 0.56/kWh* STU Charges – ₹ 1/kWh
*As per MOP orders dated 23 Nov & 30 Nov Cross Subsidy – ₹ 1.69/kWh
2021, CTU charges are proposed to be waived-off State Additional Surcharge – Nil
for the electricity generated from Solar or wind Central 9
source based Project
Periphery
Periphery
Setting-up Captive Power Plant
▸ Under Group Captive (GC) mechanism, power is purchased in a similar process like
Group Captive Power Plant
bilateral contract
▸ Emerged as a feasible and viable option Association of persons/ entities
▸ This is a feasible option in states where cross subsidy charges are very high
o Consumers of group captive power need not pay cross-subsidy charges as they are Min. 26 % equity in the plant and
exempted for a captive power plant under section 42 of the Electricity Act, 2003 consume more than 51% power
o Sale of power at mutually agreed price
o Open access charges as applicable
Variation of +10% is acceptable for
▸ Recently, with the first amendment in Electricity Rules, 2003, any subsidiaries consumption of power
companies can now consume power from RE Project set-up by their parent company
without infusing any equity, which otherwise have required to certify it as captive
transaction
MoP on 11.04.2023, designated Central Electricity Authority (CEA) as Verification Authority for certifying inter-state captive
transactions
CEA is in the process of establishing procedure/mechanism for certifying such captive transactions 10
Inter-State Transaction (RJ – MH) – Captive
₹ 5.76 / kWh at
SAIL-CFP
RE-RTC STU facility
CTU
Generator
CTU Charges
– ₹ 0.56/kWh* STU Charges – ₹ 1/kWh
*As per MOP orders dated 23 Nov & 30 Nov Cross Subsidy – Nil
2021, CTU charges are proposed to be waived-off State Additional Surcharge – Nil
for the electricity generated from Solar or wind Central 11
source based Project
Periphery
Periphery
Initiatives & diverse Regulations for
Renewable Energy
12
MOP’s Green Energy Open Access Rules 2022
MoP, in June 2022, notified Green Open Access Rules, 2022 with
an objective to include every consumer to contribute in achieving
India’s commitment of 500 GW by 2030.
Reduced OA capacity to 100KW from 1 MW
Cap on increasing of cross-subsidy surcharge as well as the
removal of additional surcharge
Banking of surplus green energy mandated
Green Hydrogen/Green Ammonia included for fulfilment of
its RPO
13
Diverse RE Regulations across the states
Transmission charges
Applicability of Transmission Charges at twice of the normal rate on actual
are applicable at Transmission charges at full rate
Transmission Charges flow of energy.
booked capacity
Treatment of surplus Surplus energy will May be entitled for RECs for Surplus energy will lapse. RE Generator will get RECs
energy lapse such energy remain unutilized equivalent to the lapsed banked energy
1. Electricity is concurrent subject in India, every state has their own policies/regulations for RE power
2. Above-mentioned waivers are mostly applicable/provided in case of intra-state transactions on Renewable Energy 14
3. As per Electricity Rules 2005, Cross Subsidy and Additional Surcharge are not applicable on captive transaction
Policy Landscape - Maharashtra
15
Installed Capacity (GW) – Maharashtra
18
Probable solutions for sourcing RE
power
19
Probable options for SAIL-CFP
RE
Sourcing
ISTS InSTS
(CTU) (STU)
On- Off-
site site
Group Captive Third party Third Party Group Captive
(Min 26% of equity) (No Equity) (No Equity) (Min 26% of equity)
REC V-
Hybrid s Hybrid
PPA Wind Solar Wind/Solar
RE-RTC around 50% RE-RTC around 50% around 30% around 20%
20-30% CUF
CUF CUF CUF CUF
1. Charges like CSS (₹1.69/kWh) will be applicable in case of sourcing of renewable energy under third party mode by SAIL-CFP
2. As per Electricity Act’03, captive transactions provides waivers for Cross Subsidy Surcharge (CSS) & Additional Surcharge (AS)
3. Considering that load of CFP is constant (~40-50 MW), it may source RE power through ISTS network without banking, under captive mode
20
4. Presently, developers are offering RE-RTC solution through oversizing the project capacity wherein >70%CUF/annum is being assured
Recommendations & Way
Forward
21
Recommended options for SAIL-CFP
Landed Cost
RE Developer SAIL to infuse min
26% of equity in Description RE-RTC
developer’s RE Project
to make it a captive
Open Access Capacity in MW 46
transaction
RE-RTC Plant Energy at Consumer’s bus in MUs/Annum 376
74%
equity Tariff in ₹/kWh 4.20
by RE
Seller 26%Equity infusion ISTS Charges in ₹ Crs. Nil
STU Charges in ₹ Crs. 17.28
RE consumption
CSS & AS in ₹ Crs. Nil
Impact of Demand Charges in ₹ Crs. 30.08
Landed Cost in ₹/kWh 5.76
Tentative Discom Grid Cost in ₹/kWh 7.70
Savings in ₹/kWh 1.94
Anticipated Annual Saving in ₹ Crores/Annum 73
Balance energy through grid as conventional Energy
Incumbent Discom
23
Return
Option 1 - Inter-state under group captive (min 26% equity)
Project Financials
Salient Features
requirement which also requires higher
equity infusion
Tariff ₹ 4.20/kWh
Equity ₹ 1260 Crs • Tariff in the range of ₹4.20 – 4.60 per unit
Anticipated
per unit ₹ 1.94/kWh • 15-25 years of PPA duration
Savings
26% of • CEA has already been designated as
Equity by ₹ ~328 Crs Verification Authority for certifying inter-
Annual
₹ 73 Crs CFP state captive transaction
Savings
24
Return
Option 2 - Intra-state under group captive (min 26% equity)
Landed Cost
RE Developer SAIL to infuse min 26%
of equity in developer’s Solar Wind
RE Project to make it a Description
(~20% CUF) (~30% CUF)
captive transaction
Open Access Capacity in MW 77 77
74% Wind/Solar Plant Energy at Consumer’s bus in
equity 120 180
by RE
MUs/Annum
Seller 26%Equity infusion Tariff in ₹/kWh 4.10 4.20
ISTS Charges in ₹ Crs. Nil Nil
RE consumption STU Charges in ₹ Crs. 13.49 20.24
CSS & AS in ₹ Crs. Nil Nil
Impact of Demand Charges in ₹ Crs. 9.61 14.42
Landed Cost in ₹/kWh 6.53 6.64
Tentative Discom Grid Cost in ₹/kWh 7.70 7.70
Savings in ₹/kWh 1.17 1.06
Anticipated Annual Saving in ₹
14.04 19.07
Balance energy through grid as conventional Energy Crores/Annum
Incumbent Discom
25
Return
Option 2 - Intra-state under group captive (min 26% equity)
Project Financials
Salient Features
may offer wind power
Tariff ₹ 4.20/kWh
• Energy replacement through solar
Savings
Capex ₹ 724 Crs is limited to 31%, whereas the
Landed Cost ₹ 6.64/kWh same is 46% in case of wind. This
is limited due to capacity
Debt ₹ 507 Crs restriction (i.e. 140% of contract
MSEDCL Cost ₹ 7.70/kWh demand);
SAIL to develop
the project • 100% own captive project will
give high returns
Salient Features
100% • Energy replacement through
equity by
SAIL
wind is limited to 55% due to
capacity restriction (i.e. 140%
of contract demand);
RE consumption
• Generation Tariff in the range
SAIL-CFP of ₹3.25 – 3.40 per unit
Project Financials
Energy at CFP
214 MUs
bus
Project Size 77 MW Wind
Generation
Savings
₹ 3.25/kWh
Tariff
Capex reduce by Capex increase by CUF Increase by Capex reduce by 10% &
Parameters Base Case
10% 10% 1% CUF Increase by 1%
Project IRR (Post Tax ) 18% 20% 17% 20% 22%
Equity IRR ( Post Tax) 48% 58% 41% 54% 64%
SAIL's Overall Saving (in Rs. Cr) 62 69 56 73 79
Net Present Value (in Rs. Cr) 501 553 449 574 626 28
LCOE for 25 Yrs Rs./kWh 3.25 3.00 3.50 3.03 2.79
CTU or STU Connected Project ???
Waiver of CTU charges if project commissioned on or before No operational projects in ISTS for C&I consumers under LTA
June 2025
Annual savings of around INR 60 - 73 Crs under captive route Will require higher equity infusion as project capacity would
be around 2.5 times
- Solar/Wind Power
- Ex-Bus Tariff Mode (₹4.10 – 4.30 per unit)
- More than 10 years of Lock-in period
- Captive / Third Party
- COD: 9-`12 months from PPA signing
- Wind / Solar
- Ex-Bus Tariff Mode (₹4.20 – 4.40 per unit)
- Minimum 10-25 years of Lock-in period
- Captive
- COD: `12 months from PPA signing
- Solar Power
- Ex-Bus Tariff Mode (₹4.10 – 4.20 per unit)
- Minimum 15 years of Lock-in period
30
- Captive Party
- COD: 9-`12 months from PPA signing
Way Forward
Considering the high Cross Subsidy and Additional Surcharge in Maharashtra, it is felt that, captive/group captive is the most
viable option for SAIL-CFP.
The higher energy generation in ISTS connected RE-RTC power provides the highest savings for SAIL-CFP. However, it would
also require higher equity infusion (~₹320-340 Crs for 300 MW project) from SAIL-CFP.
Under Intra-state captive/group captive mode, the savings are ~₹ 14 to 19 Crs per annum for around 75-80 MW Solar/Wind
project. This would require equity infusion of around ₹ 55-60 Crs for the said project.
PTC/SAIL may also consider conducting the meetings with the prospective bidders before issuance of the RFP
PTC/SAIL may also seek budgetary offers from the prospective bidders for supply of RE power
PTC shall prepare the RFP/tender documents for the option selected by SAIL-CFP regarding sourcing of RE power
31
Thank You
Evolution of the Indian Power Market
34
Options to purchase under Open Access - details
Suitable for Longer duration procurements Longer duration procurements Short-duration procurements
Market price
No No Yes
fluctuations
Payment to seller Seller may provide credit Seller may provide credit Upfront before contract
1800 800
1600 694 700
1400 600
1200
500
No. of projects
1000
400
MW
800 374
300
600
400 200
124 100
200 92
0 0
11-13 14-16 17-19 20-22
FY
Wind Solar No. of projects
36
Source- MEDA
MERC RPO Regulations 2019
22 11.5% 6% 17.5%
23 11.5% 8% 19.5%
37
Renewable Energy Key Regulations – Maharashtra
Banking
“Banking of energy shall be permitted only on monthly basis. Provided that the credit for banked energy shall
not be permitted to be carried forward to subsequent months and the credit for energy banked during the month
shall be adjusted during the same month as per the energy injected in the respective Time of Day (‘TOD’) slots
determined by the Commission in its Orders determining the Tariffs of the Distribution Licensees;”
Provided further that the energy banked during peak TOD slots may also be drawn during off-peak TOD slots,
but the energy banked during off-peak TOD slots may not be drawn during peak TOD slots.
Additional Surcharge
…Provided also that additional surcharge shall not be applicable for Green Energy Open Access consumers, if
fixed charges are being paid by such consumer…
38
Renewable Energy Key Regulations – Maharashtra
Maharashtra GR 30.06.2022
Electricity Duty
Electricity duty for ten years is exempted from date of implementation of wind, solar,
WTE captive projects
39
Options to purchase power under Open Access
Renewable Energy
Captive arrangement
Captive / Group
Open Access Bilateral Power Exchange
Captive
SAIL-CFP can make its portfolio using combination of any available alternatives 40
Key RE Developers
436
Details of other RE developers in
375
363
328
commissioned 2021
Capacity in MW
239
137
136
126
Quantum (MW) 2388 1454
100
82
No. of projects 973 123