Project : NTI SHELL SALEMBA-1 JAKARTA PUSAT Date of Daily 14-Feb-21

Client : SHELL INDONESIA Day SUNDAY


Contractor : PT. USAHA JAYA ENGINEERING Type of Work CONSTRUCTION

A. Working Conditions
Working Hours Weather Conditions Manpower REMARKS
Start Stop Over-Time Morning Afternoon Evening 1
7:00:00 AM 18:00 PM SUNNY RAIN SUNNY PERSONS

B. Description of Work and Manpower

PERAPIHAN BONGKARANG PEKERJAAN INGRESS & PERAPIHAN BONGKARANG PEKERJAAN INGRESS &
INSTALL FLAG POLES
EGRESS EGRESS
C. List of Equipment and Tools
- MANUAL TOOLS

D. Encountered Problems
-
-
-
-

E. Planning for Next Day : 15-Feb-21


- LANDSCAPE WORK
- HOUSEKEEPING
- FUELING SYSTEM BY API

Reported By : Reviewed By :
PT. USAHA JAYA ENGINEERING MEINHARDT

AGUNG PRIAMBODO