Daily Report Nti Shell Salemba 11 Februari 2021

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project : NTI SHELL SALEMBA-1 JAKARTA PUSAT Date of Daily 11-Feb-21

Client : SHELL INDONESIA Day THURSDAY


Contractor : PT. USAHA JAYA ENGINEERING Type of Work CONSTRUCTION

A. Working Conditions
Working Hours Weather Conditions Manpower REMARKS
Start Stop Over-Time Morning Afternoon Evening 5
7:00:00 AM 18:00 PM SUNNY SUNNY SUNNY PERSONS

B. Description of Work and Manpower

CONCRETING EGRESS ACCESS CONCRETING EGRESS ACCESS CONCRETING EGRESS ACCESS

C. List of Equipment and Tools


- MANUAL TOOLS

D. Encountered Problems
-
-
-
-

E. Planning for Next Day : 12-Feb-21


- LANDSCAPE WORK
- HOUSEKEEPING
- PENGERJAAN MOTIF PEDESTRIAN AKSES MASUK & KELUAR

Reported By : Reviewed By :
PT. USAHA JAYA ENGINEERING MEINHARDT

AGUNG PRIAMBODO

You might also like