SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 4/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
8.10. Squareness 24
9. NON-DESTRUCTIVE INSPECTION 25
9.1. General 25
9.8. Radiography 29
9.10. Magnetism 30
10.1. General 30
10.2. Dents 31
10.4. Defects 31
10.8. Rejection 32
11.1. General 33
11.2. Marking 33
11.3. Coating 34
13.1. General 35
13.3. Transport 35
13.4. Protection 36
14.1. General 36
14.6. Verification 38
APPENDIX A 41
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 6/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
APPENDIX B 44
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 7/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
1. INTRODUCTION
This Specification defines the minimum technical requirements for the fabrication,
coating and transport of high quality high frequency electric resistance welded line pipe
for use in the Export/Import gas pipeline for the Sincrudos de Oriente C.A. (SINCOR
C.A.) Upstream Surface Facilities between the Main Station and the SINCOR facilities
at Petrozuata station, for the diluted crude oil gathering system and for the diluent
distribution system located between well clusters and Main Station . In the case of any
detail which is not fully addressed, it shall be warranted by MANUFACTURER that
GOODS have been produced in accordance with the COMPANY's Specification and
the best recognized practices in the line pipe manufacturing industry.
Line pipe purchased to this Specification will be used for diluted crude oil with high
natural gas content and naphtha and shall comply with the requirements of the latest
editions of The American Society of Mechanical Code for Pressure Piping, ASME
B31.4 Liquid Transportation Systems for Hydrocarbons, Liquid Petroleum Gas,
Anhydrous Ammonia, and Alcohols, and ASME B31.8 Gas Transmission and
Distribution Piping Systems , and American Petroleum Institute Standard 5L,
Specification for Line Pipe, 41st Edition, April, 1995 except as modified by the
requirements set forth herein.
MANUFACTURER 's steel manufacturing and pipe mill facilities shall be approved by
the COMPANY. All line pipe shall be manufactured in an API certified mill and shall
contain the API monogram.
GOODS produced in accordance with this Specification shall strictly comply with the
requirements set forth herein. Deviations from the requirements shall only be allowed if
this Specification is revised and reissued to MANUFACTURER or if COMPANY has
approved a Concession Request in accordance with COMPANY requirements. It is the
MANUFACTURER 's responsibility to request concessions for any potentially
acceptable nonconformities identified during the provision of GOODS. COMPANY
approval of MANUFACTURER procedures and manufacturing processes shall not
relieve MANUFACTURER from the obligation to provide GOODS in accordance with
this Specification.
The line pipe surface shall be free from slivers, oil, grease and other contaminants that
may interfere with the application and integrity of external corrosion protection coating.
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 8/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
2. DEFINITIONS
Definitions of terminology used throughout this specification are in accordance with and
referenced elsewhere in the Contract documents.
Where conflict occurs between the requirements of this Specification and referenced
Codes and Standards, the conditions of this Specification shall apply. The
COMPANY‘s decision shall be final.
4. PROCESS OF MANUFACTURE
At initial production start up and after production halt periods, a pipe length will
be selected from the first pipe lengths off the mill, and will be designated Joint
A1. Joint A1 will be used for all qualification testing and inspections required by
Appendix B.
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 10/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
Failure of any of the qualification tests shall be cause for rejection of the
Manufacturing Procedure Specification and all pipe lengths produced to it.
COMPANY reserves the right to require requalification in the case of any
changes to the COMPANY approved Manufacturing Procedure Specification or
interruption in the production of line pipe. All qualification testing shall be
completed within five working days after commencement of production or
subsequent restart of production after an interruption of production.
The steel shall be made by either the basic oxygen or the electric arc furnace
process and shall be desulphurized and dephosphorized if necessary to meet
the requirement of this Specification.
The steel shall be fully killed and fine grained (grain size 9 or finer per ASTM
E112). Should vacuum de-gassing be required to meet the requirements of this
Specification, the process details shall be included in the Manufacturing
Procedure Specification.
All slabs shall be made by the continuous casting process. Information shall be
supplied to the COMPANY covering methods of avoiding center line
segregation. Macros of the slab cross section taken at a frequency given in the
manufacturing procedure specifications shall be made available to the
COMPANY.
All surfaces of the slab shall be inspected for defects and the ends of the slab
shall be cut as necessary to remove injurious defects. After hot scarfing, the
slab shall be inspected for imperfections and, if necessary, shall be rescarfed to
comply with the mill standard. Final scarfed areas shall be checked with
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 11/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
magnetic particle or dye penetrant after scarfing. The extent of scarfing shall be
agreed upon by COMPANY and described in the Manufacturing Procedure
Specification.
A well established and documented rolling particle shall be used and the mill
shall be adequately instrumented to ensure proper control of rolling
temperatures, rolling reduction, post rolling cooling rate and cooling
temperature, and hence consistency in the mechanical properties of the product.
Details of strip heat treatment shall be submitted to the COMPANY for approval
as part of the manufacturing procedure specification (see Appendix A).
The line pipe shall contain one straight seam, welded utilizing high frequency
electric resistance or induction methods. The minimum frequency for welding
shall be greater than 150 khz. The welding procedure shall be submitted for
review and/or approval by COMPANY as part of the Manufacturing Procedure
Specification. If MANUFACTURER intents to use any other welding process for
line pipe manufacturing shall propose it to COMPANY for Approval. All welding
procedures and operators shall be qualified in accordance with the requirements
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 12/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
of API 5L and ASME IX. All qualifications shall be subject to COMPANY review
and/or approval.
An area of pipe which includes the full thickness of the weld seam and heat
affected zone shall be given a heat treatment by annealing after welding. The
longitudinal weld seam shall be heat treated by a Normalizing process in the
AC3 temperature region using a narrow indicated head. The width of the heat
treated shall be a minimum of 10 mm on each side of the weld line at the inner
pipe surface, as determined by a visual macro etch. Full details of heat
treatment temperatures and times, heated band widths (internal and external)
and cooling rates, shall be submitted to the COMPANY for review and/or
approval as part of the manufacturing procedure specification (see Appendix A).
MANUFACTURER shall install a paint marking system located at and tied back
to a pyrometer which shall measure the ERW weld temperature as the pipe
leaves the heat treatment coils. Pipe which is heat-treated outside aim
temperature ranges specified in the Manufacturing Procedure Specification,
shall be paint sprayed along its length until the correct temperature is restored.
Pipe which has been incorrectly heat-treated shall be scrapped.
The MANUFACTURER shall operate a pipe tracking system which ensure full
traceability of each individual pipe to its particular heat number, slab and
strip/coil number and to records of all stages of the manufacturing process. The
MANUFACTURER shall submit full details of the pipe tracking system for
approval by COMPANY.
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 13/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
5.1. Composition
Product Analysis
Element Maximum Percentages
Carbon C 0.16
Manganese Mn 1.50
Silicon Si 0.30
Phosphorous P 0.020
Sulphur S 0.010
Aluminum (Total) (5) Al 0.060
Nitrogen N 0.009
Nickel (3) Ni 0.30
Chromium (3) Cr 0.20
Copper (3) Cu 0.35
Niobium (3) Nb 0.06
Vanadium (3) V 0.06
Titanium (3) Ti 0.02
Molybdenum (3) Mo 0.10
Boron (4) B 0.0005
Tin Sn 0.015
Carbon Equiv. (1) Pcm 0.22
Carbon Equiv. (2) CE 0.38
NOTES:
Si Mn + Cu + Cr Ni Mo V
Pcm = C + + + + + + 5B
30 20 60 15 10
Mn Cr + Mo + V Ni + Cu
CE = C + + +
6 5 15
3. Alloying elements:
• When Ti is added the max Ti/N ratio shall be in accordance with the
limits specified in the Manufacturing Procedure Specification, but in
any event should not be greater than 3:1;
MANUFACTURER shall furnish the ladle analysis for each heat of steel. The
heat analysis shall meet the limits for chemistry agreed in the Manufacturing
Procedure Specification.
pipe lengths from a heat. The elements and residuals listed in Section 5.1 shall
be reported by MANUFACTURER, from a cross section rather than from a
surface analysis of the line pipe. If the value of any element falls outside the
limits listed, the pipe lengths made from that heat shall be rejected. At the
discretion of COMPANY, MANUFACTURER may be permitted to check each
pipe length from the rejected heat for compliance with this Specification.
MANUFACTURER shall include the product analysis method in the
Manufacturing Procedure Specification submitted to COMPANY for review
and/or approval.
6.1. General
Test specimen shall be taken by MANUFACTURER, from pipe lengths that have
been successfully hydrostatically tested. COMPANY will have the right to select
pipe lengths for production testing.
The yield and tensile strength of the line pipe shall be in accordance with API 5L
(Table 3). Yield strength shall not exceed the minimum specified by more than
140 MPa., for grade X-42 and higher. Additionally, the measured tensile strength
of each test pipe length shall not exceed the minimum by more than 140 MPa. ,
for grade B, the definition of maximum yield strength shall not be applied.
Table 6.1
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 16/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
1. If heats contain less than or equal to 150 pipe lengths one test per heat shall
be performed. If heats contain greater than 150 pipe lengths, one test per
150 pipe lengths or fraction thereof will be performed. Where the skelp or
line pipe is furnace heat treated, a minimum of one pipe length per heat
treatment batch shall be tested.
Table 6.2
Notes:
The use of the ring expansion method for determination of transverse yield
strength is not acceptable. Transverse tensile properties shall conform to API
5L. The yield/tensile ratio shall not exceed 0.90. The minimum elongation shall
be 22% on a 50 mm gauge length as defined in API 5L.
Guided bend tests shall be in accordance with the requirements of API 5L (para.
6.2.3, 6.2.4, 9.3.3, 9.3.4). The test fixtures shall be of the following dimensions
with respect to the nominal wall thickness (t) specified in the Purchase Order:
• Radius of male member, Ra = 3t;
• Radius of female member, Rb = 4t + 1.5 mm;
• Width of male member, A = 6t;
• Width of female member, B = 8t + 3 mm.
No defects greater than 3 mm in length shall be evident after bending.
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 18/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
Specimens shall also be taken for macrographic examination from the cross
section of one pipe per 150. The cross sections are to include the weld seam,
outer heat band and parent material. Hardness surveys are to be conducted in
accordance with the procedures reviewed and/or approved by COMPANY with
the positions of the hardness indentations as shown in Figure 6.2. The
maximum hardness shall be 33 HRC. A macrograph at 10x magnification shall
be submitted by MANUFACTURER with the test results.
Hard spots shall be as defined in API 5L except that the hardness limit of this
specification shall apply.
Macro/micro cross sections which include the weld and base metal shall be
taken by MANUFACTURER from each pipe length manufactured from the first
coil used during line pipe production. If the results are acceptable, at the sole
discretion of COMPANY, MANUFACTURER shall take macro/micro examination
specimens at a frequency of one sample per 150 pipe lengths or one sample per
coil if a coil contains less than 150 pipe lengths. Failure of the macro/micro
examination shall be cause for rejection of the coil. In the event of a
macro/micro examination failure, every pipe length shall be examined until, at
the sole discretion of COMPANY, the macro/micro examination results are in
accordance with the requirements set forth herein.
the AC1 (lower transformation temperature) zone width on each side of the weld
have been met.
Flattening tests with the weld at 90° as specified in API 5L shall be performed by
MANUFACTURER. Macro examination shall also be performed by
MANUFACTURER on the beveled ends of all pipes subject to flattening tests.
FIGURE 6.2
7. HYDROSTATIC TESTS
MANUFACTURER shall hydrostatically test all pipe lengths at the mill in accordance
with Section 9.4 of API Specification 5L to a test pressure of 85% SMYS for a minimum
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 22/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
The hydrostatic testing gauge shall be calibrated against a dead weight tester to the
satisfaction of COMPANY before start of production and at least once per shift,
thereafter. The pressure chart recorder shall be calibrated against the hydrostatic
testing master gauge at least twice per working shift and as directed by COMPANY.
All hydrostatic pressure tests shall be chart recorded and provided to COMPANY.
The identification number of the pipe length being tested shall be legibly recorded on
the hydrostatic test pressure charts. Pressure gauges used in the hydrostatic testing
shall have a range of 1 1/2 to 3 times the minimum test pressure. The longitudinal
seam orientation during hydrostatic testing shall be such that any pinhole leak in the
seam area shall be clearly visible to the hydrostatic testing operational personnel.
The inside diameters of both ends of 5 pipe lengths per shift shall be measured
by MANUFACTURER at four locations within 100 mm of each end of the line
pipe. Measurements shall be made using an adjustable inside circumferential
ring gauge. The measured inside diameter shall not deviate from the specified
value by more than the tolerance set forth in API 5L.
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 23/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
The inside diameters of both ends of 5 pipe lengths per shift shall be measured
by MANUFACTURER using a rod type gauge, or COMPANY and/or approved
equivalent, at four locations spaced equidistantly around the circumference, 100
mm from the end of the pipe. The difference between the maximum and
minimum measurement shall be less than 0.5% of the specified inside diameter.
The outside diameter at the center of 5 pipe lengths per shift shall be measured
using a C-Gauge or COMPANY reviewed and/or approved equivalent at four
locations spaced equidistantly around the circumference of the body of the line
pipe. The difference between the maximum and minimum outside diameters on
any one line pipe length shall be less than 1% of the outside diameter.
The wall thickness of each pipe length shall be measured at several locations
and at any location shall not deviate from the specified value by more than
+10% or -5%. At the weld seam location the upset areas shall meet the
specified wall thickness +20%, -5%.
8.6. Weight
Each pipe length shall be weighted and the results shall be included as part of
the line pipe tracking record. The weight per unit length shall not vary more
than +5% or -3.5% from the nominal weight per unit length.
8.7. Length
8.8. Straightness
The maximum deviation from a straight line shall not exceed 12 mm in any 12
m. All completed pipe lengths shall be rolled over a proven flat bed to
demonstrate straightness. Any straightening shall be undertaken using
procedures fully detailed for its revision and/or approved by COMPANY.
8.9. Jointers
Jointers shall not be permitted and produced pipe containing skelp end welds
shall be removed.
8.10. Squareness
The line pipe shall be supplied with a standard ASME B31.4/B31.8 beveled ends
or as specified in the purchase order. The surface of the end shall be
sufficiently smooth and free from tool marks as to permit proper inspection for
laminations.
All pipe lengths shall be inspected to ensure that the external and internal
profiles of the weld comply with the requirements detailed in Section 10.3 of this
specification.
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 25/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
9. NON-DESTRUCTIVE INSPECTION
9.1. General
Non Destructive Testing (NDT) shall conform with Section 9 of API 5L and as
modified herein. Complete and detailed procedures for all nondestructive testing
shall be set forth in the Manufacturing Procedure Specification submitted to
COMPANY for review and/or approval prior to commencement of Work.
The NDT procedures shall include, but not be limited to, the following
information:
• Equipment
• Personnel
• Preparation
Technique sheets, for all pipes, shall contain information such as,
type of steel and form, details of any repairs and
specification/examination criteria and acceptance criteria.
• Validation
• Reporting
Each pipe shall be subject to 100% visual examination of the external surface
and 100% visual and/or optical examination of the internal surface, including the
weld area. The MANUFACTURER shall provide details of the procedures to be
used for visual inspection of the internal and external surfaces of finished pipe
for COMPANY approval. The reference standards for acceptance/rejection of
defects revealed by visual examination shall be agreed between the
MANUFACTURER and the COMPANY before the start of production.
All strip shall be examined ultrasonically for laminations over a width of at least
25 mm along all edges where welding is to be performed and throughout the
strip at regular intervals. The ultrasonic examination shall be configured on the
final strip edges. Inspection shall meet the requirements of BS 5996 Grade E3
as a minimum. With the agreement of the COMPANY, inspection other than
edge inspection, may be carried out on pipe instead of strip.
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 27/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
The full length of each weld seam shall be examined with an automatic
ultrasonic scanning device designed to disclose unacceptable longitudinal
defects. The ultrasonic device shall include 45° and 60° or 70° shear wave
probes. The ultrasonic equipment shall be calibrated against an API standard
reference pipe containing 1.6 mm or 3.2 mm diameter drilled holes in addition to
longitudinal ID and OD N5 notches. The reference standard shall be of a whole
pipe length. Calibration shall be performed at production speed.
Longitudinal notches shall be cut on each side of the weld in the reference
standard and displaced so that each notch can be independently displayed. A
total of two internal diameter longitudinal notches, two outside diameter
longitudinal notches, one internal diameter transverse notch, one outside
diameter transverse notch and one hole shall be required. Locations where
defects are indicated shall be examined by manual ultrasonic or radiographic
techniques. Manual ultrasonic units shall be calibrated by MANUFACTURER in
accordance with ASME Section V, Article 5. Calibration notch maximum length
shall be 12.5 mm.
The absolute sensitivity (i.e., minimum resolvable linear defect size) in the
longitudinal direction shall be demonstrated by actual sectioning of pipe ERW
welds containing defects. The assessment of the sensitivity shall be to the
satisfaction of the COMPANY.
The ultrasonic equipment shall be re-calibrated at least twice per working shift
and at more frequent intervals if requested by the COMPANY. If the equipment
is found to be faulty or to require re-calibration, all pipes tested since the
previous calibration shall be re-inspected. The results of all calibrations shall be
recorded and made available to the COMPANY.
If the automatic weld seam inspection equipment does not inspect 100% of the
weld seam with all detectors, the un-inspected portion of the weld seam shall be
inspected with a COMPANY reviewed and/or approved manual ultrasonics
procedure. The length of the uninspected portion of the weld seam shall be
demonstrated to the satisfaction of theCOMPANY.
MANUFACTURER shall include full details of the method used to ensure the
automatic ultrasonic equipment tracks accurately along the weld seam being
examined.
All coiled skelps shall be visually inspected during uncoiling operations for
surface imperfections.
The surface examined shall be clean and smooth, i.e., free from dirt, paint or
any other foreign matter which would invalidate tests or which may influence the
results of testing. All pipe lengths shall be 100% examined for defects along
the body by MANUFACTURER.
The surface of the bevel on all pipe lengths shall be smooth and free from tool
marks. MANUFACTURER shall inspect every completed bevel for laminations
and cracks by Magnetic Particle Inspection in accordance with ASME V, Article
7, Clauses T-743 or T-744 or COMPANY approved equivalent. If automatic
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 29/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
ultrasonic inspection does not cover the final cut ends of the pipe, bevel ends
shall also be ultrasonically examined over a width of at least 200 mm around the
periphery for longitudinal and transverse defects in accordance with procedures
in Manufacturing Procedure Specification and/or approved by COMPANY.
9.8. Radiography
The first procedure qualification pipe and four further pipes selected by
COMPANY shall be examined by radiography over a minimum distance of 200
mm from each end. This distance shall be increased where necessary to cover
that portion of the pipe not scanned by all probes of the automatic ultrasonic
equipment. COMPANY reserves the right to require examination of additional
pipes during production. Radiographic procedure qualification shall comply with
API 5L Section 9.7.3. Radiographic examination shall be conducted with X-ray
equipment using lead intensifying screens and the radiographic films shall be
reviewed and/or approved by COMPANY.
The film shall be fine grain, e.g., Gevaert D7, Kodak Industrex C, or COMPANY
approved equivalent. The density shall be within the range 2.0 - 2.8 and shall be
chosen to provide the maximum contrast and definition.
ISO or equivalent wire penetrameter shall be used. The diameter of the thinnest
wire discernible on the radiograph shall be equivalent to 1.6% sensitivity or
better thickness.
Wall thickness shall be in accordance with API 5L, Section 7.3 as modified by
this Specification.
Acceptance levels for Magnetic Particle and Ultrasonic inspection of pipe ends
shall be in accordance with ASME Section VIII, Division 1 Appendix 6-4.
The external surface of all pipe to be used for hot induction bending shall be
subjected to 100% magnetic particle examination under fluorescent light in
accordance with a procedure reviewed and/or approved by COMPANY. The
surface of pipe intended for bending shall be free of copper and other low
melting point contaminants.
9.10. Magnetism
10.1. General
10.2. Dents
10.4. Defects
Any imperfection having a depth greater than 5% of the specified wall thickness,
measured from the surface of the pipe, shall be considered a defect.
MANUFACTURER shall define defects in accordance with API BUL 5T1.
Crack or crack-like defects shall be cause for rejection of the pipe length. Crack
or crack-like defects are defined as linear discontinuities which includes a
separation of the metal.
Hard spots shall be as defined and detected in accordance with API 5L Section
7.8.7 except that the hardness limit of this Specification shall apply.
MANUFACTURER shall specify in the Manufacturing Procedure Specification
the steps taken during production to prevent the presence of hard spots.
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 32/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
Pipe lengths containing arc burns shall not be acceptable. Arc burns shall be
removed by grinding until all visible evidence is gone and then etched with a
10% ammonium persulfate solution to verify removal. Following confirmation of
removal of the arc burn the area shall be merged smoothly into the original
contour of the pipe by grinding. On completion of grinding, magnetic particle
inspection shall be carried out of the ground area. The remaining wall thickness
shall be determined using ultrasonic inspection techniques. At no time shall the
remaining wall thickness be less than the specified minimum wall thickness.
COMPANY shall be notified and at its sole discretion shall have the option to
witness all arc burn removal testing.
The repair of defects shall be allowed only with the approval of COMPANY.
Repair of minor round bottomed defects in the pipe body may be merged
smoothly into the original contour of the pipe by grinding, provided the wall
thickness after grinding is not less than the specified minimum thickness. The
ground area shall be 100% magnetic particle inspected with wall thickness
checks using ultrasonics. Repairs by welding are not permitted to the pipe body
or longitudinal weld seam.
Defects that occur near the end of the pipe length shall be rectified by removing
a cylinder from the pipe length containing the defect. The length of the cylinder
removed shall have at least 100 mm of sound material beyond the end of the
defect.
10.8. Rejection
If, at any stage in production, the failure rate exceeds 5%, the quality control
program shall be increased as appropriate until the failure rate during production
is less than 5%. If the total of test failures exceeds 10% of those tested, or if, on
any one day, more than 10% of the production is rejected for other reasons,
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 33/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
When pipe from a particular heat fails to meet the criteria set forth in this
Specification all pipes produced from that heat shall be rejected.
MANUFACTURER shall perform additional testing of the heats immediately
before and immediately following the rejected heat. If any heat fails,
MANUFACTURER shall demonstrate by further testing the acceptability of all
heats not tested.
11.1. General
11.2. Marking
The minimum requirements for marking of line pipe utilizing paint stencils shall
be applied to the external surface of each pipe and protected by clear varnish.
Markings shall be 50 mm in height minimum for pipes over 10.75” O.D., 8 5/8”
O.D. ( and under) pipes will be marked with 25 mm minimum marketing heights:
1. COMPANY
2. Heat Number
11.3. Coating
The pipe shall be free from oil, grease and metal turnings and shall be supplied
either bare or coated according to document 1060-07-16-O-SP-002:
Specification for Line Pipe Fusion Bonded Epoxy Gas Pipeline, and 1060-07-16-
O-SP-003: Specification for Line Pipe Multilayer System Epoxy-Poliolefines Gas
Pipeline, line pipe requisitions and Purchase Order. Any deviation from this
documents, shall be timely advised to COMPANY
Certification shall cover all results required by this Specification. All certificates
shall be marked with sufficient information to enable full traceability to the items
it represents and the relevant specifications and procedures.
13.1. General
13.3. Transport
Loading onto or into rail cars, trucks, lighters, ships or other conveyances shall
be performed in accordance with API RP 5L1 or API RP 5LW as appropriate. In
all cases loading shall be in accordance with the Packing, Shipping and
Handling Procedures reviewed and/or approved by COMPANY.
13.4. Protection
Suitable methods for the protection of internal surfaces from the effects of
moisture during transport shall be provided by MANUFACTURER in the
Handling procedures reviewed and/or approved by COMPANY.
Methods utilized to transport line pipe for induction bending purposes shall be
provided by MANUFACTURER to COMPANY for review and/or approval. The
methods shall include a description of the technique proposed to ensure copper
and other low melting point contaminants are not deposited on the exterior of the
line pipe.
Line pipe shall not rest on projections which could result in point stresses or be
allowed to rub on an adjacent object. Line pipe loading and unloading shall be
performed in accordance with API 5LI or API 5LW, as applicable.
14.1. General
MANUFACTURER shall:
14.6. Verification
APPENDIX A
− Steelmaking method
− Deoxidation practice
− Special additions
− Ladle treatments
− Vacuum de-gassing
− Casting process
− Slab treatments
− Heat Treatment (including temperatures, hold times, heating and cooling rate,
cooling medium and furnace details)
SINCOR
Project Title: SINCOR ,C.A.
UPSTREAM SURFACE FACILITIES PROJECT SINCOR Document : 1060-07-16-O-SP-001
SINCOR Interface Code 00
SINCOR Class: 00
(Otepi Foster Wheeler) N°: 1069-07-02-1400-ET-001
*** Page /File: 42/ 1060-07-16-O-SP-001_0
Rev./Date: 0/MAY,20-99
− Rolling temperatures (for all stages of rolling), cooling rates and percentage
reduction below 950°C
− Skelp inspection/tests
APPENDIX B
B-1. SCOPE
Section outlines the tests and criteria required for qualifying the Manufacturing
Procedure Specification. The tests specified in the paragraphs below shall be run on
the Manufacturing Procedure Qualification line pipe selected in accordance with this
Specification. COMPANY shall have opportunity to witness and approve all specimen
preparation and testing.
Pipe length designated as joint A1 shall be used for the following tests and inspections:
All tests and inspections required for production of line pipe by this Specification
shall be performed.