Professional Documents
Culture Documents
CIGRE TB 916 - Year 2023 - Handling of Fittings and Conductors For Overhead Lines
CIGRE TB 916 - Year 2023 - Handling of Fittings and Conductors For Overhead Lines
CIGRE TB 916 - Year 2023 - Handling of Fittings and Conductors For Overhead Lines
Members
Corresponding Members
G. BRAGA BR S. THADDEY CH
D. GOMEZ ES M. MITO JP
J. ALMANO NZ B. HARIDASS ZA
Reviewers
Copyright © 2020
“All rights to this Technical Brochure are retained by CIGRE. It is strictly prohibited to reproduce or provide this publication in any
form or by any means to any third party. No part of this publication may be reproduced or utilized without permission from CIGRE”.
Disclaimer notice
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any responsibility, as to the
accuracy or exhaustiveness of the information. All implied warranties and conditions are excluded to the maximum extent permitted
by law”.
WG XX.XXpany network provided access is restricted to their own employees. No part of this publication may be
reproduced or utilized without permission from CIGRE”.
Disclaimer notice
ISBN : 978-2-85873-621-8
“CIGRE gives no warranty or assurance about the contents of this publication, nor does it accept any
responsibility, as to the accuracy or exhaustiveness of the information. All implied warranties and
conditions are excluded to the maximum extent permitted by law”.
TB 916 – Correct handling of fittings and conductors for overhead lines
Executive summary
To increase reliability and availability of overhead lines, one must look at several aspects of the
overhead lines such as foundations, supports, conductor, insulators and fittings. It is this brochure’s
attempt to examine the fittings.
Prior work was published by CIGRE B2 and led to the following guides.
• WG 22.03, TB184, Composite insulator handling guide.
• WG B2.03, TB306, Guide for the assessment of old cap & pin and long-rod transmission line
insulators made of porcelain or glass; What to check and when to replace?
• WG B2.49, TB653 Safe design tensions for single conductors fitted with elastomer cushioned
suspension units.
Given that many problems experienced in the field are perceived to be due to poor handling and
installation practices, the Working Group carried out a survey of current practice by manufacturers,
contractors and utilities with regard to correct handling and installation of fittings and conductors.
This was done by means of a questionnaire and subsequent analysis of the responses together with
inputs from the experts in WG B2.50 and TAG B2.06. Replies were received from Australia, Austria,
Brazil, Canada, France, Germany, Italy, Japan, New Zealand, Norway, South Africa, Spain, and, UK.
Guidelines have been produced with the aim of promoting good practice to minimise handling and
installation problems with fittings & conductors.
This guide is not intended to cover conductor creep or wrongly manufactured or wrongly designed
fittings.
Fittings are primarily designed from a mechanical point of view respectively to withstand short circuit
currents up to one second. In service, these fittings are mainly exposed to static and dynamic
mechanical loads as well as short circuit currents and environmental influences. Thus the mating
surfaces, the string design and minimisation of torsional, bending and uneven stresses in the fittings
comes from good installation practice.
Due to the very wide range of line items captured under the general description of "fittings", an
illustrated glossary of terms is included as an appendix.
Figure 0.1 Fittings being tested for elongation and tensile strength
3
TB 916 – Correct handling of fittings and conductors for overhead lines
4
TB 916 – Correct handling of fittings and conductors for overhead lines
Contents
Executive summary ............................................................................................................. 3
1. Introduction.............................................................................................................. 10
5
TB 916 – Correct handling of fittings and conductors for overhead lines
6
TB 916 – Correct handling of fittings and conductors for overhead lines
7
TB 916 – Correct handling of fittings and conductors for overhead lines
8
TB 916 – Correct handling of fittings and conductors for overhead lines
Tables
Table 3.1 Recommended safe design tension with respect to aeolian vibrations for single
conductors ....................................................................................................................... 83
Table 3.2 Terrain categories (Table 2 of TB 273) ............................................................................ 84
Table 3.3 Frequency of visits for ground inspection ...................................................................... 104
Table 3.4 Frequency of visits for climbing inspection .................................................................... 105
Table A.1 Definition of general terms used for overhead line hardware ........................................ 110
9
TB 916 – Correct handling of fittings and conductors for overhead lines
1. Introduction
The Working Group was created at the Bangkok meeting (2011) of TAG B2.06 in the re-organisation
of CIGRE's old Working Groups into Technical Advisory Groups and Task forces into Working Groups.
The changes were announced in 2010 but for the Mechanical Aspects of Overhead Lines WG11, now
TAG B2.06, was the first of these new groups. Originally the time span of a working group was two
years and that was extended to four years.
So WG B2.47, B2.48, B2.49 and B2.50 were created at the same time and the work of WG B2.47
(TB 708 Guide on repair of conductors and conductor-fitting systems) has many similar engineering as
WG B2.50. We all met every six months as umbrella groups of TAG B2.06 in Bangkok, Reykjavik,
Tampa, Paris, Bamberg, Auckland, Brussels, Lyon, Milan, Cape Town, Montreal, Boulogne, Dublin,
Seoul and Madrid (2018).
As explained in the executive summary, we sent out a simple questionnaire, analysed the results and
show those here in the brochure. Then the members who represented the world's leading
manufacturers with hundreds of combined years of practise gave their expertise to the brochure so
that correct procedures could be followed and problems explained.
Lastly, we had utility experts construct the chapter on Inspection. As we had so much confusion on
naming of fittings across Europe, USA and Australasia as well as spelling differences, we created a
glossary with pictures as an Appendix.
10
TB 916 – Correct handling of fittings and conductors for overhead lines
2. Questionnaire results
2.1 Introduction
Given that many problems experienced in the field are perceived to be due to poor handling and
installation practices, the Working Group carried out a survey of current practice by manufacturers,
contractors and utilities with regard to correct handling and installation of fittings and conductors.
This was done by means of a questionnaire and subsequent analysis of the responses together with
inputs from the experts in WG B2.50 and TAG B2.06. Replies were received from Australia, Austria,
Brazil, Canada, France, Germany, Italy, Japan, New Zealand, Norway, South Africa, Spain, and UK.
Therefore, the following information is provided in this chapter:
• Section 2.2 provides a copy of the questionnaire that was sent,
• Section 2.3 provides a summary of the replies obtained and,
• Section 2.4 provides the detailed information collected from the replies including whenever
possible the cause of the problem and the solution that was used.
2.2 Questionnaire
Given that many problems experienced with fittings in the field are due to poor handling and
installation practices, it is proposed to carry out a survey of current practice by manufacturers,
contractors and utilities to ensure correct handling and installation of fittings and conductors. This will
be done by means of a questionnaire and subsequent analysis of the responses together with inputs
from experts in the WG and TAG B2.06. Following on from this, guidelines would be produced with the
aim of promoting good practice to minimise handling and installation problems with fittings and
conductors.
This follows on from the work of WGB2.32 on ‘Assessing the performance of aged fittings: - Testing,
acceptance criteria & recommendations for HV & UHV Lines’.
Specific Actions to meet the key needs are:
Produce an ELECTRA paper or Technical Brochure by the Paris 2014 meeting.
Produce a Tutorial in 2015.
Members of CIGRE are kindly asked to submit the filled questionnaire till the end of July 2012 to
David Havard. mailto:dhavard@rogers.com; subject=WG50 Questionnaire
All respondents will be confidential.
Figure 2.1 Wrongly assembled clevis eye (left) and clevis clevis (right)
Thanks in advance.
Peter Dulhunty, Convenor WG B2.50
11
TB 916 – Correct handling of fittings and conductors for overhead lines
Also, we are looking at all conductor fittings, hardware fittings, dampers, spacer dampers, bolted
clamps, compression fittings, joints, anchors, tools, aircraft markers, spacers but not about their bad or
good design, not about poor or good manufacture but only about;
1. Storage,
2. Warehousing,
3. Handling,
4. Conductor preparation,
5. Inhibitor,
6. Sizing,
7. Wrong conductors and,
8. Installation.
12
TB 916 – Correct handling of fittings and conductors for overhead lines
13
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
14
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
15
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
2.4.1.5 Birdcaging
Voltage Medium
Summary Birdcaging
Photo
etc.
16
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
17
TB 916 – Correct handling of fittings and conductors for overhead lines
18
TB 916 – Correct handling of fittings and conductors for overhead lines
19
TB 916 – Correct handling of fittings and conductors for overhead lines
2.4.1.9 Wires broken due to overheating and softening inside straight sleeve
Voltage 66 kV
Summary Wires broken due to overheating and softening inside straight sleeve
Cause Sleeve was compression connected without sufficiently polishing old wires, with the
result that the wires overheated, softened and finally burned out as they failed to
withstand constant tension
Solution • Thoroughly study from the planning stage to ensure reliable connection. Guide and
train installation contractors.
• Tighten post-installation inspections
Photo
etc.
20
TB 916 – Correct handling of fittings and conductors for overhead lines
Solution Reinstall the straight compression sleeve by marking a parting line of the required length
of compression and then inserting to that parting line.
Photo
etc.
21
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary Electric wire slipped off due to faulty wire insertion into a compression clamp. Electric
wire type: Hard drawn copper conductor (HDCC), 125 mm2
Photo
etc.
22
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
23
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
24
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
25
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
26
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
27
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary OHL, tower junction between OHL and underground cable (2004-12-01)
Cause Break of the connexion between tensional anchor and head of underground cable. The
bretelle of the ACAR conductor uncoupled from the pad due to a bad crimp
Photo
etc.
Figure 2.27 Break of the connexion between tensional anchor and head of underground
cable
28
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause Break of an ACSR conductor at the end of the compressed dead end joint leading to the
ruin of 4 arms of the tower. The break is consecutive to a mishandling of the joint (steel
sleeve badly centred in the joint).
Photo
etc.
Dissymétrie du manchonnage
sur le conducteur alu
29
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause
Solution Replace
Photo
etc.
30
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
31
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary OPGW (for 55 mm2) slid in the clamp due to use of incorrect sized helical rod
Cause Helical rod of wrong size (for an outside diameter of 10.6 mm) was wound around the
OPGW (outside diameter: 9.6 mm)
Photo
etc.
32
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary Branch jumper damaged due to contact with the main wire support insulator mounting
bolt
Electric wire type: Thermo resistance aluminium-alloy conductor, steel reinforced
(TACSR), 120 mm2 x 1
Photo
etc.
33
TB 916 – Correct handling of fittings and conductors for overhead lines
Solution Replace
Photo
etc.
34
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
35
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
36
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause Earth wire stalled due to the break of an anchor clamp that was installed upside down
and broke. The assembly did not allow the clamp to ensure a correct pick up of traction
efforts.
Photo
etc.
37
TB 916 – Correct handling of fittings and conductors for overhead lines
• Dissimilar metals
CIGRE TB 708 [2017] also shows conductor fatigue failure at vibration clamp and damper displaced
towards the span centre on conductor.
Examples of spacer and damper issues are shown in the following sub-sections.
38
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
39
TB 916 – Correct handling of fittings and conductors for overhead lines
2.4.3.2 Corrosion
Voltage 66 kV
Cause Electrical corrosion inside a copper alloy armor rod due to installation of a copper-wire
twist prevention damper on aluminium-plated copper stranded wire
Solution Reinstall GW and replace the damper and similar metal armour rod (aluminium Armour
rod)
Photo
etc.
40
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
41
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause • Failure to fasten the bolts of the 4-conductor spacer clamp (ordinary bolt type)
• Loosening of the clamp led to wire damage due to vibration, etc.
Solution Replace the spacer and repair the wires using a maintenance sleeve
Photo
etc.
42
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary Electric wire damaged at a double torsional damper gripper for twin conductors.
Electric wire type: Thermo Resistance aluminium-alloy conductor, steel reinforced
(TACSR), 330 mm 2 x 2
Add damper tightening to the inspection checklist and include a relevant note in contract
work specifications
Photo
etc.
43
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary Electric wire wires broken due to insufficient tightening of a double torsional damper
Photo
etc.
44
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause The jumper spacer gripper was not installed in the correct position (condition)
Photo
etc.
45
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary The damaged damper (43 years old) was sent to the manufacturer, who assumed that
the damper had fallen off due to improper tightening of the bolt during installation.
Indeed, the ground wire clamp area was checked and the wire clamp marks were thin,
suggesting that the damper may not have been tightened enough. It appears that the bolt
broke the clamp due to its impact with the tower during the fall.
Cause Insufficient bolt tightening during installation
Solution • Tighten the damper with appropriate torque during installation, while checking how it
grips the wire
• Check the right diameter clamp is suited for the conductor diameter. Mark the bolt
Photo
etc.
46
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause Over bending load is applied to pin due to inappropriate lifting of insulator string
Solution Insulator string shall be carefully lifted so as to avoid deformation of insulator pin or split
pin due to an abnormal load
Photo
etc.
47
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause Over stress to shed and sheath of polymer insulator due to inappropriate lifting position
Solution Polymer insulators can be carried by spreading hands apart from the middle. Polymer
insulators should be carried by two people
48
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause Porcelain post insulator with pivot support used as a suspension situation. This is a
30 mm cast hole, not a machined parallel hole.
Photo
etc.
Figure 2.50 Porcelain post insulator with pivot support used as a suspension situation
49
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
50
TB 916 – Correct handling of fittings and conductors for overhead lines
• Steel defects
51
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause The inner sleeves of the comealong clamp were inserted the wrong way, causing
pinpoint contact at one end and not providing enough grip, resulting in slippage
Solution Ensure clamp inner sleeves are correctly inserted and that the gripping areas are parallel
Photo
etc.
Figure 2.55 Other end shows keyway holder does not match clamp
52
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause No chamfer on tower attachment plate hole as this hole is designed to accommodate a
shackle or clevis
Solution Use shackle in combination with guy assembly U-bolt or chamfer hole adequately to
accommodate curvature of U-bolt
Photo
etc.
53
TB 916 – Correct handling of fittings and conductors for overhead lines
2.4.5.3 Birdcaging
Voltage 400 kV
Solution Replace
Photo
etc.
54
TB 916 – Correct handling of fittings and conductors for overhead lines
Photo
etc.
55
TB 916 – Correct handling of fittings and conductors for overhead lines
Solution Replace
Photo
etc.
56
TB 916 – Correct handling of fittings and conductors for overhead lines
Cause Unacceptable conductor issued from factory with loose outer layer
Solution Cut out and replace. At 765 kV, Corona noise will be unacceptable.
Photo
etc.
57
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary Incorrect assembly of bonding lead to hardware fittings instead of bonding directly to
ground wire
Solution Bonding should be to the earthwire conductor through a parallel groove clamp or a
current transfer tab in the Factory Formed Suspension unit
Photo
etc.
58
TB 916 – Correct handling of fittings and conductors for overhead lines
Solution Reject
Photo
etc.
59
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary Shackle inserted in Tower clevis without being able to split pin the bolt
Solution Redesign width of plates or use a boss fitting to take up the room
Photo
etc.
60
TB 916 – Correct handling of fittings and conductors for overhead lines
Summary Training manual incorrectly shows Fig 11.22 a Clevis Tongue LV insulator with the clevis
end joining a clevis thimble
Cause Two thimble clevises are not required. The Clevis end should meet a tongue of an eye
tongue or an eyebolt
Solution Use Thimble Eye of eye thickness small enough to go in the clevis
Photo
etc.
61
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.2 Scratch brush: white for aluminium, black for copper
In the event the application is a “repair” or is being performed on “aged or weathered” conductor, even
more cleaning should be accomplished. Un-laying of conductor strands, for the purpose of cleaning
individual strands is a good practice, although it is typically considered impractical, as extreme care
must be employed to assure proper re-laying of the displaced strands. There are some “cleaning
systems” that have been recently deployed and have been shown to provide excellent deep cleaning
of strands on “aged-weathered” conductor, however, the steps of brushing, wiping, applying inhibitor,
and post brushing through the inhibitor should still be employed after the “cleaning” device has been
employed.
62
TB 916 – Correct handling of fittings and conductors for overhead lines
63
TB 916 – Correct handling of fittings and conductors for overhead lines
64
TB 916 – Correct handling of fittings and conductors for overhead lines
65
TB 916 – Correct handling of fittings and conductors for overhead lines
Where compression fittings are required to pass through deviation angles greater than 25 degrees, the
conductor tension at the angle shall be reduced to not greater than 15% MCBL (minimum conductor
breaking load) and the joints shall be lifted through the sheave in a manner approved by the
Supervisor so as to minimise bending stresses on or near the joints.
3.1.7 Example of compression fitting installation
66
TB 916 – Correct handling of fittings and conductors for overhead lines
There should be no tension or load on the conductor or dead end assembly until all compression
procedures are complete.
7. The die size on the die and the die size marked on the steel eye barrel must be the same. The dies
must be closed for each compression.
8. Compress the barrel of the steel part body, beginning beside the knurled (or otherwise marked)
portion and working toward the outer end. Always overlap the previous die position by approximate
one quarter of the die bite. If the steel part body is bent too much to slip inside the aluminium dead
end body, it shall be cut out and replaced and the process above repeated. It should not be
straightened.
67
TB 916 – Correct handling of fittings and conductors for overhead lines
14. Beginning at the die mark nearest the pad of the dead end body, start the first series of
compressions. Continue the compressions outward to the next die mark. Always overlap the previous
die position by approximately a quarter die bite.
15. Do not compress the aluminium tube above the compressions of the steel part body.
16. Beginning at the third die mark, make the second series of compressions. Continue the
compressions outward to the end of the barrel of the dead end body. Always overlap the previous die
position. If the completed dead end is too bent it should be cut out, replaced and the process above
repeated. Bent dead ends should not be straightened.
17. Aluminium sleeves may be compressed on to tensioned conductor only when the measured
tension on the compression fitting does not exceed 5 percent of the conductor rated strength or
5000 N, whichever is less, before all compressions are completed.
18. Coat the cleaned end of the jumper conductor with the same compound as prescribed in clause 1.
Insert the cleaned end of the conductor into the jumper terminal to the full depth of the bore.
Compress the jumper- terminal.
Starting at the pad end and working toward the outer end. Always overlap the previous die position by
approximately one quarter die bite.
19. Clean the contact surfaces of the pads by wire-brushing and then rubbing compound on to the
pads. Without removing compound, bolt to the torque specified in stringing instructions. Remove
excess compound.
20. Carefully round all corners, projections and indentations resulting from the compressions to a
radius of not less than the radius between two inside faces of the die. Carefully round all other edges
and corners that have been damaged to their original radius. Smooth nicked, abraded and scratched
surfaces. Remove tape, tape residue and compounds from the dead end body and conductor.
68
TB 916 – Correct handling of fittings and conductors for overhead lines
69
TB 916 – Correct handling of fittings and conductors for overhead lines
70
TB 916 – Correct handling of fittings and conductors for overhead lines
71
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.17 Slide aluminium dead end body over steel forging
72
TB 916 – Correct handling of fittings and conductors for overhead lines
(Section 3.1.22) can play a factor, as well improper calibration of the relief valve on the hydraulic
pump. It is important to have the pump and press appropriately maintained and calibrated periodically.
Other factors which may result in improper die closure may include improper seating of the dies within
the press, or foreign matter which impedes the dies from achieving proper closure. The lineman must
be careful to observe the press operation to assure complete die closure is achieved.
Proper inspection techniques should include periodic measurements of the outside diameter of
pressed connectors, to assure the dimension is within the tolerance provided by the manufacturer.
Incomplete die closure could also happen due to excess material which will form a burr between the
two dies.
Compression dies of high quality are shaped in a way to reduce this phenomenon.
3.1.14 Wrong die used
Many connector failures have been attributed to having been compressed with the wrong die. Be
certain that the correct die has been selected, and properly installed (Figure 3.18). To achieve
absolute certainty, a measurement should be taken after the first compression.
The most common reason this occurs is using the press on different applications during the same job.
The press is swapped back and forth between two crews to improve productivity.
Another cause for this problem is simply not having the correct die, and substituting something “close”
in order to get the job completed in a timely manner. Proper planning can avoid this common mistake.
73
TB 916 – Correct handling of fittings and conductors for overhead lines
3.1.17 Conductor not fully inserted – marking where and why – and how
If the conductor is not fully inserted, different type of failures are possible. First of all, some
compressions will show the same phenomena as described under Section 3.1.16.
Usually, the compression length is based on the RTS of the conductor. If the conductor is not fully
inserted the specified breaking load cannot be reached as some mechanical grip (resistance) is
missing.
The same situation applies to the electrical loading. As contact area is missing the full current capacity
must be transferred over a reduced contact area which will lead to an increased current density.
This could result in accelerated aging as well increase of temperature.
3.1.18 Splice not properly centred – similar to 3.1.8, but worth a different mention
If the aluminium tube of a midspan joint is not properly centred all influences and phenomena
mentioned under Sections 3.1.16 and 3.1.17 could happen.
3.1.19 Not compressing to the end
This is similar to the previous section.
Usually, the compression length is based on the Rated Tensile Strength (RTS) of the conductor. If the
conductor is not fully inserted the specified breaking load cannot be reached as some mechanical grip
(resistance) is missing.
The same situation applies to the electrical loading. As some contact area is missing the full current
capacity must be transferred over a reduced contact area which will lead to an increased current
density.
This could result in accelerated aging as well as increase of temperature.
In addition, compression connectors are typically manufactured with an outside taper at the end. The
result of compressing to the end will transfer this outer taper into an inner taper (trumpet mouth) which
provides a gradual transition from no compression to full compression, commonly over 2 or more
conductor diameters. Failure to provide this results in a comparatively sharp or short transition zone
which serves as a stress riser, and also makes this area more prone to damage from vibration.
3.1.20 Bowed or “banana” connectors (causes and prevention it)
Causes:
• Not properly straightening the conductor during the installation procedure
• Unsymmetrical wall thickness of the tube, outside tolerance during production or processing. Non-
continuous compression and use of undersized dies
Impact:
• Reduced breaking load
How to prevent:
• Overlapping compression
• Placing the conductor each side of the hydraulic compressor on a supporting rack to avoid
bending
74
TB 916 – Correct handling of fittings and conductors for overhead lines
75
TB 916 – Correct handling of fittings and conductors for overhead lines
end due to the extrusion/expansion of the aluminium as it is pressed, which can result in internal
fractures sufficient to cause mechanical failure. This failure could occur instantly, while installation is
still in process, or possibly a few months or years later.
Usually, if during the pressing operation, assuming you have full insertion of the conductor, one can
make the first two presses, then let off of the hoist about 50%, make another couple of presses (a total
of 4 or 5), and then go ahead and let off the hoist. This allows the stranding to expand further into the
span, whereas the grip restricts that movement. Just be certain that the conductor is fully inserted, and
it is recommended to mark the conductor at the mouth of the fitting so that as you let off the hoist, you
can be certain that the conductor is held fast. For larger conductors, it may be necessary to make
another press bite or two to hold them securely before letting off the hoist.
Also, the more distance you have between the dead end and the grip, the less birdcaging you will
have to begin with.
3.1.23 Direction of compression – toward tension span – reasons why – possible
alternatives
The usual compression sequence is towards the span.
Reason:
Compression towards the span reduces the longitudinal stress on the wires inside the compression
clamp.
Further the risk of improper installation is reduced as the first compression (clamp side) creates a
mechanical fixing point and all further elongation of the aluminium tube will be directed towards the
span where the clamp can move freely on the conductor.
If the first compression is placed at the compression clamp end (span side) the subsequent elongation
of the tube and conductor is directed towards the clamp side.
In the case of ACSR conductors, where a separate steel part is pressed in, the exact elongation has to
be examined prior the compression to set the correct gap between tube end and steel part at the
beginning of the compression process.
If the gap is not well adjusted the risk of different extensions of the soft aluminium tube and steel part
is high, and will pre-stress the aluminium tube.
A similar phenomenon happens inside the clamp for ACSR conductors if the gap between the ends of
the aluminium strands and the end of the steel part is not properly adjusted.
Alternatives:
In case of special type of conductors (i.e., HTLS) the compression towards the span could provide
some minor increase of thermal capability which would affect short conductor lengths such as used for
laboratory tests.
3.1.24 Bolted pads and associated issues
A typical bolted pad is shown in Figure 3.20.
76
TB 916 – Correct handling of fittings and conductors for overhead lines
HTLS conductors will require pads with a larger contact area compared to standard conductors.
As the pads are made of aluminium and therefore experience some creep under the bolt compression,
an appropriate elastic compensator (i.e., Belleville washer) is of benefit.
Many tests have proven that aluminium bolts provide a better electrical connection – enduring over
time – as opposed to steel bolts. The reasons are twofold:
• The coefficient of thermal linear expansion of steel is only about ½ that of aluminium. As the
connector heats and cools over time, the steel moves. The Belleville washer can compensate for
this; however, the connector still lacks the conductivity.
• Aluminium bolts, are about 1/3 as conductive as the connectors themselves (connectors typical
40-60% IACS – bolts typically 20-25% IACS), compared to steel bolts with only 2.5% IACS
conductivity or 10% that of Aluminium bolts – and thus additional current path is provided, and
connectors operate with less overall resistance.
Regarding the comment on “creep” – using a bolt of extreme tensile strength on aluminium forgoes the
spring tension intended to be provided by the bolt, and while the Belleville washer can compensate for
this, it is necessary it be properly engineered, and properly installed. This can be accomplished,
however an overwhelming abundance of empirical evidence suggests the installation is rarely
controlled to a sufficient degree.
With bronze or copper alloy connectors, the same reasoning applies for the argument to use Silicon
Bronze bolts.
With bi-metallic connections, there is no opportunity to maintain equal coefficient of linear thermal
expansion– and one must rely on the properly engineered and installed Belleville washer assembly to
maintain constant force in the joint over the entire temperature range to which the connector will be
subjected.
The science of bolted joints may be too extensive to be properly addressed in this document.
3.1.24.2 Bolt torque requirements
The tightening torque has to be chosen according to the grade of bolt used, and also to the installed
type of elastic washer.
Depending on the elastic washer a reduced torque is required. Another opinion is that the washer
must be properly engineered for the joint, which includes the bolt and the material being joined.
Bolts should be always tightened by the use of a calibrated torque wrench.
To ensure the best quality of tightening, the bolts should be tightened crosswise, at least 2 times.
3.1.24.3 Inhibitor
An inhibitor is strongly recommended to avoid water ingress and accelerated aging due to oxidation.
The inhibitor should be without additional grit.
Cleaning of the contact area:
• The contact area should be cleaned in the same way as the conductor (see section 3.1.1).
• Special attention must be taken to clean sharp edges or burrs resulting from transportation and/or
manipulation on site.
3.1.25 Special or peculiar components related to compression connectors
The felt washer/spacer on dead ends:
• Ensure the presence of a washer; felt, rubber or elastomeric material. This is to prevent contact
between the end of the aluminium tube as it is being compressed and the annular ferrule or stop
on the steel eye of a dead end.
3.1.26 Filling of cavity with filling grease/gel
Compression dead end clamps used in cold areas (North Europe, Alp areas, Canada…) can
experience cracked clamp tubes if water ingresses into the cavity in the vicinity of the steel part, and
then expands following freezing.
To avoid water ingress whether the gap is prefilled prior the installation by applying the inhibitor in this
area or, which is more effective, filling up the cavity after the compression process.
77
TB 916 – Correct handling of fittings and conductors for overhead lines
In this case a higher viscosity grease or gel should be used to fill up the cavity and “plug” the open
conductor end inside the clamp.
The filling hole must be properly closed after the filling process.
3.1.27 Grease for High Temperature Low Sag (HTLS) conductors
HTLS conductors are designed to run up to 250°C.
But the compression clamps which are in direct contact with the conductor should be designed in a
way to avoid temperatures higher than app. 90°C to reduce the creep phenomenon.
As the grease/inhibitor is only used inside the clamps, the grease/inhibitor will not be exposed to
temperature higher than the app. 90°C.
This is the minimum dropping point of the grease normally used.
Some clients request the same dropping point for the grease as the conductor’s maximum
temperature, which is not needed.
3.1.28 Packing for transportation
Compression fittings should be packed in a way to avoid mechanical damages or contamination
during the transport, storage or manipulation at site. A separate coating of the sensitive contact area is
of benefit. Grease/inhibitors should be packed separately and hermetically sealed to avoid oxidation.
78
TB 916 – Correct handling of fittings and conductors for overhead lines
Shackles and clevis bolts do not need to be tight. The nuts should pass the split pin hole and ensure
that no threads are placed in tension.
Armour grip suspension units shall be installed such that the ends of preformed rods do not differ in
alignment by more than 15 mm.
Safety goggles shall be worn by workers handling, tensioning, or clamping in glass insulators (in case
of spontaneous shattering of the glass).
3.2.4 Bridging assemblies
Bridging / jumper assemblies are used to connect the electrical circuit on tension structures.
The contractor shall install bridging conductor such that the electrical clearances are maintained.
Where a bridging insulator string is employed, the conductor length shall be such that it exerts a
positive weight downwards on the bridging insulator string or post insulator. The bridging conductors
shall hang neatly without twists and kinks. Bridging /Jumper assemblies may also be at perpendicular
to the vertical and for low voltage can be over the top.
Where directed by the supervisor, all metallic contact surfaces between adjacent ceramic insulator
discs shall be treated with an approved conducting grease applied in a manner approved by the
supervisor. The contact surfaces of bolted conductor palms shall be thoroughly scratch brushed until
shiny, wiped clean, and immediately lightly coated with an approved jointing compound, before bolting
of the palms.
79
TB 916 – Correct handling of fittings and conductors for overhead lines
80
TB 916 – Correct handling of fittings and conductors for overhead lines
81
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.24 Aeolian vibration dampers: top left to bottom right: Symmetrical Stockbridge damper,
asymmetrical Stockbridge damper, torsional damper, elastomeric damper
The specifying of a torque value for the tightening of bolts on vibration dampers has so far been the
best means of determining the clamping force required and this value has been shown on all vibration
dampers.
If the bolt has a breakaway outer head, tighten the bolt until the breakaway head shears off. Ensure
that the wrench socket axis is aligned with the bolt axis during tightening. It is suggested to collect the
heads since they may be a hazard for animals and it is a good way to make sure that the clamp bolts
have been properly tightened.
When inserting the conductor in the damper clamp, loosen the bolt but it should not be required to
remove the bolt.
The damper clamp shall be able to accommodate any variation of the conductor diameter induced by
conductor creep and temperature variation.
3.4.2 Protected span length
The number and position of vibration dampers is optimised to attenuate aeolian vibrations on the
conductor below an acceptable limit. The length of span which may be protected with dampers to
prevent conductor fatigue depends to a great extent on the following parameters:
• The mechanical tension in the span
• The terrain category which determines the wind turbulence to which the conductor may be
exposed
• The type of conductor which determines its self-damping ability and its propensity to vibration
It is well known that stranded conductors get more vulnerable to aeolian vibrations as tension is
increased. Guidance to establish safe design tension for both single and some bundle conductors was
provided by Task Force B2.11.04 [CIGRE TB273, 2005] and is reported in Table 3.1. They discarded
the EDS concept since it led to fatigue failures in a significant number of cases. Thus, the parameter
H/w, the ratio between the initial horizontal tensile load H and conductor weight w per unit length was
adopted. This tension refers to initial horizontal tension before any significant wind and ice loading and
before creep, at the average temperature of the coldest month on the site of the line.
For damper recommendations, H/w is used in conjunction with another parameter intended at rating
the protective capacities of the damping system LD/m. That is the ratio of the product of span length L
and conductor diameter D over the conductor mass per unit length.
The recommended safe design tension for single conventional round strand conductors (all aluminium
A1 (AAC) conductors; all aluminium alloy A2 or A3 (AAAC) conductors; aluminium/aluminium alloy
A1/A2 or A1/A3 (ACAR) conductors and steel-reinforced aluminium A1/Syz (ACSR) conductors) with
respect to aeolian vibrations is provided in Table 3.1 and illustrated in Figure 3.25. The safe design
tensions depend also on terrain categories that have been divided into four categories according to
82
TB 916 – Correct handling of fittings and conductors for overhead lines
general characteristics (Table 3.2). Should there be any doubt about real terrain category, the lowest
class should be selected.
Safe tension guidelines for single conductors with elastomeric suspension clamps were analysed and
presented in CIGRE technical brochure No. 653 "Safe design tensions for single conductors fitted with
elastomer cushioned suspension units" [2016].
The analysis of safe conductor tensions was extended to bundle conductor lines and is available in
CIGRE TB 273 [2005].
Table 3.1 Recommended safe design tension with respect to aeolian vibrations for single conductors
Undamped
single < 1000 < 1125 < 1225 < 1425
conductor
Single
conductor
with span- < 15 < 15 < 15 < 15
end
dampers
Single
conductors
with 1100 m 1250m 1425m 1600m
elastomer (1275m) (1425m) (1625m) (1800m)
lined
clamps*
* The initial values are based on statistical analysis of the field data including dispersion of data.
Values in brackets are based on lower limit of field data.
83
TB 916 – Correct handling of fittings and conductors for overhead lines
Terrain
Terrain characteristics
category
Open, flat, no trees, no obstruction, with snow cover, or near/across large bodies of
1--------
water; flat desert.
2-- -- -- Open, flat, no obstruction, no snow; e.g. farmland without any obstruction, summer time.
Open, flat, or undulating with very few obstacles, e.g. open grass or farmland with few
3-- --- ---
trees, hedgerows and other barriers; prairie, tundra.
Built-up with some trees and buildings, e.g. residential suburbs; small towns; woodlands
4_______
and shrubs. Small fields with bushes, trees and hedges.
84
TB 916 – Correct handling of fittings and conductors for overhead lines
The efficiency and durability of the damper system should be validated through field testing or
laboratory tests.
Unless stated otherwise by the manufacturer, it is not critical if the asymmetrical damper is placed with
its low frequency (large weight) end outermost in the span or its high frequency (small weight) end,
however if vibration frequencies are unknown, it may be prudent to alternate their orientation from one
end of a span to the other.
85
TB 916 – Correct handling of fittings and conductors for overhead lines
86
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.29 Left: Installation of a nut cracker rubber lined clamp with latch fastener – Right: Spacer
closing tool
87
TB 916 – Correct handling of fittings and conductors for overhead lines
Positioning of the spacers on the conductors: It will be shown how to decide the orientation of the
spacer in respect to the bundle (asymmetric spacers shall be installed with alternate orientation), the
top position and how to hang the spacer on the bundle before tightening the clamp bolts.
Use of torque wrench or other installation tools: A careful training will be performed on the correct use
of spacer installation tools especially torque wrenches and fastening latch tools, in accordance with
the procedure suggested by the manufacturer.
Measurement of the subspan length: The use of cart distance counters will be explained and verified
on the trial bundle.
Control the washer position. The right orientation of the Belleville washers and the right position of the
plane washers and safety plates, if any, should be regarded in view of possible disassembling and
reassembling of the clamps.
Helical rods: The correct procedure for the positioning, alignment and installation sequence of the rods
will be explained during a trial installation.
88
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.32 Suspension clamps , Left: Metal-to-metal clamp, Right: Elastomer lined clamp
Figure 3.33 Dead end clamps, Left: Compression dead end, Middle: Preformed dead end, Right: Strain
clamp
The lengths shown in the in-span distribution tables for spacers are intended as actual sub-conductor
lengths, to be measured along the bundle catenary.
The maximum permissible tolerance on the spacer positioning is one meter.
The spacer shall be installed at a minimum distance of two meters from the mouth of joints, repair
sleeves and warning spheres in order to avoid concentration of masses that can generate fixed points
for aeolian vibration. When a spacer is to be displaced for the presence of one of these fittings, the
position of the other spacers of the span remains unchanged.
In presence of night warning devices, interphase spacers, and other heavy fittings, the spacer damper
positioning will be determined case by case in relation to the characteristics of the fittings and the
parameters of the line.
On twin bundles, the body of the symmetrical spacer dampers shall be positioned below the bundle
long axis.
On triple and quad bundles, the clamps nearer to markings like ’Up’ or ‘Top’ shall be installed on the
upper sub-conductors.
Spacers shall be installed perpendicularly to the bundle long axis with a tolerance of 3°, unless
otherwise specified by the manufacturer, that can be easily assessed visually.
When break-away bolts are used, the bolt heads shall be visible from the ground for installation
verification.
With normal clamp bolt, the use of a torque wrench is mandatory and the torque shall be the one
recommended by the manufacturer, that generally is marked on the clamp cap.
The correct installation of the spacer clamps, including the alignment in the plane perpendicular to the
bundle long axis, shall be witnessed and verified from the ground by a foreman equipped with a
binocular.
It is worth to stress that even one single clamp not correctly installed can produce conductor failures
and very expensive outages. Moreover, a survey has shown that spacer clamps account for 28% of
the problems and damage to conductors are an additional 30% of the problems reported with spacers
[CIGRE TB 277, 2005].
89
TB 916 – Correct handling of fittings and conductors for overhead lines
On triple and quad diamond bundles, the spacers are installed with alternate orientation so that the
lower arm is positioned alternatively at the right and at the left of the lower sub-conductor
(Figure 3.34). The orientation of the first spacer in each span is optional. The same principle applies to
any asymmetrical spacer-damper design.
90
TB 916 – Correct handling of fittings and conductors for overhead lines
Surface defect (see Figure 3.35), where the conductor surface has been nicked or scratched, dented
or smashed. The depth and extent of damage determines the repair method to be used. Simple
abrasion, nicks, protuberances, can be sanded down using emery cloth or fine sand paper. The use of
steel wool is not recommended since it could leave hair-like residue that could lead to corona
problems later on. In cases where individual wires have been severely gouged or broken, it may lead
to an unacceptable loss of strength, and the conductor section must be cut out or repaired with
preformed rods or compression repair sleeves. A discoloration of the conductor's surface is sometimes
observed after ocean shipment due to contact with salt water. This discoloration does not affect the
performance of the conductor.
Left to right: Abraded surface, broken wires, Drake AACSS with indentations from Klein Grip
Figure 3.35 Surface defects
Popped wire (see Figure 3.36), sometimes called proud wire, is the phenomena by which a wire is
forced out of the outside layer of the conductor. It occurs when the conductor is subjected to torsion
and the wire is more or less wrung out of place. This happens most frequently around sheaves and
travellers. Note that it can also be the result of poor manufacturing. Popped wires produce corona and
radio noise problems and in general should be dealt with by either carefully hammering them back into
the conductor with a wooden mallet, or cutting them out, covering the cut ends with preformed rods.
Type 4 conductors having up to 30% of damaged aluminium wires may be repaired using high
temperature armour rods with grit glued to the inside of the rods.
91
TB 916 – Correct handling of fittings and conductors for overhead lines
Other types of defects occur but are usually a combination of the three listed above. In most cases,
the affected part of the conductor must be spliced out.
3.6.2 Reel handling
Damage to reels during set-up in the field can lead to conductor damage and stringing problems. The
main concern when manipulating reels is to keep the conductor winding on the drum as tight as
possible (Figure 3.38) and not create conditions where the conductor could plunge within the wraps
(Figure 3.39) or come in contact with rough surfaces or sharp edges (unprotected reel flange edges,
for example) during stringing.
Reels should always be kept upright, never on their side like pancakes, and should never be dropped.
Lifting reels must be done in such a way as to ensure the conductor never bears the total weight of the
reel. Slings, straps or other types of lifting device directly on the conductor covering or wood lagging is
definitely not desirable. If forklift trucks must be used, then the forks have to be placed directly under
the flanges. This operation is not very safe and therefore not preferred.
The proper way to lift a reel is illustrated here in Figure 3.40. Reels are designed to be supported on
their axis and it is the best way to handle them.
Some metal reels have a plate or I-beam welded to their flanges, as illustrated in Figure 3.41, used as
reinforcement and space to house the ends of wood lagging. Hooks are sometimes used to grab the
welded plate or the outside of the flange of the I-beam. This method is usually not recommended by
reel manufacturers, so contractors and users should consult the conductor supplier before using this
method.
In all cases, the use of a spreader bar (Figure 3.42) is of prime importance, to prevent the flanges from
bending inward under the weight of the reel, destroying the winding, the conductor and causing it to
rub on the flanges of the reel during stringing.
Figure 3.38 "Perfect" winding. The conductor cannot "plunge" between wraps underneath
Figure 3.39 Winding with gaps between wraps leading to stringing problems and conductor damage
92
TB 916 – Correct handling of fittings and conductors for overhead lines
93
TB 916 – Correct handling of fittings and conductors for overhead lines
Conductor suppliers wind up conductors on reels in a manner called "layer winding", which means that
each turn is tightly wound over the layer underneath. All the wraps touch each other all along the
winding to fill the reel as efficiently as possible, and to avoid the creation of space between the wraps.
What can happen when the winding of the conductor is disturbed, is that there is a possibility for the
conductor to “plunge” between the loose wraps during paying off of the conductor. Plunging leads to
snagging, which leads to wire breaks and conductor damage.
Plunging can happen by applying too much tension to the conductor, or by using wood reels with
relatively small conductors. Wood reel flanges are not as rigid as metal reel flanges and can bend
more easily. This deformation is not large but could be sufficient to create enough interstitial space for
the conductor to plunge in. For this reason, it is not advisable to use wood reels with equipment that
rely on the reel to apply tension to the conductor (such as puller-tensioners). Reels should be
specified according to the kind of conductor and stringing technique used.
3.6.3 Stringing
Stringing can be done in many ways because unusual situations call for unusual procedures, but there
are two broad techniques used to string conductors: slack stringing and tension stringing.
3.6.3.1 Slack stringing
As its name implies, slack stringing involves installing the conductor using as little tension as possible.
It is not recommended for use with conductor Types 2 and 4, and for high-voltage lines. The conductor
is laid down on the ground along the line's right-of-way. It can be dragged or “deposited” along the line
usually by carrying the reel in the back of a truck, unravelling it as it goes. It is then pulled up at every
pole or tower. The conductor lying on the ground must be protected from sharp obstacles, such as
rocks, debris and others, usually with pieces of timber laid along the right of way. Figure 3.43 shows
such a method of protection. Tension is used only for sagging in the conductor. Slack stringing is used
mainly for distribution line construction where the spans are short, the poles not very high and the
voltage low enough to be of no corona concern. It has been used for transmission line erection in the
past but cannot compete with the efficiency of using tension stringing techniques on long transmission
lines projects.
94
TB 916 – Correct handling of fittings and conductors for overhead lines
the conductor entering the tensioner. The best way to avoid problems and damage while tension-
stringing is to keep everything aligned as much as possible.
As it exits the reel, the conductor should be supported to avoid touching the ground or other
conductors being pulled at the same time. Figure 3.45 shows a support system consisting of rollers,
keeping sub-conductors apart as well as allowing them to travel laterally (for Types 2 and 4 these
rollers should not be used. Full-size sheaves should be used instead).
A tensioner usually consists in one or more pairs of grooved wheels, called bull wheels, rotating in
tandem. Friction builds up along the conductor the same way as it does on a capstan. The two bull
wheels are usually aligned at an offset relative to each other to make the transition from one wheel to
the other as smooth as possible for the conductor (Some tensioners have the back bull wheel tilted
instead of offset). This offset should be in the direction of the lay followed by the outside layer of the
conductor. This way the passage of the conductor in the tensioner tends to tighten up its outer layer
which helps prevent the formation of birdcages.
Most bull wheels have a right-hand offset, matching the direction of lay of the outside layer of
overhead aluminium conductors. Some tensioners have a left-hand offset, meant to be used with
copper conductors or other constructions. Although it is possible to thread a left-hand tensioner to the
right by skipping a groove, this practice is not recommended and should be avoided (Figure 3.47).
Inspectors should be on the lookout for it. Using all the grooves of the bull wheels as shown in
Figure 3.47, is important to build friction forces gradually along the conductor.
The diameter of the bull wheels is a very important parameter, especially with Type 2 and Type 4
conductors, where it should not be less than 35 times the conductor diameter. Annealed aluminium
wires have much greater elongation than hard-drawn wires and deform more easily. V-grooved
tensioners should not be used for those two types.
The distance between the tensioner and the first tower is also important. For most high-temperature
conductors, this distance should be at least three times the height of the first break-over point.
95
TB 916 – Correct handling of fittings and conductors for overhead lines
96
TB 916 – Correct handling of fittings and conductors for overhead lines
Some reels come with an oversized side pocket used to secure the conductor at the bottom of the
winding (Figure 3.48). The large size is necessary to accommodate large conductors. If the
manufacturer did not take steps to prevent it, there is a strong possibility for small conductors to bulge
out of it during stringing and get damaged. If this is the case, the stringing operation has to be slowed
down every time the conductor is paying off close to the pocket, and if necessary, the conductor must
be moved away "by hand" from the pocket to avoid serious problems.
Figure 3.48 Oversized pocket on some reels. The welded bars prevent the conductor from bulging out of
the pocket
Accordingly most of the birdcaging occurs from the reel to the tensioner. As the number of layers
increases in the conductor, birdcages start to appear beyond the tensioner, up to the first sheave.
They usually occur, and are noted, around stringing equipment.
Birdcages between the reel and the tensioner may occur because of slack in the conductor at the
beginning of the reel. One way to mitigate this problem is to increase the distance between the reel
and the tensioner. The slack present in the conductor will be spread over a longer distance and most
likely will "pass into" the tensioner. Once under tension, the slack has more chances to disappear.
Another common location for birdcages to occur is inside the tensioner, between the bull wheels
(Figure 3.49). In most cases, this birdcage is formed because the conductor enters the tensioner with
insufficient tension, and/or the pulling tension is too high. The stringing tension must be developed by
friction within the bull wheels. Because of the large difference between the tension from the reel and
the exit tension from the tensioner, the outside layer of the conductor gets stretched, thus creating
birdcages. Increasing the back tension is usually the way to solve this problem.
Figure 3.49 Birdcage forming between two bull wheels in the tensioner
If a birdcage is formed in the tensioner and grows to a size that could impede the stringing operation
(especially if multiple conductors are strung simultaneously), it will be necessary to get rid of it. In this
case a desperate tactic is to tape the conductor ahead of the tensioner, over a distance equal to or
longer than the distance between the two bull wheels. This will push the birdcage beyond the
97
TB 916 – Correct handling of fittings and conductors for overhead lines
tensioner and into the span. This section of conductor may get damaged and will have to be spliced
out later on.
3.6.5 Sheaves
Sheaves, if not set-up properly, can cause a lot of damage to the conductor. The most important
factors to consider are the dimensions of various components of the sheave (groove diameter, overall
diameter, etc.), and their alignment with the conductor during stringing.
Sheave dimensions guidelines for Type 0 conductors are well known and can be found either from
industry guidelines such as Aluminum Company of Canada, Limited, REPAIR OF DAMAGE, Electrical
Product Bulletin [1965], or directly from the conductor or sheave manufacturers. Recommendations for
conductors of Types 1 to 4 must be obtained from manufacturers as there is no industry standard yet
that encompasses guidelines for high-temperature conductors. As a rule of thumb, sheave diameter
(for all Types) at the bottom of the groove should be approximately 20 times the conductor diameter.
Some manufacturers of Type 2 conductors recommend the use a larger "break over" sheave, that is,
the first sheave in front of the tensioner, in order to ease the conductor into the span.
Sheaves must be clean and free-wheeling. Lining, neoprene or urethane, is essential, especially with
Types 2 and 4 conductors. The lining must be in good condition. Given the relatively large bearing
pressure between the conductor and the sheave, imperfections or discontinuities in the lining may
leave imprints on the outside of the conductor. Solid, unlined plastic-moulded sheave have been
problematic with Type 2 conductors and should be used with caution. For Type 3 conductors a “Roller
Array” as shown in Figure 3.50 is used for flying angles greater than 24 degrees.
It is of the utmost importance to have the conductor travel in the centre of the sheave, and more
generally that the conductor and the sheave be in the same plane. This is generally not a problem for
sheaves suspended from cross-arms on tangent towers. Attaching the sheave directly to the pole (on
lower voltage lines) is sometimes done but is not desirable because the sheave will naturally hang at a
vertical angle. If the conductor is not running in the middle of the groove, it will rub on the flange on
entry or exit of the sheave and get damaged. Examples of what NOT to do are shown in Figure 3.51,
while pictures in Figure 3.52 to Figure 3.54 show examples of the damage that can occur around
sheaves.
Pulling conductor through angles is also critical (Vertical angles can create problems but to a much
lesser extent, since they are in the same plane as the conductor). In this case, if left alone, the sheave
will hang at an angle determined by the resultant of its own weight and the pulling tension in the
conductor. The conductor will in fact support the weight of the sheave, the angle of which is set by the
rules of static equilibrium. To do so, it will ride up on the flange. As illustrated, when the conductor
travels on the sheave's flange, it tends to roll down to the bottom of the groove and, depending on the
direction of rotation, may create popped wires or birdcages. To avoid this situation, the sheave must
be supported by mean of a sling to the angle at which the conductor will naturally lie in the middle of
the groove as shown in Figure 3.55.
Pulling through horizontal angles is not ideal and in extreme cases it should be avoided by splitting the
pull in two or more sections. There is no specific angle above which this should be considered, and
techniques such as the one discussed in the previous paragraph go a long way to avoid problems.
As a rule of thumb, horizontal angles above 20° should be given special attention. Angles above 30°
may require larger sheaves, or multiple-sheave arrangements (tandem sheaves as shown in
Figure 3.56). The principle behind tandem sheaves is to create a larger "virtual" diameter in order to
reduce the bearing pressure seen by the conductor. Tandem sheaves and their frames have to be
sturdy and are, usually, very heavy. They must be supported as discussed previously.
98
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.50 "Roller array" used for angles greater than 24 degrees on Type 3 conductors
99
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.55 Sheave position leading to conductor damage and remedial action
100
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.57 Different types of grips Top: Woven wire pulling grip, Middle: Parallel-groove clamp, Bottom:
Bolted come along
Woven wire pulling grips are used mainly to pull the conductor during stringing. They are perfect for
that application. The working principle of this type of grips is that pulling on them increases the radial
force applied to the conductor and increases its gripping force. The woven design makes this grip
strong, flexible and thin, so it can be passed through equipment such as tensioners and sheaves.
It is important to always keep this grip under tension. Double-gripping (with a swivel between the
grips) is a very common practice with this type of grips. When this is done, the forward grip actually
passes "backward" in the equipment. The danger in this situation is to inadvertently "push" the end of
the forward grip, opening it, with catastrophic consequences.
To reduce the chances of this occurring, it is recommended to apply one or even two steel bands at
the end of the grips (Figure 3.58). This ensures that it will not be pushed open. Tape should be applied
over the band(s) to protect the lining of the tensioner or sheaves.
For Type 2 conductors it is also recommended to band the aluminium under the grip, add washers in
front of it, and compress a steel sleeve over the core, as seen in Figure 3.59. This is because the
woven grip could pull only on the annealed aluminium layers, which could elongate over the core,
bunch up under the grip, damage the sheaves and eventually break. Applying the extra band, washers
and compressed steel tube helps the grip to pull the core with the aluminium layers.
101
TB 916 – Correct handling of fittings and conductors for overhead lines
102
TB 916 – Correct handling of fittings and conductors for overhead lines
Figure 3.62 Grips used in tandem and protection over the conductor
3.7 Inspection
These recommendations for inspection are for a new installation.
For each installation, a control plan is made to be followed by crews responsible for inspection.
First of all, the plan can be checked that appropriate precautions notified in the assembly instruction
are followed by the linemen. This can be during the assembly of fittings and also during unloading and
handling. Controls can be organized with planned meeting or unexpected visit. Special attention shall
be made to the attached joints, crossing spans, railway crossings, highway crossings and clipping-in
once the conductor has been brought to sag. All types of installed fittings shall be checked.
3.7.1 Inspection and maintenance during line life
The implementation of a preventive maintenance policy is necessary to optimise and to standardize
practices while ensuring compliance of existing work and maintain their capability of continuing
operation. The policy must take into account the behaviour of the fittings, the works, the constraints
they have to deal with, the environment and the stakes of the transmission grid.
Maintenance visits are recorded when done in a systematic way. They are part of the feedback that
Transmission System Operators (TSO) use to make accurate decisions about their systems in terms
of fitting behaviour and take the necessary actions for corrective maintenance or replacements if
necessary.
TSOs employ various inspection techniques to check the integrity of their transmission lines to ensure
continuous supply of power to their customers. Depending on the terrain and budgets, utilities will
determine the proper line inspection method. The most common forms of inspection are listed below:
• Walking visits
• Climbing visits
• Helicopter visits
• Remotely Piloted Aircraft System (RPAS) visits
Combination of different visits give accurate assessment of the line for asset management to consider
when making decisions about their lines.
103
TB 916 – Correct handling of fittings and conductors for overhead lines
Strategic planning is required by TSOs to ensure that the correct maintenance schedule is in place
including inspection methods and the frequency of each inspection. Visits planning is determined
according to the quality of electricity supply, safety of people and assets, current condition of the line
(pollution, lightning, wind, age and type of components). Wide variety of items need to be inspected for
potential defects which generally depends on the size of the item and the level of importance. A whole
line does see the same constraints homogeneously along its length. Planning deals with homogenous
sections.
The different possibilities of visits are explained as far as conductors and fittings are concerned.
3.7.2 Walking visits
Walking visits or ground inspection are by far the oldest method or the most common of power line
inspection. The primary reason of this method is to visually assess the condition of the line. Walking
visits offer the following visual control:
• Post construction of power line inspection -Proposed right of way
• Condition of conductors where birdcaging and broken layers can be detected
• Condition of fittings (see CIGRE TB 708 [2017])
The frequency of the visits may vary from utility to utility. Frequency of the visits depends on age,
condition of the section, environment, and safety of assets. An example of frequency is given in
Table 3.3.
Table 3.3 Frequency of visits for ground inspection
104
TB 916 – Correct handling of fittings and conductors for overhead lines
105
TB 916 – Correct handling of fittings and conductors for overhead lines
• Joints
• Suspension Clamps
• Bretelle clamps (Parallel Groove Clamps)
106
TB 916 – Correct handling of fittings and conductors for overhead lines
107
TB 916 – Correct handling of fittings and conductors for overhead lines
5. General conclusions
The responses to the survey highlighted that most problems are with compression fittings. It may be
wise to train linemen by compressing spare conductors at ground level before taking the hydraulic
compression tools in the air.
The survey showed, and the members feel, that there are also numerous problems with conductors,
spacers and spacer dampers installation issues, notably with loosened clamps.
APPENDIX A includes a glossary of line fittings. This allows the reader to see what is designed to
mate with what.
In instances where a failed fitting is found, the risk of having other fittings fail in a similar fashion
should be evaluated. The need to inspect other similar fittings installed on the line (e.g. inspection,
replacement) should be evaluated. Where one bad installation has been found then maybe all the
hardware strings in the line share the same fault.
A good proportion of conductor damage is generated during the construction of lines (Figure 5.1).
Although failures detected during construction will generally be repaired rapidly before the line is
commissioned, corrective actions to avoid re-occurrence may not automatically be taken. Corrective
actions could take the form of a review of procedures used for conductor stringing, installation of
fittings, or a requirement for increased training for contractors and linemen.
108
TB 916 – Correct handling of fittings and conductors for overhead lines
6. Future work
1) A survey of Lines Training schools would help with the prevention of wrongly installed fittings and
insulators. The survey could include: Curricula and levels of training, duration of courses, whether the
school accepts national outsiders and international outsiders.
2) There appears to be a need for a chart showing the differences in millimetres between IEC and
ANSI balls, sockets, eyes and shackle ears.
109
TB 916 – Correct handling of fittings and conductors for overhead lines
APPENDIX A. Glossary
For the purpose of this Glossary the following definitions apply. These definitions are those which do
not appear in the International Electrotechnical Vocabulary (IEV) or differ from those given in the IEV.
The definitions do not include electrical, structural or civil terms. Some items like Arcing Horns and
Grading Rings are too numerous in design shapes to mention.
Table A.1 Definition of general terms used for overhead line hardware
Term Definition
110
TB 916 – Correct handling of fittings and conductors for overhead lines
111
TB 916 – Correct handling of fittings and conductors for overhead lines
112
TB 916 – Correct handling of fittings and conductors for overhead lines
Bolted
A compression tee that has a bolted clamp
compression run
at one end.
tee
Brace
Aluminium - White
Brush, conductor
Copper – Black
Cable
In a cross-rope tower the cable element is
used in tension between the supporting
towers. Cables do not take compression
113
TB 916 – Correct handling of fittings and conductors for overhead lines
114
TB 916 – Correct handling of fittings and conductors for overhead lines
115
TB 916 – Correct handling of fittings and conductors for overhead lines
Crossarm
Crossarm brackets are used to mount a
mounting
variety of apparatus.
bracket
116
TB 916 – Correct handling of fittings and conductors for overhead lines
117
TB 916 – Correct handling of fittings and conductors for overhead lines
Extra-high
voltage Transmission line operating at a phase-to-
transmission line phase voltage of 300 kV or higher.
(EHV)
118
TB 916 – Correct handling of fittings and conductors for overhead lines
Flag
119
TB 916 – Correct handling of fittings and conductors for overhead lines
120
TB 916 – Correct handling of fittings and conductors for overhead lines
121
TB 916 – Correct handling of fittings and conductors for overhead lines
122
TB 916 – Correct handling of fittings and conductors for overhead lines
123
TB 916 – Correct handling of fittings and conductors for overhead lines
124
TB 916 – Correct handling of fittings and conductors for overhead lines
US spelling of metre.
Meter
125
TB 916 – Correct handling of fittings and conductors for overhead lines
126
TB 916 – Correct handling of fittings and conductors for overhead lines
Pulling Grip,
For pulling up conductor, can be used many
woven wire
times.
stocking
127
TB 916 – Correct handling of fittings and conductors for overhead lines
128
TB 916 – Correct handling of fittings and conductors for overhead lines
129
TB 916 – Correct handling of fittings and conductors for overhead lines
130
TB 916 – Correct handling of fittings and conductors for overhead lines
131
TB 916 – Correct handling of fittings and conductors for overhead lines
132
TB 916 – Correct handling of fittings and conductors for overhead lines
133
TB 916 – Correct handling of fittings and conductors for overhead lines
134
TB 916 – Correct handling of fittings and conductors for overhead lines
135
TB 916 – Correct handling of fittings and conductors for overhead lines
136
TB 916 – Correct handling of fittings and conductors for overhead lines
APPENDIX B. References
CIGRE Green book 1 (2017) Overhead lines, www.e-cigre.org, 1318 pages.
CIGRE Technical Brochure 184 (2001) Composite insulator handling guide, WG 22.03, www.e-
cigre.org, 29 pages.
CIGRE Technical Brochure 216 (2002) Joints on transmission line conductors: Field testing and
replacement criteria, WG B2.12, www.e-cigre.org, 10 pages.
CIGRE Technical Brochure 273 (2005) Overhead conductor safe design tension with respect to
aeolian vibrations, Task Force B2.11.04, www.e-cigre.org, 43 pages.
CIGRE Technical Brochure 277 (2005) State of the art survey on spacers and spacer dampers,
WG B2.11, www.e-cigre.org, 53 pages.
CIGRE Technical Brochure 294 (2006) How OH lines are re-designed for uprating / upgrading,
Analysis of the answers to the questionnaire, WG B2.06, www.e-cigre.org, 102 pages.
CIGRE Technical Brochure 306 (2006) Guide for the assessment of old cap & pin and long-rod
transmission line insulators made of porcelain or glass; What to check and when to replace?,
WG B2.03, www.e-cigre.org, 37 pages.
CIGRE Technical Brochure 322 (2007) State of the art of conductor galloping, Task Force B2.11.06,
www.e-cigre.org, 142 pages.
CIGRE Technical Brochure 471 (2011) Working safely while supported on aged overhead conductors,
WG B2.33, www.e-cigre.org, 64 pages.
CIGRE Technical Brochure 477 (2011) Technical Brochure on Evaluation of Aged Fittings, WG B2.32
www.e-cigre.org, 28 pages.
CIGRE Technical Brochure 653 (2016) Safe design tensions for single conductors fitted with
elastomer cushioned suspension units, WG B2.49, www.e-cigre.org, 31 pages.
CIGRE Technical Brochure 695 (2017) Experience with the mechanical performance of non-
conventional conductors, WG B2.48, www.e-cigre.org, 81 pages.
CIGRE Technical Brochure 708 (2017) Guide on repair of conductors and conductor-fitting systems,
WG B2.47, www.e-cigre.org, 55 pages.
IEC 61284, Ed. 2.0 (1997) Overhead lines – Requirements and tests for fittings, 131 pages.
Victorian Bushfire Royal Commission (2009) Exhibit 525 – HRL Technology Report – Kilmore East
Fire.
137
ISBN : 978-2-85873-621-8
TECHNICAL BROCHURES
©2023 - CIGRE
Reference 916 - September 2023