Professional Documents
Culture Documents
$RKHXDAN
$RKHXDAN
ASSIGNMENT
Due: May 31, 2024, 11:59 pm
Submit to: odtuclass.metu.edu.tr
“This is an individual assignment. Please complete the assignment on your own and do not share
your assignment file with anyone”.
Goal: The purpose of this assignment is to develop an understanding of the scheduling and resource
allocation of a bridge project and to get familiar with project management software (Microsoft
Project).
Description: You are required to develop two schedules for a bridge project. The activities (activity
IDs, descriptions, and activity durations in terms of digits in your student ID) and resource
requirements for the project are given below. The project is planned to start on June 1, 2024, and
there are no holidays in the work schedule (there will be no holidays on Saturdays or Sundays, or
on official holiday dates). While developing the schedules:
a) Assume that: There are no resource-constraints (you have an unlimited number of
resources available).
b) Assume that: The availability of each resource is one. (There is 1 excavator, 1 pile
driver, 1 carpenter crew, 1 concrete mixer, 1 masonry crew, 1 crane, and 1 backfilling
equipment available).
Required: You are required to develop two schedules; a schedule with unlimited resources (part
a), and a schedule with limited resources (part b). You should present the results in a report
format and submit the report with the Microsoft Project file(s) to ODTUClass in a zip file
formatted and labeled as pX.zip according to your student ID “X” (for report pX.docx and project
files pX_parta.mpp and pX_partb.mpp). For instance, for a student with the student ID “0621671”,
create zip file as p062167.zip. The report should include the following:
1) Brief information about the project,
2) Explanation on how to construct the precedence relations between the activities for part (a),
3) Explanation on how to redevelop your schedule in part (a) according to resource constraints
for part (b). For this part, you should at least try two different schedules, considering the
sequencing of the activities: (1) from the left side of the bridge to the right, and (2) from the
right side to the left.
4) Project completion dates for part (a) and for every schedule you have tried for part (b),
5) Precedence relationship tables for part (a) and for the shortest-duration schedule in part (b),
6) Schedule outputs obtained from Microsoft Project for the schedule in part (a) and for the
shortest-duration schedule in part (b), which include; (activity) duration, early start/finish
dates, late start/finish dates and a total float of activities,
7) Resource graph outputs obtained from Microsoft Project for the schedule in part (a) and for
the shortest-duration schedule in part (b) showing weekly resource requirements of each
resource.
Note: There will be a penalty of 25% for late submittal. Assignments submitted after June 7, 2024
will not be accepted.
Bridge project data