Display Week: 1 F S S M TWT F S S M TWT F S S M TWT F S S M TWT F S S M TWT F S S M TWT F S S M TWT No Activities Start Finish Days Status %done Elgof Civil Works 01-Mar-24 16-Mar-24 11 NS 0.0% 1 Construction of Water Points 01-Mar-24 15-Mar-24 11 NS 0.0% 1.1 Clearing of site 01/03/24 02/03/24 1 NS 0.0%
1.2 Excavation 02/03/24 04/03/24 1 NS 0.0%
1.3 hard core 04/03/24 05/03/24 2 NS 0.0%
1.4 Lean concrete 05/03/24 06/03/24 2 NS 0.0%
1.5 fix re bars 05/03/24 06/03/24 2 NS 0.0%
1.6 fix from work 06/03/24 07/03/24 2 NS 0.0%
1.7 fill mass concrete 07/03/24 08/03/24 2 NS 0.0%