MAKE OVER TOWER T & H APARTMENT URBAN HEIGHT

ID Task Uraian Pekerjaan Durasi Start Finish May June July August September October November December
Mode 5/15 5/22 5/29 6/5 6/12 6/19 6/26 7/3 7/10 7/17 7/24 7/31 8/7 8/14 8/21 8/28 9/4 9/11 9/18 9/25 10/2 10/9 10/16 10/23 10/30 11/6 11/13 11/20 11/27 12/4 12/11 12/18 12/
1 1 TIMELINE MAKE OVER TOWER T & H 169 days May 30 Nov 14 '22
GEDUNG UHR '22
2 1.1 Start 0 days May 30 '22 May 30 '22 5/30
3 1.2 Perencanaan: 15 days May 30 '22 Jun 13 '22
4 1.2.1 Tower T 15 days May 30 '22 Jun 13 '22 Wahyu
5 1.2.1.1 Gambar Arsitektur (Lay Out 10 days May 30 '22 Jun 8 '22 Firman,Jon,Dafam
Denah): (Twr- T)
6 1.2.1.2 Kitchen (Twr- T) 8 days May 31 '22 Jun 7 '22 Firman,Jon,Dafam
7 1.2.1.3 Meeting Room (Twr- T) 8 days May 31 '22 Jun 7 '22 Firman,Jon,Dafam
8 1.2.1.4 Restaurant (Twr- T) 8 days May 31 '22 Jun 7 '22 Firman,Jon,Dafam
9 1.2.1.5 Lobby Hometel (Twr- T) 8 days May 31 '22 Jun 7 '22 Firman,Jon,Dafam
10 1.2.1.6 Gambar 3D (Twr- T) 13 days Jun 1 '22 Jun 13 '22 Firman,Jon,Dafam
11 1.2.1.7 RKS & Spesifikasi Teknis 13 days Jun 1 '22 Jun 13 '22
12 1.2.1.8 RAB (Twr- T) 13 days Jun 1 '22 Jun 13 '22 Firman,Jon,Dafam
13 1.2.2 Tower H 15 days May 30 '22 Jun 13 '22 Wahyu
14 1.2.2.1 Façade 1 (Twr- H) 8 days May 30 '22 Jun 6 '22 Firman,Jon
15 1.2.2.2 Façade 2 (Twr- H) 8 days May 30 '22 Jun 6 '22 Firman,Jon
16 1.2.2.3 Gambar 3D (Twr- H) 9 days Jun 2 '22 Jun 10 '22 Firman,Jon
17 1.2.2.4 RKS & Spesifikasi Teknis 3 days Jun 11 '22 Jun 13 '22
18 1.2.2.5 RAB (Twr- H) 3 days Jun 11 '22 Jun 13 '22 Firman,Jon
19 1.3 Presentasi BOD (Twr- T) (Twr- H) 0 days Jun 13 '22 Jun 13 '22 6/13 Firman,Jon,Wahyu
20 1.4 Management 63 days Jun 14 '22 Aug 15 '22 Wahyu,Dafam
21 1.4.1 Presentasi Final oleh Dafam & GIB6 days Jun 14 '22 Jun 19 '22 Wahyu,Dafam,Firman,Jon
22 1.4.2 Proses Keputusan Management 5 days Jun 20 '22 Jun 24 '22 Wahyu,Dafam
23 1.4.3 KOM 5 days Jun 25 '22 Jun 29 '22 Wahyu,Dafam
24 1.4.4 Pembentukan Management 45 days Jul 2 '22 Aug 15 '22 Wahyu,Dafam
Pengelola
25 1.5 Pembangunan 136 days Jun 25 '22 Nov 7 '22 Dafam,Firman,Jon,Wahyu
26 1.5.1 Tower T 136 days Jun 25 '22 Nov 7 '22 Dafam,Wahyu
27 1.5.1.1 Pembuatan Dokumen 7 days Jun 25 '22 Jul 1 '22 Firman,Jon
Pengadaan & Draft Kontrak (Twr- T)
28 1.5.1.2 Proses Pengadaan (Twr- T) 18 days Jul 2 '22 Jul 19 '22 Firman,Jon,Wahyu
29 1.5.1.3 Proses Pembangunan Fasum 90 days Jul 20 '22 Oct 17 '22 Firman,Jon,Wahyu
(Twr- T)
30 1.5.1.4 Promosi (Twr- T) 90 days Aug 10 '22 Nov 7 '22 Wahyu
31 1.5.1.5 Proses Pre-Opening (Twr- T) 14 days Oct 18 '22 Oct 31 '22 Firman,Jon,Wahyu
32 1.5.2 Tower H 92 days Jul 2 '22 Oct 1 '22 Dafam,Wahyu
33 1.5.2.1 Pembuatan Dokumen 7 days Jul 2 '22 Jul 8 '22 Firman,Jon
Pengadaan & Draft Kontrak (Twr- H)
34 1.5.2.2 Proses Pengadaan (Twr- H) 14 days Jul 20 '22 Aug 2 '22 Firman,Jon,Wahyu
35 1.5.2.3 Proses Pembangunan façade 60 days Aug 3 '22 Oct 1 '22 Firman,Jon,Wahyu
(Twr- H)
36 1.6 Soft Opening Hometel (Twr- T) (Twr- H)
7 days Nov 8 '22 Nov 14 '22 Dafam,Firman,Jon,Wahyu
37 1.7 Finish 0 days Nov 14 '22 Nov 14 '22 11/14

PT. Brantas Abipraya (PERSERO) Page 1 Abipraya Properti