VOLUME PONDASI TOWER 412 TYPE FF (-3 s/d +3) KELAS 3

PEMBANGUNAN SUTET 275 KV 2CCT QUADRUPLE ZEBRA GITET GUMAWANG - GITET LAMPUNG I (PAKET GGL-01)
0056.PJ/KON.02.01/UIP SUMBAGSEL/2017, TANGGAL 22 DESEMBER 2017
KSO. PT. HASTA PRAJATAMA - PT. SEJAHTERA INTERCON - PT. KMI WIRE AND CABLE TBK

B b d1 d2 d3 d4 a d0 Df t1 t2
T.412 FF+0 Kls 3 Leg 4,00 Unit
13,40 4,00 0,50 2,40 0,40 0,80 1,40 0,15 3,60 0,05 0,10

1 Galian Tanah Biasa = 13,40 x 13,40 x 3,75 x 4,00 = 2.693,40 m³

2 Urugan Pasir = 13,40 x 13,40 x 0,10 x 4,00 = 71,82 m³

Lantai Kerja = 13,40 x 13,40 x 0,05 x 4,00 = 35,91 m³


3
Beton Adukan 1 : 3 : 5 (B.O), t = 5 cm =
Beton K225 = 623,52 m³
a. Bottom Pad = 13,40 x 13,40 x 0,80 x 4,00 = 574,59 m³
5 b. Top Pad = 4,00 x 4,00 x 0,40 x 4,00 = 25,60 m³
c. Mata Intan = ( 1,40 x 1,40 + 0.15 x 0.15 ) x 0.5 x 0.15 x 4.00 = 0,59 m³
d. Chimney = 1,40 x 1,40 x 2,90 x 4,00 = 22,74 m³
Bekisting = 262,08 m²
a. Bottom Pad = 13,40 x 0,80 x 4,00 x 4,00 = 171,52 m²
6
b. Top Pad = 4,00 x 0,40 x 4,00 x 4,00 = 25,60 m²
c. Chimney = 1,40 x 2,90 x 4,00 x 4,00 = 64,96 m²
Besi Tulangan' = 104345,69 kg
7 a. Besi Ulir BJTD 32 = Sesuai Pembesian Pondasi = 103.360,92 kg
b. Besi Polos BJTP 24 = Sesuai Pembesian Pondasi = 984,78 kg

8 Urugan Tanah dan Perataan Tanah = (Sama dengan Volume Galian) = 2.693,40 m³

9 Transport Material Pondasi ke Lokasi Tower = 623,52 + 35,91 + 71,82 = 731,26 m³

Total Kebutuhan Consumable Material :

SEMEN BATURAJA : 4879,82 ZAK SOLAR : 824,3 ltr

PASIR : 451,98 m3 PERTALITE : 741,86 ltr

KORAL : 495,16 m3

BESI D13 ULIR "LS" : 114,055 batang

BESI D22 ULIR "LS" : 2770,8 batang

BESI D25 ULIR "LS" : 81,2 batang

Triplek 12mm : 26 lembar

Kayu 5/7 : 117 batang

Paku 1,5" : 24,57 kg

Paku 2" : 24,57 kg

Paku 3" : 24,57 kg

Bendrat @25kg : 22,2454 roll