Contractor Power System Projects Kind of Work Foundation Brick Work

Project Suez Gulf S/S 500/220/22 kv Unit Cubic Meter


Location Control Building
Suez Gulf S/S 500/220/22 kv

Dimensions
Item No.
Length Width Height
Partial Deduc Total Notes

Axis 1 (+ 0.90) 1 24.40 0.25 2.55 15.56


Axis 2 (+ 0.90) 1 19.75 0.25 2.85 14.07
Axis 2 (+ 1.25) 1 4.25 0.25 3.20 3.40
Axis 3 (+ 0.90) 1 8.45 0.25 2.85 6.02
Axis 3 (+ 1.25) 1 8.29 0.25 3.20 6.63
Axis 4 (+ 0.90) 1 4.75 0.25 2.85 3.38
Axis 6 (+ 1.25) 1 4.75 0.25 3.20 3.80
Axis 7 (+ 1.40) 1 16.74 0.25 3.35 14.02
Axis 8 (+ 1.25) 1 4.95 0.25 3.20 3.96
Axis 14 (+ 0.90) 1 23.38 0.25 2.55 14.90
Axis A (+ 0.30) 1 9.73 0.25 1.95 4.74
Axis A (+ 0.90) 1 23.58 0.25 2.55 15.03
Axis B (+ 0.90) 1 20.68 0.25 2.85 14.73
Axis B (+ 1.25) 1 12.13 0.25 3.20 9.70
Between Axis A&Axis B (+ 0.90) 1 3.25 0.25 3.35 2.72
Axis C (+ 1.25) 1 20.80 0.25 3.20 16.64
Axis C (+ 0.90) 1 4.20 0.25 2.85 2.99
Axis D (+ 0.90) 1 5.05 0.25 2.85 3.60
Between Axis B&Axis D (+ 0.90) 1 6.13 0.25 3.35 5.13
Axis E (+ 0.90) 1 4.55 0.25 2.85 3.24
Axis H (+ 1.40) 1 8.60 0.25 3.05 6.56
Axes I&K (+ 0.90) 2 4.75 0.25 2.85 6.77
Axis L (+ 0.90) 1 32.73 0.25 2.55 20.86
Stairs Between Axes 2&3 1 2.29 0.25 2.55 1.46
1 1.10 0.25 2.55 0.70
1 0.78 0.25 2.55 0.50
Stairs Between Axes 5&9 2 2.37 0.25 2.55 3.02
4 1.20 0.25 2.55 3.06
Stairs Between Axes A&C 1 5.61 0.25 2.55 3.58
1 1.18 0.25 2.55 0.75
1 1.20 0.25 2.55 0.77
Stairs Between Axes 4&8 1 6.27 0.25 2.55 4.00
2 1.25 0.25 2.55 1.59
0.00

0.00
0.00
0.00

Total 217.88 0.00 217.88