MP-02 - Isolate For Maintenance
MP-02 - Isolate For Maintenance
MP-02 - Isolate For Maintenance
JOB: ISOLATE MUD PUMP FOR MAINTENANCE Sr. mechanic : Mostafa Saher Date :12/11/2010 at 15:00 MP-02
POTENTIAL HAZARDS
TOOLS /
Conditions or Actions Which RECOMMENDED SAFE PROCEDURES
KEY JOB PROCESS STEPS MATERIALS S/P RISK
Could Cause an Injury / Affect Personal Protective Devices Special Clothing Procedures
USED
Health
1. Lock tag out mud pump None Electric shock 4B HM Ask electrician to lock out from SCR.
from VFD Pump not locked out Install safety pin in DC motor local switch
Do not use wet gloves
2. Isolate the pump by closing None Back strain 1C L Ask Driller to stop other pump if running.
the discharge valves
3. Bleed off trapped pressure None slip, tripping, falling 1C L Clean working area
Ensure of good housekeeping
4. Lock out & line up the None Electric shock 4B HM Ask electrician to remove the lock
pump after repair Back strain 1C L Make sure other pump is stopped before opening
the valve
767776080.doc Page 1 of 1