Professional Documents
Culture Documents
Bba Ca Question Bank
Bba Ca Question Bank
Operations Research
I BBA CA -A
1. Operation Research approach is ____
multi-disciplinary scientific
c)intuitive d)collect essential data
2. The transportation problem, for the degeneracy of the basic
solution, the number of basic cells must be ______.
3.InLPPfunctions to be maximized or minimized are called
Objective function. (True/False)
4.AsetoffeasiblesolutiontoaLinearProgrammingproblemis
convex polygon
c)triangle d)bold
5. Hungarian methos is commonly used solve assignment problem
(True/False)
6. In an assignment problem each person is assigned
exactly one job more than one job
c) exactly two job d)exactly three job
7. Zero sum games with two players are called_____
8.PERT is the ___ oriented technique
Deterministic Probabilistic c) Float d) Dummy Activity
9. C.P.M =_____
10.If the value of the game is zero then it is called a _____.
11.The linear functions which is to be minimized or maximized is
called_____
Objective function Constraints
c) Redundant constraint d) convex Polygon
12. Any feasible solution which optimizes the objective function is
called______.
13.When demand not equal to supply the transportation problem is
called _______
14.In the Transportation problem, for the degeneracy of the basic solution , the number of basic
cells must be
𝑚+𝑛 <𝑚+𝑛−1
c)> 𝑚 + 𝑛 − 1d)> 𝑚 + 𝑛
15. Assignment Problem can be solved only if 𝑚 = 𝑛
(True/False)
16. In an assignment problem each person is assigned
exactly one job more than one job
c) exactly two job d) exactly three job
17. The time between the firs and last job is called _____
18.The number of time estimates used in PERT______
0 2 c) 3 d) ∞
19.Two person zero sum game is also known as_______
20.Game without saddle point require players to play zero-sum game.
(True/ False)
21. The limitation of graphical method is
four variables three variables
c)two variables d)None of these
22. The transportation problem, for the degeneracy of the basic
solution, the number of basic cells must be ______.
23. MODI method of obtaining an optimal solution to a transportation
problem (True/False)
24. Row wise and column wise difference between two minimum costs
is calculated under ____ method
NWCR VAM
c)LCM d)none of these
25. If the assignment problem matrix is not square then the problem is
said to be unbalanced .(True/False)
26. Each and every row and column of the assignment problem has
exactly one assigned zero the solution is
basic feasible
c)optimal d )none of these
27. PERT=_____
28.The critical activity has
Normal Float Maximum Float
c) Minimum Float d) Zero Float
29.In the value of the game is zero then it is called a ____
30.A mixed strategy game can be solved by______.
SECTION-B
X 3 3 8 9
Y 6 5 10 15
Z 7 4 12 20
P 20 10 40 25 0 500
Q 45 35 60 40 50 600
R 70 75 70 50 80 750
S 85 88 75 65 90 800
D E F G Supply
A 10 0 20 11 15
B 12 7 9 20 25
C 0 14 16 18 5
Demand 5 15 15 10
𝐽1 5 7 11 6
𝐽2 8 5 9 6
𝐽3 4 7 10 7
𝐽4 10 4 8 3
Player B
2 5
Player A [ ]
4 1
10.Define - payoff matrix, saddle point
11. Write the application of L.P.P
12. Solve by Graphical Method
Minimize 𝑍 = 2𝑥1 + 3𝑥2
Subject to 6𝑥1 + 5𝑥2 ≤ 25
𝑥1 + 3𝑥2 ≤ 10
and 𝑥1 , 𝑥2 ≥ 0
A 11 13 17 14 250
B 16 18 14 10 300
C 21 24 13 10 400
A 2 3 11 7 6
B 1 0 6 1 1
C 5 8 15 9 10
Demand 7 5 3 2
𝐽1 17 25 31
𝐽2 10 25 16
𝐽3 12 14 11
A B C D Supply
P 6 1 9 3 70
Q 4 5 2 8 55
R 10 12 4 7 70
Demand 85 35 50 45
A 19 30 50 10 7
B 70 30 40 60 9
C 40 8 70 20 18
Demand 5 8 7 14
𝐽1 8 4 2 6 1
𝐽2 0 9 5 5 4
𝐽3 3 8 9 2 6
𝐽4 4 3 1 0 3
𝐽5 9 5 8 9 5
29. Determine two-person zero sum game is pay strictly determinable and fair.
Player B
5 1
Player A [ ]
3 4
30. Define –Strategy of game.
SECTION-C
P 7 6 4 5 9 40
Q 8 5 6 7 8 30
R 6 8 9 6 5 20
S 5 7 7 8 6 10
Demand 30 30 15 20 5
A 3 7 6 4 5
B 2 4 3 2 2
C 4 3 8 5 3
Demand 3 3 2 2
A 18 26 17 11
B 13 28 14 26
C 38 19 18 15
D 19 26 24 10
E F G H I
A - 3 6 2 3
B 3 - 5 2 3
C 6 5 - 6 4
D 2 2 6 - 6
E 3 3 4 6 -
8.Construct the network and critical path for the following project schedule.
Activity: 1-2 1-3 2-3 2-5 3-4 3-6 4-5 4-6 5-6 6-7
Duration : 15 15 3 5 8 12 1 14 3 14
4 −4
9.Solve the game whose pay-off matrix is [ ]
−4 4
P 7 6 4 5 9 40
Q 8 5 6 7 8 30
R 6 8 9 6 5 20
S 5 7 7 8 6 10
Demand 30 30 15 20 5
A 15 51 42 33 23
B 80 42 26 81 44
C 90 40 66 60 33
Demand 23 31 16 30
A 10 5 9 18 11
B 13 19 6 12 14
C 3 2 4 4 5
D 18 9 12 17 15
E 11 6 14 19 10
A - 4 7 3 4
B 4 - 6 3 4
C 7 6 - 7 5
D 3 3 7 - 7
E 4 4 5 7 -
17.Draw the network, given the following precedence relationships and also find critical
path.
Event
1 2,3 4 5 6 7
Nos:
Preceded start
1 2,3 3 4,5 5,6
by: event
18. In the following table optimistic, most likely and pessimistic times are respectively
shown against each connected activity from 10 to 100 in a project.
A 10 0 20 11 15
B 12 7 9 20 25
C 0 14 16 18 5
Demand 5 15 15 10
A 3 7 6 4 5
B 2 4 3 2 2
C 4 3 8 5 3
Demand 3 3 2 2
A 3 8 2 10 3
B 8 7 2 9 7
C 6 4 2 7 5
D 8 4 2 3 5
E 9 10 6 9 10
E F G
A 9 26 15
B 13 27 6
C 35 20 15
D 18 30 20
27.Construct the network for a project in which activities have the
following precedence relationship A,C,D can start immediately.
E> 𝐵, 𝐶; 𝐹, 𝐺 >; 𝐻, 𝐼 > 𝐸, 𝐹; 𝐽 > 𝐼, 𝐺; 𝐾 > 𝐻; 𝐵 > 𝐴
28. Table below summarizes the activities of a project. Construct the network identify the
activities where slack exists:
Activity A B C D E F G
Immediate __ __ A C D B,E E,F
predecessors
Duration 10 7 5 3 2 1 14
(days)
5 2
29.Solve the game whose pay-off matrix is [ ]
3 4
30. Find the value of the value of the game
Player B
−1 2 −2
Player A [ ]
6 4 −6