应急预案
Scenario 1
情景 1
TABLE OF CONTENT
目录
SCENARIO ONE 预案1- SYNGAS RELEASE AND FIRE AT GASIFIER (U-1600) 气化框架U-
1600合成气泄漏、火灾爆炸..................................................................................................................4
SCENARIO ONE 预案1- SYNGAS RELEASE AND FIRE AT GASIFIER (U-1600) 气化框架U-
1600合成气泄漏、火灾爆炸..................................................................................................................4
1 SCENARIO DESCRIPTION 情景描述.......................................................................................4
2 ASSESSMENT OF THE DETECTION TIME 探测时间评估..................................................5
3 DETERMINE THE FUEL SUPPLY REDUCTION MEASURES 确定工艺控制措施..........5
3.1 FROM THE CCR 中控室............................................................................................................5
3.2 FROM THE FIELD 现场..............................................................................................................5
4 IDENTIFY BEHAVIOUR OF RELEASED PRODUCT 泄漏物质的特性..............................5
5 UANTIFY THE CONSEQUENCES OF A FIRE OR PRODUCT RELEASE火灾或者泄漏
的后果......................................................................................................................................................6
6 PRIORITISE THE FIRE PROTECTION MEASURES优先的消防措施................................6
7 QUANTIFY THE FIRE FIGHTING MEASURES消防设备的配备........................................7
8 ASSESSMENT OF THE SURFACE DRAINAGE CAPACITY地表排水容量的评估...........7
SHORT REFERENCE SHEET 1 OF 2................................................................................................8
SHORT REFERENCE SHEET 2 OF 2................................................................................................9
PLOT PLAN............................................................................................................................................9
APPROACH.............................................................................................................................................9
9 PIPA FLAME AND DISPERSION PLANS PIPA 火灾和气体散布模型图...........................11
9.1 GAS LEAK DISPERSION气体泄漏散布图...............................................................................11
9.2 Jet Fire Views火焰喷射图.....................................................................................................11
When field confirms leakage or fire, panel operators in CCR will press emergency
stop button 13HZ1300 to shut down the plant and start to depressurize gasifier
system.
当主控室确认泄漏或者火灾,在主控的键盘操作员将按下紧急停车按钮13HZ1300.进行
紧急停车处理,开始对气化系统进行泄压。
This will take more than 30 minutes.
此过程将用时大于5分钟。
Due to the nature of the leak, the field operator cannot do any immediate isolation.
由于泄漏气体的特性,现场操作人员不能进行任何直接的隔离。
在火焰辐射半径10m以内的设备:钢结构设备需要保护,设备电缆可能已经被损坏了。
Equipment outside 10 m in radius of fire source( equal to radiation less than 2.5KW/M2): fire
can be put out manually.
在火焰辐射半径10m以外的设备( equal to radiation less than 2.5KW/M2辐射值小
于2.5KW/M2):火焰可以人工扑灭。
Caution: Above models do not consider wind direction, which is an important parameter.
注意:以上的假设模拟没有考虑风向这一个重要参数。
如没有起火,CCR立即开始泄压。
Connect HP water to fire riser and with FIT wearing breathing equipment, at the
23.5m level, connect to the riser and approach behind a water curtain to ensure quick
dispersal of the gas.
连接高压消防栓到消防竖管,FIT人员穿戴BA,在23.5m,将消防水带与竖管接口连
接,在水幕后确保气体的及时稀释。
In the event of ignition:
如起火
Provide local cooling of surrounding equipment from the 23.5m level using the riser.
利用竖管对23.5m层的临近设备进行降温冷却。
Assum ing假定 :
When Field confirms leakage or fire, panel operators in CCR will press emergency stop
button 13HZ1300 to shut down the plant and depressurize gasifier.
CCR人员在屏幕上按下紧急停车按钮13HZ1300后进行停车减压处理。
Based upon system volume, depressurisation will take more than 30 minutes.
基于对系统容量的考虑,减压过程将用时大于30分钟。
Plan at 23.5m
Approach
型图