UNIT PRICE ANALYSIS (ARCHITECTURE WORK)

UNIT RATE AMOUNT


DESCRIPTION ITEMS OF WORKS KOEF UNIT
(Rp) (Rp)
1m2 Lime Stone Lime Stone 0.33 m3 518,571.43 171,128.57
Semen PC Bosowa 50 kg 0.21 zak 63,000.00 13,230.00
Sand 0.05 m3 360,000.00 18,000.00
Upah Pecah Batu 1.10 m2 180,000.00 198,000.00
Upah Pemasangan 1.10 m2 95,000.00 104,500.00
Sub Coating Batu Alam 1.00 m2 30,800.00 30,800.00

Tools 15,145.76
Sub- Total 550,804.33
OH 33,048.26
Profit 55,080.43
Total 638,933.02
PPH 19,167.99
Lime Stone m2 Total 658,100.00