Professional Documents
Culture Documents
XCTURGAAAAAAAAAA
XCTURGAAAAAAAAAA
7
Published by the Brick Development Association
January 1988
A REINFORCED
BRICKWORK FREESTANDING
B O U N D A R Y WALL
By G.D. Johnson B Eng(Tech) PhD MICeram MIStructE C. Eng.
Consulting Engineer, Hertford.
This File Note describes the design and in perhaps too many instances, are not
construction of a "simple" garden wall designed by structural engineers.
- a project which cost less than £4,000. Secondly the File Note describes how
Nonethelesss, it is interesting for at least tight cost constraints were fulfilled by
two reasons. Firstly freestanding walls, adopting a reinforced solution.
--``,,`,,,,``,`,,,,,,```,`,`,,``-`-`,,`,,`,`,,`---
INTRODUCTION
Brick boundary walls are a common
feature of the built environment in Britain.
They not only enhance a property but
often provide an element of both security
and privacy. While much time will
undoubtedly be spent on the planning,
design and detailing of the dwelling,
freestanding walls are seldom subjected to
an engineering appraisal but are left to the
bricklayers to build.
However, attitudes are changing and
many more walls are now being designed
on sound engineering principles. The BDA
Design Guide No 12 "The Design of
Freestanding Walls" is a useful publication
in this regard.
As with any structure, economy of
design is of importance and this File Note
describes the design and construction of
one particular boundary wall, where
economics, aesthetics and engineering
considerations led to the adoption of a
fully reinforced brickwork solution.
BRIEF
The brief was to design and construct a
boundary wall between a public footpath
and a private garden to enhance the
property and to ensure privacy. A wall
height of at least 2m above footpath level
was therefore required. Cost was an
important consideration since the wall
was to be 25m long. The side of the wall
adjacent to the footpath had to present a
smooth, uninterrupted face free from piers
and obstructions. In addition, since part of
the garden was higher than the path, the
wall was required to act as a retaining wall
in places. A further consideration was that
disruption to the footpath should be
minimal during the construction process
as should any damage to the footpath's
surface if consequent expensive
reinstatement was to be avoided. Finally,
as a planning consideration, the brick to
be used for the wall was to blend and --``,,`,,,,``,`,,,,,,```,`,`,,``-`-`,,`,,`,`,,`---
The brick chosen to complement the grouted cavity section was used. Typical
existing brickwork was in the upper half of sections are shown in Fig.2.
the price spectrum. It was obviously Some light bed joint reinforcement was
important to keep costs to a minimum and to be included in the panels to enhance
it was decided to construct the wall, as far the integrity of the wall under accidental
as possible, as a single leaf wall,supported loads.
at intervals by piers. The piers required to The concrete base was designed to
be on the garden elevation so as to leave a resist the applied moments from the piers
smooth side adjacent to the footpath. and to provide stability to the wall as a
Further economy of materials could be whole.
made by adopting a reinforced brickwork Because there was to be no significant
section for the piers. Thus for the intrusion into the footpath - thus requiring
freestanding wall all brickwork could be minimal reinstatment afterwards - the
constructed as a single skin of stretcher foundations to the reinforced brick piers
bond with intermediate 327.5mm square were extended to the rear of the wall to
hollow piers. At sections where the wall is provide the necessary stability.
called upon to retain soil, a reinforced
CONCRETE CAPPING
DPC
DPC
GARDEN
A98 MESH
PUBLIC FOOTPATH
1000
1 N ° T12 BAR
CONCRETE BASE
300
A142 MESH
AA BB
--``,,`,,,,``,`,,,,,,```,`,`,,``-`-`,,`,,`,`,,`---
Fig. 3. 1200
700
1 N° T12 BAR IN
(PEA GRAVEL) INFILL CONCRETE
327.5
200
327.5
500
200
PLAN ON PIER
1200
MASTIC POINTING +
1200
SOFT BACKING
12mm
SECTION THRO'
= 36.3 kN COLUMN THUS:
Therefore:
As REQD =
= 91 m m 2
3. Wind Panels
--``,,`,,,,``,`,,,,,,```,`,`,,``-`-`,,`,,`,`,,`---
M xx = PW (2/2 + 1.1) + Pa 1.1/3
= 5.2 kN.m/m
Therefore:
As Reqd =
= 90mm7m
2. Reinforced Brickwork
= 0.17 N / m m 2
T H E E N G I N E E R S F I L E N O T E S S E R I E S B I N D E R
A specially designed binder has been produced to hold the File Note Series and is available from the
Promotional Manager, the Brick Development Association,
Woodside House, Winkfield, Windsor, Berkshire SL4 2DX.
Please enclose £2.50 remittance per binder to cover post and packing.
Readers are expressly advised that, whilst the contents of this publication are believed to be accurate, correct and complete, no reliance should be placed upon its
contents as being applicable to any particular circumstances Any advice, opinion or information contained is published only on the footing that the Brick
Development Association, its servants or agents and all contributors to this publication shall be under no liability whatsoever in respect of its contents.