Professional Documents
Culture Documents
RZQ 200 My 1
RZQ 200 My 1
RZQ180MY1
RZQ200MY1
1
CAUTION
1-2 Special notice of product
2-1 Combination
• Be sure to connect a dedicated indoor unit. See the catalog
for indoor unit models which can be connected.
(inch) 3/4
Top plate
Gas side
Connection (mm) Ø19.1
piping (inch) 3/8
Liquid side
(mm) Ø9.5
Front plate screw
2-4 Accessories
Inlet holes
Check if the following accessories are supplied with the unit.
(Remove the front plate and they are in the accessory bag) Conner
Name Operation manual Installation manual Clamp Outdoor unit
Handles
Quantity 1 pc. 1 pc. 2 pcs.
Shape
Note
Shape Do not place your fingers into the inlet holes of the casing
while moving the unit. Failure to do so may result in
deformation. Only hold the corner of the unit with your hands.
Use the accessories or the specified parts to install the required parts.
Accessory bag
0 or
(5) The refrigerant gas (R410A) is nontoxic, nonflammable and 50
safe. It is necessary to take measures against to keep
refrigerant concentration from exceeding allowable safety
limits in a small room in the event of refrigerant leakage.
(6) An inverter air conditioner may cause home appliances
produce noise. ore
When selecting the location for installation, keep the air o rm
1 00
conditioner and wiring a proper distance away from radios,
computers and stereo equipment as shown in the following figure. • Obstacle on the suction side and both sides
Particularly for location with weak wave reception, be sure to keep
s
a distance of at least 3m between the indoor unit and the remote les
1000 or more
0 or
controllers and place the power supply wiring and transmission 50
wiring in conduits, and connect the conduits to the ground.
In addition, use the shielded wires for all electric wires between
units.
Indoor unit Branch circuit
Branch circuit breaker (over 15
breaker (over current circuit 0o
rm
more
re
ore
breaker) remote 15 r mo
1m or m
1.5m or
1000 or more
10 s
0o
rm r les
ore 0o
50 • No obstacle above
1. Stand-alone installation
10 10
00 0o
or rm
mo ore
re
H
ore
L
20
0o rm
rm o ore
ore 300 o rm
1 00
(7)-2 Where there is an obstacle on the discharge side: L>H o re
o rm
• No obstacle above 00
10
1. Stand-alone installation 2. Series installation (2 or more) (note1)
100
or m
ore
100
or m
ore
H
ore
L
o rm re
500 mo
0 or
2. Series installation (2 or more) (note1) L>H 30
ore
10 o rm
0o 00
rm 10
ore
10 • Obstacle above, too
0o
rm 1. Stand-alone installation
ore
The relations between H, A and L are as follows:
L A
0<L≤1/2H 750
L≤H
re
mo 1/2H<L≤H 1000
or
00 H<L Set the stand as: L≤H.
10
• Obstacle above, too (Note) Close the bottom of the installation frame to prevent
the discharged air from being bypassed.
1. Stand-alone installation
ss
le ss o r le
0 or 5 00
50
1000 or more
1000 or more
ore
L
o rm
H
2 50
m ore
re or
mo A
or
00
10 2. Series installation (2 or more) (note1)
2. Series installation (2 or more) (note1) The relations between H, A and L are as follows:
s L A
r les
0o
1000 or more
10 0<L≤1/2H 1000
0o
rm 50 L≤H
ore 1/2H<L≤H 1250
H<L Set the stand as: L≤H.
10 (Note1) Close the bottom of the installation frame to prevent
0o
rm the discharged air from being bypassed.
ore
(Note2) Only two units can be installed for this series.
re
re mo
r mo 0 or
00o 50
10
1000 or more
10
0o
rm
ore
re
L
mo
H
r
0o
30
o re
rm
Ao
• No obstacle above L A
1. Stand-alone installation 0<L≤1/2H 250
L≤H
L≤H 1/2H<L≤H 300
H<L Set the stand as: L≤H.
H
(Note1) Close the bottom of the installation frame to prevent
the discharged air from being bypassed.
(Note2) Only two units can be installed for this series.
ore
L
o rm (Note3) If the distance exceeds that within the ( ), even L>H,
100 there is no need to set the base.
m ore
or
H 1000 or more
00 s
10 les
0 or
2. Series installation (2 or more) (note1) 50
The relations between H, A and L are as follows: 100 or
more
L A
L
0<L≤1/2H 250
1/2H<L≤H 300 ore
rm
Ao
re
100 mo
or m 0 or 0)
0 0
ore 15 (22
100
or m
ore
(7)-4 Double-decker installation
H
L
500 or more
15
• Obstacle above, too
1. Stand-alone installation A
The relations between H, A and L are as follows:
L A ore
o rm
0<L≤1/2H 100 00
L≤H 10
1/2H<L≤H 200 (Note 1) Do not stack more than two unit.
H<L Set the stand as: L≤H. (Note 2) To prevent the drainage of the upper outdoor unit
from being frozen at the bottom, put the flap (field
(Note1) Close the bottom of the installation frame to prevent
the discharged air from being bypassed.
supply) as A part.
(Note2) If the distance exceeds that within the ( ), even L>H, (Note 3) Adequate space should be kept between the
there is no need to set the base. upper outdoor unit’s bottom plate and the flap.
(Note 4) Close the gap A (the gap between the upper and
s lower outdoor units) to prevent the discharged air
les
1000 or more
500 or more
L
re
r mo
Ao A
re
mo ore
0 or 0) rm
0 0 o
10 (17 3 00
ore
rm
100 Ao Projections Projections
ore
or m
0 or m (4 places) (4 places)
ore 300
ore
100 or m
H
or m 600
ore ore
rm
0o
150
(Note 1) When install the indoor units side by side, space
more than 100mm needs to be kept around them.
3. Connect the commercially-sold polyethylene tube
(inner diameter 25mm) to the drain socket (A).
5. PRECAUTIONS DURING INSTALLATION (If the tube is so long that it nearly hangs down, secure it
properly to prevent the tube from being twisted or bent.)
• To prevent vibration and noise, check the foundation is solid and 4. Check there is no water leakage from water outlets ,
level before installation. and .
• As shown in the following figure, firmly secure the unit to a
stable base using anchor bolts. Note
(Prepare four sets of M12 foundation bolts, nuts and washers If the water outlet is covered by the hanging bracket or floor,
each which are available on the market.) block up the air conditioner and keep an interspace over
• The foundation bolts should be inserted 20 mm. 100m under the outdoor unit’s footing.
20
Ground plan
Connect the
wires of the Clamps (accessories)
same size to Never connect Never connect
the sides two wires two wires of
respectively. together. different size.
• Refer to the table below for the tightening torque of the terminal
screws. Shielded part
Power wiring Electric wires
Tightening torque (N • m)
between units
M5 Power supply terminal 2.39~2.91 Clamps
M4 Shield earthing 1.18~1.44
(accessories)
Earth wire
M3 Internal unit wiring terminal 0.8~0.97 (yellow/green)
WARNING Note
After electrical work is completed, check to make sure there are no
After the fuse is blown, ask the serving agency to replace it.
loose connections for the connectors of each electrical component
Do not replace the fuse by yourself. Otherwise, it may cause
in the electrical component box and the terminals.
accidents such as electric shock.
Note
• Select the power wiring in accordance with the local and
F1 F2
national regulations in your area by referring to the above table. Using the
• Specifications of the field power wiring should be in compliance shielded 2-core Indoor unit
with IEC60245. wire (no polarity)
• Use wire type H05VV when the protective conduits are used for
the power wiring.
• Use wire type H07RNF when the protective conduits are not used. About length of the electric wires between units
• Only proceed with wiring work after turning off all the power. Exceeding the following length may result in abnormal signal
• Always earth the unit in accordance with the local and national transmission. Be sure to observe.
regulations in your area. Max. wiring length 300m or less
Total wiring length 600m or less
Max. number of branches 16
[ To open ]
7-1 Installation tools
1. Open the valve lid and turn the shaft counter clockwise with the
To withstand the pressure and prevent entry of any impurities inner hexagon wrench (JISB4648).
into the air conditioning system, always use the special 2. Turn it until the shaft stops.
installation tools for R410A.
3. Tighten the valve lid. (Refer to the column “Tightening torque”
• To withstand the pressure and prevent entry of for the tightening torque.)
any impurities (mineral oils such as specialized
Service port
Multi-purpose lubricating oil and moisture), be sure to use the
gauge hose special installation tools for R410A.
(Screw specifications for R410A and R407C are On Valve lid
different.)
Off
• Make sure that the engine oil in the pump will not
flow backward into the air conditioning system Pinched piping (large)
Vacuum pump when the pump stops. Cut off here
• Use the vacuum pump able to lower the pressure Pinched piping
to -100.7Pa (5Torr, -755mmHg). (small)
[ To close ]
7-2 Selecting piping material
1. Open the valve lid and turn the shaft clockwise with the inner
• Do not use the pipes covered with sulfur, iron oxide, dust, cutting hexagon wrench (JISB4648).
oil, moisture or other contamination inside. (Better not to exceed 2. Tighten the valve safely until it contacts with the gasket of the
30mg/10m for the oil inside the pipes). valve body.
• Select a thickness for the refrigerant piping in accordance with 3. Tighten the valve lid. (Refer to the column “Tightening torque”
the local laws and regulations. for the tightening torque.)
For R410A, the design pressure is 4.0 MPa.
• Use the refrigerant piping with its thickness complying with WARNING
Japan’s High-Pressure Gas Control Law (January 2003).
While removing the pinched piping (large), the residual gas and
• Thickness and size: determine them based on the precautions oil remained in the piping of the valve body may cause the stop
for piping size selection on the back. valve cracks, and the flames of the latter may result in burns
• While performing the piping work, make sure that the piping is also.
within the maximum allowable ranges for length, height in
difference and branch piping length listed on the back. • Before brazing the removed pinched piping (large) and field
piping connection
7-3 Piping protection Take cooling measures for the stop valves (such as wrapping a
wet and dripless cloth to them). Failure to do so will result in
• Maintain and protect the piping to prevent moisture from getting damage to the valve body and cause the system leaks.
into and the entry of the impurities and dust, etc.
• Brazing piping locally (liquid side and gas side)
• Pay special caution when penetrating the copper pipes through
the walls till outside. 1. Remove the two piping cover plates under the unit.
2. When brazing, it is necessary to penetrate the electrode
Location Installation schedule Protection measure from the front of the unit and the welding torch from the right
More than a month Pinch side to braze with the flames facing outside and avoid the
Outdoor compressor sound-proof material and other piping.
Less than a month
Pinch or seal with tape (Refer to the figure on next page)
Indoor Random
Note
1. Before brazing, peel off the caution label and check there
is no residual tape.
Otherwise, it will adversely affect the brazing.
2. Braze the liquid side piping (thin) and the gas side piping
(thick) in order.
Brazing methods are same for the two.
10
Right
Front Electrode Back
Front plate screw
Notch
• Be sure to charge nitrogen into the pipe when brazing.
Be sure to perform nitrogen purge or nitrogen charge when
Notch
brazing. Failure to do this will create large quantities of oxide film
on the inside surface of the pipes, which would adversely affect
the valves and compressors in the refrigerating system and
• After drilling through the knockout holes, it is recommended to
prevent the normal operation.
coat the notches at the edge and the area around them with
Note anti-corrosion paint to prevent rusting.
• When charging nitrogen before brazing, the pressure • When leading the electric wires through the knockout hole, wrap
regulator must be set to 0.02 MPa (0.2 kg • f/cm2 or less: as a the wires with the protective tape to avoid damage.
slight breeze on your cheek). Connect the piping forward
• Do not charge other refrigerant other than the specified one
for the refrigerating system.
Gas side accessory
• Do not charge the air for the refrigerating system. piping (1)
Nitrogen
Nitrogen
Packing
Manual valve Gas side accessory
piping (2)
11
Example of connection
Cut the piping to
the required length Outdoor unit
Note
7-6 Piping insulation To increase the size of the piping joint (Ø19.1mm→Ø22.2mm and
• If temperature within the ceiling exceeds 30ºC and the humidity Ø9.5mm→Ø12.7mm), connect it using joints of different apertures
over RH 80%, thicken the insulation material of the refrigerant (field supply).
piping. (Thickness at least 20mm) In addition, connection part should be set beside the outdoor unit
(Condensation might form on the surface of the insulation (behind the 1st bending outside the unit).
material.)
• The connection piping (liquid side, gas side) and the refrigerant
branch kit must be insulated.
(Otherwise, it may cause water dripping.)
(Be sure to use the insulation material with high-heat-
resistance performance as the gas side piping can reach
temperature of about 120ºC)
12
( ) ( )
Total length of Total length of unit Indoor unit
R= liquid side piping ×0.12 + liquid side piping ×0.059 +
size at Ø12.7 size at Ø9.5
Nitrogen
( )
Total length of Valve
liquid side piping ×0.022 (open) Stop valve service port
size at Ø6.4
Vacuum pump Charge hose
Check the following after piping connection is finished. Service port To open
To open
Shaft
Air tight test
Always use nitrogen. (Refer to Stop valve operation procedure for Valve lid
service port’s position.)
<Liquid side> <Gas side>
[Procedure]
Pressurize the liquid side piping and the gas side piping to 4.0MPa
(do not exceed 4.0 MPa). If the pressure does not drop within 24
hours, the system passes the test. Shut off valve operation procedure
If there is a pressure drop, check for leaks. (Discharge the nitrogen
after confirming there is no leakage.) Prepare two inner hexagon wrenches.
To open
Vacuum drying
1. Put the inner hexagon wrench to the valve shaft and turn it
Use a vacuum pump able to evacuate the system to -100.7 kPa counterclockwise.
(5Torr, -755mmHg) or less. 2. Turn it until the shaft stops. The valve is opened.
[Procedure] To close
Evacuate the system from the liquid side piping and gas side piping 1. Put the inner hexagon wrench to the valve shaft and turn it
using a vacuum pump for more than 2 hours to -100.7 kPa or less. clockwise.
Keep the system under this condition for more than 1 hour, check if
the vacuum gauge indication rises or not. 2. Turn it until the shaft stops. The valve is closed.
(If it rises, the system may either contain moisture inside or have
gas leak.) About valve lid
If moisture might enter the piping (e.g. if doing work during the • Be sure to tighten the valve lid after valve operation is
rainy season, if the actual work takes long enough that condensation completed.
may form on the inside of the pipes, if rain might enter the pipes About service port
during work, etc.)
After performing the vacuum drying for 2 hours, pressurize to • Operate with the charge hose with a pushing stick.
0.05 MPa (vacuum breakdown) with nitrogen gas, then depressurize • Be sure to tighten the valve lid after operating.
down to -100.7 kPa or less and hold for an hour using the vacuum
pump (vacuum drying). Tightening torque
(If the pressure does not reach -100.7 kPa even after depressurizing Look through the table below for the stop valve tightening torque.
for at least 2 hours, repeat the vacuum breakdown-vacuum drying
process.) After vacuum drying, maintain the vacuum for an hour and [Specifications]
make sure the pressure does not rise by monitoring with a vacuum
Liquid side stop valve Ø9.5mm
gauge.
Gas side stop valve Ø19.1mm
13
Size Tightening torque N·m (turn clockwise to close) Stand the tank upright Stand the tank
(mm) Shaft (stop valve body) Cap (valve lid) Service port and charge. upside-down and
(Due to the siphon pipe charge.
Inner hexagon within the tank, there is
Ø9.5 5.4~6.6 13.5~16.5
wrench 4mm
11.5~13.9 no need to turn over the
Ø19.1 27.0~33.0
Inner hexagon
22.5~27.5
tank to charge).
wrench 8mm
1. Calculate the refrigerant charge according to “How to calculate
the refrigerant to be charged” in “7. REFRIGERANT PIPING
CONNECTION”.
8. CHARGING REFRIGERANT 2. After completing vacuum drying, discharge the air in the charge
hose, then open the valve and charge the refrigerant of the
WARNING calculated amount in the liquid phase from the liquid side stop
valve service port.
• Be sure to inform other installers or attach the front panel 3. Close the valve after completing refrigerant charging.
well before you leaving with the power supply turned on for Note) If it is impossible to charge the amount calculated
the outdoor unit. according to above procedure, charge the refrigerant
(Raise the front panel as high as possible during installation again using procedure on the right.
to clamp it with the top panel.)
State of the stop valves and valve A
• For operation instructions of the stop valves. refer to Stop valve operation
procedure in “7. REFRIGERANT PIPING CONNECTION”.
8-1 Before charging refrigerant
R410A tank
• Check the following works are completed in accordance with the (with siphon pipe)
installation manual. Liquid side Outdoor Gas side
stop valve unit stop valve
• Piping work
• Electrical work
• Air tight test and vacuum drying Gauge
Valve A Stop valve
Indoor unit
service port
8-2 About refrigerant tank
Liquid side Gas side
• Check whether the tank has a siphon pipe before charging and ON/OFF state of the valve A and stop valves Valve A
stop valve stop valve
place the tank properly so that the refrigerant is charged in the Before starting charging OFF OFF OFF
liquid phase (see the figure in 8-3 Charging refrigerant). During charging operation ON OFF OFF
8-3 Charging refrigerant If the refrigerant of the calculated amount is not charged fully
Perform refrigerant charging operation according to the following
Electric shock warning procedure to charge refrigerant. For settings of refrigerant charging
operation, refer to the “Service Precautions” label attached under
• Never touch other parts excluding the push buttons of the PC the front panel of the electronic component box.
board (A1P) during setting.
• There is a risk of electric shock if you touch wrong, since this [Procedure]
operation must be performed with the power on. 1. Turn on the power supply of all indoor and outdoor units of the
system.
2. Open the gas side and liquid side stop valves and perform
CAUTION refrigerant charging operation. (Open the valve A immediately
• Use protective equipment (groves and goggles) when charging after compressor starts up.)
the refrigerant. 3. After charging a specified amount of refrigerant, press the
• To prevent the liquid hammer, the refrigerant must not be RETURN button (BS3) on outdoor unit’s PC board (A2P) to
charged over the allowable maximum amount. stop refrigerant charging operation.
• Do not perform the refrigerant charging operation when indoor 4. Close the valve after completing charging operation.
unit is under construction.
• Beware the fan running when opening the front panel. State of the stop valves and valve A
The fan may continue rotating after the outdoor unit stops. • For operation instructions of the stop valves. refer to Stop valve operation
procedure in “7. REFRIGERANT PIPING CONNECTION”.
• The service port (for refrigerant charging) is within the outdoor unit.
Note • Since the unit is filled with refrigerant when shipped out of the factory, take
care while installing the charge hose.
• The refrigerant charge port is connected to the unit piping.
• Be sure to close the service port cover (for refrigerant charging) after
When shipped, the unit’s piping is charged with refrigerant, take completing refrigerant charging. Tightening torque of the service port cover is
care when attaching the charge hose. 11.5 ~ 13.9 N·m.
• After refrigerant charging is completed, secure the refrigerant Service port
charge port cap tightly, to a tightening torque of 11.5~13.9 N∙m. (for refrigerant charging)
• See stop valve operation procedure under “7. REFRIGERANT Gas side stop valve Outdoor
PIPING CONNECTION” for details on Stop valve operation Liquid side stop valveunit
procedure. Valve A R410A tank
• When the refrigerant charging operation is completed or (with siphon pipe)
paused, close the valve of the refrigerant tank immediately. If the Stop valve
tank valve is left open, the amount of refrigerant which is Gauge
service port Indoor unit
properly charged may be off the point. Because even if the air
conditioner stops, the refrigerant will be charged into the unit
Liquid side Gas side
under the residual pressure. ON/OFF state of valve A and stop valves Valve A
stop valve stop valve
Before starting charging OFF ON ON
During charging operation ON ON ON
14
5. Press TEST button (BS4) for • This display of the remote controller
5 seconds or more to perform indicates symbol if test run during this
10. ABOUT TEST RUN test run.
See Test run precautions on •
operation.
Ask other installers to perform test run or
the “Service Precautions” label attach the front panel before having to leave
To start smoothly, a crankcase heater is equipped to the unit. for details. the outdoor unit working alone.
To power up the crankcase heater, be sure to turn on the • Test run is automatically stopped after about
power supply 6 hours before operation. 15 minutes (maximum 30 minutes)
operation. (When charging the refrigerant of
calculated amount, test run is automatically
WARNING stopped after 30 minutes (maximum 1 hour)
operation.)
Be sure to inform other installers or attach the • If there is a malfunction code on the display
front panel well before leaving with the power of the remote controller, please check the
supply turned on for the outdoor unit. malfunction code details on page 16 and fix
the malfunction. After that, push and hold
(Raise the front panel as high as possible during
the RESET button for 5 seconds.
installation to clamp it with the top panel.) Then make sure to perform a test run again.
• After test run is completed, If there is no
malfunction code on the display of the
remote controller, the unit can perform
Before powering on
normal operation 3 minutes later.
6. Be sure to attach the front panel of the outdoor unit after test run is completed.
• Indoor unit connected with the outdoor unit will operate
automatically after powering on.
To ensure safety, check the indoor unit installation has been
completed.
[About test run]
• If the system is started within 12 minutes after turning on
10-1 Powering on – test run the power supply using the remote controller, H2P will light
up and the compressor will not operate.
• Make sure to perform a test run first after installation. (If the unit Before operating, always check whether the symbols indicated
is operated with the indoor unit’s remote controller but without on the LED display are those in the table under 10-1 Powering
performing test run, the malfunction code test “U3” will be on – test run 2.
indicated on the display of the remote controller and the unit will • In order to ensure uniform refrigerant distribution, it may take up
not operate normally.) to around 10 minutes for the compressor to start up after the
• After turning on the power supply, do not touch any parts unit starting operation. This is not malfunction.
excluding button switches and changeover switches when • Be sure to perform malfunction check for all indoor units.
setting the outdoor unit’s PC board (A1P). After completing test run, operate the system normally with the
(For positions of the button switches (BS1~5) and changeover remote controller.
switches (DS1-1~4) on PC board, refer to the “Service
Precautions” label.) • Test run cannot be performed when the unit is in other modes
such as refrigerant recycling mode.
• Check the state of the outdoor units and fault wiring with this
operation. • Never perform test run with suction pipe thermistor (R2T),
discharge pipe thermistor (R3T) and pressure sensor (S1NPH,
S1NPL) removed. Failure to do so will result in compressor
damaged.
15
16
17