Professional Documents
Culture Documents
Transpot of Materials and Equipment For The Construction of The Kainji Hydro Electric
Transpot of Materials and Equipment For The Construction of The Kainji Hydro Electric
Mr G . Belloni, lmpregilo
The teamwho studied the transportof cement for Kainji Dam, in co-operation with a
large group of engineers and experts, have subsequently carried out a study to solve
transport problems at Tarbela Damin Pakistan, where 80 million tons of gravel and
silt had tobe moved from borrow areas to the dam, with a hauling distanceof 6 miles
and a rate of placing of 3.1 million cu. yd/month. A conveyor system has been in-
stalled which carries the materials from the borrow area to the dam site, in tunnel and
in the open.
Mr MacKichan
I should like to thank Mr Guglielmini for his description of the developments in the
field of cement transportation since the time of construction of the Kainji Dam.
82. Mr Belloni has spoken of the problems of transporting 80 million tons of fill
dam materials for the construction of Tarbela Dam, at the rate of 3.1 million cu. yd/
month. There were 10 million cu. yd of materials in the Kainji fill dams and at this
rate they could have been finished in a little over three months. Physically this could
not have been possible but it is an interestingcomparison and emphasizes the
enormous size of the Tarbela Dam.
83. At Portage Mountain Dam in British Columbia, Canada, of the order of
50 million cu. yd of materials had to be moved to form the dam. A conveyor was
also used there to transport theprocessed gravels and silts 17 miles to the dam site.
84. Mr Gwynn rightly said that the cause of the road accidents was basically due
to human errors. New roads had been provided, which compared with other local
roads invited fast driving, but once the speed limit was rigidly enforced the number of
accidents was reduced. On the whole the incidence of accidents was no more than
elsewhere in the country. The record for the transport of plant was good as Mr
Gwynn says.
85. During thetenderperiod when tenderers’ delegations were visiting Nigeria
and the dam site to obtain necessary information for their tenders, high floods were
experienced in Nigeria. Bridges were washed out, people were marooned and road
surfaces suffered. The timing was opportune as tenderers were thus able to see what
some of their transport difficulties might be. In the event, thehappenings of that year
were much more severe than experienced during construction.
Mr Jeffery
Mr Sorber referred to $ 14 concerning thepossible construction of a railway spur from
Mokwa to Kainji. Road access on the right bank, road access on the left bank from
the main north road (all weather) at Mokwa, and a rail spur from Mokwa separately
and in combination were considered. An all weather road on the left bank from
Mokwa was far more economical than the equivalent on the right bank, and, by
761
Conversion factors
Imperial units SI units
1 ton 1.016 t
1 cu. yd 0.7646 m3
762