Progres Bobot Semarang
Progres Bobot Semarang
I UMUM
1 Mobilisasi 1.00 Ls 17,000,000.00 17,000,000.00 0.54 1.00 17,000,000.00 0.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Manajemen Mutu 1.00 Ls 12,750,000.00 12,750,000.00 0.40 1.00 12,750,000.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Sub Jumlah 29,750,000.00 0.94 29,750,000.00 0.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
II PEKERJAAN PEMBONGKARAN
1 Pembongkaran Beton Struktur 1,468.84 m³ 208,250.00 305,885,930.00 9.66 347.71 72,410,846.78 2.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.38
Sub Jumlah 305,885,930.00 9.66 72,410,846.78 2.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.38
III PEKERJAAN TANAH DAN GEOOSINTETIK
1 Galian biasa untuk dibuang (waste) 1,569.00 m³ 38,000.00 59,622,000.00 1.88 371.42 14,114,017.95 0.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.44
2 Urugan material berbutir (granular backfill) 784.50 m³ 280,500.00 220,052,250.00 6.95 185.71 52,091,868.88 1.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.31
Sub Jumlah 279,674,250.00 8.84 14,114,017.95 2.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.74
IV PERSIAPAN TANAH DASAR
1 Pemadatan dengan Stamper 2,791.30 m³ 9,000.00 25,121,700.00 0.79 660.77 5,946,934.43 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.61
Sub Jumlah 25,121,700.00 0.79 5,946,934.43 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.61
V LAPIS PONDASI AGREGAT
1 Lapisan Pondasi Agregat Kelas A 784.50 m³ 297,500.00 233,388,750.00 7.37 185.71 55,248,951.84 1.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.63
Sub Jumlah 233,388,750.00 7.37 55,248,951.84 1.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.63
VI PEKERJAAN PERKERASAN
1 Pengersan Beton Semen Fast Track 3 hari 523.50 m³ 1,870,000.00 978,945,000.00 30.93 123.93 231,740,755.13 7.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.60
2 Pengersan Beton Semen Single Wire Mesh Fast Track 3 hari 313.89 m³ 2,337,500.00 733,717,875.00 23.18 74.31 173,689,363.96 5.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.69
2 Wet Lean Concerte (t=10cm) 2,791.30 m² 115,000.00 320,999,500.00 10.14 660.77 75,988,606.64 2.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.74
Sub Jumlah 2,033,662,375.00 64.24 307,729,361.76 15.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49.04
VII PEKERJAAN LAIN-LAIN
1 Expantion Joint Aspal (Asphaltic Plig Joint) 67.20 m 2,500,000.00 168,000,000.00 5.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.31
Sub Jumlah 168,000,000.00 5.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.31
VII PENGAMANAN LALU LINTAS
1 Pengamanan dan Pengaturan lalu lintas Tipe A 60.00 Hari 1,500,000.00 90,000,000.00 2.84 5.00 7,500,000.00 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.61
Sub Jumlah 90,000,000.00 2.84 7,500,000.00 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.61
JUMLAH HARGA DAN BOBOT 3,165,483,005.00 100.00 492,700,112.77 22.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 77.30
YUSWADI, ST
Nip. 19760521 200904 1 004