PROYEK : PEMELIHARAAN PERIODIK (SFO) DAN REKONSTRUKSI PERKERASAN PADA LAPORAN

RUAS JALAN TOL SEMARANG 2024 PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN Rekonstruksi Perkerasan Beton pada Ruas Jalan Tol Semarang


LOKASI Semarang KONTRAKTOR PELAKSANA
NO. KONTRAK MINGGU ke - 1
TGL. KONTRAK PERIODE I
PROGRESS S.D SAAT INI 22.70 %

NILAI KONTRAK REKON L1 REKON L2 REKON L3 REKON L4 EXPANTION JOINT


BOBOT YANG BELUM
NO URAIAN PEKERJAAN VOLUME KONTRAK SAT JUMLAH JUMLAH JUMLAH
HARGA SATUAN (Rp) JUMLAH HARGA (Rp) BOBOT (%) VOLUME JUMLAH HARGA (Rp) BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME JUMLAH HARGA (Rp) BOBOT (%) DIKERJAKAN (%)
HARGA (Rp) HARGA (Rp) HARGA (Rp)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

I UMUM
1 Mobilisasi 1.00 Ls 17,000,000.00 17,000,000.00 0.54 1.00 17,000,000.00 0.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Manajemen Mutu 1.00 Ls 12,750,000.00 12,750,000.00 0.40 1.00 12,750,000.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Sub Jumlah 29,750,000.00 0.94 29,750,000.00 0.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
II PEKERJAAN PEMBONGKARAN
1 Pembongkaran Beton Struktur 1,468.84 m³ 208,250.00 305,885,930.00 9.66 347.71 72,410,846.78 2.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.38
Sub Jumlah 305,885,930.00 9.66 72,410,846.78 2.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.38
III PEKERJAAN TANAH DAN GEOOSINTETIK
1 Galian biasa untuk dibuang (waste) 1,569.00 m³ 38,000.00 59,622,000.00 1.88 371.42 14,114,017.95 0.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.44
2 Urugan material berbutir (granular backfill) 784.50 m³ 280,500.00 220,052,250.00 6.95 185.71 52,091,868.88 1.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.31
Sub Jumlah 279,674,250.00 8.84 14,114,017.95 2.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.74
IV PERSIAPAN TANAH DASAR
1 Pemadatan dengan Stamper 2,791.30 m³ 9,000.00 25,121,700.00 0.79 660.77 5,946,934.43 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.61
Sub Jumlah 25,121,700.00 0.79 5,946,934.43 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.61
V LAPIS PONDASI AGREGAT
1 Lapisan Pondasi Agregat Kelas A 784.50 m³ 297,500.00 233,388,750.00 7.37 185.71 55,248,951.84 1.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.63
Sub Jumlah 233,388,750.00 7.37 55,248,951.84 1.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.63
VI PEKERJAAN PERKERASAN
1 Pengersan Beton Semen Fast Track 3 hari 523.50 m³ 1,870,000.00 978,945,000.00 30.93 123.93 231,740,755.13 7.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.60
2 Pengersan Beton Semen Single Wire Mesh Fast Track 3 hari 313.89 m³ 2,337,500.00 733,717,875.00 23.18 74.31 173,689,363.96 5.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.69
2 Wet Lean Concerte (t=10cm) 2,791.30 m² 115,000.00 320,999,500.00 10.14 660.77 75,988,606.64 2.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.74
Sub Jumlah 2,033,662,375.00 64.24 307,729,361.76 15.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49.04
VII PEKERJAAN LAIN-LAIN
1 Expantion Joint Aspal (Asphaltic Plig Joint) 67.20 m 2,500,000.00 168,000,000.00 5.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.31
Sub Jumlah 168,000,000.00 5.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.31
VII PENGAMANAN LALU LINTAS
1 Pengamanan dan Pengaturan lalu lintas Tipe A 60.00 Hari 1,500,000.00 90,000,000.00 2.84 5.00 7,500,000.00 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.61
Sub Jumlah 90,000,000.00 2.84 7,500,000.00 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.61

JUMLAH HARGA DAN BOBOT 3,165,483,005.00 100.00 492,700,112.77 22.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 77.30

Disetujui Oleh, Diperiksa Oleh,


Pengawas Lapangan

YUSWADI, ST
Nip. 19760521 200904 1 004