LL-MN-03 - Rolling Mill Fix Compensation Influence On The Network
LL-MN-03 - Rolling Mill Fix Compensation Influence On The Network
LL-MN-03 - Rolling Mill Fix Compensation Influence On The Network
Notes
The PFM300 ANALYZER is installed at the PCC (230kV Line) of Las Lomas Substation in order to register
and analyze the behavior of the EAF and LF furnaces.
The Monitor tool of the PFM300 ANALYZER has a recording rate of every 1 second. All instantaneous
peaks value obtained in a sample time of 1 second.
On October 26, 2021 Furnace stop operation at 10:45 am due to some problems. Rolling Mill in the
other side operated until 17:52 pm.
POWER MV SIDE
Figure 1
U THD HV SIDE
Figure 2
VOLTAGE HV SIDE
Figure 3
VOLTAGE MV SIDE
Figure 4
After Operation
U THD
Figure 5
VOLTAGE
Figure 6
FLICKER
Figure 7