OFFICE OF THE PROJECT DIRECTOR RSRDC LTD. UNIT - IV JAIPUR.

Email:- pdrsrdcunit4@gmail.com

BRIEF NOTE
As on 04.09.2023

Construction of Para Academy Hostel Building at Vidhyadhar Nagar


1 Name of work
Stadium Jaipur (excluding cost of cement)

2 Name of client Rajasthan State Sports Council, Jaipur

1.) Sanction cost of the work : Rs. 300.00 Lacs.


3 Ref. of A & F sanction
issued vide शासन उप सचिव क्रमाां क -- F 11(4)Sports/2022 चिनाां क 23.08.2022

4 Fund Received Rs. 300.00 Lacs


Expenditure incurred
5 68.00 Lacs
upto Date (Rs. In Lacs )
6 Name of Consultant Inspiring Infraatech Consultants Architects, Planners, Interiors & PMC
7 Structure designed for G+2
Total Builtup Area (New
8 1400 Sqm
construction)

9 Agency
M/s Shri Govind Construction Co.,Jaipur
S. no Name of Agency

i WO. NO. / LOA NO. PD/JPR-IV/2022-23/35 dated 14.02.2023


ii Work order Amount Rs. 19045813.79
iii Stipluated date of Start 24.02.2023
iv Stipluated date of Comp. 23.10.2023
v Expected date of Comp. 23.10.2023
vi Expenditure in WO 57.13 lacs
Status Work in progress
vii
10 Scope of Work

S. N. Location Facilities Physical Progress


1 Ground floor Reception, Entrance Lobby, Office, Warden Room, Ground Floor roof
Dining Area, Kitchen, Rehabilitation Hall (2Nos), casted

2 First Floor Rooms (12 Nos), Housekeeping Store, Utility Area First floor
reinforcement work
in progress

11 Hinderance -