Ra

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 14

Project : Design, Construction, Finance, Operation and Maintenance of Four-Laning of Narketpally-Addanki-

Medarametla Road (SH-2) from Km. 0.000 to 212.500 in the state of Andhra Pradesh under Public Private
Partnership on DBFOT (Toll) Basis.
Concessionaire: M/s. N.A.M. Expressway Limited
Independent Engineer: M/s. LEA Associates South Asia Pvt. Ltd
Name of Work: PUP at Ch. 201+410 under negative Change of Scope
Summary of Item wise Rate Analysis as per Standard Data Book and SoR 2014-15
BoQ SDB
S. No Item Item Description Unit Rate (Rs)
No. No.
Construction of embankment with approved material obtained from borrow
1 1.01 3.16 pits with all lifts and leads, transporting to site, spreading, grading to Cum 195.00
required slope and compacting to meet requirement of table 300-2.
Providing and laying 25 mm thick mastic asphalt wearing course with
paving grade bitumen meeting the requirements given in table 500-29,
prepared by using mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid surface with bitumen
2 2.01 5.14 precoated finegrained hard stone chipping of 13.2 mm nominal size at the Sqm 505.00
rate of 0.005 cum per 10 sqm and at an approximate spacing of 10 cm center
to center in both directions, pressed into surface when the temperature of
surfaces is not less than 1000C, protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 515.
Provision of an Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed with M-40
grade concrete with HYSD reinforcement conforming to IRC:21 and dowel
bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded
3 3.01 8.22 Meter 2729.00
asphalt filler board, keyed to the structure on which it is built and installed
as per design given in the enclosure to MOST circular No. RW/NH -
33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified
Earth work in excavation of foundation of structures as per drawing and
12.1 B technical specification, including setting out, construction of shoring and
4 4.01 Cum 94.00
(i) bracing, removal of stumps and other deleterious matter, dressing of sides
and bottom and backfilling with approved material. - Depth upto 3 m
Plain/Reinforced Cement Concrete in Open Foundation complete as per
5 4.02 12.8 A Cum 3716.00
Drawing and Technical Specifications. - PCC Grade M15
Plain/Reinforced Cement Concrete in Open Foundation complete as per
6 4.03 12.8 G Cum 4377.00
Drawing and Technical Specifications. - RCC Grade M30
Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in
7 4.04 12.40 MT 51054.00
Foundation complete as per Drawing and Technical Specifications.
Plain/Reinforced cement concrete in sub-structure complete as per drawing
8 5.01 13.5 G Cum 4652.00
and Technical Specifications - RCC Grade M30
Supplying, fitting and placing HYSD bar reinforcement in sub-structure
9 5.02 13.6 MT 51200.00
complete as per drawing and Technical Specifications
Providing weep holes in Brick masonry/Plain/ Reinforced concrete
abutment, wing wall/ return wall with 100 mm dia AC pipe, extending
10 5.03 13.8 Each 501.00
through the full width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical Specifications
Providing and constructing filter media behind abutments, wing walls,
11 5.04 13.10 retaining walls and return walls complete as per Drawings and Technical Cum 745.00
Specifications Clause of IRC: 710.1.4 & 2200
Furnishing and Placing Reinforced/ Prestressed cement concrete in super-
12 6.01 14.1 C Cum 5084.00
structure as per drawing and Technical Specification - RCC Grade M30
Supplying, fitting and placing HYSD bar reinforcement in super-structure
13 6.02 14.2 MT 52328.00
complete as per drawing and technical specifications
14 6.03 14.9 Drainage Spouts complete as per drawing and Technical specification Each 5385.00
PCC M15 Grade leveling course below approach slab complete as per
15 6.04 14.10 Cum 3573.00
drawing and Technical specification
Reinforced cement concrete approach slab including reinforcement and
16 6.05 14.11 Cum 6811.00
formwork complete as per drawing and Technical specification

Concessionaire Independent Engineer


Project : Design, Construction, Finance, Operation and Maintenance of Four-Laning of Narketpally-Addanki-Medarametla Road (SH-2) from Km.
0.000 to 212.500 in the state of Andhra Pradesh under Public Private Partnership on DBFOT (Toll) Basis.
Concessionaire: M/s. N.A.M. Expressway Limited
Independent Engineer: M/s. LEA Associates South Asia Pvt. Ltd
Name of Work: PUP at Ch. 201+410 under negative Change of Scope
Summary of Item wise Rate Analysis as per Standard Data Book and SoR 2014-15
BOQ SDB Ref to
S.No Item Item MoRTH Description Unit Quantity Rate (Rs) Cost (Rs) Remarks / input Ref.
No. No Spec.
Construction of Embankment with Material
1 1.01 3.16 305
obtained from Borrowpits
Construction of embankment with approved
material obtained from borrow pits with all
lifts and leads, transporting to site, SDB (First Revision) Page
spreading, grading to required slope and No.68
compacting to meet requirement of table 300-
2.
Unit = cum
Taking output = 100 cum
a) Labour

Mate day 0.040 345.00 13.80 S. No.71 in Pg. no.8 of Part-II

Mazdoor day 1.000 295.00 295.00 S. No.73 in Pg. no.8 of Part-II

b) Machinery
Hydraulic Excavator - 60cum/hour hour 1.670 2848.50 4757.00 S. No.4 in Pg. no.22 of Part-II
Tipper 10 tonne capacity (160 X L) tonne. SDB (First Revision) Item
320.000 6.36 2035.20
L=2 Km km No.1.4
Add 10 per cent of cost of carriage to cover
203.52
cost of loading and unloading
Dozer 80 HP for spreading - 200cum/hour hour 0.500 2575.60 1287.80 S. No.1 in Pg. no.22 of Part-II
Motor grader for grading - 100cum/hour hour 1.000 3216.00 3216.00 S. No.2 in Pg. no.22 of Part-II
Water tanker 6 KL capacity hour 4.000 624.00 2496.00 S. No.10 in Pg. no.22 of Part-II
Vibratory roller 8 -10 tonnes - 100cum/hour hour 1.000 2678.30 2678.30 S. No.7 in Pg. no.22 of Part-II
c) Material
Cost of water KL 24.000 0.00 0.00
d) Overhead charges @ 4.615% on (a+b+c) 783.75
e) Contractor's profit @ 10% on (a+b+c+d) 1776.64
Cost for 100 cum (a+b+c+d+e) 19543.00
Rate per cum (a+b+c+d+e)/100 195.43
say 195.00

2 2.01 5.14 515 Mastic Asphalt

Providing and laying 25 mm thick mastic


asphalt wearing course with paving grade
bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker
and laid to required level and slope after
cleaning the surface, including providing
antiskid surface with bitumen precoated
SDB (First Revision) Page No.
finegrained hard stone chipping of 13.2 mm
151
nominal size at the rate of 0.005 cum per 10
sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed
into surface when the temperature of surfaces
is not less than 1000C, protruding 1 mm to 4
mm over mastic surface, all complete as per
clause 515.

Unit = sqm
Taking output = 35.00 sqm (0.87 cum )
assuming a density of 2.3 tonnes/cum.-2
tonnes
a) Labour
Mate day 0.44 345.00 151.80 S. No.71 in Pg. no.8 of Part-II
Mazdoor day 10.00 295.00 2950.00 S. No.73 in Pg. no.8 of Part-II
Mazdoor skilled day 1.00 310.00 310.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 357.00 21.42 S. No.16 in Pg. no.22 of Part-II
Air compressor 250 cfm hour 0.06 507.50 30.45 S. No.14 in Pg. no.22 of Part-II
Mastic cooker 1 tonne capacity hour 6.00 65.00 390.00 S. No.31 in Pg. no.23 of Part-II
Bitumen boiler 1500 litres capacity hour 6.00 209.00 1254.00 S. No.29 in Pg. no.23 of Part-II
Tractor for towing and positioning of mastic
hour 1.00 415.00 415.00 S. No.11 in Pg. no.22 of Part-II
cooker and bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60
per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40
per cent .
I) Bitumen @ 10.2 per cent by weight of mix.
tonne 0.20 39339.00 8025.16
2 x 10.2/100 = 0.204

Concessionaire Independent Engineer


BOQ SDB Ref to
S.No Item Item MoRTH Description Unit Quantity Rate (Rs) Cost (Rs) Remarks / input Ref.
No. No Spec.
ii) Fine aggregate passing 2.36mm and
retained on 0.075mm sieve @ 31.9 per cent by
cum 0.39 725.61 282.99
weight of mix = 2 x 31.9/100 = 0.638 tonnes =
0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium
content not less than 80 per cent by weight @
tonne 0.36 2491.00 896.76 M-188 in Page.21 of Part.I
17.92 per cent by weight of mix = 2 x
17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @
40 per cent by weight of mix = 2 x 40/100 = cum 0.55 1090.45 599.75 S. No.48 in Page.4 of Part.II
0.8 MT = 0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal
size for skid resistance = 35 x 0.005/10 = cum 0.02 1249.17 22.49 S. No.48 in Page.4 of Part.II
0.018
vi) Bitumen for coating of chips @ 2 per cent
by weight = 0.018 x 1.456 x 2/100 = 0.0005 kg 0.50 39.34 19.67
MT = 0.5kg
d) Overhead charges @ 4.615% on (a+b+c) 709.30
e) Contractor's profit @ 10% (a+b+c+d) 1607.88
Cost for 35 sqm (a+b+c+d+e) 17686.66
Rate per sqm (a+b+c+d+e)/35 505.33
say 505.00
3 3.01 8.22 809 Reinforced Cement Concrete Crash Barrier
Provision of an Reinforced cement concrete
crash barrier at the edges of the road,
approaches to bridge structures and medians,
constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:21
and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded SDB (First Revision) Page No.
asphalt filler board, keyed to the structure on 237
which it is built and installed as per design
given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June
1994 as per dimensions in the approved
drawing and at locations directed by the
Engineer, all as specified
Unit = Linear metre
Taking output = 10 m
a) M 40 grade concrete cum 3.00 4128.07 12384.20 SDB Item 12.11 (ix)
b) Labour
Mate day 0.04 345.00 13.80 S. No.71 in Pg. no.8 of Part-II
Mazdoor day 1.00 295.00 295.00 S. No.73 in Pg. no.8 of Part-II
c) Material
HYSD steel including dowel bars MT 0.28 39365.00 11022.20 S. No.62 in Page.4 of Part.I
d) Overhead charges @ 4.615% on (a+b+c) 1094.46
e) Contractor's profit @ 10 % on (a+b+c+d) 2480.97
Cost for 10 metre (a+b+c+d+e) 27290.62
Rate per metre (a+b+c+d+e)/10 2729.06
say 2729.00
12.11 RCC M40 Grade
Using Batching Plant, Transit Mixer and SDB (First Revision) Page No.
(ix)
Concrete Pump 353
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 51.60 3105.00 160218.00 S.no 5 in Pg.No. 1 of Part.I
Coarse Sand cum 54.00 904.19 48826.42 S. No.94 in Page.6 of Part.II
20 mm Aggregate cum 64.80 1303.00 84434.40 S. No.28 in Page.3 of Part.II
10 mm Aggregate cum 43.20 894.00 38620.80 S. No.26 in Page.2 of Part.II
Admixture kg 206.00 62.00 12772.00 S. No.70 in Page.4 of Part.I
b) Labour
Mate day 0.84 345.00 289.80 S. No.71 in Pg. no.8 of Part-II
Mason day 3.00 357.00 1071.00
Mazdoor day 18.00 295.00 5310.00 S. No.73 in Pg. no.8 of Part-II
c) Machinery
Batching Plant hour 6.00 1041.60 6249.60 S. No.32b in Pg. no.23 of Part-II
Generator 100 KVA hour 6.00 1126.00 6756.00 S. No.43 in Pg. no.24 of Part-II
Loader 1 cum capacity hour 6.00 1646.00 9876.00 S. No.5 in Pg. no.22 of Part-II
Transit Mixer for lead upto 1 km. hour 15.00 1941.10 29116.50 S. No.33 in Pg. no.23 of Part-II
Transit Mixer 4 cum capacity for lead beyond tonne.k
6600.00 6.36 41976.00 As per SDB Item no.1.4
1 km. (300 X L), L=10 Km. m
Concrete Pump hour 6.00 803.00 4818.00 S. No.34 in Pg. no.23 of Part-II
d) Formwork @ 10 per cent on cost of
concrete i.e. cost of material, labour and 10% 45033.45
machinery
Cost for 120 cum (a+b+c+d) 495367.97
Rate per cum (a+b+c+d)/120 4128.07

Concessionaire Independent Engineer


BOQ SDB Ref to
S.No Item Item MoRTH Description Unit Quantity Rate (Rs) Cost (Rs) Remarks / input Ref.
No. No Spec.
Earth work in excavation of foundation of
structures as per drawing and technical
specification, including setting out,
SDB (First Revision) Page No.
4 4.01 12.1 304 construction of shoring and bracing, removal
323
of stumps and other deleterious matter,
dressing of sides and bottom and backfilling
with approved material.
B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 345.00 110.40 S. No.71 in Pg. no.8 of Part-II
Mazdoor day 8.00 295.00 2360.00 S. No.73 in Pg. no.8 of Part-II
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2848.50 17091.00 S. No.4 in Pg. no.22 of Part-II
c) Overhead charges 4.615% on (a+b) 902.76
d) Contractor's profit 10% on (a+b+c) 2046.42
Cost for 240 cum = a+b+c+d 22510.57
Rate per cum = (a+b+c+d)/240 93.79
say 94.00
1500, Plain/Reinforced Cement Concrete in Open
SDB (First Revision) Page
5 4.02 12.8 1700 & Foundation complete as per Drawing and
No.335
2100 Technical Specifications.
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 3105.00 12823.65 S.no 5 in Pg.No. 1 of Part.I
Coarse sand cum 6.75 904.19 6103.30 S. No.94 in Page.6 of Part.II
40 mm Aggregate cum 8.10 808.00 6544.80 S. No.30 in Page.3 of Part.II
20 mm Aggregate cum 4.05 1303.00 5277.15 S. No.28 in Page.3 of Part.II
10 mm Aggregate cum 1.35 894.00 1206.90 S. No.26 in Page.2 of Part.II
b) Labour
Mate day 0.86 345.00 296.70 S. No.71 in Pg. no.8 of Part-II
Mason day 1.50 357.00 535.50
Mazdoor day 20.00 295.00 5900.00 S. No.73 in Pg. no.8 of Part-II
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 453.00 2718.00 S. No.38 in Pg. no.24 of Part-II
Generator 35 KVA hour 6.00 861.70 5170.20 S. No.43 in Pg. no.24 of Part-II
d) Formwork @ 4 per cent on a+b+c 4% 1863.05
e) Overhead charges @ 4.615% on (a+b+c+d) 2235.47
f) Contractor's profit @ 10% on (a+b+c+d+e) 5067.47
Cost for 15 cum (a+b+c+d+e+f) 55742.19
Rate per cum (a+b+c+d+e+f)/15 3716.15
say 3716.00
1500, Plain/Reinforced Cement Concrete in Open
SDB (First Revision) Page
6 4.03 12.8 1700 & Foundation complete as per Drawing and
No.344
2100 Technical Specifications.
G RCC Grade M30
Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 3105.00 151524.00 S.no 5 in Pg.No. 1 of Part.I
Coarse sand cum 54.00 904.19 48826.42 S. No.94 in Page.6 of Part.II
20 mm Aggregate cum 64.80 1303.00 84434.40 S. No.28 in Page.3 of Part.II
10 mm Aggregate cum 43.20 894.00 38620.80 S. No.26 in Page.2 of Part.II
Admixture @ 0.4 per cent of cement kg 195.20 62.00 12102.40 S. No.70 in Page.4 of Part.I
b) Labour
Mate day 0.84 345.00 289.80 S. No.71 in Pg. no.8 of Part-II
Mason day 3.00 357.00 1071.00
Mazdoor day 18.00 295.00 5310.00 S. No.73 in Pg. no.8 of Part-II
c) Machinery
S. No.32b in Pg. no.23 of Part-
Batching Plant @ 20 cum/hour hour 6.00 1041.60 6249.60
II
Generator 100 KVA hour 6.00 1126.00 6756.00 S. No.43 in Pg. no.24 of Part-II
Loader 1 cum capacity hour 6.00 1646.00 9876.00 S. No.5 in Pg. no.22 of Part-II
Transit Mixer for lead upto 1 km. hour 15.00 1941.10 29116.50 S. No.33 in Pg. no.23 of Part-II
Transit Mixer 4 cum capacity, lead beyond 1
T-Km 6600.00 6.36 41976.00 As per SDB Item no.1.4
Km, (300 X L), L=10 Km
Concrete Pump hour 6.00 803.00 4818.00 S. No.34 in Pg. no.23 of Part-II
d) Form Work: Add 3.5% of cost of material,
3.5% 15433.98
Labour and Machinery
e) Overheads @ 4.615% on (a+b+c+d) 21063.09
f) Contractors profit @ 10% on (a+b+c+d+e) 47746.80
cost of 120 cum = a+b+c+d+e+f 525214.79
Rate per cum (a+b+c+d+e+f)/120 4376.79
Say 4377.00

Concessionaire Independent Engineer


BOQ SDB Ref to
S.No Item Item MoRTH Description Unit Quantity Rate (Rs) Cost (Rs) Remarks / input Ref.
No. No Spec.
Supplying, Fitting and Placing un-coated
HYSD bar Reinforcement in Foundation SDB (First Revision) Page
7 4.04 12.40 1600
complete as per Drawing and Technical No.448
Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and
tonne 1.05 39365.00 41333.25 S. No.62 in Page.4 of Part.I
wastage
Binding wire Kg 6.00 59.00 354.00 S. No.3 in Page.1 of Part.I
b) Labour for cutting, bending, shifting to
site, tying and placing in position
Mate day 0.400 345.00 138.00 S. No.71 in Pg. no.8 of Part-II
Blacksmith day 2.000 385.00 770.00 S. No.49 in Pg. no.8 of Part-II
Mazdoor day 6.000 295.00 1770.00 S. No.73 in Pg. no.8 of Part-II
c) Overhead charges @ 4.615% on (a+b) 2047.46
d) Contractor's profit @ 10% (a+b+c) 4641.27
cost for 1 MT (a+b+c+d) 51053.98
Rate per MT say 51054.00
1500, Plain/Reinforced cement concrete in sub-
SDB (First Revision) Page
8 5.01 13.5 1700 & structure complete as per drawing and
No.458
2200 Technical Specifications
g RCC Grade M30
Same as Item 12.8 (A) upto 5 m height, except
for formwork which shall be 10 per cent SDB (First Revision) Page
12.8 G
instead of 4 per cent of cost of material, No.344
labour and machinery.
Using Batching Plant, Transit Mixer and
Case II
Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 3105.00 151524.00 S.no 5 in Pg.No. 1 of Part.I
Coarse sand cum 54.00 904.19 48826.42 S. No.94 in Page.6 of Part.II
20 mm Aggregate cum 64.80 1303.00 84434.40 S. No.28 in Page.3 of Part.II
10 mm Aggregate cum 43.20 894.00 38620.80 S. No.26 in Page.2 of Part.II
Admixture @ 0.4 per cent of cement kg 195.20 62.00 12102.40 S. No.70 in Page.4 of Part.I
b) Labour
Mate day 0.84 345.00 289.80 S. No.71 in Pg. no.8 of Part-II
Mason day 3.00 357.00 1071.00
Mazdoor day 18.00 295.00 5310.00 S. No.73 in Pg. no.8 of Part-II
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1041.60 6249.60 S. No.32b in Pg. no.23 of Part-II
Generator 100 KVA hour 6.00 1126.00 6756.00 S. No.43 in Pg. no.24 of Part-II
Loader 1 cum capacity hour 6.00 1646.00 9876.00 S. No.5 in Pg. no.22 of Part-II
Transit Mixer 4 cum capacity for lead upto 1
hour 15.00 1941.10 29116.50 S. No.33 in Pg. no.23 of Part-II
km.
Transit Mixer 4 cum capacity, lead beyond 1
T-Km 6600.00 6.36 41976.00 As per SDB Item no.1.4
Km, (300 X L), L=22 Km
Concrete Pump hour 6.00 803.00 4818.00 S. No.34 in Pg. no.23 of Part-II
d) Form Work: Add 10% of cost of material,
10% 44097.09
Labour and Machinery
e) Overheads @ 4.615% on (a+b+c+d) 22385.89
f) Contractors profit @ 10% on (a+b+c+d+e) 50745.39
cost of 120 cum = a+b+c+d+e+f 558199.29
Rate per cum (a+b+c+d+e+f)/120 4651.66
Say 4652.00
Section Supplying, fitting and placing HYSD bar
SDB (First Revision) Page
9 5.02 13.6 1600 & reinforcement in sub-structure complete as
No.459
2200 per drawing and Technical Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and
tonne 1.05 39365.00 41333.25 S. No.62 in Page.4 of Part.I
wastage
Binding wire kg 6.00 59.00 354.00 S. No.3 in Page.1 of Part.I
b) Labour for cutting, bending, shifting to site, tying and placing in position
Mate day 0.340 345.00 117.30 S. No.71 in Pg. no.8 of Part-II
Blacksmith day 2.000 385.00 770.00 S. No.49 in Pg. no.8 of Part-II
Mazdoor day 6.500 295.00 1917.50 S. No.73 in Pg. no.8 of Part-II
c) Overhead charges @ 4.615% on (a+b) 2053.31
d) Contractor's profit @ 10% (a+b+c) 4654.54
cost for 1 MT (a+b+c+d) 51199.89
Rate per MT say 51200.00

Concessionaire Independent Engineer


BOQ SDB Ref to
S.No Item Item MoRTH Description Unit Quantity Rate (Rs) Cost (Rs) Remarks / input Ref.
No. No Spec.
Providing weep holes in Brick
masonry/Plain/ Reinforced concrete
abutment, wing wall/ return wall with 100
2706 & SDB (First Revision) Page
10 5.03 13.8 mm dia AC pipe, extending through the full
2200 No.461
width of the structure with slope of 1V :20H
towards drawing foce. Complete as per
drawing and Technical Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 S. No. 1 in Class-15 in Page.5
metre 31.50 237.00 7465.50
per cent) of Part.IV
Average length of weep hole is taken as one
metre for the purpose of estimating.
MS clamp each. 30.00 165.00 4950.00 M-101 in Page.16 of Part.I
collar for AC pipe (average) taking 10% of
each. 10.00 23.70 237.00
above pipe rate
SDB Item 12.6 excluding
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 2812.00 140.60 overheads & Contractor's
Profit
b) Labour
Mate day 0.03 345.00 10.35 S. No.71 in Pg. no.8 of Part-II
Mason day 0.50 357.00 178.50
Mazdoor day 0.25 295.00 73.75 S. No.73 in Pg. no.8 of Part-II
c) Overhead charges @ 4.615% on (a+b) 602.52
d) Contractor's profit @ 10% on (a+b+c) 1365.82
Cost for 30 m = a+b+c+d 15024.04
Rate per m (a+b+c+d)/30 500.80
say 501.00
SDB (First Revision) Page
12.6 Sub Cement mortar1:3 (1cement :3 sand)
No.333
Analysis Unit = 1 cum
Taking output = 1 cum
a) Materials for 1:3 Mortar
Cement MT 0.51 3105.00 1583.55 S.no 5 in Pg.No. 1 of Part.I
Sand cum 1.05 904.19 949.40 S. No.94 in Page.6 of Part.II
b) Labour
Mate day 0.04 345.00 13.80 S. No.71 in Pg. no.8 of Part-II
Mazdoor day 0.90 295.00 265.50 S. No.73 in Pg. no.8 of Part-II
Per Cum Cost (a+b) 2812.00
Providing and laying of Filter media with
granular materials/stone crushed aggregates
satisfying the requirements laid down in
clause 2504.2.2. of MoRTH specifications to a
710. 1. 4.
thickness of not less than 600 mm with
of SDB (First Revision) Page
11 5.04 13.10 smaller size towards the soil and bigger size
IRC:78 No.463
towards the wall and provided over the
& 2200
entire surface behind abutment, wing wall
and return wall to the full height compacted
to a firm condition complete as per drawing
and Technical Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 345.00 110.40 S. No.71 in Pg. no.8 of Part-II
Mazdoor for filling, watering, ramming etc. day 7.00 295.00 2065.00 S. No.73 in Pg. no.8 of Part-II
Mazdoor (Skilled) day 1.00 310.00 310.00
b) Material
Filter media of stone aggregate conforming to
cum 12.00 329.00 3948.00 M-012 in Page.12 of Part.I
clause 2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 624.00 37.44 S. No.10 in Pg. no.22 of Part-II
d) Overhead charges @ 4.615% on (a+b+c) 298.63
e) Contractor's profit @ 10% on (a+b+c+d) 676.95
cost for 10 cum of Fiter Media = a+b+c+d+e 7446.42
Rate per cum = (a+b+c+d+e)/10 744.64
say 745.00

Concessionaire Independent Engineer


BOQ SDB Ref to
S.No Item Item MoRTH Description Unit Quantity Rate (Rs) Cost (Rs) Remarks / input Ref.
No. No Spec.
Furnishing and Placing Reinforced/
1500
Prestressed cement concrete in super- SDB (First Revision) Page
12 6.01 14.1 &1600
structure as per drawing and Technical No.478
1700
Specification
C RCC Grade M30
Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.79 3105.00 151492.95 S.no 5 in Pg.No. 1 of Part.I
Coarse sand cum 54.60 904.19 49368.94 S. No.94 in Page.6 of Part.II
20 mm Aggregate cum 64.80 1303.00 84434.40 S. No.28 in Page.3 of Part.II
10 mm Aggregate cum 43.20 894.00 38620.80 S. No.26 in Page.2 of Part.II
Admixture @ 0.4 per cent of cement kg 195.16 62.00 12099.92 S. No.70 in Page.4 of Part.I
b) Labour
Mate day 0.88 345.00 303.60 S. No.71 in Pg. no.8 of Part-II
Mason day 3.00 357.00 1071.00
Mazdoor day 19.00 295.00 5605.00 S. No.73 in Pg. no.8 of Part-II
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1041.60 6249.60 S. No.32b in Pg. no.23 of Part-II
Generator 100 KVA hour 6.00 1126.00 6756.00 S. No.43 in Pg. no.24 of Part-II
Loader 1 cum capacity hour 6.00 1646.00 9876.00 S. No.5 in Pg. no.22 of Part-II
Transit Mixer 4 cum capacity for lead upto 1
hour 15.00 1941.10 29116.50 S. No.33 in Pg. no.23 of Part-II
km.
Transit Mixer 4 cum capacity, lead beyond 1
T-Km 6600.00 6.36 41976.00 As per SDB Item no.1.4
Km, (300 X L), L=22 Km
Concrete Pump hour 6.00 803.00 4818.00 S. No.34 in Pg. no.23 of Part-II
d) Form Work: For solid slab super-structure,
20% 88357.74
20-30 per cent of (a+b+c)
e) Overheads @ 4.615% on (a+b+c+d) 24466.26
f) Contractors profit @ 10% on (a+b+c+d+e) 55461.27
cost of 120 cum = a+b+c+d+e+f 610073.98
Rate per cum (a+b+c+d+e+f)/120 5083.95
Say 5084.00
Supplying, fitting and placing HYSD bar
SDB (First Revision) Page No.
13 6.02 14.2 1600 reinforcement in super-structure complete as
489
per drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars includes 5% for laps and wastage tonne 1.05 39365.00 41333.25 S. No.62 in Page.4 of Part.I
Binding wire Kg 8.00 59.00 472.00 S. No.3 in Page.1 of Part.I
b) Labour for cutting, bending, tying and
placing in position
Mate day 0.440 345.00 151.80 S. No.71 in Pg. no.8 of Part-II
Blacksmith day 3.000 385.00 1155.00 S. No.49 in Pg. no.8 of Part-II
Mazdoor day 8.000 295.00 2360.00 S. No.73 in Pg. no.8 of Part-II
c) Overhead charges @ 4.615% on (a+b) 2098.54
d) Contractor's profit @ 10% (a+b+c) 4757.06
cost for 1 MT (a+b+c+d) 52327.64
Rate per MT say 52328.00
Drainage Spouts complete as per drawing SDB (First Revision) Page No.
14 6.03 14.9 2705
and Technical specification 499
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including
Kg 4.00 50.14 200.55 M-087 in Page.16 of Part.I
5 per cent wastage
GI pipe 100mm dia metre 6.00 622.00 3732.00 S. No.32 in Page.2 of Part.I
GI bolt 10 mm Dia each 6.00 18.00 108.00 M-110 in Page.17 of Part.I
Galvanised MS flat clamp each 2.00 165.00 330.00 M-101 in Page.16 of Part.I
b) Labour
For fabrication
Mate day 0.02 345.00 6.90 S. No.71 in Pg. no.8 of Part-II
Skilled (Blacksmith, welder etc.) day 0.02 385.00 7.70 S. No.49 in Pg. no.8 of Part-II
Mazdoor day 0.02 295.00 5.90 S. No.73 in Pg. no.8 of Part-II
For fixing in position
Mate day 0.01 345.00 3.45 S. No.71 in Pg. no.8 of Part-II
Mason day 0.01 357.00 3.57
Mazdoor day 0.20 295.00 59.00 S. No.73 in Pg. no.8 of Part-II
Add @ 5 per cent of cost of material and
labour for electrodes, cutting gas, sealant,
5% 222.85
anti-corrosive bituminous paint, mild steel
grating etc.
c) Overhead charges @ 4.615% on (a+b) 215.98
d) Contractor's profit @ 10% on (a+b+c) 489.59
Rate per metre (a+b+c+d) 5385.49
say 5385.00

Concessionaire Independent Engineer


BOQ SDB Ref to
S.No Item Item MoRTH Description Unit Quantity Rate (Rs) Cost (Rs) Remarks / input Ref.
No. No Spec.
PCC M15 Grade leveling course below
SDB (First Revision) Page No.
15 6.04 14.10 2700 approach slab complete as per drawing and
500
Technical specification
Unit = 1 cum
Taking output = 1 cum
Concrete, Rate as per item No. 12.8 (A) less SDB (First Revision) Page No.
12.8
formwork 335
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 3105.00 12823.65 S.no 5 in Pg.No. 1 of Part.I
Coarse sand cum 6.75 904.19 6103.30 S. No.94 in Page.6 of Part.II
40 mm Aggregate cum 8.10 808.00 6544.80 S. No.30 in Page.3 of Part.II
20 mm Aggregate cum 4.05 1303.00 5277.15 S. No.28 in Page.3 of Part.II
10 mm Aggregate cum 1.35 894.00 1206.90 S. No.26 in Page.2 of Part.II
b) Labour
Mate day 0.860 345.00 296.70 S. No.71 in Pg. no.8 of Part-II
Mason day 1.500 357.00 535.50
Mazdoor day 20.000 295.00 5900.00 S. No.73 in Pg. no.8 of Part-II
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) capacity hour 6.000 453.00 2718.00 S. No.38 in Pg. no.24 of Part-II
Generator 63 KVA hour 6.00 861.70 5170.20 S. No.43 in Pg. no.24 of Part-II
d) Formwork 0.00
e) Overhead charges @ 4.615% on (a+b+c+d) 2149.49
f) Contractor's profit @ 10% on (a+b+c+d+e) 4872.57
Cost for 15 cum (a+b+c+d+e+f) 53598.26
Rate per cum (a+b+c+d+e+f)/15 3573.22
say 3573.00
1500, Reinforced cement concrete approach slab
1600, including reinforcement and formwork SDB (First Revision) Page No.
16 6.05 14.11
1700 & complete as per drawing and Technical 500
2704 specification
12.8 G RCC Grade M30 SDB (First Revision) Page No.
Case II Using Batching Plant, Transit Mixer and Concrete Pump 345
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 3105.00 151524.00 S.no 5 in Pg.No. 1 of Part.I
Coarse sand cum 54.00 904.19 48826.42 S. No.94 in Page.6 of Part.II
20 mm Aggregate cum 64.80 1303.00 84434.40 S. No.28 in Page.3 of Part.II
10 mm Aggregate cum 43.20 894.00 38620.80 S. No.26 in Page.2 of Part.II
b) Labour
Mate day 0.840 345.00 289.80 S. No.71 in Pg. no.8 of Part-II
Mason day 3.000 357.00 1071.00
Mazdoor day 18.000 295.00 5310.00 S. No.73 in Pg. no.8 of Part-II
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1041.60 6249.60 S. No.32b in Pg. no.23 of Part-II
Generator 100 KVA hour 6.00 1126.00 6756.00 S. No.43 in Pg. no.24 of Part-II
Loader 1 cum capacity hour 6.00 1646.00 9876.00 S. No.5 in Pg. no.22 of Part-II
Transit Mixer for lead upto 1 km. hour 15.00 1941.10 29116.50 S. No.33 in Pg. no.23 of Part-II
Transit Mixer 4 cum capacity lead beyond 1 tonne.k
6600.00 6.36 41976.00 As per SDB Item no.1.4
Km, (300 X L), L=22 Km. m
Concrete Pump hour 6.00 803.00 4818.00 S. No.34 in Pg. no.23 of Part-II
d) Formwork
Form work may be added at the rate of 2 per
cent of cost against 3.5 per cent provided in 2% 8577.37
the foundation concrete.
e) Overhead charges @ 4.615% on (a+b+c+d) 20188.13
f) Contractor's profit @ 10% on (a+b+c+d+e) 45763.40
Cost for 120 cum (a+b+c+d+e+f) 503397.42
g) Cost for 1 cum (a+b+c+d+e+f)/120 4194.98
h) HYSD bar reinforcement tonne 0.05 52328.00 2616.40 As Per SDB Item No. 14.2
Rate per cum (g+h) say 6811.00
Cost of Haulage Excluding Loading and SDB (First Revision) Page No.
1 1.4
Unloading 12
Haulage of materials by tipper excluding cost of loading, unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.40 922.00 368.80 S. No.6 in Pg. no.22 of Part-II
Time taken for empty return trip. hour 0.29 922.00 267.38 S. No.6 in Pg. no.22 of Part-II
cost for 100 t km 636.18
Rate per t.km = (a)/100 6.36
say 6.36

Concessionaire Independent Engineer


Project : Design, Construction, Finance, Operation and Maintenance of Four-Laning of Narketpally-Addanki-Medarametla
Road (SH-2) from Km. 0.000 to 212.500 in the state of Andhra Pradesh under Public Private Partnership on DBFOT (Toll)
Basis.
Concessionaire: M/s. N.A.M. Expressway Limited
Independent Engineer: M/s. LEA Associates South Asia Pvt. Ltd
Name of Work: PUP at Ch. 201+410 under negative Change of Scope

ROAD METAL RATES (As per Reformulated SoR 2014-15)

Less Machine
Contractors Blasting crushing
Lead Conveyance Toal Cost per
Profit & Basic cost charges charges (25%,
Sl. No Description of Material in Cost per Km unit (Rs.)
Overheads (Rs.) (S.No. 36 of S.No. 37 of
Kms (Rs.) (a+b+c+d+e)
(Less 14%) on Part-2) (Rs.) Part-2) on (c)
(a) (Rs.)

A) For Road Works (a) (b) (c ) (d) (e ) (f)

1 Un Slaked Lime 21 2491.00 2491.00


HBG of 12 mm to 14 mm size (
2 21 285.70 -35.09 742.85 70.00 185.71 1249.17
IRC and MORTH )
HBG of 9.5 mm to 11.2 mm size
3 21 285.70 -35.09 624.75 70.00 156.19 1101.55
( IRC and MORTH )
HBG of 5 mm to 7 mm size (
4 21 285.70 -35.09 480.00 70.00 120.00 920.61
IRC and MORTH )
HBG of 2.36 mm to 5 mm size (
5 21 285.70 -35.09 293.35 70.00 73.34 687.30
IRC and MORTH )
HBG Stone Chips 2.36mm and
6 21 285.70 -35.09 324.00 70.00 81.00 725.61
below
B) For Structure Works

1 Filter media/Filter Material 0 0.00 0.00 329.00 329.00

2 40 mm SS-5 HBG M/C metal 0 0.00 0.00 590.40 70.00 147.60 808.00

3 20 mm SS-5 HBG M/C metal 0 0.00 0.00 986.40 70.00 246.60 1303.00

4 10 mm SS-5 HBG M/C metal 0 0.00 0.00 659.20 70.00 164.80 894.00

5 Sand for Concrete 40 504.10 -61.91 462.00 904.19

6 Cement (per MT) 3105.00 3105.00

7 HYSD Steel (per MT) 39365.00 39365.00

8 Corrosion resistant Structural steel (HSCR Bars) (per MT) 50138.00 50138.00

Concessionaire Independent Engineer


Project : Design, Construction, Finance, Operation and Maintenance of Four-Laning of Narketpally-
Addanki-Medarametla Road (SH-2) from Km. 0.000 to 212.500 in the state of Andhra Pradesh under Public
Private Partnership on DBFOT (Toll) Basis.
Concessionaire: M/s. N.A.M. Expressway Limited
Independent Engineer: M/s. LEA Associates South Asia Pvt. Ltd
Name of Work: PUP at Ch. 201+410 under negative Change of Scope
Labour Rates as per Common SoR 2014-15
Rate per
S.No Labour Reference
day (Rs)
2 Blacksmith 385.0 S. No.49 in Pg. no.8 of Part-II
2 Mate 345.0 S. No.71 in Pg. no.8 of Part-II
3 Mazdoor 295.0 S. No.73 in Pg. no.8 of Part-II
Mason C-I : 385 (Item.a in Page.6 of Part.II)
4 Mason 357.0
Mason C-II : 345 (Item.1 in Page.8 of Part.II)
Head Mazdoor: 345 (Item.1 in Page.8 of Part.II)
5 Skilled mazdoor 310.0
Man Mazdoor: 295 (Item.2 in Page.8 of Part.II)

Material Rates as per Reformulated SoR 2014-15


Rate per
S.No Material Reference
Unit (Rs)
1 Binding wire 59.0 S. No.3 in Page.1 of Part.I
2 G I Pipe 100 mm dia B Class 622.0 S. No.32 in Page.2 of Part.I
3 Super plastisizer admixture 62.0 S. No.70 in Page.4 of Part.I
4 Compressible Fibre Board 472.0 M-084 in Pg.No.16 of Part.I
5 Galvanized MS flat clamp 165.0 M-101 in Page.16 of Part.I
6 GI bolt 10 mm Dia 18.0 M-110 in Page.17 of Part.I
7 Paint 198.0 M-131 in Page.18 of Part.I
8 AC Pipe 100mm dia 237.0 S. No. 1 in Class-15 in Page.5 of Part.IV
9 Water 73.0 M-189(b) in Page.21 of Part.I

Plant & Equipment Rates as per Common SoR 2014-15


S. Rate per
Plant & Equipment Reference
No hour (Rs.)
1 Dozer 2575.60 S. No.1 in Pg. no.22 of Part-II
2 Mortor Grader 3216.00 S. No.2 in Pg. no.22 of Part-II
3 Excavator 2848.50 S. No.4 in Pg. no.22 of Part-II
4 Front End Loader 1646.00 S. No.5 in Pg. no.22 of Part-II
5 Tipper 5.5 Cum 922.00 S. No.6 in Pg. no.22 of Part-II
6 Vibratory Roller 2678.30 S. No.7 in Pg. no.22 of Part-II
7 Water Tanker 6 KL 624.00 S. No.10 in Pg. no.22 of Part-II
8 Tractor 415.00 S. No.11 in Pg. no.22 of Part-II
9 Air compressor 507.50 S. No.14 in Pg. no.22 of Part-II
10 Mech.Broom 357.00 S. No.16 in Pg. no.22 of Part-II
11 Bitumen Boiler Oil-Fired 209.00 S. No.29 in Pg. no.23 of Part-II
12 Mastic Cooker 65.00 S. No.31 in Pg. no.23 of Part-II
13 Batching Plant 15-20 Cum/hr 1041.60 S. No.32b in Pg. no.23 of Part-II
14 Transit Mixer 1941.10 S. No.33 in Pg. no.23 of Part-II
15 Concrete Pump 803.00 S. No.34 in Pg. no.23 of Part-II
16 Crane (3 tonnes) 352.00 S. No.35c in Pg. no.23 of Part-II
17 Concrete Mixer (0.28 cum) 453.00 S. No.38 in Pg. no.24 of Part-II
18 Generator 100 Kva 1126.00 S. No.43 in Pg. no.24 of Part-II
19 Generator 35Kva 861.70 S. No.43 in Pg. no.24 of Part-II
20 Plate Compactor 48.00 S. No.48 in Pg. no.24 of Part-II
21 Truck/Tipper 5.5 cum per 10t 6.36 As per SDB Item no.1.4

Concessionaire Independent Engineer


Project : Design, Construction, Finance, Operation and Maintenance of Four-Laning of Narketpally-Addanki-
Medarametla Road (SH-2) from Km. 0.000 to 212.500 in the state of Andhra Pradesh under Public Private
Partnership on DBFOT (Toll) Basis.
Concessionaire: M/s. N.A.M. Expressway Limited
Independent Engineer: M/s. LEA Associates South Asia Pvt. Ltd
Name of Work: PUP at Ch. 201+410 under negative Change of Scope
QUARRY MAP

Narketpalli Km. 00+000

Hyd-GNT Road

B.Plant/HM Plant
1.5 Km
100 mtrs

Km. 181+500
Stone Quarry
1.5 Km
Ramanjaneya Puram
Km. 199+000 Gravel Quarry

PUP - Km. 201+410

5.90 Km
Km. 213+690
Medarametla

0.00 Km

Thimmanapalem
Gundlakamma River Sand

Concessionaire Independent Engineer


Project : Design, Construction, Finance, Operation and Maintenance of Four-Laning of Narketpally-Addanki-
Medarametla Road (SH-2) from Km. 0.000 to 212.500 in the state of Andhra Pradesh under Public Private Partnership
on DBFOT (Toll) Basis.
Concessionaire: M/s. N.A.M. Expressway Limited
Independent Engineer: M/s. LEA Associates South Asia Pvt. Ltd
Name of Work: PUP at Ch. 201+410 under negative Change of Scope
LEAD CALCULATION FOR VARIOUS MATERIALS
1a For Crusher metal: (Road works)
a) Crusher to NAM Road Km 0.000 1.500 = 1.50 kms
e) NAM Road to Working Site Km 201.410 to 181.500 = 19.91 Kms
Total = 21.41 Kms
Total lead Or say: 21.00 Kms
1b For Crusher metal: (Structure works)
a) Crusher to Plant Location Km 0.000 0.100 = 0.10 kms
Total = 0.10 Kms
Total lead Or say: 0.00 Kms
2 For Gravel:
a) NAM road to Working site Km 201.410 to 199.000 = 2.41 Kms
Total = 2.41 Kms
Total lead Or say: 2.00 Kms
3 For Embankment materials: = 2.00 Kms
4 For Sand :
a) Gundlakamma River to Medarametla Km 0.000 to 5.900 = 5.90 Kms
b) NAM Road Km 181.500 to 213.690 = 32.19 Kms
c) NAM road to Plant Location Km 0.000 to 1.600 = 1.60 Kms
Total = 39.69 Kms
Total lead Or say: 40.00 Kms
5 For all Grades of Bitumen:
Metalled road length:
a) Chennai City Limits Km 0.000 to 6.900 = 6.90 Kms
b) Chennai - Kolkata Highway (up to Medarametla) Km 0.000 to 319.000 = 319.00 Kms
c) Medarametla to Site Km 213.690 to 201.410 = 12.28 Kms
Total = 338.18 Kms
Total lead Or say: 338.00 Kms
6 Plant Location to Working Site
a) Plant Location to NAM Road Km 0.000 to 1.600 = 1.60 Kms
b) NAM Road to Working Site Km 201.410 to 181.500 = 19.91 Kms
Total = 21.51 Kms
Total lead Or say: 22.00 Kms

Concessionaire Independent Engineer


Project : Design, Construction, Finance, Operation and Maintenance of Four-Laning of Narketpally-
Addanki-Medarametla Road (SH-2) from Km. 0.000 to 212.500 in the state of Andhra Pradesh under
Public Private Partnership on DBFOT (Toll) Basis.
Concessionaire: M/s. N.A.M. Expressway Limited
Independent Engineer: M/s. LEA Associates South Asia Pvt. Ltd
Name of Work: PUP at Ch. 201+410 under negative Change of Scope

Lead Charges as per Part-I


Earth / Gravel / Sand Metal
Distance Km
(Rs.) (Rs.)
Lead upto 1 31.50 30.40
Lead upto 2 44.10 42.60
Lead upto 3 58.90 58.90
Lead upto 4 71.50 71.50
Lead upto 5 84.10 84.10

For every Km beyond 5km to 30 KM 12.60 12.60


For every Km beyond 30 KM 10.50 10.50

Lead upto 6 96.70 96.70


Lead upto 7 109.30 109.30
Lead upto 8 121.90 121.90
Lead upto 9 134.50 134.50
Lead upto 10 147.10 147.10
Lead upto 20 273.10 273.10
Lead upto 21 285.70 285.70
Lead upto 30 399.10 399.10
Lead upto 40 504.10 504.10
Lead upto 53 640.60 640.60
Lead upto 60 714.10 714.10
Lead upto 70 819.10 819.10
Lead upto 80 924.10 924.10
Lead upto 90 1029.10 1029.10

Concessionaire Independent Engineer


Project : Design, Construction, Finance, Operation and Maintenance of Four-Laning of Narketpally-Addanki-
Medarametla Road (SH-2) from Km. 0.000 to 212.500 in the state of Andhra Pradesh under Public Private Partnership
on DBFOT (Toll) Basis.
Concessionaire: M/s. N.A.M. Expressway Limited
Independent Engineer: M/s. LEA Associates South Asia Pvt. Ltd
Name of Work: PUP at Ch. 201+410 under negative Change of Scope

BITUMEN LEADS & RATES

STRAIGHT LEAD :: 338.00 Km

Bitumen (VG-30 & CRMB 60) Base Price Effective Apr. 2013 at IOCL, Chennai

Conveyance Rates Preamble 7.0,


Lead (2 x 338 Km)
Pg-7 of Common SoR 2014-15

Lead (Chennai) for Emulsion (round the trip) 676.00 Km Rs. 1.50
Lead (Chennai) for Bulk Bitumen (round the trip) 676.00 Km Rs. 1.50

Bulk Bulk Emulsion Emulsion


VG-30 CRMB 60 (SS -1) (RS -1)
TYPE OF BITUMEN
(Cost per MT (Cost per MT (Cost per MT (Cost per MT
in Rs.) in Rs.) in Rs.) in Rs.)
Initial cost 38325.00
Lead charges 1.5 x 676 1014.00
Total Cost per MT in Rs 39339.00 0.00 0.00 0.00

Concessionaire Independent Engineer

You might also like