Professional Documents
Culture Documents
Dry Docs (Pianc)
Dry Docs (Pianc)
on
DRY DOCKS
sidered in Chapter 3.
mittee No. II and the date fixed for the receipt of the Clrap.t:u 7 deals with filling of Dry Docks.
report on Dry Docks was to be not later than the end of
of dry docks and a study of modern trends. In this respect 2. MEMBERS OF THE COMMISSO
I N
PRESIDENT :
Clrap.t:u 1 consists of definitions of dimensions and
Professor R . KUHN, Dr. -Ing . ,
size of docks in order to achiern standardisation of infor
Rhein-Main-Donau A . G . ,
mation. Prokurist i. r. ,
Munich , F.R. Germany
Clrap.t:u 2 is concerned with the planning of Dry
GENERAL REPORTER :
Docks, including their size, siting and arrangement of
Mr G . P . MARTIN, BSc FICE,
facilities, serdces and equipment.
Senior Partner, T . F . Burns and Partner s ,
Consulting Engineers,
Clrap.t:u 3 deals with the choice of o\·erall structural l1nited llingdom
design of a Dry Dock, the final decision ha\·ing a profound
SECRETARY :
effect on constructional costs of the project.
Mr A. LEFEBVRE,
Clrap.t:u 4 sets out notes on the design of Yarious
Engineer of Highways Departmen t ,
Ministry of Public Works ,
types of Dry Dock floors that may be adopJed following a Brussels , Bel.giua
REI'BERLARDS
u.s.s.R.
Mr VAN DER HORST, M.Sc.
Senior Engineer, Professor V .M. SELEZNEV,
B.v. Aannemingsbedrijf NBM, River Fleet Ministry,
The Hague Leningrad .
3.3 The influence of the available space and execution 8.6 Ability to open against a head
3.4 The influence of soil condition and groundwater situ 8.8 Parking space availability
3.7 Overall structural design method 8.12 Access across top of gate
3.8 Factor of safety of dry dock against flotation 8.13 Methods of construction
3.9 Structural analysis by finite element method 8.14 Free floating gate (ship type caisson)
Dock
( Neap tides )
quoins
Depth of dock
Clause 1.6 Width of Barrel
Clause 1.4
Dock sill
Dock floor
Width of entrance
Cl ause 1. 3 Altars
Width of Barrel
Cl ause 1.4
Dock sill
Dock floor
• �-· . 1
Width of entrance
Clause 1.3
D
Clause 1.4
Dock sill
Dock floor
Width of entrance
Clause 1.3
Width of Barrel
Clause 1.4
Dock sill
Figs 1.3, 1.4, 1 . 6 - Diagrammatic cross section of dry docks showing defined dimensions
Dock
-
Gate
Depth if Depth if
keel block s keel blocks
below sill above sill
Clause 1.6 Clause 1.6
O utline �- �'.2�- __
Clause 1.5
-- - - --
/
Figs 1. 5 and 1. 6
Diagrammatic longitudinal sections of dry docks showing defined dimensions
2.2. CLEARANCES BETWEEN SHIP AND DRY DOCK The size of a new dry dock will generally be im·esti
gated at the preliminary planning stage when initial feasi
The clearances for working space will need to be bility studies are carried out. Such studies would include a
assessed in relation to the maximum size o f vessel to be comparison of the effects of increased dock size and con
docked when deciding the leading dimensions of a dry dock. struction cost with the likely increased re\·enue accruing
from handling bigger ships. The investment strategy may
The clearance under a ship will normally be go\·erned
also need to take account of national policy, for example,
by the height of the keel blocks, and it is often considered
a desire to be able to maintain the biggest ships in the
desirable that personnel can walk upright under the ship. In
national fleet.
general, the height of blocks is a matter for the indh·idual
yard and the techniques used for repair and construction. Some of the largest dry docks in the world were
The recent use of mechanical equipment on wheeled sized on the basis of an anticipated increase in ship size,
vehicles to clean and paint the underside of ships has which it was considered might rise to J,000,000 dwt. It now
required higher clearances and a minimum keel block height appears unlikely that ships of this size will eYer be. built.
FIG.·Z·J(o..)
10
. . . . . . .
: . . . . . . . .
I !
.J .L
I I IJ 11[; IJ IJ
JS.SOm• M.S.L.
2 OVERHEAD
I SOI
TOTAL LIFTING
I SOI
SI
CAPACITY 200 I
E
OOCKSHEO 150 •SO m
0
E
� �
N
HEATING
ASSEMBLING ARE A
WORKSHOPS
3.SOm•M.S.L :=;;�����
fF
COMMISSIONING QUAY �ts
="'="'="'=c; �� ��L.O��
Om•M.S.l�
.
=::§:� -
: !
I_
r,=�=====<--
M.H.W 0.9m• : E ORYOOCK 1l.5·30•t0 m :
- :;:_ :'.::l �- --.- -- -- ----+<
...';';rn:;'.'.�.;:;;:.;:;m - -H-- -H-----1+--· -+- 5? - --·---- Jiil._-1-
1 :
\ ;
...... __ ______,__ _______________ ...... '
6.00m-M.S.L
7.00m-H.S.L
Closed
Main Dock
-----
Gate
Open
Intermediate
Gate
Dry docks may be designed to accommodate more area for the remainder of the ship to be added, is a very
than one vessel at a time. Some are divided by an inter efficient use of dock space. The intermediate gate in such
mediate gate to convert the dock into a shipbullding dock a dock can be sited in various positions to permit
and a secondary shipbuilding area so that stern sections of variations in the sizes of completed ships and stern
ships can be assembled simultaneously. Assembly of the sections. The construction of each ship has to be
stern section may take twice as Jong as construction of programmed so that each section of the dock can be
the rest of the ship and its prefabrication in the smaller flooded at the appropriate time for launching completed
secondary area and subsequent transfer to t!ie main dock ships.
(b) The highest water level ·likely to be attained in the It is difficult to predict the likely frequency of visits
dock. In some cases it may be desirable to raise the by damaged ships to a dry dock and the additional depth
water Je,·el in the dock higher than the water Je,·el required. It is thus a matter of commercial judgment as to
outside. In this case th� gate would need to be designed the economic Yiability of pro\·iding additional depth. It
for re,·erse head capability. should be noted that the additional capital cost of proYiding
additional depth may vary depending on the type of design
(c) The provision of external sen-ices and possible open
adopted.
galleries near the dock cope and the necessity or
otherwise for them to remain in the dry when the
dock is filled. 2.6. SITING OF DRY DOCKS
and the ad,·antage of maintaining the cope level similar The siting of· a dry dock in a new shipyard is more likely
to the ground level. to be affected by other factors and may in itself be a
major factor in determining the choice of site for the
2.5. DEPTH OF DRY DOCK whole shipyard. The siting of shipyards is outside the scope
of this report.
The depth of water o\·er the sill will, in most cases,
control the draft of the ship able to enter the dock. It
2.7. SUBSOIL CON DITIONS
may be possible to accommodate ships of greater draft by
timing docking and undocking operations at or near spring
The soil type and strength will greatly influence the
tides.
choice of dock structure which, in turn, will influence the
In considering depth, due account should be taken of
construction method and time as well as the cost. It is
the longitudinal inclination of the dock floor and/or keel
therefore essential that an accurate sun·ey of the subsoil
blocks as this could in some cases be limiting. In general,
conditions for the chosen site or sites should be available
unloaded ships will ha,·e a deeper draft at the stern due
so that the dry dock can be positioned to best advantage.
to the weight of the engines and other machinery. If a
The presence of rock at floor Je,·el may lead to a
longitudinally inclined floor is prodded, it is normal to
very economic floor design and w hilst exca\·ation in rock
slope the floor up from the gate end of the dock which
for the dock barrel may be expensive, no temporary works
then suits docking 'bow first', assists drainage, and gives
to support the sides of the exca\'ation are required and it
economy of construction towards the head of the dock. It
may be possible simply to provide dressed rock walls,
should be noted that there may be operational factors in
thereby eliminating the cost of concrete walls. The possi
farnur of 'stern first' docking and it would then be normal
billty of horizontal fissures in rock containing water under
to pro,·ide a horizontal floor. This solution has the advan
pressure should be considered. The danger may be elimin
tage that the stern of the ship may be closer to the
ated by draining, grouting, or anchoring.
centre of the shipyard, thereby reducing the time for
transporting material and personnel to the part of the ship The presence of suitable imperYious substrata at dock
requiring most work to be carried out. floor le\·eJ or at a leYel into which a cut-off can be
formed may lead to a drained floor design being adopted.
Consideration may also need to be giYen to the inter
The cost of pumping water from under a dock floor of
relationship between the depth of the dry dock, the draught
this type to preYent the build up of hydrostatic pressure is
of the ship, the time taken to position the ship over the
normally cheaper than the provision of a gra,·ity or tied
blocks, the height and rate of fall o f the tide and the
down structure even though it will be necessary t o continue
characteristics of the dock gate. The dock gate should
pumping throughout the life of the dock. If the water
normally be closed and water pumped out of the dock to
carrying layers (aquefers) · cannot
the de be closed off,
seat the ship on the blocks before the tide level drops to .
watering of the em·ironment by the necessary drainage may
produce re\·erse head conditions across the dock gate. In
be of deciding importance.
areas of high tidal range consideration may need to b e
given t o designing the gate for rernrse head conditions t o An adequate depth of water at the dock entrance and
overcome this problem. associated quays is clearly essential finally, but due con-
_ ________ -----
r Dry Dockfloor __
Dock Sill
Remove by
Dredging
sideration should be given to the necessity of providing fitting out quay. Modern practice generally dlt:tates that at
temporary cofferdams during construction which are cheaper least two repair/fitting out quays should be provided for
to form in shallow water. Dredging will normally be re- each dry dock. Sufficient depth of water will be required
quired to remove bunded cofferdams (dykes) and the at all states of the tide at anchorages and quays.
dredging can then be extended to form the necessary
depths for the dock entrance without great extra expense. 2.10. AVAILABILITY OF SERVICES
However, dredging in rock is extremely expensive and time
consuming and should be minimized by suitable positioning The availability and routing of electric p ower, fresh
of the dock and other structures. water and other services should be considered when the
The final position of the dock is normally a matter position of the dry dock within the shipyard is determined.
of compromise and judgment and the necessity of an
accurate subsoil investigation by qualified specialists 2.11. PREVAILING WIND
together with land and bathymetric surveys cannot be over
e mphasized. The wind direction is generally a minor factor in the
choice of the position of dry docks due to the importance
2.8. NA VIGA TION AL APPROACH of the other factors involved. However, the centre line of
a dry dock should be aligned as close as possible to the
Dry docks should be sited to provide an easy navi direction of the prevailing wind. This greatly assists the
gational approach, if possible. At building docks ships will docking operation since manoeuvring large ships in an un
generally only be required to leave the dry docks. This loaded condition in a cross wind even with tug assistance
may be before completion of the ship's engines and i t is very difficult. This is more relevant to shiprepair docks
would then b e necessary to manoeuvre the ship from the where ships may be expected to enter and leave the dock
dock to the fitting out berth using only tugs. At repair more frequently than shipbuilding docks.
Flap;
gate'.
:!. Bollards Dredged lo - 9-0 m MSL :
� Arch lenders (-7·4 m COJ
n Cyhndncal fenders
Pump \
qi Wheel fenders chamber '
c Capstans
a F1lhn9 valves
Scale of melres
'* Lighting lowers
II 10 I winch
J_
I
10 m gauge and
roadway
Collector trench
3·6 m
Fig. 2.9 ( a ) - A typical repair dry dock with two associated quays
Soulh quay
Control
room
Substation Substation ,
,,
Dredged 10
- 9 -0 MSL (- 7..C CO) 1
Hau1tng-1n
winch
Winch conlrol
tower
-.!11!1'. -· -·-·-·-·
�o�
I-:::J
� 70
/I
60 50
Slewing radius
I"p�·-·-t
27
�
-·-·
- -·
l --
r:
;:,
-> 52 m clear width
•
ol dock
l I
,--L- ----- - - --...1-.,
: Travelling :
1 dock arms 1
I
• Hauhng-in·track
0 10
Services to
Dock Floor 2.15. ACCESS TO DRY DOCK FLOOR
I hondrail
2 cable inlet
3 ckcuic: connection
-1 brid,&ing sl.:i.b 1500 x �00 x 250 mm
S h:.Hch SOO x �OCX> mm
6 mastic joint filler
7 inlet bush
8 cable :a:nd pipe cuhen
9 !>en ice Slllcry
10 \lOoJcn fender 2�0 "' :<00 mm
II �a1crstop
11 columns XIO • �00 mm •n .i.1 m Clrs
Ll anchor 80 mm dia. ai JO m �trs
i li)S
..:.. _25 50 --· �p5__
I .
;_QL:
;, . ..
F ig. 2.14 (b) - Typical arrangement of dry dock cope and wall
Access steps are often provided at the four corners centres. These are generally of galvanised steel and may
of the dock for personnel access between the cope level require frequent maintenance.
staircases should be considered. Alternatively, they may be Lifts are not normally provided in modern dry docks
positioned in tunnels behind the dock wall but in this case due to the difficulty in maintaining them in operation in
provision needs to be made for removing silt and other the very aggressive conditions.
debris.
Ramps have been provided at many of the dry docks
Suitable access for stretcher carrying wounded from
constructed recently for vehicular access to the dock floor.
the dock floor is required by some authorities.
Ramps are usually provided at the head of the dock. Ramps
Ladders are provided for emergency access only and typically have a slope of 1:10 with transition curves, are
are recessed into the walls of the dock at about 25 m about 5 m wide and are flooded with the dock. The centre
Fig, 2.14 (c) - Typical arrangement of dry dock cope showing services in open
.................... --
.... _ ..,-
.......
,,....,,,.
\�.._::'.!
-
I I
I
I
I I
I I
.------J I
I I
I
I I
'
�
l I
I I
I I
I I
12"
SWITCH BOX
2" OXYGEN
2" PROPANE
£=-- �
HAULING IN CARRIAGE
Fig. 2.14(;f')
. 11 I '1 I
;'.
•
I : l1 I
'
·1
1:1.
u
I�i l� 1�\ !u1 1u\ luJ
;I i1
73. S.57 = 71..21 ; 5 19 ,,.1.0
section of the ramp often takes the form of a tunnel vehicular access and, in the older shipyards where space
whereas the top and bottom sections are unroofed. Ramps was at a premium, by workshops. In modern shipbuilding
are used for transporting to the dock floor, materials of yards considerable space is required adjacent to the dry
all types, dock cleaning equipment, truck mounted hoists, dock for prefabricated ship sections to be offloaded prior
The area immediately surrounding a dry dock is often The areas surrounding a dry dock are usually paved
used for short term storage of ship parts or sections, either with concrete interlocking blockwork or asphalt to
I
t
I
t
i
ir=====---
i
i
i
i
i
•
k
Fig 3. 2( a)
__ ,-.'T_)
FIG. 3.2-b) •
,,__ -+--·
�-1 8=.0�1�· ��2��0 __ ��· -��- -���� -�---t--"-'--�
9
1
I
�
8
1�
i: " �\
·,1
\i
_,,.t.!?.
"
!iu ..
·•
::
+ I\
I\
11
l\
\1
11
L---
8 �
+ -+- +
��- /1L ..
,,,,,,
,,
f!".ll!\
�.,.,.,.,,
, '/'/'/
• •1•1 •1•1•i'l'I'
\tl'''f'/ 'l'l'l'i' 'I'\'\'
1•1•1•\1111'1'1'1'\'1' \J\
:'
:'- � ..-.- •
�
-:::::=:: -
• -
�· �
'l•t•1 l
,,,,,,,,.1 1 ----
0 · �
- · - - •
-
- - .. __.::::-:;- ---:-=
.
· ·-
·-
·-· - ·- -· """' ; ·-
_,.,;;; ·-· ...-
· ·-
I
�--·- - I
/...-- .......
'
I
I
__ l __
-- - --·
r------- �dY�-� D
-
I
I
L_ - - - - -�-1-.ll.J'i;.;.,;;;..;.;.:;,;;,;.;i,i,;;....""'-'-'""'"'=-'"""""'-'-.._--'-...,..._"'-'-'='
I
\.,
Ill V £ R t A 0 US
be subjected.
3. OVERALL STRUCTURAL
DESIGN OF ORY DOCK
I
3.1 . INTRODUCTION
dock
The
will
dimensions
be determined
of the
by l
phase
the requirements of the ship
the waterfront
etc.
- in land
front by a cofferdam
- surrounded by dikes
surrounded by structural
0
Inventory and
Boring logs
Cone penetrations
r--
Geological profile
v
-w
Interpreta- Literature
tion of
r---.
Existing data Permeabilities i..-
Geo-hydrological
Geographic situation profile
Boundary conditions - !"'---.. I
w
......
Bay
River . .
Calculation model "'- I
&..--"'
0
Investigation No infiltration
------
�___L� �
-
------
Only infiltration
of the from river from river
Extreme
Situations . \V w
Dewatering capacity De.watering capacity
Drawdowns Drawdowns
-
.....
0
Provisional
Data existing winninBS
Original potentials 'I/
Design I Most like l y situation !
of the
w
Dewateiing
\ '7
I
Dewatering capacity
Drawdowns
tge :L1..n.mn;;u
'7
Report:
Technical description
CV
Conclusions
w
Conclusions
H7
I
I 'f
CV Additional tests l
�
Additional
Investi-
gations
l
I I
Pumping tests Borings
Organization �
1::!S
C0
Decisions
w
Decisions about building pit .......,
.._ I
and drainage dock
.
Fig. 3,4 ( a ) - Dewatering - Schematic summary of the study
portant maritime civil engineering
sheet piling.
C O N E B E A R I N G C A P A C I T Y ( k g tc m2 1 F R I C T I O N R AT I 0 { 0/o) S O I L
0 100 200 300 0 2 4 6 B l N T E R P ( TATION
3.4. THE INFLUENCE OF SOIL CON- 0
DITION AND GROUNDWATER
SITUATION :r
....
0..
w
The most i mportant items influ
0 0
z
< :r
encing the type of dock structure are ,_
"'
the quality of the soil and the ground 3::
:z:
a:
<(
water situation. Sufficient data about w w
..I "'
these items must be known to answer u z
w
the i mportant questions : .... 20 !-----+----+---< 0
w
w
Can the dock be built in the dry or ...
:z:
must it be constructed totally or Or
Z<
partially under water ? <( ..I
..,, u
L
dewatering possibilities more or less
0
along the scheme as given in figure C L A Y · S AN O I-
"'
M I X T U R ( A N.0 w
3.4 (a ) . SIlTS l:
0 ..J
Sometimes it is clear from the S O F T R O CK
beginning what type of structure for a llr;uh• nf :\ pc-nr!rati<>n lt« I prdnrmrcl hr Pmf,.smr Srhmrrlm;mn
certain situation is the best. Further
In many cases however, a decision on the structural data, is to draw a geological profile of the site. Extra
type can only be taken after a thorough and extensive borings and penetration tests may have to be made to
study. The first thing to do after studying the available have more information about the continuity of the different
..
-- -
- -------
coarse G and
-
. ...... _ _ _ _ _ -
- /
JC
u
/
,/'
G<'.01.(X;CAl l'ROFllE
..
lt<Gf!UOIOIU.t. SECTIC>l
x
11 - 11
•
-s
-.- I
. . ©.
I
(j)
I
©
I ,/ .
0·
I
· ©
I
�<D
9>(<)<�,<0>&'95�99.S�
j__
,H• i.. H .
j ·
30m ·
·
>..
2500 m'ldcy
1 10o-2soom cqui!..r .
:
·
I . . c
. • . .
•
.
;m�rvious bO:�
0 20
Fig. 3 . 4 ( o )
, 5pacing 1 5rr! .
----- · - - _w·
35.CXlm
CllOSS S£CTI0!4 l - I
....
..
·s.._
""--.L·_ ··�
·__,.--1"·- �w . .
I
CROSS SECTION 2 - 2
!- -- - - - - ·-· LT - --------<
!_,o
I
.0__ .._.,. .• --· .... ......_ .CiQ___ -+---5G_ ---t
.
I
I Rl
I BI R2
Fig. 3 . 4 { d )
OUAY WALLS WITH P R E PAKT FLOOR CELLULAR S T R U C T U R E WITH P REPAKT FLOOR
f!NIStUHG \U(R TQ
flHiStllHG
DfU,ttO.Q[ O.PH11NO� 'ht( 0-RY
l.ll[A 1Q t1:
h--..--c-"""""r"<--.-
1111111111111111
rot.
PLASln: F'Oll.., llllllllllll1ill
CONClitlC WITH GR>.VH Wlltt GRAVtl F�U
P R C PAKl t;ONCRtt£..- ._PL;.. S 11C
�PR [ PAl<l Fill
lMICKM( S S )$• Al CONCRr'J( Wilt' GllAV(l rlLl fLOOR lHICXHESS. H - " At Wl!H GR.&Y[L fltL
TklCJ<ktSS lt·r J.:J COHCRr:lE Wilti fH.l OF' l[AD StJ.G$ :zs· AI C0t<CR£1£ WllH: f tLt or l [J. 0 SlAGS
flOOR PR(PAKT P R t PAKT (0HCRt:1£
flOOR Pfi:(PAi<T FLOOR lHICf(.N(SS PR CPAKT
F'lNIS�ING U.YER 10 EE
l .l.Y£R ...CASl ,,.. lHE. ORY
C A S'f IN l�£ oi:n .1.so Uk(
WAllS A N O 'J#ISHtNG
]_0 m
T°R.P.
O R £0Glt¥:G
,..
F'll. l
.:r
�· ·1SAND
��
. . eun.OINC PIT UO' WlD[ ,., ,ButLO I HG PIT 'l7 0 ' WIO� .
Lson. tKPRCVEHENf
P R E PAKT FLOOR WITH WALLS CAST IN T H E DRY DOCK WITH T E N S I O N AND C O M PR E S SION PILES
A.S C H O$E N
... . .... If....... _ . GUllOINO ..u OR 5J<l' WlOt . .... ....
Pr!
..
WA.US
C.15.l lH 1H£
( ' J_O
ANO F'IH!StUWG lA'r(R
OR\'
1111111111111111
lHICKN£SS ll" 141. fREP•J<1 CO�CAt:lt WITH GRAV(I. Ffll f\,OOR 1tUCKH£SS to• A! R[IHFORC[D t:O.,:C-R£Tt
tH1C••irss n· 14 PRt,4KI CO•CAtlE Wr!H fill or U:•D SLAGS tttW:.ttHtSS 10' JJ U�t1£RWAl'£R CONCR(lt
fLOl)ft
HOOR FLOOR
Fig. 3 . 5 ( a ) - Constructions considered partly in the wet and partly in the dry
/
! Af=
6
�����t::::,,...,..�����/ IF
I dredged >lope 6 st one filling
2 �lling i culvert for electrical St:rvia:s
3 canh fill 8 kvel keel block strip
4 reinforced c.onae!e topping placed in 9 piped �crviccs
the dry JO sub�station
5 grout inlru,(ion conctclc placed under l I crane beam and trnHey channel
water
c.
d. e. f.
a caisson floated over prepared bed e floor grouted, over-height of front wall
sunk by water ballast of caisson demolished, backfill
b caisson filled with soil by conveyor continued from land
c partial backfill behind caisson by barge f floor topping laid, crane track piles and
d floor stone placed, further backfill and beam constructed
subway construction started
� n
11
II 3
\
�--·r
II Ii
11 •
11 "
11 I "
11I
1, II .i 11 n
II 1 ii "
II Ii tl
11
,, /I tl
"
4 n
"
"
9
- 10 50 � 1 1 20
10 I
- 1700 " 18.00
F'IG . 3 - 5-b )
working platform on floating oil 5 gr6uting pipe driven through stone by 9 top or ungrouted stone
drums light compressed a i r hammer 10 shoe for driving
2 grouting point 6 floating service platform travels. IJ grouting comp leted
3 lengths of grouting pipes removed as forward approx. 3 m in every 12 h 12 next area to be grouted
pipes are l ifted 7 pipe to be extracted 13 parallelogram area being grouted
4 grout supply line 8 top of grout intrusion concrete 14 pipe lifted immediately after grouti n g
just clear of grout
layers. It is recommended to limit the number of borings 4 an d 5 ) o r whether an o\·erall treatment must first b e
to a\·oid making too many holes in watertight layers. I t is adopted.
By indicating the aquifer and the boundary condi tions must have an adequate safety margin against flotation. The
and by adding rnlues for permeability and transmissivity calculations should assume the highest possible leYel for
the geological profile will be developed into a geohy the ground water and the lowest expected density for con
drological model. See fi gures 3.4 (c) and (d) as examples. crete with no ship or other loading on the dock floor. It
measuring after stopping information can be obtained about The upward load calculated to be resisted by pre
the water flow direction. stressed ground anchors or anchored piles is usually in
of the water carrying layers was not possible and bringing whole
Structural analysis of the dry dock structure
the water back into the ground by way of infiltration
may be undertaken by computer using the finite elei:nent
wells did not work well in the related soil type, the dock
method. Care must be taken to include appropriate para
had to be l;luilt partly under water.
meters and the results should be ,-erified by experienced
F i gure 3.5 (b ) gives an example where the building pit engineers in this field. Appendi x ' B' consists of a technical
could not be pumped dry and where the dock floor had to paper describing the process i nvoked.
Ha\'ing made the decision as to the basic dock struc 4.1. INTRODUCTION
ture to be proYided, consideration must be gi\·en to the
method of design of the structure and whether it can be Dock floors are now almost im·ariably constructed of
treated in its separate parts i.e. floor and walls (chapters concrete. There are three main types of dock floor
I. Dock bedded in :
2. or
nhova :
ffi>-<
2.l C l o s e d rock Impervi o u s y y D l D J ( ll l , B I O )
2.2 Cons o l id a ted c l ay Ilnpc1·vious ll' N y DL I ( BJ )
�
lligh
perme a bi l i ty y N A l A2 ( 1l l , B l 0 ) AL l (BJ , ll4 )
2.4 Rock wi th wnter
carrying s l i t s .
l'o s s i b i l i t y t o c l o s e ? :
y N ;>- Exces s i v e
permeabil i ty
@--4 N N G W l GWJ(ll5) Gw5 (B7 )
:s
Bearing capacity
s u f f i ci en t :
3. 1. I
®------7
S i l ty Low
permeab i l i t y l I Y Y D5 ( 1l9) DLJ ( ll l 6)
If ll i s too high J. 1 .2 Medi um Hoder a t e
for cut off or permcabil i t y 12 � Y N A J ( l!9 ) A5 A6 A7 ( D9 , ll l 0 )
Car i n f l uence of AL2 ( Il i 6 ) AL4 AL5 AL6 ( l! l 6 , ll l 7 )
lower lnycr on J. I .J Coarse l::x ccssivc
<lock s true t ur e permeab i l i ty IJ N N /\Wl ( ll l 5 ) Gli2 Gll4 ( ll6) GW7.( 1l l 5)
then
J.2 Bearing capacity
no t s u f f i c i en t :
Improving p o s s i bl e ? :
y N )
�- If drainage dock ·
pos s ib l e :
a<l<l supporting p i l e s Low
tension and
permeabil i ty
� y y D l l ( ll9 ) DL8 ( U l u·
�
upl i f t fo r : - mod .. perm. y y D 7 DB ( ll l l ) DL5 ( 1l l 6) D I l ( ll l 1 ) DLB ( ll l 6)
- buildinc p i t alone hich perm. I
N N AW! ( B I S ) AW! ( ll 1 5)
- drain;:ir;c dock - h ir;ll perm. 2
- mod. perm.
� y
y
y
N
D9 ( 1l l l ) DL6 ( ll l 8)
115 /\6 /\7 /\8 ( 3 1 1 )
/\L4 /\LS AL6 ( B l 8 )
D l l ( ll l l ) DL8 ( ll 1 8 )
A8 ( n l I )
/\LS AL6 ( B l 8 )
c;:
Improvinr; possibl e ? :
y
vertical drains
� .:.< � . �
re.inforce.d concrete -
under-wate.r concre te. --+
0 :y �
. f}/
...
.
.
·�· ..::.
· .....
.. ._._
•.•_"""...,....,.-i....,..., .... -', .
,�)0.·:.: �� .
.
• \ " 4
·"
. '· ' . .
8 -.-,--_-!-.-.- t,
'\.
-
.
•
..
' .,
F ig 3.6 (DJ
.....ro--c-�-- e ( .
.. .. ...
. .
. • • -
,.
..
• •
• ,
.
*�I ,.
'
.....
t •� •
'
·� ' t •• • 1" i .
. �1... •.�11!"..��:·.'�
-
.' .. �.::·: ..
. ..
.
i:' ,. . ;, �°':..
• • .. C' • f
t • ,• r ..•
• I
....
•
�. , ': � �· .
. "
Fig . 3.6(E)
BI
B3 B4
:����fl\��h'·��\i,�\�t�:'.'
l imi ted build ing pit
B7
("\
r - - -o if·�-:-
.-.-
. �
I
- - - - -l
BIS
__ -.e� -- -
ANCHORED DOCK
anchor-p i l e s
---·�--··-- - )� --·
_____ .
DRAINAGE DOCK
HHWS. �
� _gl.JL
H W
DOCK WITH
\
TENS ION-SUPPORT I
PILES
l:f.2 to It.It.
l:f.7 .
between
can
the
be
walls
designed
to
to
assist
span across
resistance
/l]j � . :
..... 2
: ·: ·: -----
to uplift, a thick floor is usually also
_J
l s:ttdrovc:r
conditions permit, but several dry docks
2 uav•l
3 PVC pipe 200 mm dia
]_
have been built in recent years using . · • •
4 JOCktt
gravity design. S gavel
6 �nd
Modern designs of gravity docks
extends
viding
past
heels
the
to
dock walls, thus pro
FLOORS
provided to· more than half of the dry Fig. 4 . 3 ( a) - Details of under-drained dock floors
t lOt&
4,ii
UOtl
r
'
---- ----
11\
layer
i�v
: sheet p i les ��
11
- sand layer
!• The two sand layers are connec ted by ver t i ca l sand drains because !i
l: the b o t tom of the upper c l ay layer is too high to avoid up l i f t by !!
:l the water pressure under that layer . ::
�hzzv_zzzzl777_2ZZ727ZZ?Zzmzz:zz7zt?zzL
• relie fvalves �
�·
-· --0
�
H'
...
f l ow d i re c t i on in the f i l te r
reliefval ve
inspection channel
dock.
water.
ground water, a drainage layer of no-fines concrete (i.e. It is important to recognise that in some ground con
porous concrete) or gravel is usually provided immediately ditions under-drained floors cannot be permitted. A perma
below the dock floor with a series of porous pipes and nent lowering of the water table can sometimes cause
drainage culverts to lead the water to a sump in the consolidation of clays and silts with the result that unac
pumphouse. Pumping is usually arranged to be intermittent ceptable settlements of surrounding buildings, roads and
with the pump commencing operation when the sump fills other structures are produced. It is also possible that the
up and cutting out when the sump has been emptied. water supply of the district can be affected either b y a
Pumping is required to be carried out throughout the life reduction in the yield of wells or by enforced contamination
of the dry dock. Regular monitoring of the pumped water by sea water.
should be, carried out to confirm that no fine grained
In some highly sensitive areas even temporary ground
material is being extracted from the soil.
water lowering cannot be undertaken and special , measures
Under-drained floors are generally designed to be of construction may be necessary. These may consist of
much thinner than gravity floors since a large mass to forming a complete cut off surrounding the site by sheet
resist uplift is not required and the floor may be sized piling or diaphragm walling or alternatively by constructing
from structural considerations only. On a sound rock foun the dock structure unqer water. Piezometers are rec
dation, the floor thickness may be reduced to less than ommended to be installed in fully or partially relieved dry
system to remain in operation whether the dock is flooded 4.4. ANCHORED DRY DOCK FLOORS
or empty. The underfloor pumping system i s thus indepen
dent of the main. dock pumping system and should be Anchored dock floors may be provided, if su itable
designed accordingly. If the principle of continuous pumping ground conditions permit, in conditions where an under
is adopted there will be a minimum of ground water drained floor is not feasible for the reasons discussed
movement and the ground water regime will be as stable above, or due to high ground permeability. In this type of
as possible. lt is also preferable that a small static head floor the uplift forces resulting from the upward pressure
do ck f"lcer
• u mp
SOLUTION A
Three separated compartments under
the dockfloor, with three sumps �
No drai nage under the dock sections
intermedi a t e got c s
I
I
II lI s ON C
Three scp-ar<Jlcd compartments under
the dockfloor. There i s only one
sump. The discharge channels f rom
2 1
the three compar tu,cnts arc separated.
3 main g o t c
Only i n emergency cases when a
f i l l ed sections i s l eaking very much ,
' '
"'- i n t ermediate
the valve in the d i scharse channel
gotes
i s closed to scpar:itc the concerned
compa rtmc:o t .
I�
-t---it!lt+l-H-+---+t!-l-t+-l·--1-7-'"]J_--- ":'°
H·+·+-t-H J- � -�
I �
.
\
.... � ":- ; l � \J
\ IN1"-n""'t¥An LA"i'C.fl
are resisted by piles or ties anchored at depth below the produce a satisfactory solution in suitable soil conditions.
Anchors may be of many different types including below the floor girn a positi\'e solution and can readily be
steel strand or bar attached to anchor blocks or grouted tested. Drilled and grouted anchors ha\·e been successfully
steel H piles, or reinforced concrete piles. In the case of used but precautions against corrosion must be taken.
should be appreci ated that the stress corrosion is most 4.7. GROUND IMPROVEMENT
free hydrogen as a .by-product of ordinary electro chemical Poor ground conditions may be i mproved by rnrious
corrosion. It follows that measures to arnid ordinary cor methods and have been successfully used, although in some
'
rosion should be of the highest order. High tensile steel cases it tends to be both expensive and time consuming.
rods (st 52} are considered by some authorities as preferable Ground i mpro\·ement may b e carried out by replacing
to cables but sim ilar precautions against corrosion are weak o r compressible soil by a granular material which can
essential. be well consolidated by rolling or vibration. The granular
made, the piles will be subject to tension and compression Where the dock is to be constructed in reclaimed
alternately during their life. When the dock is filled, the land and dykes are required around the building pit, the
uplift water pressure will be counterbalanced and the piles weak soil may be excavated and used for the temporary
will be supporting the mass of the dock structure and thus construction of the dykes. Good granular soil can then be
be i n compression. This re\"ersal of stress can, i n some soil used for the area under the floor without great extra cost
Where in-situ reinforced concrete piles are used with the rnlume of underground water ultimately to be pumped
mild steel (St 37) the design stress in the steel should be for a drainage dock will be reduced. The life performance
Drainage of the dock floor i s desirable so that water as required. If ser\'ices are required at dock floor leYel
from rainfall, ship cleaning and water discharged from the they are generally located in recesses in the dock walls.
drainage channels at the perimeter of the dock. ConYen Joints may be required in the dock floor to provide
tional surface water drainage using gulleys drained by pipes hinges as part of the o\·erall structural design of the dock.
in the dock floor is i mpracticable since a system of this Joints may also be required to cater for expansion and
type would block up with debris from shotblasting and shrinkage. Construction joints will also be required. Joints
shipcleaning processes. may be provided with water bars, joggles, dowel bars and
sealers, as approprla te.
Drainage mar be by longitudinal fall only usually from
the head towards the dock entrance but with n o lateral or Expansion joints are rarely used in dry dock floors
cross fall. One of the adrnntages of haying no cross fall since the t emperature of the floor slab tends to be
is that, for flat bottomed ships, bilge blocks need not to goYerned by the temperature of the underlying ground
be altered in height when adjusting their position laterally water, which is generally fairly constant.
Cross falls may alternath'ely be provided in the dock in the dry to reduce the effect of the shrinkage as the
floor to assist drainage and in this case, it is normal to floor hardens. It ls normal to cast the floors i n alternate
proYide a fall from the centre of the dock towards the bays or to lea\·e shrinkage gaps.
Longitudinal drainage channels are often provided at water bars may sometimes be omitted. Reinforcement is
the edge of the dock floor adjacent to the dock walls. usually continued through construction joints. The concrete
One channel discharges direct into a sump in the pumphouse sides of a construction or shrinkage joint is either mechan-
(i) Upward reaction from the ground and ground water and of the same order as the bilge block loads.
(ii) Loading from water in the dock with the dock full of
water, As noted in 3.7 structural analysis of the dock floor
is sometimes initially carried out in conjunction with the
(iii) Loading from the ship or ships including tank testing
design of the dock walls and other elements of the dock.
loads and isolated loads from jacking etc.
Notwithstanding this, a separate and detailed design of the
Loading from (i) and ( i i) abo\·e can be estimated floor is almost always required. The loading parameters and
fairly simply depending on the ground conditions and the alternatiYe loading conditions are applied as appropriate.
general arrangement of the dock. The loading from the The design of the dock floor is usually carried out to
ship or ships cannot be determined with any precision, Dry elastic principles. The floor slabs may need to be designed
docks will normally be required to accommodate a large as slabs on elastic foundations, the modulus of elasticity of
range of different sized ships up to the limits of the dock the underlying strata being used to calculate the bending
dimensions. Ships will normally be in a ' light' condition moments and shear forces in the floor slab. In docks with
but this wi1l not always be the case, particularly for thin floors subjected to a hea\·y keel block l oading, the
repair docks where damaged ships may be docked. floor is sometimes thickened at the centre of the d.ock to
increase · load spread and reduce reinforcement quantities.
The procedure normally followed is first to assess the
docking weight of the biggest ship that can be accommo In dew of the uncertainty attached to the loading
dated in the dock by reference to Lloyds or other lists and ground parameters it is not always appropriate to
gi\·ing \·essel statistics. The proportion of load carried by carry out the designs to great accuracy and simple hand
the keel block and bilge blocks respectiYely must then be calculations may be preferred initially and then checked by
estimated. For flat bottomed ships such as tankers it is computer finally.
of ten assumed that 50 % of the mass of the ship is sup
ported by the keel blocks and 50 % by the bilge blocks.
5. DESIGN OF DRY DOCK WALLS
For ships with finer li nes a greater proportion of the mass
of the ship will be carried on the keel blocks. Raking
shores may be used instead of bilge blocks, particularly for 5 . 1 . INTRODUCTION
warships, and in this case the whole mass of the ship will
be carried on the keel blocks. The aYerage loading on the Dry dock walls are usually designed in conjunction
keel blocks · is thus assessed and is usuall�· expressed in with the dock floor. In addition to the loads transmitted
tonnes per metre run. through the dock floor, the dock walls are designed for a
\'ariety of loadings and load combinations, including earth
Loading at the ends of a ship, particularly at the
pressure and surcharge, ground water pressure, seawater
stern, may be higher than the a\·erage loading and these
pressure from inside the dock and loading from equipment
sections of the dock are often designed for a keel block
and fittings including quay cranes, mobile cranes, ship
loading 50 % higher than the a,·erage loading. The effect
hauling gear, dock arms, bollards, shores, strong points and
of sew loading due to Yessels being docked out of trim
sen·ices. In some locations it is necessary to consider
may also need to be considered.
earthquake loading which should conform with the local
Bilge blocks are usually arranged in rows parallel with regulations in force for retaining walls. Layout of the dock
the keel blocks. The rows may be positioned anywhere walls is co-ordinated with the serYices gallery required at
from close to the dock wall to close to the keel blocks. the cope. There are many different types o f dry dock
Bilge blocks are usually designed to carry 50 % of the walls as outlined hereafter.
mass of the ship but in some circumstances the loading
may be higher. Bilge blocks may be widely spaced l ongi
5.2. MASS CONCRETE DOCK WALLS
tudinally and indh·idual blocks may therefore carry a
similar load to the keel blocks.
Dry dock walls prior to the first part of the 20th
In shipbuilding docks, it is common for ships to be century were generally of massive construction, usually
built off centre. In wide docks two or more vessels may with stepped altars on the front face. This wall profile
be constructed side by side. The dock may also be used was conYenient for supporting horizontal shores to the sides
of ships and at the same time followed the line of thrust ha\'e been constructed with reinforced concrete walls. Re
from the earth pressure. The back of the wall was also inforced concrete walls \·ary greatlr in their arrangement.
sometimes stepped to economize in material. Mass concrete The following types are the most common :
water pressure on the whole dock. 5.4. SHEET PILED DRY DOCK WALLS
5.3. REINFORCED CONCRETE DRY DOCK WALLS Steel sheet piling has been successfully used for drr
About 50 % of the dry docks built since about 1950 concrete walls. The following factors must be taken into
r
T i e Ro d s
Anchorage
Stee l Sheet
P i l i ng
Dry Doc k
Fl oor
Underf l oo r
U n d e rf l o or
Dr a i n a g e
Dr a i n a g e
L ay e r w i t h
C u l vert
Por o u s D ra i n s
Fig. 5 , q (a) • Sheet piled dry d ock wall ( with drained dock floor)
M
rod
�· , root i...,
slop1 o5 "!.
I I
:: ( t or s. t t 1 l pHt i )
!. '
Fig. 5 . 4 ( b } - Sheet piled dry dock wall with floor on tension-supporting piles
of water to be pumped.
The dewatering time for a dry dock is normally
Sheet piling may also be used with great ad\·antage if
specifie d as being the time taken to empty the dock from
a ground water cut off is required to make possible an
high water {spring t ides) without a ship in dock.
efficient under-drained dock. I n this case the piling forming
Docks used for shiprepairing normally require fast
the dock walls may be extended downwards and terminate
4 hours.
thus reducing the quantity of water to be continuously
proYe the aesthetic effect. Shiprepairing docks often require one ship to Jeaye
reclaimed from the sea. Caissons mar also be used i n ,·ery On the other hand, having floated a new ship out of
t:
where. the floor i s horizon
horizontal or ,·ertical
house.
by the user.
the water leYel in the dock is low and each should be installed, operated and maintained.
the original design had taken this into account and pro- ·
initially.
Drainage pumps with their suction in the dry dock
main sumps are required to deal with the water remaining Arrangements for the remoYal and replacement of all
in the dock after the last of the main pumps ha,·e cut the major equipment should be incorporated in the design
out. These pumps should ha\·e adequate capacity to deal such as the proYision of removable panels in the roof
with the maximum ' run off' from the dock floor in the which would normally be within the reach of t h e dockside
shortest possible time and at the same time remoYe the cranes.
rain water and any leakage from the gate, floor and walls.
Some pumphouses are equipped with an oYerhead crane
The design of the pumphouse for a dry dock should remo,·ed from the pumphouse using the dockside crane.
ULUST rm
)WI HUI
f!RE JOtrEY
mm
hlDD '/.
DISCHARGE
CULVERT
<]
I
-t:<l.. ri:";.i--=�=
. .,
mir DISC KU&{ :
mrm SYfHD•S
.
•
.
�
·r
l
hlOO
2 100 ·1•
'l•J
S(LWA T C R 1n
.
I
•
•
. ..
.
- - - - - "l
..,,
I
-��l
..
HOUS{ o�mm
':-�
.,. PUHtS
··-
2,100 .,. hlnO '/,
f (tJ
HY.
8 l mmL
=�-�������-::-'--�����_..:·��
: -!_'====�!
ru1-1r mvc
SUHr
� ISQl!TlkG
�
' SOlBOID GHHHD
11111 D£W1i [ RIXI mirs DOC! DUIUtE
YAlYE
l
'/,Jj
h�D '/,
( h ll
'/,] tUHPS
li1DO
1 1 . 100 ·1.1
-l<l- m-HlURI
VALVE
m ·nu1sE nm
rvKflXC uurmm1
Fig. 6 . 6
the pumphouse.
operation.
placed baffles.
7.1. INTRODUCTION
Je,·eJ is needed.
DOCK
USED
-+
Equilibrium filling YalYes are
Fig. 7 , 3 ( b ) ->
8.1. INTRODUCTION
8.5. COST OF CONSTRUCTION
8.9. EASE OF MAINTENANCE completed gate floated to the site. Erection of the gate
Consideration should be given to the ease of mainten prematurely flooded is also possible, but may produce some
ance of the gate. Preference should be given to those practical difficulties depending on the details of design.
8.10 LABOUR FORCE REQUIRED TO OPERATE GATE form with the structural and operational requirements of
can vary between one man controlling a single winch to a located in a close fitting groove in the dock walls and
considerable number of men forming mooring gangs com dock sill, it may be trapezoidal.
sidered when choosing the design. Prefabri Fig. 8 . 1 4 - Typical free floating gates
cation of units of the gate in factory con- Top : Trapezoidal gate - Bottom : Rectangular gate
nears completion.
'!
Dock Entrance
Hi nge
(c) The gate may be designed as a gravity
case
gate
it
to
will normally be necessary for the
outside of the gate is possible i ncluding the Fig. 8 . 1 5 (a) - Hinged floating gate.
(a) Requires mooring gangs and possibly a tug to operate. duction in width of gate and thus a cost advantage.
(b) Takes considerable time to operate. The structural principles of the gate are similar to
(c) Operation may be delayed in moderately poor weather the free floating gate except that it is difficult to arrange
conditions. for the gate to be located in a groove and thus reverse
(d) Operation may require careful monitoring of pumps and head conditions cannot normally be accommodated.
water levels.
i ntroducing a loose hinge or hinges on one side. The (c) Civil engineering works simple.
by
gate may be - opened and closed by means of wire ropes or (d) Can accept a wide roadway.
chains operated by a winch. An alternative method is by a (e) Does not require extra depth of water.
?���,.. I
I
,,;,, : !�-��� temporary sheet p i l ing
for main tenance of
r---- -'�,::, _ _ _ _u, "�.��
sealing flaps
I '-, /
I ·�����-.l!--:..�
' r- - .. - - -
-- ,
I I
I 1 support 1I
I I I
' � -- - - - - - -�
I
CAI S S ON GATE
I
I guiding p in
I seal ing a t g a t e b o t tom !
I r - -·"' - -, - ..· - --- ... .J
I I I dock s i de
I 1 s up po r t 1
I I I
I '
I L _ _ _ _ __ J I
I I
I I
I I
::;:.
I.- - - - - - - -... -- !
Fig. 8 . 1 5 ( b )
(a) Requires tug or extra machinery to operate. The sliding {or rolling) caisson gate is one which is
(b) Medium time to operate. housed, when open, in a recess or ' camber' at the side of
(c) Operation may be delayed by very poor weather con- a dock. To close, the gate moves across the entrance
(d) Some monitoring of water levels required. wire rope • . Before movement, the gate may be deballasted
(e) Cannot easily accept reversal of water pressure. to become semi-buoyant and in some cases wheels are
(f) Cannot operate against a head. designed to be jacked down under the gate to reduce
r
(e) Small number of operating
personnel required.
Dock Entrance
(f ) Can accept a wide road
Camber Cover Jacked up
to a 1 1 ow Gate to Open way.
Wi nch A 1
.";;.. -..·.==-:.·..l-=::: ::::.::-c:::..--:::-:-- �
c:.-::;::::::
( g) Not affected by weather
1, ;1G':..�di::::.r�-;;..£:;� conditions.
( Handrai 1 folded l 1,.,. «•t T! DAL
repair.
eering work.
Temporary Stop logs
for Gate Mai ntenance (b ) Mai ntenance possible but
difficult.
(c) M e c h a n i c a l maintenance
considerable.
ment expensive.
Gate Open
'· i n C amber (e) Camber requires consider
'•
able space.
Dock
PLAN
The cross section of the gate is usually rectangular support which, together with the two hinges, form a three
and thus be able to accept a reversed water pressure as figuration so that the bottom edges of the gates are in ·
would be require ? for i mpounded docks. contact and form water-tight meeting faces. The gates are
camber completely, leaving the gate in the dry for main mechanism to be protected against an overload should a
� Dock
win� rope which passes over shea\·es o n the gate and is
ELEVATION
ON AA
Dock Floor To Wi nch
iDock
Gate Open
Fig. 8 . 1 7 - Mitre gates of the gate is greatly influenced by the shape of the
(g) Watertightness difficult to maintain. (c} Simpl e and cheap ciYil engineering works.
( h) Generally considered unsuitable for Yery large entrance (d ) Can be built on site or remote from s i te.
dock sill and remains horizontal when open to allow a ship (a) Requires extra depth of water outside s i ll.
to pass o\·er it to enter or lea,·e a dock. The whole of (b) Cannot easily accept a reverse head.
Dock Cope
8.20. CANTILEVER FLAP GA TE
The operation of strutted flap gates may be by winch Fig. 8 . 20 ( a ) - Cantilever flap gate
and wire rope using a multiple sheave system if the load
is too great for a single rope. The gate is usually made
semi-buoyant to reduce the lifting load.
(a) Can be used for very wide entrances.
{b} Fast to operate.
(c) Can be prefabricated remote from site.
(a) Can be used for very wide entrances. (d) Can be erected in-situ.
(b) Fast to operate. (e) Only one man required to operate.
(c) Can be prefabricated remote from site. (f) Narrow roadway on top possible.
(d) Remoyal and repair not easy with some designs. timber keel blocks, the full weight of the ship thus being
Other gate designs are numerous and are usually The outer ends of the shores usually rested on altars
deYeloped for special purposes where special conditions are formed on the dock walls. The shores were normally placed
present. Gates l ifted out by a floating crane haYe been in position and adjusted during the pumping process at the
adopted where a suitable crane is a\·ailable without a t i me when the keel just touched the blocks and buoyancy
prohibitiYe hire charge being required. Sectional gates lifted still proYided some stability. Additional blocks were some
into. position with joining seals to form i m m ediate gates t i mes placed under the ship' s bilges for additional stability
for di\·ision of large dry docks are in common use in ship after the dock was fully pumped out. These additional
Bilge blocks which are remotely adjustable both in hose or regularly spaced automatic supply points filling a
position and in height have been introduced into some dry tank carried on the dock arm carriage. Supplies of paint
docks with Yarious degrees of success. Many such instal and grit or shot must also be carried on the carriage.
The remornl of blocks for repair purposes when under There are many differing systems used but most are
load from the ship has always presented a problem. Sand based on self tensioning winches with ropes. attached to
boxes on the top of the blocks with arrangement made for trollies or mules running on rails on the dock cope. It is
the sand to be remo\·ed by water jet have been \•ery essential to plan carefully the interaction between the
successfully used. hauling system and the dock arms although fortunatelr the
A feature of modem ship repair docks has been the In these cases the trollies are sometimes pro\·ided
introduction of dock arms. A dock arm can be described with braking systems so that, when appl i ed, the trollies
as a mobile platform supported on an adjustable hinged can be used to centre the ship by hauling on the main
canti le\·er arm fitted to a carriage which runs on rails winches as appropriate.
fixed to the dock wall and cope. These ha\·e only become
In all cases there is angular pull on a trolley with a
possible with the elim ination of side shores.
high upward and outward component which must be resisted
High pressure water cleaning, shot blasting and paint by the trolley' s wheel srstem which requi res up to six
ing o f the ship' s hull can be performed from the dock arm running surfaces.
dry docks throughout the world with special reference t o their size,
type of construction, type of gate and type and capacity of pumps.
of modern docks are of the under drained floor type. It will also be
noted that only the Netherlands and Germany P.R. have a majority of
gravity docks.
The most common gate used appears to be the steel flap type,
closely followed by the steel hinged caisson. The mitre gate which was
once very popular appears to have lost favour as the widths of docks
have increased.
CONSTRUCTION
.µ ,..... -
0 'O ro s::
tlJ) c Q) 0
s:: s:: ..µ [/)
tll · .-! 'O 0. E Q) · .-! 0 [/)
� .µ Q) 'O ro ro 0. 4-< s::: ·.-!
() s:: ro tlJ) 0. Q) ..; Q) >., Q) ._. c;S
0 0 0 s:: ro .µ J:>.. P:i .µ 'O 0
0 'O [/) ..; ·.-! ..; .µ . ......, Cl)
4-<
0
c
:;:
0
.µ
·
>.,
.-!
'O
Q)
s::
Q)
f..
0
�
0
[/)
· .-!
ro
�
..;
s::
0
[/)
::c
..;
s::
0
[/)
4-<
..;
;:l
f..
.µ
.µ
s::
ro Q)
.µ
f..
0
tlJ)
c
•.-!
'O ·
s::
.-!
Q) ..µ
s:: :> · .-! .c s:: (.) Q) [/) Q) [/) Q) [f.) 0. (.) f.. 0. 'O tll) ro
. � ro ro () � Q) •.-! Q) · .-! Q) • ro .
.µ 0. · .-! c 0
0 s:: f.. f.. s:: s:: (.) .µ <ll +' ro .µ .µ ..; .µ •.-! ;:l ..; · .-! ..;
z ::::> 0 0 <i: ::::> 0:: [f.) (.) [f.) (.) [f.) [f.) 4-< [f.) ::.::;:: [f.) [f.) ::r: �
AUSTRAL I A 1 1 1
BE LGIUM 7 6 1 -
1 2 4
BRAZIL 2 1 1 1 1
CUBA 1 1 1
CANADA 2 2 -
1 1
D E NMARK 7 1 1 5 6 1
E GYPT 1 1 -
1
E IRE 1 1 1
FI NLAND 1 1 1
GERMANY FR 10 10 -
4 1 2 2 1
FRANCE 8 1 2 4 1 4 2 1 1
GREECE 2 1 1 -
1
GI BRALTAR 1 1 -
1
I ND I A 1 1 1
I TALY 4 2 2 2 2
J APAN 43 43 6 18 19
KENYA 1 1 1
MALAY S I A 1 1
MALTA 1 1 1
MEXI CO 2 1 1 -
2
MIDDLE E AST 4 4 1 3
NETHERLANDS A . 1 1 -
1
NETHERLANDS 13 10 3 3 8 2
NORWAY 3 3 2 1
PAKISTAN 2 2 -
2
POLAND 2 1 1 1 1
PORTUGAL 7 7 -
1 5
S I NGAPORE 8 5 3? 4? 4 1
SOUTH KOREA 6? 4 2 4? 2
SPAI N 2 1 1 -
2
SRI LANKA 1 1 -
1
SWEDE N 4 1 3 3 1
THAI LAND 1 1 -
1
U.K. 16 5 8 3 -
2 2 11 1
U.S.A. 24 21 3 13 9 1
Ref Year Use Entrance IXlck Ef'fectr- Depth Tidal Canstructicn Construction Soil 'fype of 'fype
No. !.ocaticn Owner or Yartl in of Width Ba:r:rel ive over range of Walls of Floor i;}'pe Gate of Mo:ir1
coocrete - drained
caisscris
stooe filled
ClllW)A
Saint John Saint Jchn 1923 B/R 33.2 38.l 431. 8 12.8 8.5 Reinforced Reinforced coocrete rock Steel caisson 3 electric 8):i; 2 ancillary
:-0 N.B. Shipb.rl.lcling Ltd extended coocrete slabs o. 91!'.:rn - 1400 tens vertical spindle purps - 963t/h
3.lm thick 0.7621\ drai.ned c�rtri� purps each. 1 SU!p
s;: 1983
z and excavated Reinforced ccn:::rete 11, lrot/f each J"fP 6S.8t/h
9 rock face slab - drained
en exte'!Sicn
i'.':
"O Saint John Saint John 1942 R 18.3 21 .3 134.1 7.3 8.5 Ccncrete 3.an O::ncrete slabs sandy Steel 2 electric hori:ir- 9 2 SU1P purps
() N.B. Shipb.rl.lcling Ltd ttti.ck o.an thick ooder clay Mitre cntal centrifugal 132t/h each
� keel strips - rock puips 382t/h each
drained
CD
c:
r-
r- lENIWlK
m
-l
z Helsing.or B 21 .9 146 7 2Y,
(J)
co
co Nakshov Nakshov Shipyard 27.5 176 8.4 Reinforced Reinforced cmcrete 2
coocrete - Drained
z
0
"'
FrederiKshavn Frederickshavn R 26 176 Precast lhreinforced coocrete �
00 Vaerft og Tordok A/S coocrete - Drained
Lindo Odense Shipyard 2 1969 83.9 415 8.7 Reinforced Reinforced ccncrete firm
ccncrete 0.35- - Drained clay
0.73n thick
Ccpenhagen app . B/R 3'.).3 218 8.25 Chlcrete th:lerwater concrete sand over- 1%
195,5 at HI/ caisscns 4-!'.:rn ttti.ck lying
5.::rn wide Gravity l:imestcne
�en Bunreister & Wain 38 240 6.5 Reinforced Reinforced cmcrete clays/ Steel Flap
Shipyard cmcrete 1.0-1. !E thick gravels
- Drained
�.CIRl.D DRY 00'.YS BillLT SHT.E 19::0
Ref Year Use Entrance Dock Effect- Depth Tidal C'.onstruction C'cristructirn Soil Type of Type De- Renarl<s
!"·h . Locatim Ov.ner or Yard in of Widtti Barrel ive over range of Walls of Floor type Gate of Main (secondary
N3re Service Dock Width Sill DesiBJ1 Fhllosophy Furps ir..nps)
(m) (m) lml (m) ( m)
Alexandria 1965 R 39.6 42.0 2:B 10.8 Reinforced Reinforced c=rete sand Steel floating 3
ccncrete up to 2. 7m thick with caisscn
with anchor ties shells
in deep leyer
or sandstcne
(Jl
\>.QRill DRY o::x::KS BUILT SIN::E 19:0
)>
O> Ref Year Use Entrance Dock Effect- D.:."'Ptil Tidal Ccnstructioo Ccnstructim Soil 'l'.',>pe of fype De- R�
No. Locatioo Owner or Yaro in of Widtil llarTel ive over range of Walls of Floor type Gate of Main Watering (secood-ory
Nare Service Dock Widtil l/>.ngth Sill D.:.-'Sigp Fhlloscphy f\J1ps Time(hrs) prnps)
(m) (ml (m) (m) (m)
Hu.sun Husumer 1974 B/R 22.0 25.0 120.0 4.10 3.50 Horizootal O:ncrete with anchor filled Mitre Gates 2
Schiffswerft at anchored steel steel piled bottcrn sand
M-!JS Sheet pile wall thickness l .CDn fine
sand
H..1sun HJsurer 1900 B/R 22.0 25.0 150.0 5.20 3.:0 furizootal Coocrete with steel filled Mitre Gates 2
Schiffswerft at anchored steel piled bottcm sand
l'IH#5 sheet pile wall thickness = 1. ron fine
:u sand
£
z
0 Thyssen 1954 B/R �.o 32.0 218.0 8.20 Ccncrete U frane, thickness of walls Floating 3 l\b. electric 2.6 2 l\b. ancillary
l\brdseewerke at and botton = 2.0n. Botton anchored caisson vertical spindle purrps 360t/h each
;:: M-!JS against uplift with prestressed cable gate 294t centrifugal purps 2 No. arergency
'o anchors 7 . z:tJ t/h each pulps: 218t/h each
0
:z
Kiel HoJ/aldtswerl<:e 1976 B/R 88.4 88.4 426.0 10.0 Steel sheet Ccncrete with anchor sa'ld Floating
co DeutcheWerft pile wall with steel pile bottcms in ex- caissoo
c inclined steel thickness "' 1.3'.rn
.- change gate
.-
m pile anchors for silt
-!
deposits
z
-
<D
CD
CD
Brall"'..n llrerer Vulkan 1973 B/R 58.0 ee.2 331 .6 8.6'.) 3.90 Left side - Ccncrete wi til anchor Support beam 2 No. electric 2 No. ancillary
at angular cooc- piles system Franki with skin vertical spindle pl.llpS
z
0
l<Th'IS rete retaining plate centrifugal purrps 5JJt/h each
"'
"' wall . Ri,Pt elements 10. CXl)t/h e.ach
side - steel
sheet pile wall
as part of a
cofferdam.
Bra:ner Vulkan 1979 B/R 25.0 25.8 170.0 8.� 3.90 Steel sheet thderwater coocrete Single leaf' 2 l\b. electric 3 3 l\b. ancillary
at pile wall with thickness 1. Qn with witil buoyancy vertical spindle puips 400t/h each
Mi\S inclined steel steel anchor piles charrbers borne centrifugal purrps Covered dock
pile anchors a1d concrete coostn>ctioo in gudgecn & 5.0COt/h each w:i th hangar
floor l. Qn thick plintle bearing dim3nsioos 37x
190n hei,Pt of
ridge over dock
boti=rd 5Qn
heigi't of ent-
ranee over MilJ
LIO. 7:'rn.
WJRID DRY J)'.X;l(S BUILT Sll'CE 1950
!Ref Year Use Entrance Dock Effect-- Depth TidaJ Ccnstructicn Constructicn Soil Type of 1yPe De
N::J . locaticn o.ner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of M3.in Watering
Name Service Dock Width Length Sill Desi@1 Fhiloocphy Ptlrps Time(hrs)
(m) (rn) (m) (rn) (ml
Papenburg Meyer Werft R 35.0 35.0 2:0.0 6.50 +.40 Hvrizcntal Concrete with anchor filled Steel flap 3 N::J . electric 1 2 N::J .
mchored steel piles system Franki sand gate vertical spindle pu1ps
sheet pile centrifugc!l purrps
wall 11. OX>t/h each
Kiel N::J . 7 Howaldtswerke 1953 B/R 38.0 38.0 260.0 6.63 Angular Ccncrete thickness filled Floating 3
Dock Deutsche Werft remining = l . lQn sand caisson
concrete wall with anchor piles gate
Widening: System Franki
( as above
l'b.7 1900 B 50.25 :0.25 310.10 6.63 ( Leng'"J1ening: as above as alxlve as above 5
enlargement ( concrete wall
( en steel piles
Howaldtswerke 1953 B/R M.00 44.00 285.0 6.63 Ps d<x;k l'b. 7
Deutsche Werft
Papaiburg Meyer Werft 1987 B/R 40.0 40.0 257.0 9.50 O.LIO Horizcntal Ccncrete with sand Steel flap Covered cb::k .
at an:::hored anchor piles gate Cover 101 . 8n x
M3L steel sheet system Franki 265-n heigJ'lt ffin
OJ
c pile wall ridge . Entrance
r heig)1t 41m above
ffi
z
MllL .
ID
CD
CD
z
0
Pemo Wartsila
\l.ORlD DRY ro:::KS BUil.T SII>CE 19:0
)>
00 Ref Year Use Entrance Dock Effect- Depth Tidal Ccristruction Coostructim Soil Type of Type De- R61larl<s
No. Location CN.ner or Yard in of Width Barrel ive (Jlfer range of Walls of Floor type Gate of i'l'ain Watering -· _ ,
!'are Service Dock Width Length Sill Desi!?)1 Ihllosoph,y PU!ps Tilre{hrs)
{m) {m) (m) {m) {m)
FRAN:E
Dunkerque Jlb.6 Dock 1978 :0 52 310 -5 Sheet piling Reinforced cmcrete fine Steel flap 3 1*>. purps 2
with ties at en filter layer sand 130'.l Kw
2 levels oo clay 3 x 8 rrr /s
;::
1l
h Marseilles Jlb.10 Dock 1975 R 85 85 465 -11 .0 Reinforced Reinforced cmcrete clay Prestressed 3 No. J'.lUTPS 3)4 3 dewatering
;.:: at lJil crncrete with l.O-l . 5n thick cmcrete 3 x 13 5ii' /s purps
relieving on filter layer caissoo
CD platform
c
r
6 Brest No.2 Ccncessimnaire 1968 R 53 55 338 -7.3 Reinforced 5n thick anchored rock Caissoo 4 centrifugal 4 2 nfilntenance
purps
z 0::1 to rock purps
4 x 15.crotf /h
�
<O
00
00
z Brest N:>.3 1900 00 00 42) -7. 4 Reinforced 1 . !':m thick en schist Prestressed 3 No. puips 1-3 3 pmps +
0
(J) a:ncrete filter la,yec- ccncrete 40 , o:xni' /h 3 dewatering
w
caissoo plllpS
Scar-� Hellenic Shipyards 1977 R 75 420 Reinforced Reinforced ccncrete resid- Steel cantilever
O:xrpany cuicrete Lan thick ual gate
originally i'IDChored soils
with prestressed
piles rD# drained
�
� (1986)
z
0
� GlHW..'fllR
'u
h Gibraltar Shipngpa:ir Ltd 10Cl5 R 37.8 37.8 Z76 12.42 r.Ess Gravity Floating caissm
z Refurbished cxncrete
1985
ID
c
r
r
m
::! INJ!A
z
�
<O
<X>
Visakhapatnam Hindustan
<X> Shipyard Ltd
z
0
� ITALY
Palerno 1979 68 370 11.3 Reinforced cco- Reinforced ccncrete Lime- Steel flap Dock bt.1ilt :in
crete caissms caisscns co piles/ stale/ gate twJ secticns
reinforced ccncrete alluvial
2. 5"n thick with ties clep:sits
Trieste Cantiere Navale !:',6 3:'D 8.5 Reinforced Re:infarced cax:rete Reck
del Italccntieri coocrete tied to rock
foondaticn
Livano Crnsorzio Livomese 1S75 !:',6 3&) 10 Re:inforced Reinforced ccncrete mixed Steel flap 4 l'b. vert . 3.5 3 l'b. centrif.
Bacini Carena,ggi.o cco:::rete - Gravity (sea Gate prq:ieller @ 2,crot/h. 3 fb.
)>
bed) 27,COJt/h 200t/h
(0
\>.ORl.D DRY ro::KS B'JILT SIN::E 19:0
::t>
Ref Year Use Eni:r'dl1Ce IX:ck Effect- Depth Tidal Ccnstructioo Ccnstructicn Soil 'fype of 'fype De- Re;arks
0 No. LoCaticn O.ner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of �'.a:in Watering (secmdary
Natre Service IX:ck Width Length Sill Design Philooophy fuJps Time(hrs) prnps )
(rn) (m) (m) (m) (m)
JAPAN
1 Aioi No.l ED Ishikawajima 1975 B ro ro 291. 5 11.3 7.9 Reinforced Reinforced Ccncrete rock Steel Caisson
HariJra Heavy Calcrete on gravel layer & sand
Industries Ltd Drained
2 Aioi No.l FID 1963 R 35.3 41 .3 238.1 11.7 9.07 Plain Reinforced Ccr1erete rock Steel Caissoo ) Diagonal JJUTP 1.5 ) Cam=
Concrete & sand l 24.cro ni' /au ) use
) }
) )
3 Aioi !'b. 2 RD 1963 R 21.2 30.0 152.14 9.27 6.42 Pla:in Reinforced Ccncrete rock Steel Caissoo ) s.cro ni' /2x2 1.0 ) 540 rri' /h
Ccncrete & said ) )
:0
s;: 4 Aioi No.3 RD 1973 R 56.0 !Xl.O 340.0 11.0 8.0 Reinforced Reinforced Ccncrete sand Steel Flap Gate Diagoo;il JJUTP 2.5 Diagooal puip
z Cc:ncrete oo gravel layer 24 .cro ni' /M 7CO n? /h xl
!."> Drained
5 Kure l'b. 2 ID 1969 B 65.0 65.7 339.65 10.15 6.81 Reinforced O:nc:rete rock Steel Caissoo "=' 10.0 Centrifugal.
� Grav:ify """""" �""" -- -i:::>""
6 Kure No.3 ED 1973 B 80.0 80.0 !003 . 2 12. 5 8.91 Grav:ify Reinforced Concrete rock Steel Caisson Diagcnal 7.0 Diagcnal
en
c 'fype en gravel layer & sand 2:).cmrr /h x3 lcmiT /h x2
r
r Drained
m
-i
z 7 Kure i'b.4 RD 1974 R 44.4 46.6 331 . 2 15.4 12.8 Plain Reinforced Ccncrete rock Steel Caissoo Diagonal 3.0 Diag::nal
...
<O Ccncx-ete 12.cmrr /h x2 :ooii' /h x2
"'
"' 15.cro xl
19.CIXl x2
0
z
°' 8 Tokyo No.2 RD 1962 R 24.0 30.0 100.0 9.9 7.25 Plain Reinforced Concrete sand Steel Caisson Centrif\igal 2.0 C'.entrifugal
(.:>
CcrlCrete 2. 7COi1' /h xl �
3.CXXJ xl
3.42:) xl
9 Yokohara RD 1966 R :x>.o 06.0 35'3.0 1 1 . 5 8.6 Sheet Reinforced Ccncrete sand Steel Flap Gate Diagcnal 4.0 Diagonal
Pile 24.cmiT /h x2 240x2
10 Aichi ID 1984 B 92.0 92.0 518.0 13.0 9.62 Reinforced Reinforced Ca1Crete sand Steel Caisson )Diagcnal 10.0 )Diagcnal
Ccncrete oo gravel layer )3'.l.CIXl x2 )10'.Xl x.l
Drained ) )
) )
11 Aichi RD 1980 R 43.4 43.4 290.5 13.0 9.62 Reinforced Reinforced Ccricrete sand Steel Caisson )Centrifugal 5.0 )Turbin
Concrete )6XXJ xl ) 200 xl
\l.ORW DRY DXKS BUILT SIN::E 19:0
Ref Yezr Use Entrance Dock Effect- Depth Tidal O::nstructicn C'.onstruction Soil Type of Type De- RE<Tm'ks
!'b . l=ation o.ner or Yard in of Width Barrel ive over ra'1ge of Walls of Floor type Gate of 1"ain Watering (secoodary
Nare Service Dock Width Length Sill Desigp Fhiloscphy PLJrps Tilre(hrs) purps)
(m) (m) (m) (m) (m)
JAPAN (Ccntin.Jed )
12 Tsu J'b.IBD Nippcn Kokan K.K. 1969 B 75.0 75.0 348.3 7.9 2.1 Reinforced Reinforced Concrete sand Steel Caisson Electric vertical 4 Electric vertical
at Hl\IS Ccncrete 0.7$-2.0m thick with over Steel wt= mJ spindle miJ<ed flOH spindle nill<ed flOI>
0.75n thick Water cut off clay ton PUJP 39 , CXXlt/h purp fD)t/h
Drained
13 Tsu l'b.2BD Nippcn Kol<an K.K. 1969 B/R 75.0 75.0 143.0 7.9 2.1 Reinforced Reinforced Concrete sand Steel Caissm *Carbined use 1 *Ca!bined use
at tt.\15 Ccrr
.,rete 0.7:m-2.0m thick with over Steel wt= mJ 2 i'b. electric 2lb electric
0.75n thick water cut off en clay ton vertical spindle vertical spindle
gravel layer 4ffi.. 650 miJ<ed flOH purrps nill<ed flry,1 P'JlPS
� thick Drained 39, CXXlt/h each fD)t/h each
}>
z
9 14 Tsu Nippon Kokan K.K. 1970 R 75.0 75.0 500 . 0 10.2 2 . 1 Reinforced Reinforced Concrete sand Steep Flap 4
Repair Dock at tt.\15 Ccncrete 0.00-2.0m thick with over Steel wt= 900
?:'.: 0.75n thick water cut off and clay ton
'u water relief well
h system en gravel layer
� 450-6:0 thick Drained
CD
c 15 Kobe J'b.4 Kawasaki Heavy 1969 R 33 . 5 33 . 5 215.0 6.0 N/A Reinforced Reinforced Concrete sand- Steel Flap N/A 3Y,
r-
r- Industries Ltd Ccncrete Stene
m
-i
z
�
(!)
CD
CD 16 Sakaide i'b.l 1967 B 62.0 62.0 300. 0 5.9 N/A Reinforced Reinforced Concrete clay Steel Flap N/A 5 Exclusively for
Concrete on gravel 50-4:0 thick and building offshore
z0
Drained silt strucb.Jres
CJ)
U>
17 Sakaide i'b. 2 1968 R 72.0 72.0 4:0.0 7.9 N/A Reinforced Reinforced Concrete clay Steel Flap N/A 3Y,
Concrete on gravel layer 100- and
4:0 thick Drained silt
18 Sakaide i'b . 3 1972 B 75.0 75.0 420.0 6.2 N/A Reinforced Reinforced Concrete clay Steel Flap N/A 5
Concrete en gravel layer and
100-4:0 thick silt
Drained with water
relief well system
)>
V.ORID DRY lXlCKS BUILT SIN:E 19::0
)>
..... Ref Year Use Entrance iX1ck Effect- Depth Tidal Coostructioo Constructicn Soil Type of Type De- Rema."'ks
[\) N:>. L:x:aticn 0."1et' o:r Yan:l in of Width BarTel ive over ra.'1ge of Walls of Flooi- type Gate of !fain Watering (secoodary
fl0re Ser-vice Dxk Width Length Sill Design Fhi.lascphy PU!ps Tilre(hrs) puips)
(m) (m) (m) (m) (m)
JAPAN (Q:ntimed)
19 Tamano N:i . 1 Mitsui Zcsen O:>rp 1974 81 81 187 . 2 9.3 2.3 Reinforced Reinforced Ccocrete granite ffiXhi' /Hx9 9.5
�Tete etc.
al 01iba l'b. lA 1962 B 45.0 47.0 100.0 5.5 2.2 Reinforced Reinforced Ccncrete sand- Steel Flap 6.5
Ccncrete stcne
21 Qdba N:l.lB 1965 R 45.0 45.0 310. 0 5.5 2.2 Reinforced Reinforced Ccncrete sand- Steel FJ.l¥,l 114ffili' /Hx2 4
Ccncrete stcrie
�
)>
z 22 01iba !'b . 2 1968 B 72.0 72.0 400. 0 7.7 2.2 Reinforced Reinforced Ccncrete sand- Steel Caisscn 19aX:lli' /Hx2
9 Ccncrete oo gravel lqyer stcrie
2C!)..,l50
l thick with
Q)
Q) 24 Yura N:i . l 1973 R 65.0 65.0 350.0 9.5 2.5 Reinforced Reinforced Ccncrete rock Steel Fl!:IP Electrical Vertical 2.5
Concrete oo gravel layei- Mixed Flow Putp
z x
0
3'.l.cx.xrr? /Ii 3
°'
CU
25 Yoko.suka Sumi tmo Heavy 1972 B/R m.o .m.o !:ro.O 9.2 2.0 Reinf'orced Reinfor-ced Ccncrete vecy Steel Floating � N/A Th.ial entrance
Industries Ltd Ccncrete oo gravel layer- hard
Q:ipalra Shipyan:l 21XJ-700 thick clay
Drained
26 Toyahaski l',ariazash.i 1977 B 66.0 66.0 380.0 10.7 2.4 Reinfon::ed Reinforced Concrete fine
Aichi Zosen Ltd Ccncrete ro gravel layei- sand
Dmined
WORLD DRt rxx::KS BUILT SITO: 19::0
Ref Year Use fatrance Dock Effect- Depth Tidal Constructirn Constructicn Soil Type of fype De- R6!0l'.i<s
No. Lccatirn O.i.ner or Yard in of Width Barrel ive aver range of Walls of Floor 1;ype Gate of Main (secondary
N3me Service Dock Width Sill Desigp Fhllcoopey furps prnps)
(m) {m) (m) (m)
JAPAN (Ccntir:ued)
Z7 Tadotsu Hashihara 1975 B eo.o eo.o 38:).0 11 . 5 3.5 Reinforced Reinforced O::ncrcte clqy
Kagawa Zosen Ltd Ccncrete en gravel l"llfer sand
Drained
28 Oshirra Osaka 1975 B oo.o 00.0 53'3.0 13.0 3.3 Reinforced Reinforced Ccncrete rock
Naga.51'.i Zosen Ltrl O:ncrete layer
29 � MU � 1976 B 56.0 56.0 375.0 10.15 3.3 Reinforced Reinforced Ccncrete rock Steel Flap Vertical spindle 2.5 2 No. VS::: purrps
N::>. l Ccncrete o.an thick on axial flON purps lo:xni' /H
� 0.5n thick gravel layer 23CXXhi' /Hx3
Drained
;r:.
z
0 21) Nagasaki 1965 R 56.0 :'6.0 375.0 10.15 3.3 - ditto- -ditto- rock -ditto- Purp in camon 2.5 in crom:n
f'b. 2 wi th above dock with above
?::
'o 31 � 1900 R 38.8 41 . 0 276.6 9 . 33 3.3 Ccncrete Ccncrete 0.94m thick rock Steel caisscn Vertical spindle 4.0 1 [b. vs:: purrp
0 N::>. 3 l .2m thick oo gravel pU1p 48)if /H. Si.lb-
� �
1 purrp
Cl! l purrp roil' H
c
r-
r- 32 Koyagi 1972 B 100.0 100.0 790.0 11 . 65 3.3 Reinforced Reinforced Ccncrete rock Steel caisscn Vertical spindle 9.5 3 No. VSA purrJS
!!l No.I crncrete 1 . 5n thick en axial flow PLJTPS lo:xni' /H
z O. Sn thick gravel layer ro.cmrr /Hx3
�
<O � thick
Cl>
Cl> Drained
z 33 Koyagi 1973 R 100.0 100.0 400.0 11 . 65 3.3 Reinforced -ditto- reek Steel flap Vertical spindle 3.5 2 No. VSA ptrnpS
2(XXhi' /H
0
34 Konnuku �HI Yol<oharra 1003 R ::0.8 !'0.8 332.6 8.84 2.0 Reinforced Reinforced Ccncrete clqy Steel flap Vertical spindle 2.0 2 No. VSA pl.JlpS
ccncrete 1.an thick oo gravel axial fl<M pu!pS lo:xni' /H
0. 5n thick layer Drained
35 1003 R !:D.8 !:D.8 57.4 8.84 2.0 Reinforced Reinforced Ccncrete clay Gate in Purps in cam= 2.0 Purps in camon
ccricrete 1 . an thick on gravel cmm:n with with above with above
a. Sn thick layer Drained above
WJRlIJ DRY JXC'i<S BUILT srra: 1900
)>
JAPAN (c.:ntirued)
:06 Homuku M:Il Yokoharra 1972 R ro.o ro.o 270.0 9.85 2.0 Reinfoixed Reinforced O:::ncrete clay Steel flap Purps in crnm:n 2.0 Purps i n =m:n
ccn::rete l.Qn thick en with above with above
gravel layer
31 1005 R 30.0 30.0 100.0 10.7 2.0 Steel sheet Reinforced Coocrete cla.y Steel flap Vertical sp:indle 2.0 1 No. VSA purp
piles l. cm thick oo aidal fle>N purps l<XXlli' /H
gravel layer l!'lX'Oii' /Hx2
38 K1.m31roto !'b. l Hitachi :&sa1 1973 ? 85.0 85.0 620.0 10.8 4.7 Reinforced Reinforced Ccncrete clay Steel caisson Electric vertical 10
:u Prof Nagaik Corporaticn 600-:nl 600-:nl on gravel flcm 3'.l. <XXlli' /HJ<2
Ariak� thick and layer Drained
;i.
z steel sheet with water relief
� piles well system
;i>- 39 No.2 1973 ? 85.0 85.0 :ni.o 10.8 4.7 -ditto- -ditto- cla.y -ditto- -ditto- 6
'o
0 40 Sakai !'b.l Hitachi Zasen 1966 B/R !"X>.O 56.0 400.0 7.8 0.3 Reinforced Reinforced Coo:te:re clay Steel flap Electric vertical 4
� Osaka Corporaticn ccncrete an-2.an thick with centrifugal
Osaka \llarl<s 2.lrn thick gravel lqyer 25. <XXlli' /HJ<2
Ol Drained
c
....
.... 41 !'b.2 1972 B/R 62.0 62.0 455.0 7.8 0.3 -ditto- -ditto- clay -ditto- Electric vertical 3
m
::!
z
�
"'
Q)
Q) 42 !'b.3 1900 B/R 100.0 100.0 lZl.O 9.3 0.3 Slcping !'nrm asphalt en clay Steel caisson
earth s:om. crushed
143
z greni te
0
°'
"' Innoshima Hitachi Z.OSen 1965 B 45.0 45. 0 227.25 11.3 3.5 Re:infoixed Reinforced Ccncrete silty ?
Hi.rcsh:ima Carporatioo en gravel en 12JO..- clay &
Jlb.3BD Innoshima Works 1300 thick sand over
Drained dock
llEN'iA
!Ref Year Use Entra.'1Ce Dock Effect- Depth Tidal Ccnstructioo Constructia; Soil 'fype of 'fype Re<narns
!lb. locaticn CMner or Yard in of Width Ba.""rel ive over t"dllge of Walls of F1oor type Gate of Main ( sc-cdary
cn
Nane Service Dock Width Sill Desigp Fhil�hy Purps pwps)
(m) (m) (ml (m) (m)
Ml\LAYSIA
MALTA
� r.rnrrro
"O
h
;z Ciudad ltadero '37 249 9.0 Anchored steel Reinforced ccoorete Floating
at M5L sheet piling o.an thick i. 7m thick steel
and steel under keel strip caisson
OJ
c sheet piled - Drained
r
r caf'ferdam
m
-I
z
.....
<O Veracruz B 36 36 269 5.7 M3!;s coocrete Gravity Floating 3 N::> .
°' steel in line
°' at MHW walls
caissa; sumersible
z
"'
0
"'
MIIDIB EAST
Dubai Dubai Dry Dock Co. R 66 '370 2.28 Reinforced ccn- Reinforced ca;crete Rock l?rq)ped 5 No. vertical
Dock No . l crete caissons 1 . 511 thick steel mixed flow pUtpS
- Drained flap gate to serve all docks
arranged in tv.o
purplxA.lses
Dubai Dubai Dry Ikx:k Co. R 100 525 2.28 Reinforced cm- Reinforced coocrete Rock l?rq)ped
Dock No.2 crete caissons 1 .511 thick steel
- Drained flap gate
Dubai Dubai Dry Dock Co. R eo 415 2.28 Reinforced cm- Reinforced ccncrete Rock l?rq)ped
Dock N::J . 3 crete caissons 1 . 511 thick steel
- Drained flap g;ite
)>
Bahrain f.sry 75 Reinforced Reinforced ccncrete
......
(Jl concrete - Dra.ined
:J>
.... Ref Year Use Entrance Dock Effect- Depth Tidal Constructioo Constructioo Soil Type of Type De- Renarks
O'> l'b. Location e>.ner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of M3.in Watering (secondary
Name Service Dock Width Sill Desigp fhlla;qIDy PL1!ps Till>3 (hrs) purps)
(m) (ml (m) (m) (m)
ffi:JllERLAN) ANl'Il..llS
Curacao Curacao Dry Dock 1971 47.70 48 200 8. 5 • 5 Reinforced Reinforced ccncrete weathered Hinged 3 l'b. vert • 3
Caip. Inc. ccncrete - Drained rock floating 12,crot/h
t£JlERLN'1[6
Den Helder Dutch Royal Navy 1978 R 23 153 9 Reinforced Reinforced coocret e soil Hinged floating Covered dcrJ<
� coocrete - Gravity desilir! :iJlprove- caisson for frigates
)>
z ment med
9 Sloe- Kon rt11 "De Schelde" 1961 R 24 25.3 175 6.5 3 Reinforced Reinforced concrete sand Steel flap ) 3 !'b. vert. ) Purp r=n
Vlissingen Dock I ccncrete - Gravity d� ) spindle ) for
� ) 10,crot/h ) 2 docks
'u
h Sloe- Kon "1Y ''De Schelde" 1961 R 29.5 29.00 215 7.6 3 Reinforced Reinforced coocrete sand Steel flap ) )
� Vlissingen Dock II ccncrete Gravity desigp. ) )
Schiedam Dok-en Werf- pre ' 66 R 47.3 tl9 305 9.4 3 Reinforced Reinforced concrete sand 3 l'b. puirps 2
M3atschappij coocrete 6. 211 thick ancrored and 25, roJ t/h each
Wilin'l-Fijenoord with sheet to precast ccncrete gravel
N.V. Dock 8 piled backing piles
RosenbJrg Verolmz- 199'3 B 43.5 297.0 app 3 Reinfon:;ed Reinforced coocrete Hinged floating
(Scheur) l'b. 4 5.0 cmcr-ete 2.0-6.&n thick caissoo
at M3L min. wall - Gravity desilir!
thickness 2. Qn
�JJRlD 00\I ro::l<S BUILT SIN:::E 1950
f Year Use Entrance Dock Effect- Depth Tidal Coostruction Coost:ruction Soil Type of Type Rerrarks
!'b. 1=ation CMner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of M3in (seccndary
Narre Service Dock Width length Sill DesillP Fhlloscphy Puaps pl.ITpS )
(m) (m) (m) (m) (m)
Ml:'� (Ccnt:inJej)
Rosenburg Verolme- 1962 R 36.0 230.0 app 3 Reinforced Reinforced cc:ncrete Hinged
(Scheur) l'b.5 8.0 a:ncrete 4.0-6.0n thick floating
at MSL - Gravity desillP caisson
�
;i.. Rosenburg Verollre- 1971 R 90.0 410.0 app 3 Reinforced Reinforced cc:ncrete Hinged
z (Scheur) !'b. 7 12.0 crocrete app 3.0n thick steel floating
9 at MSL app 3.0n teision/carpressim caisson
thick piles
�
'o
h Harlingen Frisian Dockyard 19:)7 B 30 30 145 6 2 Steel sheet Reinforced concrete sand
� piles
OJ
c
• Amsterdam Netherl andsche Dock 1956 R 36.6 39 . 50 245 8.4 Reinforced Reinforced coocrete sand
• en Scheepsba.!\\l- concrete app 5.0n thick
m
-i maatschapip j - Gravity desillP
z
'°
�
00
00
z
0
O>
w N:BJIM
P.AKISTAN
Karachi Pakistan Irrlustrial 1959 R 27.4 27.4 190.8 7.8 3.0 Reinforced Reinforced caicrete fine St.eel floating 3 !'b. propeller 2Y, 2 !'b. bilge
DevelO[l'le'lt Corp. at ccncrete 1.2- l. 8n thick with sand caissm purps purps
!'b.l IJcck MM 3.an thick prestressed anchors 6, 6Xl t/h each 3rot/h each
!'b . 2 IJcck 1971 R 24.33 24.38 170.70 7.2 3.0 Reinforced Reinforced ccncrete fine Steel floating
at M-111 o::ncrete min l . 511 thick with sand caisscn
prestressed anchors
�
)>
z
0
i::
'o roLAJI[)
b
� Gydnia Centroror'-lhlted B/R 42.5 239. 3 7.1 Reinforced Reinforced ccncrete sand/ Steel flap 2 !'b. purps 4
Shipyan:ls cooc:rete 2.8-4.an thick cley 7 ,200 t/h each
CD 3.6m thick - Gravity
c
.-
.-
m
-i Gydnia Centrarol'.'-lhited B 70 38'.) 7.1 Steel sheet Reinforced o::ncrete sand 8 l'b. puips 8
N:J. 2 3,a::o t/h to
z
.... Shipyards IJcck piling with l. 7-2.411 thick
"'
00 - Drained 6,100 t/h each
00
relieving
platform/
gallery
z
0
"'
"'
WJRlll DRY ro::KS BUILT SIN::E 199:>
Ref
lib. Lxaticn 0...ner or
Name
f1:RlUll\L
Lisbm Lisnave 1970 B 54.0 54.0 300 7.55 3,30 Reinforced Reinforced ccncrete miocenic Steel caisson 3 vertical spindle 4 2 filter purps
Tagus f'b.10 Dock ccncrete floor slab 0.911 thick silt hinge:! self purps lfilXl nf /H
estuary walls o,ron and keel beam; under'- clay prcpelle:l each
thickness floor drainage
and r.ccric-
rete gravi ty
wall£ O,OOn
thickness
:0 Lisbm Lisnave 1967 R 54.0 54.0 350 11 . 70 3.30 Reinforced Reinforced coricrete miocenic Steel flap 3 vertical spindle 2.5 2 filter purps
)> Tag.is No.11 Dock o:ncrete floor slab .911 thick silt purps lfilXl nf /H
z esruary gravi ty and keel beam; under clay each
9 walls LOO floor drainage
and 3.COOn
;::: thickness
'u
h Lisbm Lisnave 1967 R 42.0 54.0 263 11 . 70 3 . 30 Reinforced Reinforced cmcrete miocenic Steel flap 2.5 2 filter p.rrps
z
TagL1s !lb.12 Dock ccncrete floor slab .911 thick silt
estuary gravity and keel beam; under clay
Cl walls 1 . 00 floor drainage
c and 3.00n
r
r
m thickness
-i
z
� Lisl:x:n Lisnave 1971 R oo.o 97.0 5.3:) 12.00 3.30 Reinforced Reinforced ccncrete miocenic Steel flap 3.0 2 centrifugal
"' Tagus [lb.13 Dock ccncrete floor slab . 9n thick silt filter purps
"'
"' b.rttrese
s s and keel l:ica-n; under
estuary clay 15'.X) nf /H each
and meta.lies floor drainage
z0 gabicns
m
VJ
Setuba1 Setenave 1974 B 75.0 75.0 420 6.50 3.10 Reinforced Reinforced ccncrete hydraulic Re<rovable 3 SJRK vertical 2 KSB
Sado l'b.2:) Dock concrete slab and keel bo
..an sand iretalics 2000 each
estuary walls l .2:ln over reclalined area fill plus 2 KSB
and .70n (sand) purps l::a:J nf
thickness each
Setubal Setenave 1974 R 75.0 75.0 4::0 6.::0 3.10 Reinforced Reinforced ccncrete hydraulic Steel flap 3 SORK vertical 2.5 2 !<SB PLl1PS
Sada l'b.21 Dock (17) ccncrete slab and keel beam sand spindle purrps 2000 ii /H each
estuary with over reclaimed area fill 3EOX> nf /H each plus 2 KSB
l:uttresses (sand) purps l:>:X>
nf /H each
SeUJbal Setenave 1974 R 55.0 55.0 3::0 10.00 3.10 Reinforced Reinforced ccncrete hydraulic Steel flap 3 s:lRK vertical 2 KSB purps
Sade l'b.22 Dock ocncrete slab and keel bean sarrl spindle purps 2000 nf /H each
estuary with over reclaimed area fill 3SXXl nf /H each plus 2 KSB
buttresess (sand) purps l::a:J
)> nf /H each
.....
CJ:)
1/XlRl.D Dffi' OCCKS BUILT SIN::E 19&>
)>
Ref Year Use Entrance Dock Effect- Depth Tidal Ccnstructicn Ccnstructicn Soil Type of Type De- Renarl<s
I\) l'b. Locatiai Owner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of M3:in Water:ing (seccndary
0 tare Service Dock Width J..ength Sill Desi!lTl Philosq:ihy PuJps Tlire(hrs) purps)
(m) (m) (m) (m) (m)
SilG\IUlE
Tuas Keppel Shipyard Ltd R 52 52 3)2 9 2.4 Reinforced ccn- Reinfol'Ced ca:icrete Steel 3 Jib. mixed flo.< 21;
Tenasek Dock at MSL crete with 0.8-l .2m thick flap pu!pS z:m'.)t/h
ccunterforts - Drained gate eoch
Tuas Keppel Shipyard Ltd R 00 335 9.4 2.45 ReinfOl'Ced ccn- Reinforced ca:icrete dense Steel 3 lib.
Rafiles Ib::k at �l:!JB crete 0.3-0.55 0.8-l .65n thick clayey flap
thick with - Drained silt gate
ccunterforts
� Sanbawang Sarbawang Shipyard Ltd 1975 R 64 65 384 8.0 Reinforced Reinforced o:ncrete Steel Centrifugal
)> Prenier Ib::k at ll'fMS ccncrete piled floip
z
p
Serbawang Seibawang Shipyard Ltd 39.6 42. 5 � 13 ll'ass ll'ass caicrete Steel Centrifugal
� King George VI Ib::k at !II-MS o:ncrete caissm
'u
b Singapore Slipwey 1982 R 20 20 lCO 3. 5 2.2 Sheet piled Reinfol'Ced ccncrete rrat"ine Steel 4 No. Flygt �
;z & Engineering Co (Pte) Ltd at MSL with relieving 0.92511 thick m clay flap sulmarsible puiµ;
platform steel piles - drained gate
OJ
c:
r
r 00 00 Efl.s:Dt/h totru
Tanjcng Hitactii Zcxsa1 R 35 6.0 a:mt/h total
� Qil ROOin DockYard (Pte) Ltd at LIJil
z
-' Channel
"'
co
co
Mitsubishi Singapore R 00 00 300 9.0 Steel 35. crot/hx3 2Y, lcrot/hx:2
Heavy Industries ( Pte) Ltd flap
z
0
gate
°'
(.:>
Jtll'.'CXlg JUl:"Q:lg Shipyard Ltd R � 56 3:0 5.64 39.9COt/h total
at Ll.Jil
\\QRUJ DRY IX:CKS BUILT Sm::E 19:0
Ref Year Use Entrance Dock Effect- Depth Tidal O::nsb:uctioo Coos1nlctioo S:lil 'fype of' 'fype De- Ranarl<s
l\b, Locatioo CJl..ner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of Main Watering (seccndary
Narre Service Ilock Widlh Length Sill Design Fhilo;opcy Fl.Jrps Time(hrs) puips)
(m) (m) (m) {m) (m)
IDJlH l«llEA
Okpo Da..
"'VXJO Shipbuilding & B 131 131 529 Reinforced cm- Reinforced cmcrete rock Steel inverted 4 vertical mixed
Heavy Machinery Ltd crete CDlll1ter- o.s-1.an thick 'T' floating flow puips
forts - Drained caisson
Daew:io Shipbuilding 1983 B/R 81 81 3!50 10 Reinforced coo- Reinforced ccncrete rock Steel inverted 4
& Heavy M3ch:inery Ltd at M:iL crete 0.45-0.fm 0.8- 'T' floating
thick with - Drained caisson
OOJnterforts
!'..'.
'o
h
z
SPAIN
Ol
c: cadiz 1975 386 4 No.
r
R 55.6 12.0 Reinforced con- Reinforced coocrete Steel flap
r at M3L crete caissons - Drained gate 24,CX::O each
gj
z
(Strutte:l)
"' 36
CD
El Ferrol l\stilleros del 1969 B/R :'>/.00 254 Chart D Reinforced con- Reinforced cmcrete sandy Steel flap Electric vertical
CD l\broeste SA -8.48 crete gravit;y gravit;y 5. ::on silt gate 3 side spil'.'dle centrifugal
dam 4.0J:n with boulders slate bearing pt.rrpS
z
"
"'
"'
ERI LAN<A
ColClltx) Colaitxl Dockyard 1985 R .a3 44 263 48.5 0.77 Reinforced cm- Reinforced ccncrete rock Steel flap 3 N:J. vertical <%
Ltd at LW crete 0.5n thick 0.5-1 .lm thick gate mixed flOll purps
with counter'- - Drained 14,CXXl t/h each
forts
\\ORl.D DRY DXKS BUILT Sil'O!: 19::0
)>
I\)
I\) Ref Year Use Entrance Dock Effectr- Depth Tidal Ccnstructicn Ccnstructioo Soil Type of Type De- Re1Erl<s
lib. Locatioo Ol!.ner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of !lain Watering (secoodary
Nooe Service Dock Width Length Sill Desi!?}'l fhilcsophy fu!ps Tbre(hrs) purps)
(rn) (rn) (rn) (ml (rn)
Uddevalla lkldevallavaret AB 100 400 Rock with cm- Reinforced concrete i.=k Steel
crete prctectioo 0.35n thick Floating
- Drained caissoo
�
)>
z Gothenburg Aredal Shipyard
9
Gothenl:urg Eriksberg 65.2 381.9 Rock with thin - Drained reek
�
"1)
concrete
CJ coating
z
CD
c
r-
r-
�
z '.lHAILAN)
....
co
O:>
O:> Bang}<ok Royal Thai Navy 1981 22.5 118.3 Steel sheet c.oncrete Um thick Steel Flap gates 1Y,
!Xlckyard piles with with anchors with buoyancy
z 2 l\b. Docks concrete t.q:J clarbers hinged
a>
0
at floor
....,
\\OOID DRY D:Xl<S BUILT SIN:,'E 19::0
Ref Year Use Entrance Dock Effect- Depth TI.dal Ca:istructim Constructicn Seil 'fype of 'fype De- Remarks
!'b. U:>cati01 Owner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of Main Watering (secondary
Naire Service Dock Width Length Sill Desi@'I fhllosq>ey Purps Time(hrs) purps)
(m) (m) (m) (rn) (m)
lM'lEJ KThtD'.ll!
1 1'bM:h Shields Smith's Dock Co Ltd 1954 R 29.0 2-0.5 216.l 8.2 4.6 Sheet piled - Reinforced crncrete boulder Steel flap 2 No. electric horizontal 3 3 l'b. ancillary
No.8 Dock at slq:>e 20:1 1 .8 - 3 . &n thick cley gate-190t spindle centrifugal p.mps p.mps 0.3m dia
!IHllS Gravity 10,00J t/h each
2 Newcastle Swan H..tnter and 1995 R 32.0 34.7 217.9 8.8 4.6 Reinforced Ccncrete 3 .1 - 4 . '.h boulder Steel flap 2 lb. electric horizontal 2Y, 3 l'b. ancillary
(Wallsend) Wigtiam Rich--mlson at concrete thick - Gravity clay/ gate spindle centrifugal purps puips 0.3m dia
Ltd. lb.4 Dock !IHllS 3.&n thick sand 14,400 t/h each
3 South Shields Brigtiam & Ccmar1 19"6 R 28.9 28.9 217.9 6.4 4.6 !'recast C01Crete Reinforced crocrete boulder Steel flap 2 lb . electric vertical 4Y, 2 lb. ancillary
buttresess with 1 . 1-1.:ln thick with clay/ gate spindle centrifugal pLUpS purps 0.3TI dia
� insitu concrete H pile anchors soft 6,8XJ t/h each
)> between - Tied sand
z
p 4 Falm?uth Fa.1.m:uth Dock and 1958 R 39 . 6 39 . 6 289.0 11.0 Reinforced cuic- Moss coocrete reek Steel flap 3 lb. double entry, single 2%
Engineering Co Ltd at rete o.an thick awrox l . lm thick gate-s:::ot stage, split casing,
;:: Mi.I'S with reek anchors - Vented vertical spindle,
'o centrifugal purps
h 14,400 t/h each
;z
5 Inminghool H..m:>er D:lck and 1960 R 27 . 4 29.9 182.9 6.7-* Reinforced ccnc- Coocrete 4.lm thick sand/ Steel flap 2 lib. h:rizootal split 3'i:i *�ding en level
Ill Engineering Co Lt.cl 8 .2 rote 3.an thick reinforced under gravel gate casing centrifugal purps in >.et deck ccl:side
c keel strip-Gravity 6,8Xl t/h each 3 1'b. • 3TI dia
r
r ancillary purps
m
-i
z Jarrow The �tarcantile Dry
�
6 1960 R 25.9 28.3 182.9 7 .2 4.6 Steel sheet liass concrete boulder Steel flap 2 No. horizontal split 3Y, 2 tb • • 3m dia
°' 7 Hebbum Vickers ._. ..... . 't> 1962 R 44.2 44.2 2!'B .1 10.7 4.6 'lied re:inforced Mass ccncrete cley Steel flap 3 Jib. vertical spindle 2Y,
"'
(Sf>;'.'" '' ' -'�-::; Ltd at cmcrete 1 . 7m 7 . 3m thick over gate axial flCM purrps
l'b . 2 Dock M-!IB thick Gravity sand 548t 18, 3::0 t/h each
8 Greenck
c .Firth of Clyde 1964 R 44.2 44. 2 a:i4.8 8.2 3.1 Re:inforced crno- Ccncrete O.&n thick reek Steel flap 3 l'b. vertical prr,peller
Dry Dock Co Ltd at rete 3.lm thick l . lm thick under gp.te-5'Dt type 23,Z:O t/h each 2Y,
MlllJS keel strip-Drained
9 Belfast Harland & Wolff 1968 R :D.3 9'.l. 9 335 11.6 3.9 Steel sheet Reinforced ccncrete clay Steel flap 3 No . electric vertical 3� 3 !'b. ancillary
llHiB piling with 3.l-\3.4n thick with gate-647t spindle axial DCM purrps purrps lcm t/h each
relieving grcund anchors and 28, Ero t/h each underfloor clra.inage
platform pressure relief drains =54 t/h approx
)>
[\)
(;)
!i.ORlll DRY J:)XKS BUILT SIN:E 19:0
)>
!Ref Yli>.ar Use Entrance Dock Effect- Depth Tidal Ccnstructirn Constructirn �il Type of Type De- R�
f\)
.i::. l'b. I=atirn o...ner or Yard in of Width Barrel ive over range of Walls of Floor type Gate of Main Watering (secc:ndary
l'hre Service Ikx:k Width Length Sill Design Fhilceqol\)I Purps Ti!T>2(hrs) purps)
(m) (m) (m) (m ) (m)
10 Belfast Harland & Wolff 1969 B 93.0 93.0 556 8.38 3.9 Reinforced crnc- Reinforced ccncrete clay Steel 2 l'b. vertical spindle 12 2 lb . underfloor
at rete L rn steel 1.8-2.311 fuick en caisscn electrically driven drainage pU1ps 135
Mi;/$ piles-Headwall drained broken mixed flCM pu1pS t/h each. 3 l'b.
tied reinforced rock fi 11-Drained 20. 5'.Xl t/h each dock floor puips
ccncrete HID t/h each
11 Nigg Bay Bro-.n & Root + 1974 B* 122 176 305 13.5 4.6 Slq:iing 1 : 1 : 5 Crushed granite sayj/ Concrete 4( +4 standby) 217 *far offshore
George W:i.npey & bituiai sand sand- caisscn 2Xhrn Flygt pU1pS structure
Co Ltd covered stale
12 SUnderland Sunderland Ship- 1975 . B 49 :o.o 181 5.47 4.4 Precast crnc- Reinforced ccncrete lime- Steel 2 l'b. 24" vertical Covered deck
:0
builders Ltd at rete panels, 0.22511 thick stale caisscn axial flCM pu1pS
� Pal.lien JIH>IS wal:ings and - Drained
z
colums
!:">
- Drained
� 13 Birl<.enhead Cannell Laird 1961 R 42.7 45.l 289.6 10.3 9 . 2 Rock (0.15-n thick ccno- sayj/ Sliding 2 l'b. harizcntal shaft
,,
h (Shiprepairers ) Ltd at (as excavated) rete with 0.45 thick stale steel centrifugal purrps
� Princess Dry Dock llf'f;B keel strip caisscn 24,:oJt/h each
- Vented cn ciro-
ular tra:k
Ill
c:
r 14 Devooport Ministry of Defence 198J R* 21 147 Reinforced ccno- 'Ihin reinforced rock Steel flap 2 l'b. ** 4
r approx * Sul::rnarine refit
m 14 Dock lQn rete 1 . 25-n cx:ncre te Drained gate (ll ,3:0t/h ea:h) ** l?\.IJpha.lse serves
-i
z 15 Dock thick 1>.1th 1=k up ties ( lOOt) both docks
-
(.0
()) 15 Stmderland Steel flap furphcuse for l'b. 2
()) T W Greenwell & Co 1952 R 26.7 28.6 205.7 8.3 4.5 Reinforced cooo- Reinforced ccno- rock 1%
Ltd. No . l Dry Dock at rete 1. 2-4. 3n rete 1.4-1 . :rn gate deck used
z Mi\$ - Drained - Drained
0
"'
<.:> 16 Swansea Duke of Edi.nbu:rWi 19$ R 28 2:)4 6.4 Reinforced cone- Reinforced ccno- cx:ncrete Caicrete (Siared p.npha.ise ) 2Y, with ship
Dry Dock at rete rete - Gravity caisscn in d::x;k
llORLD DRY DOCK BUILT SlllCE 1950
Count ry : U .S . A .
Sheet l o f 3
REF YEAR USE ENTRANCE DOCK EFFECT- DEPTH TIDAL CONSTRUCT! ON C O!lSTRUCTI Oil SOIL TYPE OF TYPE OF DE- REHARKS
NO. LOCATION OWNER OR YARD Ill OF WIDTH BARREL IVE OVER RANGE OF \/ALLS OF FLOOR TYPE GATE MAIN PtmPS WATERING ( SECO!IDARY)
NA.ME SERVICE DOCK WIDTH LENGTH SILL DESIGH PHILOSOPHY TIME PUl!PS)
(m) (m) (m) (m) (m) (HRS)
l Bangor U . S . Navy 1981 R 32 . 07 27 .43 2 18 . l 16 . 16 3 .05 Reinforced Concret e , Reinforced Concrete , Sand Floatill8 3-Electric Driven, 2 .75 2-Electric
Washington TRIDENT \/EST Varies from 4 .87m 4 .87m to 5 . 79m, and Caisson, 5 4 , 000 GPM, Driven,
Refit Facility at Floor to 2 .74m G ravity Type , Gravel Rectall8ular Mixed Flow, 2 , 500 GPM
at Service Gallery Soil Supported Box Typ e , Vertical
Steel
2 Charleston U . S . Navy Rebuilt R 32 .31 28.35 176 .8 1 1 . 46 l . 07 Reinforced Concret e , Reinforced Concrete , Marl Floatill8 2-Electric Driven, 2 .75 2-Electric
SC Charleston 1968 varies from 3 .28m l . 22m und er Keel, Caisson, 83 ,000 GP!l, Driven,
Naval Shipyard at Floor to 3 .20m Partially Relieved Rectall8ular 48" , 550 HP 2 , 000 GPf.!,
DD#2 at Copill8 Soil Supported Box Type , 8 " , 250 HP
Steel
3 Charleston U . S . Navy 1964 R 40 .24 33 . 69 193 . 6 ll .28 l .07 Reinforced Concrete , Reinforced Concrete , Marl Floatill8 3-Electric Driven, 3 2-Electric
SC Charleston 3 .35m 2 .74m under Keel, Caisson, 65 , 000 GPM, Driven,
Naval Shipyard Partially Relieved , Rectall8ular 42" , 700 HP 10 , 000 GPH,
DD#5 Soil Supported Box Type , 14" , 150 HP
Steel
4 Norfolk U . S . N avy Rebuilt R 2 9.57 23 .28 148 .4 l l . 37 0.85 Reinforced Concret e , Reinforced Concrete, Sand , Floatill8 1-Electric Driven, 2 .7 5 2-Electric
Virginia Norfolk Naval 1966 Sloped , 5 .Sm at l . 06m und er Keel, Clay Caisson, 45 ,000 GPM, 42" , 600 HP , Driven,
Shipyard Floor to 4 .89m at Partially Relieved,. and Recta!J8ular 1-Electric Driven, 4 , 500 GPM,
DD#2 Copill8 Pile Supported Shells Box Type , 5 0 , 000 GP!l, 42" , 600 lil' , 12 " , 125 HP
Steel 1-Electric Driven,
96 , 000 GPH, 42" , 800 lil'
Philad elphia U . S . Navy Rebuilt R 26 .04 23 .26 131.7 8 .41 l .70 Reinforced Concret e , Reinforced Concrete , Sandy Floatill8 2-Electric Driven, l.5 2-Electric
5
Pennsylvania Philad elphia 1956 0 .9lm et Floor, 0 .762m under Keel, Clay Caisson, 34 , 000 GPM, Driven,
Naval Shipyard 0 . 4 lm above alter, Fully Relieved , Rectall8uler 36 " , 500 HP 7 , 500 GPf.!,
DD#l 2. 9m et Copill8 Pile Supported Box Type, l6" , l25 HP
Steel
6 Kittery U . S . Navy Rebuilt R 23 .78 18 . 9 148.3 l l . 28 2 . 44 Reinforced Concrete , Reinforced Concret e , Bedrock Floeti!J8 2-Electric Driven, 2 2-Electric
Maine Portsmouth 1962 l . 92m 3 .54m, Gravity Type , Caisson, 30,000 GPM, Driven,
Naval Shipyard Rock end Pile Rectall8uler 36 " , 350 HP l , 500 GPM,
DD#3 Supported Box Type, 8", 40 HP
Steel
7 Bremerton U . S . Navy 1962 R 52.59 5 4 . 88 35 1 .2 1 6 . 23 3 . 29 Reinforced Concrete , Reinforced Concret e , Sand Floetill8 4-Electric Driven, l.5 3-Electric
lleshill8ton Puget Sound Column Support ed , 2 . l3m, end Caisson, ll4,000 GPJ.I, Driven,
Naval Shipyard 3 .66 et Floor, Fully Relieved , Sandy Rectell8uler 54 " , 1 , 500 HP 15 , 000 GPM,
DD#6 8 .84m et Copill8 Soil Supported Gravel Box Type, 20" , 400 HP
Steel
?. '!{O"t:i \:
8 Sturgeon Bey Ship- 1976 B/R 42 . 68 42 . 68 353 7 . 92 l .28 Reinforced Concrete , Reinforced Concrete, Coarse Hill8ed 2-Electric Driven, 7.5 2-Electric
Bay, Wi s . buildill8 Corp. Sloped 0. 9lm to 0 .76m, Send Gate, 28 , 000 GPM, Driven,
0 . 305m Fully Relieved, and Steel Vertical 2 , 000 GP!-!,
Soil Supported Gravel Vertical
This information is taken from existill8 documentation which i s approved for Public Release end is in the Public Domain.
WORLD DRY DOCK BUILT SINCE 1950
C ountry : U . s .A .
Sheet 2 of 3
YEAll USE EJITRANCE DOCK EF - DEPTH TI DAL C OIISTRUCTI O!i C ONSTRUCT I Oll SOIL TYPE OF TYPE OF DE- REMARKS
LOCATI O!I OWNER OR YAllD Ill OF WI DTH BARREL I OVER RANGE OF WALL S OF FLOOR TYPE GATE MAll! PUMPS WATERil!G ( SECOllDARY )
NAME SERVIC E DOCK WIJJ.l'H L SILL DESIGN PHILOSOPHY TH!E PUJ.IPS)
(m ) ( m) ( (m) (m) (HRS)
9 Sparrows Bethlehem 1971 B - 4 5 . 43 329 . 5 7 .36 0 . 335 · l . 67m Diame t e r , Reinforced Concrete , Unknown Floating 2-Electric Driven, 18 )-Electric
Point , MD 17 , 800 GPM Driven ,
1�
St eel Corp . Prestressed 1 . 22m,
C oncrete Cylind e r Fully Relieved , "� � - :::;:;, 3 . 50 0 GPH
Piles Soil Suppo rted Box Type ,
St e e l
10 G roton DD#l, General 1963 B/R 2 1 . 03 22 . 17 159.6 1 0 . 15 0 . 914 Sheetpile C el l s , Reinforced Concrete , Bedrock Hinged Gat e , 2-Electric Driven, 3.5 4-Electric
C o nnecticut Dynamics , Filled with Sand 0 Steel 5 0 , 000 GPM, Driven,
Elect ric Boat and G ravel Fully Vertical 2 , 00 0 GPM,
Division I S o i l Supported Vertical
ll Groton DD#2 , General 1968 B/R 2 6 .85 2 9 . 167 190 .85 9 .7 5 0 . 914 C el l s , Reinforced Concrete , Bedrock Hinged G at e , 2-Electric Driven, 5 4-Electric
C o nnecticut Dynami c s , with Sand 0 . 914m Steel 3 0 , 000 GPM, Driven,
Electric Boat and G ravel Fully Relieved , Vertical 2 , 000 GPM,
Division Soil Supported Vertical
12 G roton DD#5 , General 1977 B 3 3 . 91 2 9 .42 188 . 2 11.7 0 . 914 Sheet}'ile C ells Eart h , Floating Bed rock Floating 2-24" Air Lift 92 1-12" Air
Connecticut Dynamic s , C o fferdams, Platform within Caisson, Pump s , 8000 GPM Lift Pump ,
Electric Boat 1 9 . 83m Diamet e r , Super- s t ructure Rectangular 640 GPM
Division Filled with Sand Soil Support ed Box Type ,
and Gravel Steel
13 G eneral 1958 B 37 .4 38.32 264 . 2 4 . 87 2 .8 9 Sheetpile C ells Reinforced Concrete , Fine Hinged Gat e , 2-Electric Driven, 13 2-Electric
Dynamic s with Sand and l .22m, Sand , Steel 12 , 000 GPH, Driven ,
Quincy Division Gravel F i l l , and Fully Relieved , Trace V e rtical 3 ,800 and
DD#6 Steel Bulkh eads Soil Supported of Clay 2 , 000 GPH
14 Quincy G ene ra
I ""·-"-' "Q
l 1958 ll 44 . 8 1 44 . 87 289 . 8 4 . 87 2 .8 9 Steel Eulkheads Reinforced Concre t e , :Fine
l�!:;
ed Gat e , 2-Electric Driven, 8 2-Elect ric
Mass .
, -, l . 22m, Sand , 12 , 000 GPM, Driven,
! Quincy Division Fully Relieved , Trace Vertical 5 , 800 and
I DD#7 S o i l Suppo rted of Clay 2 , 000 GPM
15 General 1958 B 38 .2 38.22 264 . 9 4 . 87 2 .8 9 Sheetpile C ells Reinfo rced Concrete , Fine · Hinged Gat e , 2-Electric Driven, 13 2-Blectric
Dynamics with Sand and l . 22m , Sand , St eel 12 , 000 GPM, Driven,
Quincy Division Gravel F i l l , and :Fully Relieve d , Trace Vertical 3 , 80 0 and
DD#S St e e l Bulkhead Soil Supported of C lay 2 , 000 GPM
C e l ls Reinforced Concret e , l �i
lfu�;,
16 Quincy 1975 B 44 , 7 44 . 7 9 266 . 6 4 . 87 2 . 89 Fine nged Gat e , 2-Electric Driven, 10 . 5 2-Elect ric
Mass . with and Fully Relieved , Send 5 0 , 000 GPM, Driven,
Division Grave l Fill So i l Suppo rt ed Vertical 2 , 000 GPM
l
Thi s informat i o n is taken from existing documentation which i s approved for Public Release and is in the Pub lic Domain.
WORLD DRY DOCK BUILT SINCE 1950
Count ry : U .S . A .
Sheet 3 of 3
-- -
REF YEAR USE EJITRA!ICE DOCK EFFECT- DEPTH TIDAL C Ol!STRUCTI Oll C O!ISTRUCTI OI! SOIL T!PE 01'
no.
Tll'E OF DE- RE!IARKS
LOCATI OJI O\niER OR YARD Ill OF ill llTH ilARREL IVE OVER RAJlGE OF WALLS OF FLOOR TYPE GATE MAIN PUHPS WATERillG ( SEC OJ/DARY )
NA.ME SERVICE DOCK Wl lY.l'H LENGTH SILL DESIGN PHILOSOPHY '.i'HIE PUJ.!PS )
(m ) (m) (m ) (m) (m) (HRS)
19 San N ational Steel 1976 ll 5 1 .2 5 5 4.8 8 304.87 1.71 Steel Reinforced Concret e , Float ing 1-El ect ric D riven , 21 2-1000 GPM
l'o 1 H '<'!'n' -
6 .40 Soft
Vert i c al
Ship Building Cells, 0 . 609m, to Gate, Not a 1,800 GPM,
& Dry Dock C o . with Sand and Fully Relieved, F i rm C a isson Vertical Turbine
DD#l
G rave l S o i l Supported Clay
20 Newport News Newport Neva Rebuilt il/R 35 . 97 38 .2 6 2 62 . 67 9.56 0 . 798 Reinforced Reinforced Concrete, Marl F l oat i ng 2-Electric Driven, 1.5 I-Electric
Virginia Ship Buildi il8 1959
Concret e , 0 . 635m, C a i aeon 115 , 000 GPM, 60", Driven,
II: Dry Dock C o .
Slant e d , Fully Relieved , ::�� •a"!>" 600 HP 2 0 " , 600 GPJ! ,
DD#2
Vari ea from O .83t Soi l Supported Box I-Electric
to l . 7 0m
21 Newport News N ewport Jlews Rebuilt ll/R 1 9 . 93 2 l .34 156 .4 1 0 . 06 0 . 7 98 S t e e l Sheetpile Reinforced Concret e , Marl Float ing 1-Electric Driven, 3.0 2-3" SubDe rsible
Vi rgini a Ship Building 1980 aod Reinforced 0 . 915m, Caisson, 60" and
& Dry Dock C o .
Concrete Fully Relieved , Rectangular 1-Electric Driven.
DD#3
Soil Supported :Box Type , 20·
St e e l
22 N ewport News Nevport News 1981 ll/R 21.7 2 2 .86 160 . l 1 0 . 06 0 . 7 98 1 . 67m Diamet e r , Reinforced Concre t e , Ma rl Float ing 2-Electric Driven, 3 .78 2-Elect ric
Vi rginia Ship iluild ing
Prestreaaed o . 915m, Caisson 25 , OOO GPM, 36" Driven,
& Dry Dock C o .
C o nc ret e , Fully R e l i eved , Rectangular Mixed Flov, 200 HP 2 , 000
DD#4 Cylind ri c a l P i l e s S o i l Supported ilox Type , 16" f
Steel 2 5 HP
lilij ""'"
45 . 5 2 27 6. 5 7 . 87 0 . 314 S t e e l Sheetpile Reinforced Concret e , 4-Electric Driven, 4 2-Electric
Florida Shi pyard Inc .
C e l l s and Fully Reli eved , Steel 30,000 GPM
Reinforced Soil Supported 1 , 200
C oncrete
-
e
'" ..
This information is taken from existing documentat i o n which is spprovea for Public Release and i s in the Public Domain .
APPENDIX " B"
by
Graving drydock structural analysis by the finite The gra\'ing drydocks are constructed on the shoreline.
element method is described . Structural and geotechnical
They are, generally, e mbedded i n the ground to a depth of
parameters, which are important in setting up structural
models are discussed. Loads include static load, the 50 to 70 ft, the width ranging from 100 f t to 1 60 ft and
earthquake induced dynamic load, and the ship weight .
the length from 800 to 1 200 ft. Since each case is different
The analytical method is useful for evaluation of drydock
stability and in certifying the safety of drydooks. in shape, size, and type of backfill soil and drydock struc
Because of the complexity of the drydock structure, the (3) Partially Relie\·ed - A partially relie\'ed drydock pro\·ides
analysis should begin setting up structural models which relief for the floor only. Its use reduces the amount of
can accurately include structural and geotechnical para floor concrete and minimizes difficulty i n the cofferdam
meters for finite element numerical analysis. The accuracy to be used temporarily during construction. It features
of the results can then be checked through a comparison the following : (a) cutoff wall to surround the floor
of the d i fferent models used in the analysis. This paper area only; (b) filter course under the floor; and (c)
describes the analytical procedures for drydock stability holes in the floor for the water seepage flow into the
analysis, and includes examples of the results. The results drydock chamber.
docks.
MODES CAUSING PROBABLE DRYDOCK FAILURE
are two types of drydock failure mopes which may be will experience active earth pressure as well as earth
caused by seismic loads ( 4) : quake induced pseudo-static pressure. These two pressures
A. FLOAT AND TILT (b) The opposi t e side wall will deYelop semi-passh·e earth
or may not act at the floor slab even when the dock is
B. OVERSTRESS AND/OR OVERTURN OF DRYDOCK WALL
empty. · Figure 3 shows a ful i hydrostatic type with the
uplift force.
Should an earthquake occur when the dock is e mpty,
joint between the drydock wall and the floor slab. Obviously
assumption.
rtilUy
h!!!......ll '!Unn<l
by
1 . La:teJtal Eiuth P.t�e.. To establish lateral earth
pressures acting against the walls, the follbwing assumptions
are made :
Yi-
I
l\t 1Wt.f.
the earthquake versus drydock wall friction factor is as
follows :
�
..,.,-.,7.,T .. -,
,,.
. , ._...._..J... E .,,-
1 :..
. ...1 I "L
,__'J;
.1-L__L__J__ h ,.,.. , ,.ur
''.J---',___-;:
/- 37 a (g)
h
These
would provide a restraint to the lateral r.•7.6 1t1p1 i -su 1t1p1ftt21tt r,•t . 1
s.02 luf
ltlp•
)
,
loads. i •17.50 lr.lp•fft
,
Kt•14S kip• f f •
Figure 5 . An Example of Finite Element Model
toad Case
LOADING TO BE USED IN STRUCTURAL ANALYSIS
The concrete tie beams at the top corners of the wall are
A. SHIP LOADING CONDITIONS
modelled by horizontal springs with a computed stiffness of
ship on center or off center; aft keel line or aft quarter flags all stresses which exceed prescribed values. A second
loading; midship loading; or with a higher earthquake load. post-processor (PLTSTRS) is used to interactively generate
A. GENERAL DESCRIPTION
B. FORMULATION OF FINITE ELEMENT MESH
The soil foundation is modelled as a series of vertical, for the generation of a model requiring concentration of
linear springs using ELAS2 elements (scaler spring element) . elements in some areas while requiring less concentration
in other
structure
areas.
into
The use of
quadrilateral
DCKMSH
sub-regions
involves
prompted
dividing the
by either
1
geometrical or element concentration considerations. One of
(b) Maximum Disp lac emen t : 0 . 221 inc hes
the important features of DCK MSH is the numbering
pattern for nodal points and elements. These numbering F i gure 7 . Drydock Displacement Under Load ing
_
schemes facilitate plotting the output stresses and displace (a) Wi th Ship Load , and Kh•O . JOg
(b) Wi thout Ship Loa d , Kb•0 , 1 5 g
ments by computer.
the analysis.
or achieve the conditions of the active state of the back the displacement and stresses for the different models. The
fill. In the analysis, we apply the resultant of dynamic results are reviewed to determine whether the tensile,
lateral earth pressure at the two-thirds point of the wall compressive, and shear stresses are within or beyond the
ment of the wall ranges from 0.3 to 0.7 inches, and the 1. Geotechnical mechanics principles can be applied to
floor slab ranges from 0.09 to 0.36 inches. the structural analysis of a drydock. However, over-simpli
Some nodal points, mainly at the center of the floor cepts, such as a simplified flexural equation of f=My I /
slab, were chosen to summarize the results and compare should not be adopted for the overall analysis.