Professional Documents
Culture Documents
10.work Permit Procedure-RH2
10.work Permit Procedure-RH2
10.work Permit Procedure-RH2
/Z/z,'dʹt/^&Z
ŽŶƚƌĂĐƚEŽ͘DD-2021-138
ŽŶƚƌĂĐƚŽƌ ŽŶƐƵůƚĂŶƚ WD ůŝĞŶƚ
tKZ<WZD/dWZKhZ
Signature
,^DĂŶĂŐĞƌ dĞĐŚ͘DĂŶĂŐĞƌ WƌŽũĞĐƚƐDĂŶĂŐĞƌ
/ƐƐƵĞĚ&Žƌ͗
܈ƉƉƌŽǀĂů ܆/ŶĨŽƌŵĂƚŝŽŶ ܆ƐZĞƋƵĞƐƚĞĚ ܆ZĞǀŝĞǁΘŽŵŵĞŶƚ
KE^h>dEdZ^WKE^
ŽŵŵĞŶƚƐ͗
After a thorough review and evaluation for the proposed Permit to Work (PTW) procedure has been
approved as B Code
- PTW issuers and receivers should get appropriate training from an authorized third party or
competent person.
- Receivers shall keep permit copies inside the permit box at the job location, always, so that it is
available for inspection or cancellation if necessary.
^ƵďŵŝƚƚĂů͗
Ͳ܆ƉƉƌŽǀĞĚ ܆B- ƉƉƌŽǀĞĚĂƐEŽƚĞĚ
܆ ܆C- ZĞǀŝƐĞĚΘZĞƐƵďŵŝƚ ܆D- ZĞũĞĐƚĞĚ
ZĞǀŝĞǁĞĚďLJ ^ŝŐŶĂƚƵƌĞ͗
^ŝŐŶĂƚƵƌĞ͗ WƌŽũĞĐƚDĂŶĂŐĞƌ ^ŝŐŶĂƚƵƌĞ͗ ĂƚĞ͗
Elshafie Ali Riyadh Hasan 13/05/2024
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
1|Page
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Table of Contents
2|Page
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
2. Purpose
The purpose of the Permit to work OH&S Requirement is to outline the formal
administrative process to ensure the control of high-risk activities by implementing a
systematic process used to authorize controlled work in nonstandard, potentially hazardous
conditions. The process includes risk assessment, the establishment of safety protocol
specified in the Permit to work, communication, and oversight to minimize the risk to carry
out the work under strict controls.
This standard applies to the work being done by all personnel on the construction site.
The Permit to Work Policy is split into several components dependent on the type of work
to be performed, Cold Work, Hot Work, Working at Heights, Excavation work and/or
working in Confined Spaces, Lifting Permit, Night Work Permit, and the safety
requirements of each.
3. Intent
x The Salco Internal Work Permit Procedure establishes minimum guidelines and responsibilities for the
Issuing/receiving of work permits, and for certifying those responsible for implementing the system.
When issued, permits serve as an official recordof conditions and requirements agreed upon by the issuer
and receiver. They list minimumsafety precautions to be taken and hazards which must be controlled.
Salco undertakes to comply with to and incorporate all permit-to-work procedural standards and
guidelines as specified in the DD-SWD-SW-SWD-000-000-DGD-MNR-HS-000021.
4. References and Standard.
Standards
3|Page
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
5. Definitions
Restricted areas: - Those areas or activities which have been designated Salco as requiring
the work permit procedure.
Authorized Person (Work permit issuers): - Employees designated by the issuer, who
must be experienced, competent and familiar with the requirements of work permit system
and be able to perform the duties associated with issuing work permits. Designated
representatives can only sign work permits.
6. PTW Training.
Safety department will assign one designated Trainer for the course. In case
non-availability o f Trainer, safety manager/ safety supervisor or officer will conduct.
the trainer.
x All personnel involved i n the use of the Permit to Work system or Permit procedures
shall be both trained and assessed as competent to the appropriate level.
x Refresh training shall be conducted every one year of period.
x Record kept at Safety office of Training.
Work permit forms must be issued, as appropriate for specific work on a specific site. These
work permit forms are for all types of work in restricted areas. Work must be identified as
one or a combination of the following and the proper permits issued.
8. Type of Permits.
Cold Work Permit - Work that does not create enough heat or sparks to ignite flammable
gas-air mixtures or flammable materials and such work is not done in confined space area.
In classified areas, cold work will primarily be work done with hand-held, hand operated
tools, which do not normally produce sparks.
Hot work: - Any work that develops sparks, flames, or heat sufficient to cause ignition.
This work permit will apply to the use of spark or flame producing tools and equipment,
including the use of internal combustion engines in restricted areas.
Working at Heights: - Any work that has a fall exposure of 1.8 meters above or greater
is considered as working at heights.
4|Page
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Confined space: - C.S Entry is the entry of personnel into any space or structure (i.e.,
tank, vessel, vault, excavations when 1.2 m (4ft) or deeper, etc.) not normally intended for
human occupancy, where entry, movement within, or exit is restricted.
Lifting Work: - Includes any equipment used at work for lifting or lowering loads including
attachments used for anchoring, fixing, or supporting it. The regulations coverthe wide range of
equipment including cranes, forklift trucks, lifts, hoist, mobile elevating work platforms and
vehicle inspection platform hoist the definition also includes lifting accessories such as chains,
slings, eyebolts etc.
Night Work Permit: -Work activities during the hours of darkness are greatly
discouraged due to the associated hazards and will only be allowed by fulfilling
requirements under the valid night work permit.
9. Permit-to-Work Procedure
Permits-to-work provide a formal safety control system aimed at prevention of accidents, damage to
property and damage to products, when for see ably hazardous works are undertaken. International
and national standards and client safety standards placed further duties on employers to “provide and
maintain plant and systems of work that are, so far as reasonably practicable, safe and without risks
to health”.
Permits to work do not, in themselves, make a job free from risk: they rely upon effective control
and coordination in order that hazards are identified, and risks are suitably and sufficiently assessed.
EŽƚĞͲdŚĞǁŽƌŬƉĂƌƚLJͬƉĞƌŵŝƚŚŽůĚĞƌŵƵƐƚŚĂǀĞŝƚƐŽƌŝŐŝŶĂůǁŽƌŬƉĞƌŵŝƚĚŽĐƵŵĞŶƚĂŶĚĂĐĂƌďŽŶĐŽƉLJǁŝůů
ďĞǁŝƚŚƚŚĞƌĞĐĞŝǀĞƌ͘
x Shall ensure that all foreseeable hazards associated with the proposed job have been
identified and appropriately assessed.
x Shall ensure that all steps necessary to ensure the safety of the site or installation have been
identified.
x Shall ensure the work site has been examined, and all precautions specified to be taken
before work commences (including isolations) have in fact been taken and shall remain
effective while the permit remains in force.
x Shall verify that the permit holder, including further staff tasked with undertaking works
under the PTW, have appropriate competence to undertake the role and fully understand the
risks.
x Shall ensure that the permit holder is aware of the precautions taken, any additional ones
which are to be taken, particular equipment to be used or worn, and any other procedures
which are to be followed.
x Shall ensure that any work activities that may work activities that may conflict with one
another are clearly identified and conflictions are avoided, or precautions included on the
permit (e.g. Use of welding shields)
x Shall ensure that all relevant people are aware of the permit’s duration, and action to be
taken if the work is suspended; (viii) Shall authorizing, by signature, the work to proceed
following confirmation that all control measures are implemented and have been signed
off.
x Shall ensure that copies of all issued permits are displayed at an appropriate location and in
a consistent arrangement so that site personnel can readily see and check which equipment
is under maintenance and not available for operation.
x Shall undertake ongoing inspections of the PTW to ensure risk control measures are being
maintained.
x Shall ensure that the work site is examined at any time when work is suspended and before
it is restarted, and finally when the work is completed to ensure that it is in a safe condition.
x Shall ensure that the shift handover procedure is complied with shall ensure that the
worksite is examined on completion of the works and the PTW is correctly closed, and the
relevant persons informed.
x Shall ensure appropriate records of all permits and the master controls sheet are maintained.
x Shall ensure that they and the people working with them understand the operation of (and the
consequences of non-compliance with) the PTW systems applicable to the areas in which they
are responsible for work.
x Shall ensure any necessary information, instruction or training is given to users to ensure that
they understand the PTW systems, and the specific precautions required for their work.
x Shall ensure that the AP (permit issuer) and permit users fully understand their responsibilities
under the PTW system.
x Shall ensure that the conditions and precautions specified in the permits are fully understood,
implemented, and effectively monitored.
x Shall immediately stop / suspend work if conditions require or if the PTW requires change.
x Shall communicate effectively with all parties during the operation of the Permit.
x Shall ensure that all parties are aware of the completion of the works and the permit is correctly
closed with the Authorized person (AP)
x Shall understand the scope of work and the control measures implemented.
x Shall participate in the development or review of the risk assessment.
x Shall ensure that all control measures defined in the PTW are strictly followed.
x Shall not interfere with the work of their colleagues and shall adhere to the roles and
responsibilities assigned under the PTW.
x Shall cease work and inform the Permit Holder when there is a breach of the PTW conditions;
and
x Shall leave a clean and safe work site.
Hot work is defined as works that involves temperatures that could give rise to risks of fire and
ignition of flammable substances and combustible materials and includes work which involves the
use of naked flames or generation of sparks, smoke or fumes.
Pre-Start Inspection:
8|Page
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Before signing the permit-to-work, the Competent Person shall inspect the working area for
the following control measures (where applicable):
x Cutting and welding equipment is in good repair.
x All gas hoses are securely clipped.
x Welding / Cutting equipment is fitted with regulators and flashback arrestors.
x The area is adequately ventilated.
x Gas cylinders are secured in a vertical position on a trolley.
Fire watch:
The Competent Person shall also ensure that the following general controls are in place:
x Suitable and sufficient fire extinguishers are readily available.
x Operatives are trained in the use of fire extinguishers.
x Adjacent smoke heads are covered to prevent false alarms.
x Security & Reception are advised if it is deemed necessary to take the local alarm system
off automatic 911 call out.
x All fire doors are closed.
x Arrangements are in place to make sure that the hot works area is not left unattended, for
example during tea breaks, lunch etc.
x Operatives are aware of actions in case of emergency.
x No other people are working in the area that might be endangered by the hot works.
x Arrangements are in place to carry out a check of the area at least 1 hour after the hot works
have ceased.
x Security is advised that the alarm should be put back on automatic 911 call out at cessation
of the work.
The following works carried out on electrical equipment located on the Company’s premises shall
be subject to a permit-to-work:
x Switching off any isolate, switch fuse, distribution board, or mains circuit board that may
affect the company’s information technology systems or the safety of anyone on the
company’s premises.
x Test on live electrical apparatus.
x Test on electrical distribution systems that need the installed safety systems/barriers
defeated or removed.
x Work on electrical distribution systems that expose personnel to shock hazards.
x Work on remote and automatically controlled low voltage switchgear.
x Isolation of electrical equipment to make it safe unless carried out by a competent person
holding a valid Authorization Certificate.
x Test on any earthling system whilst the supply is still live.
Electrical equipment is defined as anything used, intended to be used or installed for use, to
generate, provide, transmit, transform, rectify, convert, conduct, distribute, control, store, measure
or use electrical energy.
Live: means that the equipment in question is at a voltage, by being connected to a source of
electricity as, for example, in normal use.
Charged: means that the item has acquired a charge either because it is live or because it has
become charged by other means such as by static or induction charging or has retained or regained
a charge due to capacitance effects even though it may be disconnected from the rest of the system.
Live work is defined as work on or near conductors that are accessible, and which are 'live' or
charged’. Dead means not electrically 'live' or 'charged'.
Isolated is used to indicate equipment, or part of an electrical system, which is disconnected and
separated by a safe distance (the isolating gap) from all sources of electrical energy in such a way
that the disconnection is secure, and cannot be re-energized accidentally or inadvertently.
10 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Low voltage is regarded as a voltage exceeding 50v AC or 120v DC between conductors or earth,
but not exceeding 1000v AC or 1500v DC between conductors or 600v AC or 900v DC between
any conductor and earth.
In addition to the above contents, the following should be included, where applicable:
x The necessary steps to be taken to protect against inadvertent contact with other live parts
nearby. Wherever practicable, this should be achieved by the erection of physical barriers
and/or the use of temporary insulation.
x The arrangements for identifying electrical equipment before disconnection or isolation.
Wherever possible this process should be aided by the use of appropriate drawings, diagrams
and other written information. Labeling on circuits and equipment may be used to assist in the
identification process, it must however never be assumed that labeling is correct;
x The arrangements for ensuring that once the circuit or equipment to be worked on or near has
been identified, that it shall be disconnected from every source of electrical energy;
x The arrangements for ensuring that electrical equipment, which has been made dead, cannot
become electrically charged during the work. Wherever practicable this should be carried out
by locking off all isolators. Where such facilities are not available, the removal of fuses or links
is permissible.
x The arrangements for testing that the isolated circuit or equipment including all parts to be
worked on, or near, are dead, even if the isolation has been achieved automatically through an
interlocking system. If it is a three-phase system or equipment with more than one supply,
prove that all supply conductors are dead. The device used for proving dead shall itself be
proved immediately before and after testing;
11 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
x The arrangements to ensure that, even if the above precautions fail, all conductors are earthed
using properly designed earthling devices or earthling leads
x Where applicable, those additional earths are available at the point of work, if this is remote
from the point of isolation. But these should be applied only after proving dead at the point of
work. (These procedures are essential for high voltage apparatus and stored energy equipment.
The earthling conductors and their connections should be suitable for the energy that may flow
in the event of a failure of the above precautions.
Note: Earthing low voltage equipment is particularly desirable if there is a risk of re-
energization. In other low voltage equipment, however, it may be physically impractical to
apply earths, or the risk of short circuit from introducing an earth near adjacent live parts may
outweigh the benefit of earthling the apparatus being worked on.
Work on or near live conductors shall only be permitted in exceptional circumstances and only
when directly authorized by the Manager or the Engineer having taken prior advice from an
authorized or competent person.
Live working shall not be permitted unless each of the following is true:
o It is unreasonable for the work to be carried out dead;
o Suitable precautions can be taken to prevent injury; and
o It is reasonable in all circumstances to work live:
The decision to work live must not be taken lightly. All economic and operational factors must be
evaluated against the risks involved before planning.
12 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Work at Height method statements should normally include the following so far as is relevant in the
circumstances:
x The receiver (Supervisor, General Foreman) requests the work permit forms from the
Safety Department.
x The issuer will issue the work permit after he (or his designated representative) has
conducted a joint site inspection with the receiver as appropriate, performed the
necessary gas tests, (If required) listed applicable precautions and restrictions, and
reviewed aspects of the job with the receiver.
x Before issuing the work permit all necessary actions to approve the proposed work
and/or possible configuration changes must be completed.
x The issuer and receiver are jointly responsible for the safety of personnel and
equipment in the area. The issuer is responsible for specifying precautions so that the
work can be done without incident. The receiver is responsible for performing the
work in accordance with the conditions and requirements agreed upon with the issuer
and written on the work permit.
x For some jobs, the issuer (or his designated representative) may determine that a joint
site inspection is not required for jobs with extremely low risk. Examples include: cold
work in a safe area, carpentry, lubricating, cleaning, brush painting, non-flash
photography, instrument checking and a vehicle entering a non-hazardous area.
x When there is any doubt about whether a hazard exists, a joint site inspection must be
conducted. When the issuer determines a joint site inspection is not required, he must
specify the reasons in the appropriate space on the permit. Renewal of the workpermit
is permissible for two consecutive operating shifts. The renewal requires the
signatures of both the issuer and the receiver coming on shift.
x Signing the work permit indicates complete agreement with the conditions stated on
the form and transfers the responsibility to those coming on shift.
x The work permit is for specific work on a specific site. It cannot be transferred except
to the following shift. Transferring from one craft to a different craft is not permitted.
x A work permit may be issued for periods over 12 hours but not more than 7 days. This
applies to extended construction or maintenance work where the job requirements
remain essentially unchanged. The permit must be approved by the project manager
or above of the issuing department and the following conditions must be satisfied:
x It must be highly unlikely that conditions will develop which would create an
additional hazard to personnel or operating facilities.
13 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
x Precautions must be taken prior to starting the job, to ensure safe conditions
throughout the job.
x Both the project manager and the construction manager must be in agreement as to
job conditions and risks involved and both must sign the work permit.
x The receiver of a work permit must keep in his possession or within view of the job
site for the duration of the job so that it may be available for inspection and
cancellation if necessary. If he must leave the job site for any reason, for example to
obtain additional tools or equipment, etc., he must, if the issuer concurs, relinquish
supervisory control to a senior crew member who is fluent in written and spoken
English, until he returns. The senior crew member must know the requirements of the
job and understand the precautions/conditions stated on the work permit.
The receiver:
x Has the responsibility to stop work and advise the issuer of his action any time he
determines that the conditions of the job do not meet the conditions on the work
permit. He and the issuer shall take action to correct deficiencies and resume the job.
x All unnecessary personnel whose presence adversely affects the safety of the job
must be kept away from the job site or work shall be stopped.
x Work permit courses will be conducted by a competent person. The purpose of the
courses is to acquaint potential issuers & receivers with the company internal work
permit system,
Work permit certificates will be issued internally to employees confirming them as
issuers & receivers as appropriate.
x Any person issuing or receiving a work permit must have in his possession a valid
14 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
issuer's or receiver's work permit certificate, as appropriate, at the time of issuing
or receiving permits.
x All Supervisor/Foreman must maintain records of their work permit issuer &
receiver certified personnel. Certificates expire two years after the date of issue.
Accordingly, the issuers and receivers must be recertified every two years.
23. Appendices
a) Appendix 1: Excavation Work Permit
b) Appendix 2: Confined Work Permit
c) Appendix 3: Working at Height Work Permit
d) Appendix 4: Night Work Permit/Holiday Work Permit
e) Appendix 5: Lifting Work Permit
f) Appendix 6: Electrical Work Permit
g) Appendix 7: General Work Permit
h) Appendix 8: Hot Work Permit s
15 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Section II:(Request for the permit) Permit Receiver to mark all boxes either with (only for relevant
ones) or mark as X
Required permit for buried services has been Workers are given training – Risk Identification and
obtained from the concerned authority. Precaution
Are all the buried services located (with the Required caution boards / warning notices are
help of drawings and by trial pit, detectors etc) provided
Is Shoring / sloping required? If so, has the Barricades / Handrails installed around the
material been arranged? proposed excavation site
The access details to the pit finalized and Are any traffic diversion signs / flashers required If
materials arranged accordingly yes are these items provided?
Following additional precautions shall be taken after taking up the excavation work: (Tick relevant boxes
alone)
Verification of the condition of shoring at regular intervals
Usage of PPE such as _________________________________________
Verification of the condition of handrails, access, flashers etc
Storage of surplus earth at least _2_ m away from the edges of excavation
Block stops at the edges of excavation to limit the access of vehicles
Emergency escape (evacuation procedures)
Construction equipment exhaust away from excavation
I request for an Excavation Permit for the above-mentioned work at the location specified above. I have
personally inspected the work place to ensure that the applicable precautions mentioned above have been
complied with.
Name: _ _ _ _ _ _ _ _ _ _ _ _ Signature: _ _ _ _ _ _ _ _ _ _ _ _
16 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Appendix 2: Confined space work Permit
Project: PARKS AND TRAILS PROJECT Date:
Location: Permit No:
Name of the sub-contractor (if applicable):
Section I: (To be filled by authorized Receiver)
Description of the work /Reason for Entry: (enclose location sketch if required):
Section II:(Request for the permit) Permit Receiver to mark all boxes either with (only for relevant ones) or mark as X
Checks Yes No N/a Yes No N/a
Suitable & Sufficient access provided to the confined All the employees trained in working in confined
space? space?
Required warnings signs (Danger – Restricted Entry, Gas test been done to check the absence of
Permit Required), Emergency Contacts no displayed flammable gases
Have low voltage & flameproof lighting been
If any other gases are anticipated, has it been checked?
arranged?
Confined space checked for oxygen deficiency All concerned persons been informed
I request for a Confined Space Entry Permit for the above-mentioned work at the location specified above. I have
personally inspected the work place to ensure that the applicable precautions mentioned above have been complied with.
Name:
17 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Appendix 3: Work at height permit
18 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
19 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Appendix 4: Night Work permit/Holiday Work permit
20 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
21 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
22 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
23 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
6. COLD WORK PERMIT / GENERAL WORK PERMIT
Note: Advisory checklist tobefilledupandcompletedwithinformation&attachedonpermitpriorforapproval & issuance if work to be carried out
isahighriskactivitysuchasEnergizedElectrical,Erection/Modification&DismantlingofScaffolding,WorkingatHeights,IsolationofLifeSafety
COLD WORK
PERMIT
PERMITDURATION Details of work sponsor
Start date Finish date Days/Hours Duration Name: Department:
RAMS available and attached to YES / NO Is any isolation and/or Lockout System YES / NO
permit? required forth work?
(Please encircle)
Approved drawing /sketch provide& YES / Is gas testing required? YES / NO
Attached to permit?
NO If yes, please complete gas
test section below for results
and monitoring
Personal & Protective If yes, please tick the items needed for this work:
Equipment required?
Breathing Apparatus Air Mover Barricades Warning Signs Fire Extinguisher
YES / NO
Safety Harness with Line Hard Hat Safety Shoe Hand Protection Eye Protection
Others, (explain further insection2 below)
SECTION2: Additional Precautions (Extra safety precautions, comments from the receiver)
SECTION5:Workcompletion/closure(aftersigningpleasereturnworkpermittoWorkPermitControlOfficeforrecordkeeping)
Is joint site inspection conducted? YES NO if NO, why not?
Is the site and equipment left in a clean and safe condition? YES NO (if NO, permit shall not be closed.)
Name WP cert.no. Badge No. Signature Date
Work Permit Issuer
Work Permit Receiver
ProtectionSystemsi.e.firefightingequipment,fireprotectionanddetect
24 | P a g e
Project Name: PARKS AND TRAILS PROJECT
Document Title: WORK PERMIT PROCEDURE
Location: DIRIYAH GATE – WADI SAFAR
Appendix 8: HOT WORK Permit
25 | P a g e