Professional Documents
Culture Documents
Report 05 Centauro
Report 05 Centauro
Report 05 Centauro
Activity Activity
DESCRIPTION percentage percentage ID*
ITO EPC
Centauro
Perimeter fence Materials on site
Perimeter Fence Topographic Stakeout
Perimeter Fence Installation
Topographic Stakeout of Inland Accesses and Roads
Construction of Accesses and Internal Roads
Tracker Estructure on site
Piles on site
Modules on site
CDT / Inverter on site
Combiner Box on site
Control room on site
Cellars on site
MV wire on site
Aerial MV wire on site
AC wire on site
DC Strings wire on site
DC Combiner wire on site
Generator on site
Weather station on site
Control Gabinet on site
Recloser on site
CCTV equipment on site
All major components on site
Work Offices Installed
Control of trenches
Filling and covering trenches
Staking out foundations
construction foundations
Piles Topographic Stakeout
Installation of Piles
Assembly Installation of Trackers and structures
Assembly Installation of Modules
Assembly Installation of inverters
Assembly Installation of Transformation Center
Assembly Installation Main Equipment connection point
Assembly Installation Combiner box
Assembly Installation generator
Installation poles and chambers
Installation DC/AC Duct Bank
Integration CCTV / SCADA sistem
Installation of equipment at connection point
Configuration of equipment at connection point
Laying of String wire
Laying of MV/AC Wire
Laying of DC String wire
Laying of DC Combiner box wire
Laying of LV/AC wire
Terminations And Connections MV/AC wire
Terminations And Connections LV/AC wire
Equipment Connection
Serial of Modules
Cold Measurements of Connection Point Equipment
DC Strings wire test
DC Combiner wire test
MV/AC wire test
LV/AC wire test
CDT / Inverter test
Weather station test
Control Gabinet test
Combiner Box test
Trackers tests
Grounding system test
Test SCADA
AC System Acceptance Tests
Tests and Measurements with load
commissioning
Punch List General Electric
General Construction Punch List
Completion of Minor Works
Asbuilt Plans
Quality Documentation
% AVERAGE PROGRESS ITO / EPC #DIV/0! #DIV/0!
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
20d 1/11/2022 11-30-2022
20d 1/11/2022 11-30-2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
12d 1/11/2022 11/15/2022
12d 11/14/2022 11/30/2022
12d 11/14/2022 11/30/2022
12d 11/14/2022 11/30/2022
12d 11/14/2022 11/30/2022
0d 1/9/2022 1/10/2022
0d 1/10/2022 1/10/2022
0d 1/10/2022 1/10/2022
20d 1/11/2022 11-30-2022
20d 1/11/2022 11-30-2022
20d 1/11/2022 11-30-2022
20d 1/11/2022 11-30-2022
20d 1/11/2022 11/30/2022
20d 1/11/2022 11/30/2022
13d 11-14-2022 11/30/2022
13d 11-14-2022 11/30/2022
13d 11-14-2022 11/30/2022
13d 11-14-2022 11/30/2022
20d 1/11/2022 11/30/2022
20d 1/11/2022 11/30/2022
20d 1/11/2022 11/30/2022
20d 1/11/2022 11/30/2022
20d 1/11/2022 11/30/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
11d 1/12/2022 12/15/2022
10d 12/16/2022 12/30/2022
10d 12/16/2022 12/30/2022
10d 12/16/2022 12/30/2022
10d 12/16/2022 12/30/2022
10d 12/16/2022 12/30/2022
10d 12/16/2022 12/30/2022
DATE INSPECTION 29/12/22
OBSERVATIONS
OBSERVATIONS 05 SP CENTAURO
Location Description
Location Description
Photovoltaic park •In sector 6-7, there are different piles turned and unplu
Location Description
Modules In the trackers, 28.1 / 36.1 / 37.1 are without modules, due to da
Location Description
Location Description
Location Description
the supporting structure with zinc-plated bolting
Combiner boxs
In addition, the structure does not have galvanized trea
NS 05 SP CENTAURO DATE INSPECTION 29/12/22
escription Details
escription
escription
escription
escription
ture with zinc-plated bolting
oes not have galvanized treatment.