Co-Commissioning Procedure
Co-Commissioning Procedure
Index
1. INTRODUCTION............................................... .................................................. ..........5
2. OBJECTIVE............................................... .................................................. ...................5
3. SCOPE ............................................... .................................................. ....................5
3.1. Start-up objectives ........................................................... ....................................5
3.2. Overview of the start-up process ................................................ .........5
4. RESPONSIBILITIES................................................... ................................................7
4.1. Responsibilities Diagram ................................................ ................................7
4.2. From the address of the commissioning protocol ........................................... ......7
4.3. From the DC/AC System Inspection ........................................... ................................8
4.4. From the supervisors................................................. .................................................. ...8
4.5. From the person responsible for risk prevention ........................................... ...................8
4.6. From the professionals............................................... .................................................. ..9
5. TECHNICAL PERSONNEL ................................................ .................................................. .9
6. REFERENCE DOCUMENTS ........................................................... ................................9
7. SYSTEM DESCRIPTIONS AND EQUIPMENT IDENTIFICATION ............10
7.1. System Descriptions................................................ .......................................10
7.2. System equipment lists ........................................................... ...................................10
7.3. System Descriptions................................................ ........................................eleven
8. SECURITY ................................................. .................................................. ..............eleven
9. GENERAL RISK PREVENTION RULES ...................................................11
9.1. Legal aspects applicable to the start-up procedure ...........................11
9.2. General Safety Information ................................................ ...........................12
9.3. Specific photovoltaic safety information ........................................................... ...12
9.4. Safety considerations for personnel involved ...........................................13
9.5. Environmental considerations................................................ ...................................13
9.6. LOTO Policy ................................................ .................................................. .............13
9.7. Tools and instruments................................................. ...................................14
10. SUBSYSTEM LEVEL TESTING ........................................... ..........................fifteen
10.1. Start-up process flow chart ...................................................15
10.2. Civil works ................................................ ...................................................16
10.3. Quality inspections................................................. ................................17
10.4. Marking and labeling ................................................ ...................................17
10.5. DC subsystem ................................................ ................................................17
10.5.1. Open Circuit Voltage Test ........................................................... ..............17
10.5.2. DC cable (string).................................................. ................................................17
10.5.3. Investor................................................. .................................................. .......17
10.6. AC subsystem ................................................ ................................................18
10.6.1. Ancillary Services Panel (ASP) ........................................... ...................18
10.6.2. AC collector cable ................................................. ............................................18
10.6.3. Transformer ................................................. ................................................18
10.6.4. Arc flash requirements ................................................ ...........................19
10.6.5. Main switch (Recloser) ........................................................... .............19
10.6.6. Measurer................................................. .................................................. ........19
10.6.7. SCADA................................................. .................................................. ...........19
10.6.7.1. Energization and operational tests ................................................ ...............twenty
10.6.7.2. Monitoring................................................. .................................................. ....twenty
11. CHECKLISTS AND RESULTS OF PREFUNCTIONAL
TESTS ....................................................... ...............................................twent
y-one
11.1. Pre functional Checklist................................................. ..................................twenty-one
11.2. Pre functional Electrical Test ................................................ ...........................22
11.3. Commissioning of the inverter ........................................................... .......................24
12. COLD START-UP ........................................... ...................................24
12.1. Previous activities................................................ .......................................24
12.2. Connection and energization of the connection point ...................................................25
12.3. Powering up the Switchgear ................................................ .......................25
12.4. Energization and voltage verification of LV cabinets ..............25
12.5. Connection and energization of the DC system ........................................... .......25
12.6. DC voltage verification................................................ ............................25
13. ENERGY PLAN ........................................................... ............................................26
13.1. Prevention procedures ................................................ .....................26
13.2. Energization procedures................................................... ...................26
14. HOT START-UP................................................. ...........................28
14.1. Commissioning of the trackers ........................................................... ...................28
14.2. Start-up of Scada................................................. ...........................28
14.3. Commissioning of CCTV ........................................................... ...........................28
15. SUMMARY OF TESTS TO BE PERFORMED ........................................... .......................29
1. INTRODUCTION
This report describes in detail the sequence of activities required for the commissioning of the Photovoltaic
Plant, where the resources and technical personnel involved who will be in charge of verifying the operation of
the equipment and systems are indicated.
2.
OBJECTIVE
The objective of the following procedure is to previously define the sequence of energization and testing to
avoid any type of unwanted event that affects the physical integrity of the people involved, as well as to avoid
damage and deterioration to structures and/or installed equipment.
3. SCOPE
This procedure must be followed in its entirety by the personnel related to the corresponding commissioning
and testing work, whether these are the operators and any person who has a direct relationship with the
activity .
The start-up of Ametel power plants attempts to meet the following goals:
Verify that the installation of structures and equipment has been completed according to the
corresponding engineering
Verify correct operation of individual components
Verify system performance.
Figure 1 shows the flowchart of the start-up process. The arrows following the Equipment and Structural
Inspection highlight the different subsystems of a PV power plant.
Equipment Energization and acceptance tests MET station and SCADA
and system
structural DC Subsystem Inverter AC
inspection Subsystem
FIGURE 1 GENERAL SCRIPTION OF THE FRAMING PROCESS
The start-up process has four main activities: Equipment inspection according to previously executed
quality protocols, validation, Energization and Acceptance testing. Each activity has a separate verification
sheet or results included in an appendix, verifying that the activity was performed and the plant passed
successfully.
Equipment inspection
Before energizing the equipment, a quality inspection is aimed at identifying any possible problems that
need attention and tracking their resolution, your subcontractor's compliance with the associated protocols
should be reviewed and with those documents in hand, perform a new review. . This includes reviewing a
list of all equipment required according to the design drawings for the project, ensuring that mechanical
assembly and connection completion tasks have been completed, conducting a final inspection of each
piece of equipment, and verifying the installed capacity of the equipment. equipment described later in this
document.
Validation
The validation focuses on the following aspects:
The structure is inspected for alignment and proper function of the follower. A sample of structural
fasteners is checked to ensure they are tightened to specifications. If any deficient point is found, the
subcontractor is asked to separate and improve the information, where the structural fasteners, driven
pillars, screws, torque tubes, motors, etc. are reviewed.
The modules and connections are inspected to guarantee that they are installed correctly and ensure
their good physical condition, verifying that they do not have damage that would prevent the operation
of the start-up. Module connections should also be checked.
The weather station (MET), along with the entire SCADA network consisting of sensor boxes,
communication boxes, fiber optic devices and/or power controllers, is inspected according to their
respective protocols to verify that it is complete and functioning correctly, and all key parameters are
recorded to establish a baseline. See more detail in the installation and testing manuals provided by
the manufacturer.
The installed components of the DC subsystem are tested using the corresponding equipment
calibrated and certified according to standards.
Tests include open circuit voltage of strings, polarity tests, insulation resistance of DC cables, short
circuit current and IV curve. The investor undergoes a
thorough visual inspection. Your inputs, outputs and communications are tested according to the manual
provided by the manufacturer, before and after being included in the energized system.
The entire AC subsystem is inspected and functionally tested. This includes the AC gathering system,
transformers, grounding systems, protective relays and main circuit breaker. Additional equipment
may include distribution cabinets, income metering, and power control box.
Energization
Once all validation steps are completed a secure boot procedure is initiated. The start-up procedure
depends on the equipment implemented and the activation requirements of each electrical service. A
ground-specific energization procedure is prepared prior to energization. The sequence always starts with
the AC subsystem and works towards the DC side. The circuit
main Medium Voltage connection s
and closes with the help of the Distribution Company. The site's main switch or switchyard, which
energizes the collector circuit, is then closed. This step also energizes the transformers located in each
PCS. Finally, the inverters turn on, completing the procedure and starting solar generation.
Acceptance test
The acceptance of the plant will be provided with the results of the tests included in the contract.
4. RESPONSIBILITIES
4.1. Responsibilities Diagram
5. TECHNICAL PERSONNEL
TABLE 1 LIST OF TECHNICAL PERSONNEL
Name/Role Function Company
Mauricio Nieto Commissioning protocol address HydraLuvx
Franklin Reyes Commissioning protocol support Ametel
Aron Torres-Jaime Ruiz DC/AC Systems Inspection Ametel
Marcos Marchante - Jaime Ruiz MT equipment operator Ametel
Claudio Rodriguez Risk prevention manager Ametel
Gorka Rojas Quality manager Ametel
Mauricio Nieto Lotus Leader HydraLuvx
Aron Torres-Franklin Reyes Support in electrical supervision Ametel
Huawei Technician Inverter maneuvers Huawei
Mains Technician Transformation center maneuvers Mains
CGE Technician POI maneuvers CGE
6. REFERENCE DOCUMENTS
757-QA-GEN-DOC-AMET-02-00- Quality Plan
757-HS-GEN-DOC-AMET-03-00- Environmental Plan
757-HS-GEN-DOC-AMET-04-00- Health & Safety Plan
AMETEL - Internal Regulations of Order, Hygiene and Safety
IEC 62446 – Grid-connected photovoltaic systems. Minimum requirements for system documentation,
commissioning testing and inspection
Cold Commissioning Procedures
8. SECURITY
Commissioning follows strict safety guidelines and protocols in accordance with NFPA 70E electrical safety
standard and OSHA 1910.147 Lock-Out-Tag-Out (LOTO) Hazardous Energy Control .
SUPREME DECREES
SUPREME DECREE No. 40 Approves the regulations on the prevention of professional risks.
Regulations on basic sanitary and environmental conditions in workplaces.
SUPREME DECREE No. 594
Please refer to the test equipment requirements detailed in each individual test procedure. The
personal protection elements to use are detailed below:
Safety Helmet
Safety Glasses
Dielectric Safety Shoes
Class 2 work clothing includes reflective vest
Kid and dielectric gloves
Ametel's quality team uses quality control plans to ensure that field installations meet all Ametel and
other standards set out in the Quality Management Plan.
The quality team will make all quality checklists available to the start-up team for review.
10.5. DC subsystem
The components of the DC subsystem are tested as follows:
10.5.1. Open circuit voltage test
The open circuit voltage (Voc) of all strings is measured at the start + and – terminals of each
string. Open circuit voltage testing ensures that each input to the inverter is correctly sized and has
the expected output voltage. The polarity of each incoming connection is also tested at the same
time.
10.5.2. DC cable (string)
DC cables carry power from the solar array to the inverter. It is critical to inspect and test this cable
to ensure that the wires land on the correct terminals and that the integrity of the cable is intact.
Tests performed on all DC cables include:
Visual inspection
Low voltage cable insulation resistance test
Polarity test.
10.5.3. Investor
Commissioning of the inverter begins with a thorough visual inspection of the unit
(equipment assembly checklist). The key aspects of the inspection process are:
Correct installation and fixing, good appearance and physical integrity.
The firmness of the connections.
Polarity.
Ground connection verification.
10.6. AC subsystem
The components of the AC subsystem are tested as follows:
The ASP provides power to low voltage components in the PCS pad, communications equipment
in the sensor box, sensors in the goal station, and any other devices operating at less than 1000 V.
The ASP consists of a dead front electrical panel feeding several circuits protected by circuit
breakers. Tests performed at the ASP include.
Inspection of the general installation.
Ground connection verification.
Wiring inspection.
Inspection of all outgoing circuits and their proper identification.
10.6.2. AC collector cable
The design and supply requirements for arc flash prevention and protective signage must be met
as indicated in:
IEC 62271-200 Medium voltage internal operation test;
ISO 3864: safety colors and safety signs
Arc flash certificates from the manufacturers of the main plant equipment demonstrating the
suitability of the equipment for use under the project conditions must be delivered to the client.
10.6.6. Measurer
The pricing meter is used to compute the overall performance of the plant. Charging meters
provide information such as instantaneous voltage, current, real power, reactive power,
symmetrical components (positive, negative, zero sequence), as well as historical power
generation values. Typical tests performed on the pricing meter will be carried out by a third
company certified by the SEC according to the standards of the National Electric Coordinator.
These tests will be carried out on the day of energization and the corresponding certificates will be
delivered.
10.6.7. Scada
The meteorological sensors are individually inspected for correct installation prior to energization
and after it the calibration and output inspection is carried out. After power-up, it will be confirmed
that the communications system, including device addresses and data transfer speeds, is
functioning correctly.
The entire power plant must be fully operational before the SCADA system
can be powered, tested and optimized.
Once the entire power plant has been energized, the SCADA circuit is tested once again to
confirm that the measurement devices and data acquisition modules are reading and
communicating the appropriate values. The readings from the weather sensors are compared to
those from the energy meters and the inverter readings. When querying remote databases and
websites, communications links are also tested.
10.6.7.1. Energization and operational tests
Once all SCADA system validation steps are completed, a safe startup and testing procedure
will be initiated as per the requirement of the SCADA system provider. The focus of the first
part of the process is the safe and error-free activation of high-power AC equipment. The
switchyard is energized to deliver power to the solar plant. Transformers are brought online
and “soaked” (energized without load) to ensure proper operation. Once the entire AC
subsystem is online and confirmed to be operational, the inverters are individually energized
according to the procedures specified by the manufacturer.
10.6.7.2. Monitoring
Each Ametel project monitors with a supervisory control and data acquisition (SCADA)
solution. The SCADA system connects inverters, transformers, weather sensors and
protection relays to the internal operations center of the SCADA provider.
The main points monitored include:
❖ Investor
- DC input voltage
- Output voltage per phase, current, power, power factor and frequency.
- Current and aggregate energy production.
❖ Transformer
- Transformer over temperature alarm.
- Oil level
- Oil pressure
❖ Weather sensors
- Irradiance in the horizontal plane and plane to the trackers.
- Room temperature
- Wind speed and direction
- Module Temperature
❖ Protection relay
The protection relay continuously monitors the output power signal characteristics to
trip the main breaker immediately (within a few cycles) if a critical event occurs.
Important points monitored include:
- Switch status.
- Phase voltages, currents, power, power factor
- Accumulated energy production.
- Communication status
The above items have been inspected and/or tested according to Ametel's commissioning process.
Any discrepancies found have been corrected or noted in the Commissioning Log.
1.5. Low Voltage Cable Insulation Resistance (“IR”) Test (String, Combiner Box, and LVPB)
1.6. Continuity test
4.1. Insulation resistance Tests on each bus section, phase to phase, and phase to ground
4.2. Bolted electrical connections for high resistance; Use of low-resistance ohmmeter
4.4.2. Insulation-resistance Tests (each pole, phase to phase, phase to ground with switch
closed, and across each open pole (winding to winding and each winding to ground)
4.4.3. Verify open and close operation from control devices
4.4.4. Secondary wiring integrity Test. Verify correct potential at all devices.
4.4.5. Correct secondary voltage, energize primary winding with system voltage, measure
4.4.6. Correct function of control transfer relays with multiple control power sources
8.2. Contact- step voltage, GPR >2-5kV of the utility's predetermined factor
12.2. insulation-resistance Test, each bus section, phase to phase and phase to ground
13.1. insulation-resistance Test, each bus section, phase to phase and phase to ground
23
14. Verification of DC low Voltage drop
The above items have been inspected and/or tested according to Ametel's commissioning process.
Any discrepancies found have been corrected or noted in the Commissioning Log.
Responsible:
PASSED CHECK
PRE-ENERGIZATION PROCESS CHECK
TO. Preliminary acceptance report available for all AC equipment including medium voltage
transformers and all Switchgear components.
d. Complete the 1 kV - 35 kV energized work permits (EEWP) with the necessary information.
PASSED CHECK
PRE-ENERGIZATION PHYSICAL CONTROLS
1. CONFIRM that ALL grounds in the switchgear cabinet are up.
2. CLOSE Switch disconnector SWD1 by the distribution company (confirm presence of Cia
brigade. Distributor on the ground, with the necessary implements)
16. During the waiting period, enter the perimeter to verify the presence of the expected voltage on
the transformer. Appropriate PPE must be used at all times.
the activity according to regulations.
17. CLOSE general low voltage protection -Q0
18. CLOSE main thermo-magnetic circuit breakers of LV panel, following the order established
in the field
19. Check phase voltages. All phases should now be visible (expected voltage
800V LL)
20. Energize Inverters one at a time, following the order established on the ground.
20.1. Verify correct operation of the Inverters
20.2. Check AC Voltage Present
20.3. Check DC Voltage Present
20.4. Verify upstream phase sequence of LV thermomagnetic circuit breakers.
27
21. After the entire system has run for 10 minutes at 30% rated load, OPEN the E1-Cell A
disconnect switch corresponding to TxE1. (this process is repeated at 70% and finally at 100%
of the nominal power of the inverter in intervals of 10 minutes each)
22. When the entire procedure has been completed, the stoppage time is recorded and the
procedures of Form 9 of the PMGD standard are carried out under the responsibility of the
Distribution Company personnel.
28
Cold Commissioning
Insulation resistance test Solar cable
Low voltage cable (Inverters, AC Box)
Medium voltage cable
polarity test Solar cable
Low voltage cable (Inverters, AC Box)
Continuity test Solar cable
Low voltage cable (Inverters, AC Box)
VLF test Medium voltage cable
Step and contact test CT area
Resistance test Cross-linked CT grounding
AC Box
Investors
Trackers
CCTV poles
Hot Commissioning
Test run Trackers
Investors
Scada
CCTV
Meter