Professional Documents
Culture Documents
Extra Site Schedule
Extra Site Schedule
Extra Site Schedule
Team Mobilization to
8 Supposed to start from 15th January
Karimganj Poly
When will the Project Manager reach the site? This is very urgent considering
the number of site increasing and no any technical person able on site to
coordinate all jobs.
If still there is any confusion regarding the material then immediately plan a
meeting with our team and supply the electrical materials asap
The material has reached, and there is pressure from Client end. Please
update when the work will start.
Your 4 sites have been started and you have only one supervisor. What are
your plan?
REQUIRED TEAM SUMMRAY on D
No. of Category No. of No. of
Sl. No. Team Moveme Site
Manpower Skilled Helper nt
1 RoofSheet T1 8 3 5 7 4
2 LGSF T1 6 2 4 4 2
3 LGSF T2 6 2 4 2 1
4 Electrical T1 5 2 3 5 3
5 Electrical T2 3 2 1 4 3
6 Painter T1 3 2 1 9 3
7 Painter T2 3 2 1 6 3
8 False C T1 4 2 2 3 3
9 Tile T1 8 3 5 3 3
10 Window T1 2 1 1 3 3
11 RS Team 3 1 2 3 3
13 HR Erection T1 8 3 5 except 3
14 Project Manager 1 All
15 Electrical Engineer 1 All
16 Site Supervisor 3 per site
17 Safety Supervisor 3 per site
71
ED TEAM SUMMRAY on Date-18th Jan
Duration Existing
From To Manpower
1/16/2024 2/29/2024 5
1/16/2024 2/20/2024 4
1/22/2024 2/10/2024 4
1/16/2024 3/15/2024 4
1/27/2024 3/15/2024
1/19/2024 3/15/2024 3
1/25/2024 3/15/2024 0
2/1/2024 2/29/2024
1/28/2024 2/25/2024
2/1/2024 2/25/2024
2/1/2024 2/12/2024
1/16/2024 2
Remark
Need to increase manpower
Need to increase manpower
For
Housekeeping/Cleaning/loading/unloading/etc
or Snag Point