Detailed Pre-Commissioning Procedure Piping Cleaning: Ethylene Drying Pre-Cooling (131-2-25-05)
Detailed Pre-Commissioning Procedure Piping Cleaning: Ethylene Drying Pre-Cooling (131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 1 / 46 Rev L
Agreement Ref.: 4700000900
COSING S. Schifano
Filename: 131-SZ-103-000225-05_L
Digital signature
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 2 / 46 Rev L
Agreement Ref.: 4700000900
Contents
1 GENERAL .......................................................................................................................................... 3
1.1 PURPOSE & SCOPE ..................................................................................................................................3
1.2 REFERENCE DOCUMENTS ........................................................................................................................3
1.3 DEFINITIONS AND ABBREVIATIONS .........................................................................................................3
1.3.1 DEFINITIONS ................................................................................................................................................................ 3
1.3.2 ABBREVIATIONS AND TERMS....................................................................................................................................... 3
2 SAFETY ASPECTS ............................................................................................................................... 3
3 CLEANING CLASS & CLEANING METHODOLOGY ................................................................................. 3
4 PREPARATORY WORKS ..................................................................................................................... 4
5 DESCRIPTION OF SEQUENCE OF ACTIVITIES & ACCEPTANCE CRITERIA ................................................ 5
6 PRECOMMISSIONING CERTIFICATION & CHECK LISTS ......................................................................... 6
6.1 CERTIFICATES..........................................................................................................................................6
6.2 CHECK LISTS............................................................................................................................................6
7 TIGHTNESS LEAK TEST (AS APPLICABLE) ............................................................................................ 6
8 PRESERVATION OF PIPING ................................................................................................................ 7
9 P&ID MARKUP ................................................................................................................................. 7
10 APPENDICES ..................................................................................................................................... 8
10.1 APPENDIX 1 – REFERENCE DOCUMENTS..................................................................................................8
10.2 APPENDIX 2- ABBREVIATIONS AND TERMS .............................................................................................9
10.3 APPENDIX 3 - INSTRUMENTS AND SPECIAL IN-LINE COMPONENTS ........................................................10
10.4 APPENDIX 4 - P&ID MARKS-UP .............................................................................................................11
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information
is not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 3 / 46 Rev L
Agreement Ref.: 4700000900
1 GENERAL
1.1 PURPOSE & SCOPE
The purpose of this procedure is to provide the detailed methodology regarding the air blowing activities.
The work steps are analyzed, all hazards identified, and the necessary safety mitigation measures are
defined so that air blowing can be executed in a safe and efficient manner.
The scope covers the cleaning of the piping comprised in the indicated subsystem. The subsystem to be
cleaned is identified and prepared according to mark-ups in enclosed P&IDs.
1.2 REFERENCE DOCUMENTS
Look up in Appendix 1.
User is intended having acknowledged the content related to safety in documents in the reference item no.1 and 4.
Particular attention must be given to safe conditions at blow off point. Any flying object carried by the blown off
air must be contained within the controlled area. As guideline, the blown off air must hit a wooden ply with
minimum thickness of 6 mm and large enough to be securely hold in place. A net must be installed all around
the blow off point to contain any flying object coming out from inside of the pipe.
PSV with valid calibration certificate is installed at compressor delivery for overpressure protection. If the line
design pressure is less than mentioned PSV set pressure at compressor discharge, additional PSV with lower set
point will be used or approved mitigation actions must be considered.
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 4 / 46 Rev L
Agreement Ref.: 4700000900
Note-1: In case, during pressure accumulation, we exceed the pressure set for the quick depressurization, the operator must
stop the compressor and then depressurize the line slowly through the sacrificial valve and only when pressure has been
dropped in the range 2 – 2.5 barg, he can snap open the sacrificial valve for air blowing.
Note-2: Not having any previous experience with same line size and same Polyethylene sheet lot, the blasting will be started
with one layer and will proceed by adding a layer at each step. The total number of layers will be to achieve a bursting
pressure between 2 and 2.5 barg, preferring the lower side of the range if this is considered already sufficient for cleaning.
Do not increase blasting pressure at any first indication of line vibration.
In case during pressurization, we exceed the target pressure of the blasting procedure, we must stop the compressor and
de-pressurize the line through available line vents or from the vent at compressor discharge.
4 PREPARATORY WORKS
User is intended having acknowledged related content in reference item no.1. Instruments And Special In-
Line Components to be removed as per table in Appendix 3.
Dry Air supply is provided by Oil-free Air compressor (Atlas Copco PTS 1600) + Air dryer
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 5 / 46 Rev L
Agreement Ref.: 4700000900
PREPARATORY ACTIVITIES
No. P&ID Line/Equpt. Description
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 6 / 46 Rev L
Agreement Ref.: 4700000900
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 7 / 46 Rev L
Agreement Ref.: 4700000900
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 8 / 46 Rev L
Agreement Ref.: 4700000900
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 9 / 46 Rev L
Agreement Ref.: 4700000900
mechanical cleaning.
• Install temporary blind 13122505-TB-24 on line 3"-131-ET-20004
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 10 / 46 Rev L
Agreement Ref.: 4700000900
mechanical cleaning.
• Install temporary blind 13122505-TB-42 on line 14 "-131-ET-
20001
14"-131-ET-20001 pressure.
11 131-PP-152-20102
14"-131-ET-20231 • After finish blowing at BP-12, Install a temporary Blind 13122505-
2"-131-ET-20173
TB-30 on the flange of line 14"-131-ET-20001 for facilitating air
blowing through other BPs,
• For mechanical cleaning,
• Remove Spectacle blind 131-SB-20102-18 and install temporary
blind 13122505-TB-43 on line 2"-131-ET-20173
• Remove spool between VA-29 and continuous line valve to do
mechanical cleaning.
• Install temporary blind 13122505-TB-44 on line 14"-131-ET-
20001
• For BP-13, Disconnect the two lines
• Remove valve VA-19 and install temporary spool TS-11 in place.
• Remove valve VA-20
14"-131-ET-20035 • Install temporary blind 13122505-TB-31 on line 20"-131-ET-
131-PP-152-20102 20"-131-ET-20009
12 20009 for isolation.
1"-131-ET-20175
• Install polyethylene sheet of 500 gauge on the top of flange with
help of Temporary collar flange TF-07 for cardboard blasting. No
of layers of polyethylene sheet will be install depends on blasting
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 11 / 46 Rev L
Agreement Ref.: 4700000900
pressure.
• After finish blowing at BP-13, Install a temporary Blind 13122505-
TB-32 on the flange of line 14"-131-ET-20035 for facilitating air
blowing through other BPs,
• For mechanical cleaning,
• Remove Spectacle blind 131-SB-20102-17 and install temporary
blind 13122505-TB-49 on line 1"-131-ET-20175
• Remove spool between VA-32 and continuous line valve to do
mechanical cleaning.
• Install temporary blind 13122505-TB-50 on line 14"-131-ET-
20035
• For BP-14, Disconnect the two lines
• Remove valve VA-21, VA-22 & VA-23 and install temporary spool
TS-12, TS-13 & TS-14 in place accordingly.
• Remove valve VA-24
• Remove spectacle Blind 131-SB-20103-10
• Install temporary blind 13122505-TB-33 on line 14"-131-ET-
20234 for isolation.
• Install polyethylene sheet of 500 gauge on the top of flange with
help of Temporary collar flange TF-08 for cardboard blasting. No
14"-131-ET-20017 of layers of polyethylene sheet will be install depends on blasting
13 131-PP-152-20103 14"-1 31-ET-20234
pressure.
2"-131-ET-20164
• After finish blowing at BP-14, Install a temporary Blind 13122505-
TB-34 on the flange of line 14"-131-ET-20017 for facilitating
air blowing through other BPs,
• For mechanical cleaning,
• Remove Spectacle blind 131-SB-20103-11 and install temporary
blind 13122505-TB-51 on line 2"-131-ET-20164
• Remove spool between VA-33 and continuous line valve to do
mechanical cleaning.
• Install temporary blind 13122505-TB-52 on line 14"-131-ET-
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 12 / 46 Rev L
Agreement Ref.: 4700000900
20017
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 13 / 46 Rev L
Agreement Ref.: 4700000900
mechanical cleaning.
• Install temporary blind 13122505-TB-54 on line 14"-131-ET-
20021
• Remove Spectacle blind 131-SB-20103-15 and install temporary
blind 13122505-TB- 55 on line 1"-131-ET-20165
• Remove spool between VA-35 and continuous line valve to do
mechanical cleaning.
• Install temporary blind 13122505-TB-56 on line 14"-131-ET-
20021
• For BP-20, Disconnect the two lines
• Remove valve VA-30 and install temporary spool TS-16 in place.
• Remove valve VA-36
• Remove spectacle Blind 131-SB-20102-20
• Install temporary blind 13122505-TB-45 on line 14"-131-ET-
20039 for isolation.
• Install polyethylene sheet of 500 gauge on the top of flange with
help of Temporary collar flange TF-11 for cardboard blasting. No
of layers of polyethylene sheet will be install depends on blasting
pressure.
16 131-PP-152-20102 14"-131-ET-20001
• After finish blowing at BP-20, Install a temporary Blind 13122505-
TB-46 on the flange of line 14"-131-ET-20001 for facilitating
air blowing through other BPs,
• For mechanical cleaning,
• Remove Spectacle blind 131-SB-20102-21 and install temporary
blind 13122505-TB-47 on line 2"-131-ET-20174
• Remove spool between VA-31 and continuous line valve to do
mechanical cleaning.
• Install temporary blind 13122505-TB-48 on line 14"-131-ET-
20001
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 14 / 46 Rev L
Agreement Ref.: 4700000900
1 Before starting the blowing activities, ensure that no water has been left inside the subsystem pipes after the
hydrotest, otherwise drain it.
2 Ensure that safe conditions are in place at blow off point location as indicated in the JSA and dedicated PTW which
has been approved.
Ensure that all vent and drain valves are closed and all other BPs are closed for facilitating the air blowing through
3 BP-1 and ensure polyethylene sheets are installed with help of temporary collar flange at BP-01
4 At air injection point IP-01, start the compressor, then gradually open Valve TV-01 and then gradually open TV-02
and pressurize the line until bursting of polyethylene layers, reading the pressure on PG-01.
Adequate Pre-caution will be taken at blowing points. Ensure complete depressurization of the line and the
5
compressor delivers flow without restrictions.
Keep unrestricted compressor flow for about 1 minute.
6 De-pressurize the line by closing the valves TV-01 and TV-02 on air supply arrangement.
7 After the line de-pressurization, again install the polyethylene sheet at BP-01 with the help of Temporary collar
flange and then raise the pressure until the bursting of the set of Polyethylene layers. Cardboard blasting is
performed at BP-01according to methodology guidelines in paragraph 3.
8 Operator shall repeat actions indicated in the sequence point no. 4 to 7 for minimum four times and more
depending on the length of the line which is blown. As general guideline, the number of quick depressurizations
will be repeated twice after a clean air blow off is detected.
After last depressurization, the dew point of the air from the blow off point shall confirm that no water pockets are
9
left inside the pipe (dew point at outlet blow off point shall be near the dew point of the air downstream
compressor dryer).
Once cleaning is accepted at BP-01, injecting air from IP-01, let remove the temporary collar flange and install the
10 temporary blind directly on the flange of the pipe to facilitate the air blowing through other BPs.
11 For air blowing at blow points BP-02 to BP-03, Operator shall follow the actions in sequency from point no. 3 to
point no. 09 for each BPs.
12 After accepting the BP-01 to BP-03 ensure that temporary blinds are installed on respective BPs, to facilitate the air
blow through vent, drain and instrument connection points.
13 At air injection point IP-01, start the compressor, then gradually open Valve TV-01 and then gradually open TV-02
and pressurize the line up to 0.5 to 1 barg, reading the pressure on PG-01. And blow the vents and drain and
instrument connection points BP-04 to BP-06 and BP-26.
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 15 / 46 Rev L
Agreement Ref.: 4700000900
14 After finishing air injection through IP-01, Remove the air supply arrangement from IP-01 and install at IP-02.
Install temporary blind at IP-01 for protection.
15 For air blowing BP-07, Ensure that all vent and drain are closed and all other BPs are closed for facilitating the air
blowing through BP-07 and ensure polyethylene sheets are installed with help of temporary collar flange at BP-07
16 At air injection point IP-02, start the compressor, then gradually open Valve TV-01 and then gradually open TV-02
and pressurize the line until bursting of polyethylene layers, reading the pressure on PG-01.
17
Operator shall follow the action in sequence from the point no. 3 to point no.9.
18 Once cleaning is accepted at BP-07, injecting air from IP-02, let remove the temporary collar flange and install the
temporary blind directly on the flange of the pipe to facilitate the air blowing through other BPs.
19 For air blowing at BP-08, Ensure that BP-07 and all other BPs are closed, remove the temporary blind from
Temporary sacrificial valve.
20 At air injection point IP-02, start the compressor, then gradually open Valve TV-01 and then gradually open TV-02
and pressurize the line until 2 barg, reading the pressure on PG-01.
With adequate PPE, the operator will quickly open the sacrificial valve until the complete depressurization of the
21 line and compressor delivers flow without restrictions.
Keep unrestricted compressor flow for about 1 minute.
22
Close sacrificial valve again and wait until line is pressurized again between 2 and 2.5 barg
23 Operator shall repeat actions indicated in the sequence point no. 20 to 22 for minimum four times and more
depending on the length of the line which is blown. As general guideline, the number of quick depressurizations
will be repeated twice after a clean air blow off is detected.
24 After last depressurization, the dew point of the air from the blow off point shall confirm that no water pockets are
left inside the pipe (dew point at outlet blow off point shall be near the dew point of the air downstream
compressor dryer).
25 Once cleaning is accepted at BP-08, injecting air from IP-02, let remove the sacrificial valve and install the
temporary blind directly on the flange of the pipe to facilitate the air blowing through other BPs.
26 For air blowing at BP-09 Operator shall follow the actions indicated in the sequence from point no. 19 to point
no.25.
27 After accepting the BP-07 to BP-09, ensure that temporary blinds are installed on respective BPs, to facilitate the
air blow through vent, drain and instrument connection points.
28 At air injection point IP-02, start the compressor, then gradually open Valve TV-01 and then gradually open TV-02
and pressurize the line up to 0.5 to 1 barg, reading the pressure on PG-01. And blow the vents and drain and
instrument connection points BP-10 and BP-27 to BP-30.
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 16 / 46 Rev L
Agreement Ref.: 4700000900
29 After finishing air injection through IP-02, Remove the air supply arrangement from IP-01 & IP-02 and install at IP-
03. Install temporary blind at IP-01 & IP-02 for protection.
30 For air blowing at blow points BP-11 to BP-16 and BP-20, Operator shall follow the actions in sequency from point
no. 3 to point no. 09 for each BPs.
31 After accepting the BP-11 to BP-16 and BP-20, ensure that temporary blinds are installed on respective BPs, to
facilitate the air blow through vent, drain and instrument connection points.
32 At air injection point IP-03, start the compressor, then gradually open Valve TV-01 and then gradually open TV-
02 and pressurize the line up to 0.5 to 1 barg, reading the pressure on PG-01. And blow the vents and drain and
instrument connection points BP-17 to BP-19 and BP-21 to BP-25 and BP-31 one by one.
33 It is mandatory to close all open ends when flushing or blowing is interrupted or stopped during execution of
cleaning procedure.
34 After acceptance of all the BP, then reinstate the line with final gaskets and according to design. The reinstatement
must be executed as fast as possible to avoid that results of the cleaning are disrupted by adverse environment.
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 17 / 46 Rev L
Agreement Ref.: 4700000900
A tightness test should be performed prior to any other testing. The tightness test allows personnel to locate and repair
gross leaks within the system before introducing other testing media at higher pressures, reducing wasted testing media.
A leak test shall be carried out after the reinstatement of the sub-system with the aim to verify grossly the tightness of
every flanged and/or threaded joint. The tightness test shall be carried out at low pressure (maximum 2 - 3 barg).
Once the sub-system has been pressured-up, it shall be hold for one hour and the pressure shall be monitored by an
adequate pressure gauge (pressure range: 0 to 5 barg).
In case of leakage from a welded and/or threaded joint, seal weld, etc., the execution of the Tightness Test shall be
stopped, and the leakage shall be promptly addressed and rectified.
The Tightness Test shall be considered successfully completed in case a pressure drops not higher than 0.5 bar is detected
during one hour.
8 PRESERVATION OF PIPING
After reinstatement and, if applicable, the tightness test, the subsystem is depressurized and kept sealed at ambient
pressure.
9 P&ID MARKUP
See Appendix 4.
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 18 / 46 Rev L
Agreement Ref.: 4700000900
10 APPENDICES
10.1 APPENDIX 1 – REFERENCE DOCUMENTS
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information is
not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge).
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 19 / 46 Rev L
Agreement Ref.: 4700000900
ABBREVIATION/TERM DESCRIPTION
BD Burst Disk
BFLG Blind Flange
BP Blowing Point
C Close
DRV Drain Valve
ISBL Inside Battery Limit.
IP Injection Point
NRV Non-Return Valve (Check Valve)
O Open
OSBL Outside Battery Limit.
PSB Permanent Spacer Blind
PPB Permanent Spade (Paddle) Blind
P&ID Piping and Instrumentation Diagram
PG Pressure Gauge
SB Spectacle, Spade, Spacer Blind
TF Temporary Collar Flange
TH Temporary Hose
TSV Temporary Sacrificial valve
TSB Temporary Spacer Blind
TB Temporary Spade (Paddle) Blind
TS Temporary Spool
TV Temporary Valve
VA Permanent Valve which does not have
Tag Number in P&ID
VSP Vent Pipe Spool
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information
is not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 20 / 46 Rev L
Agreement Ref.: 4700000900
Included in Test
After cleaning
After testing
Component Temp. Temp.
Ref.
Included in
Cleaning
Isolated
Isolated
spool or spool or
removed removed
1 Analyzers X X X
2 Control Valves X X X
9 Gauge glasses X X X
24 Filters internals X X X
This document contains CONFIDENTIAL and PROPRIETARY Information of Abu Dhabi Polymers Company Limited (Borouge) or any of its Licensors. This information
is not to be used, disclosed, or reproduced in whole or in part to anyone outside of Abu Dhabi Polymers Company Limited (Borouge) and its subsidiaries, except
pursuant to a written agreement with Abu Dhabi Polymers Company Limited (Borouge
TCM Identification Code
DETAILED PRE-COMMISSIONING PROCEDURE
PIPING CLEANING 4300-DZ-VD-SCP4131L14225-05
ETHYLENE DRYING PRE-COOLING
(131-2-25-05)
Borouge 4 Project –
LOCATION: RUWAIS - U.A.E. EPC Package 3 - PO Unit Sheet 21 / 46 Rev L
Agreement Ref.: 4700000900
P&IDs List
No. Line
1 131-PP-152-20100
2 131-PP-152-20102
3 131-PP-152-20103
4 131-PP-152-20104
5 131-PP-152-20105
6 131-PP-152-20106
Page 21 of
A B C D E F G H
GENERAL NOTES
3/4" V
S
D0KP01 A0KP01 NOTES:
3/4" S 0.50 %
131-SP-2020
3/4"-131-ET-20139-D0KP01-V 3/4"-131-HF-20134-A0KP01-V 1) NOT USED.
131-S-2001-6 781 131-PP-152-09103
131-SB-20100-1 NC 131-2-19-02 2) DOUBLE PSV'S SHALL BE EQUIPPED WITH KEY / INTERLOCK SYSTEM REF. SPEC. BGS-LU-013.
NOTE 4 6306 607
S TO HP FLARE SPECIAL ITEM TAG REFERS TO INTERLOCKING SYSTEM ONLY.
131-2-25-05 131-2-19-02 3) 131-PSV-2411A/B PROTECTS 131-HE-204A/B SHELL AND 131-HE-202 TUBESIDE.
1 T5378-V 1
4300-VZ-DM-131020100
131-2-25-05 131-0-70-01
TO ANALYSER AT-2010R (H²O),
131-PP-152-20100
B2GP01 D0KP01
13122505-TB-19 GENERAL NOTES:
MIN. LENGTH
TC 3/4" T P A) ALL FLARE LINES TO BE SLOPED TOWARDS THE FLARE HEADER WITH TOP ENTRY.
CONTRACTOR :
FROM B.L. C V
20"-131-ET-20005-B2GP01-V B) SCOPE BREAK BETWEEN VENDOR AND BOROUGE 4 EPC CONTRACTOR IS INDICATED BY:
BOROUGE :
131-2-25-05
131-2-19-02
D) DELETED.
V PSV
T0722-X NOTE 2 T
+ E) ALL INSTRUMENT TAG AND INTERLOCK NUMBERS ON THIS DRAWING HAVE THE PREFIX 131.
2411B
0.50 % Q1 ILTE 3/4"
BP-08 F) DELETED.
6"-131-HF-20001-A0KP01-V LO NOTE 3
131-PP-152-09103 32776 13122505-TB-22 G) DELETED.
131-2-19-02 600# H) DELETED.
607 13122505-TB-21 131-SP-2072 6"x3"
TO HP FLARE 300#
TSV-01 I) DELETED.
2" X 3"
PSET=42.0 barg
131-2-25-05
131-2-19-02
2 V 3"x2" 2
BP-09 PSV
REFERENCES:
+
3/4" T 2411A
131-SP-2070
6"-131-HF-20242-A0KP01-V NOTE 3
131-PP-152-09103 782 FOR GENERAL NOTES AND REFERENCES SEE DWG. FROM PU-PP-152-01000-01÷15.
PP
131-2-19-02 LO 600# PIPING AND INSTRUMENTATION DIAGRAM-SYMBOLS, ABBREVIATIONS AND GENERAL NOTES.
607 NOTE 2 6"x3" TSV-02
TO HP FLARE ILTE 300#
Q1
13122505-TB-23 3"x2" 3/4"
T0722-X BP-30 3/4" V BP-29
Q1 V
1"-131-ET-20137-D0KP01-V T
T5655-X T
LO NOTE 131-SP-2073 LC
6306 TS-07
131-SP-2071 VA-112 TS-06NOTE 2
V ILTE ILTE VA-10
A0KP01 D0KP01
3"-131-ET-20003-B2GP01-PP
0.50 % 3/4" T BP-10 MIN. Q1 Q1
T0722-X
1"-131-HF-20241-A0KP01-V NC T
T0722-X
131-2-19-02 NC
607 131-SB-20100-2 D0KP01 B2GP01
6301
VA-12
600MM MIN. Leq. MAX=93M
131-2-19-02 131-2-25-05
MIN.
3"-131-ET-20004-B2GP01-PP PP
13122505-TB-24
6301
3 3
13122505-TB-58
MIN.
THIS INFORMATION IS NOT TO BE USED, DISCLOSED, OR REPRODUCED IN WHOLE OR IN PART TO ANYONE OUTSIDE OF ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE) AND ITS SUBSIDIARIES,
TI TT TE TG
BP-28 BP-27
2009 2009 2009 2218
13122505-TB-59
TW TW TW
+ +
+
131-SB-20100-3
V
131-SB-20100-4
TS-01 TS-02
IP-02 T 3/4"
DRY AIR FROM 24"x20" 24"x20"
2"x3/4"
COMPRESSOR
I
131-HE-204A N4A N1A
TV-01 TH-01 TV-02 24"
4 SHELL: 131-VZ-20089-B2GP01-I N6 2" 24" 4
EXCEPT PURSUANT TO A WRITTEN AGREEMENT WITH ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE).
I
6301 N3A 24"
N2A
13122505-TB-15
24" 24"
131-HE-204B N1B
N4B
SHELL: 131-VZ-20090-B2GP01-I
I
6301 24" N5 2"
N3B N2B
13122505-TB-35 131-SB-20100-6 24"
BP-15
131-SB-20100-5
I
2"x3/4"
24"x20" 24"x20"
TF-09 3/4" T
D
13122505-TB-36 1-1/2" TG
2221
ETHYLENE TW
20"-131-ET-20017-B2GP01-I I + BP-31
8188 131-PP-152-20103 2221
131-2-25-05
6303
FROM ETHYLENE
5 CO TREATER 131-VC-203 A/B 5
H
TT TI
2005 2005
L 13122505-TB-60
TG TE
2222 2005
TW TW
+ +
2222 2005
ETHYLENE Q1 22-Feb-2024 APPROVED FOR CONSTRUCTION - REVISED A.Waykole P.Perego/S.Naik/
R.Soldinger
I 1-1/2"
R.Santangelo/A.Pirani
20"-131-ET-20008-B2GP01-I 1-1/2"
131-PP-152-20101 8190 Q 29-Jun-2023 APPROVED FOR CONSTRUCTION A.Waykole R.Soldinger
P.Perego/S.Naik/
R.Santangelo/A.Pirani
131-2-25-05
6301 P 02-Dec-2022 APPROVED FOR DESIGN A.Waykole P.Perego/S.Naik/
R.Soldinger
TO ETHYLENE PREHEATER R.Santangelo/A.Pirani
GENERAL NOTES
14"-131-ET-20035-B2GP01-I
2"-131-HF-20158-A0KP01-V
0.50 %
13122505-TB-32 NOTES:
131-PP-152-09103 28450 6303
131-2-19-02 607 TF-07
TO HP FLARE I 1) STAGGER THERMOWELLS AT 120° TO EACH OTHER AND EXTEND MINIMUM 300 MM.
NC VA-20 0.50 % INTO THE VESSEL IN THE CATALYST BED, NOT IN INERT BED.
BP-13 S TO HP FLARE
1"-131-HF-20164-A2GP01-V
609 131-PP-152-09102 2) SUFFICIENT HEIGHT MUST BE AVAILABLE UNDER MANHOLE TO ENABLE DUMPING OF CATALYST.
ETHYLENE 131-2-19-02
20"-131-ET-20009-B2GP01-I I 601 MANHOLE AND HANDHOLE INSERTS TO BE FLUSH FITTING.
8202 131-PP-152-20101
131-2-25-05 3) REMOVABLE SPOOL PIECE FOR VESSEL ISOLATION WHERE REQUIRED FOR ACCESS AND MAINTENANCE.
FROM ETHYLENE 6303
1
13122505-TB-31 4) CHECK VALVE TO BE "SWING CHECK" TYPE.
1
4300-VZ-DM-131020102
PREHEATER 131-HE-201
OFF GAS OFF GAS
2"-131-ET-20167-B2GP01-V NNF 2"-131-ET-20026-B2GP01-V 5) HIGH ALARM VALUES DURING:
8220 131-PP-152-20103 131-2-22-02 8240 131-PP-152-20105
131-2-22-02 6303 - PRESSURIZATION
6303
131-PP-152-20102
36 BARG RAW NITROGEN 131-2-19-02 131-SB-20102-2 B2AP01 6306 0.50 % SYSTEM 2 VENT COOLER
1"-131-HN-20005-B2AP01-V 131-2-24-07 B2GP01 A2GP01 131-2-19-02 131-SB-20102-5 S 131-HA-268 BY CATALYST VENDOR.
V
BOROUGE :
10"
6830 6830 6802 131-2-19-02
8227 131-PP-152-09102 9) ALTERNATE DESIGN CONDITION: 343°C AND 11 BAR FOR REGENERATION.
14"x10" NC 131-2-24-07 G 131-SB-20102-4 PP INSUL D0KP01 D0KP01 PP INSUL 601
10" 131-2-25-05 131-2-19-02 TO HP FLARE
131-2-25-06 131-2-24-07 131-2-19-02 10) FOR CATALYST PRETREATMENT AFTER LOADING USE H2 FROM FV-2021A (SWING PIPE SP-131-2042 MUST BE ON
G M NC 131-SB-20102-3 INSUL B2GP01 G NCB2GP01 I INSUL
NO POCKETS G H2 POSITION) AND N2 FROM FV-2019, THE SUITABLE MIXTURE SHALL BE DONE BY CHANGING THE SETPOINT
131-2-25-06 131-2-24-07 NC G NC G 20"x14" 20"x14"
OF FIC-2021 AND FIC-2019. PRIOR TO UNLOADING, CATALYST NEEDS TO BE OXIDIZED USING AIR.
I
1"-131-HN-20007-B2AP01-V MIN. 14"-131-ET-20009-B2GP01-I M G 0.5 %
131-SB-20102-6 NOTE 13 6"-131-HF-20454-A0KP01-V 11) FO SIZED FOR THE SAME DP AS THE BEDS.
131-2-25-06 131-2-19-02 26766 131-PP-152-09103
14"-131-ET-20030-B2GP01-I
383 PSV V 6303 131-2-25-06 6302 6303 131-2-25-05 131-2-19-02 12) LOCATE ANALYZER TAP 15 PIPE DIAMETERS DOWNSTREAM.
3/4" 607
1-1/2" X 3"
+
131-SB-20102-19
V PSV 6303 1-1/2" X 3" PSV 607
300# PSET=42.0 barg 131-20102-V1 V TO HP FLARE - NORMAL OPERATION / STAND BY / PRESSURIZATION.
T +
S 3/4" T +
131-SP-2237
3/4" S LO 6"x3" 1-1/2" X 3"
T0724-X
LO 131-SP-2302
NO POCKETS10"-131-P-20214-B2GP01-PP PP
3"x1-1/2" 2421B PSET=42.0 barg 2422A 0.50 %
HIGHALARM VALUES DURING:
3/4" 6302 V PSET=42.0 barg 6"-131-HF-20016-A0KP01-V
3/4" 6303 - PURGING / HEATING / COOLING.
3"-131-ET-20043-B2GP01-PP
131-2-25-06 131-2-22-02
607
131-SB-20102-10
M 300# NOTE 6 300# Q1 NO INSUL. TO HP FLARE 15) PERSONNEL PROTECTION FOR REGENERATION RETURN LINES HAS TO EXTEND OVER THE WHOLE LENGTH OF THE PIPE.
131-2-25-06 131-SP-2301 3/4" S LO 0.5 %
NOTE 17 NO INSUL PSV
B2AP01 NOTE 17 NO INSUL 3"x1-1/2" ILPE NC M PP INSUL. 16) DISSIMILAR TYPE CHECK VALVE.
Leq MAX= 92 m
131-SB-20102-8
NO POCKETS 14"-131-ET-20177-B2GP01-I
ILME
6302 26769 131-PP-152-09103 17) DOUBLE PSV'S SHALL BE EQUIPPED WITH KEY/INTERLOCK SYSTEM. REF. TO SEC. BGS-LU-013. ITEM TAG REFERS TO
6302
3/4" M
1"-131-ET-20178-B2GP01-I
131-SP-2300 V B2GP01 3/4" M 600# 131-2-19-02
6830
NC I INSUL LC V 6302 M NC NC 131-SP-2234 3"x1-1/2" 300# 131-SP-2236 V 131-SB-20102-11 607
TO HP FLARE INTERLOCKING SYSTEM ONLY.
1"-131-ET-20171-B2GP01-I
ILME
M B2GP01 M I INSUL NOTE 17 NOTE 17
3/4" M 131-2-22-02 NOTE 17 LO 18) CHANGE OF RATING FOR PG MONO FLANGE CONNECTION.
PP
MIN. 6302
T2715-K ILME PP Q1 NC 131-2-25-06 3"-131-ET-20045-B2GP01-PP V
131-0-74-05 2" 131-2-25-06 2" M
6302
131-2-25-06 ILME Q1 T2715-K
T2715-K NOTE 2, 7
6302
M 131-SB-20102-9 PG 6302 M
Q1
PG
NOTE 7
HH
T0724-X 3/4"
HH
131-SP-2235 PP NC GENERAL NOTES:
V 131-SP-2051
SP
SP
3/4" 131-SP-2049 2230 600#
M Q1 B2GP01 D0KP01 V D0KP01 A0KP01
600# 2223 NOTE 3 3" NOTE 3 Q1
NO POCKETS
V NOTE 18
M H2 M H2 BP-22 I INSUL. NO INSUL. A) ALL FLARE LINES TO BE SLOPED TOWARDS THE FLARE HEADER WITH TOP ENTRY.
NOTE 18
16" N6
NC
3/4" 16" N6
T0724-X VA-32 3/4" S
NC NC 1"-131-ET-20175-D0KP01-I
0.50 %
M 3" T0546-X M NC 1"-131-HF-20161-A0KP01-V B) SCOPE BREAK BETWEEN VENDOR AND BOROUGE 4 EPC CONTRACTOR IS INDICATED BY: C V
3/4" M 599 131-PP-152-09102
12" Q1 12" 131-2-19-02
12"x14"
N5 I N5
S 6306 131-SB-20102-17 607 TO HP FLARE
S1 S-2011 S1 S-2011 FO 131-2-25-05 131-2-19-02 C) PACKAGE DETAILS REFER TO THE CURRENT CONFIGURATION AS REPRESENTED ON
+
2230 K3A O XA E) ALL INSTRUMENT TAG AND INTERLOCK NUMBERS ON THIS DRAWING HAVE THE PREFIX 131.
TE TI I TAH TE TI I TAH
3 HH HH 20"x14" TS-12 2079 F) DELETED. 3
I PI PT TE 2021 2021 2021 I PI PT TE 2024 2024 2024 13122505-TB-50
2" L 2" L G) DELETED.
2215 2215 2223 I-2035 TYPE 1A 2216 2216 2230 I-2036 ETHYLENE
TW TW S I 14"-131-ET-20016-B2GP01-I H) DELETED.
THIS INFORMATION IS NOT TO BE USED, DISCLOSED, OR REPRODUCED IN WHOLE OR IN PART TO ANYONE OUTSIDE OF ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE) AND ITS SUBSIDIARIES,
I-2035
+
I-2036
+
TYPE 1A 28754 131-PP-152-20103
PAL TT I 2021 PAL TT 2024 131-2-25-05 I) DELETED.
NC 6303
2215 2223 2216 2230 VA-21 S-2012 TO ETHYLENE CROSS HEAT
S1 S-2011 S1 S1 S-2011 EXCHANGER 131-HE-204A/B
NOTE 14 S1 NOTE 14 O XA
S-2011 TT I TAHH TT I TAHH
TAHH I 2013
2022 2022 NOTE 5 S-2011 2025 2025 NOTE 5
2223 NOTE 1 TAHH I NOTE 1
NOTE 5 K3B TE TI I TAH 2230 I K3B TE TI I TAH
REFERENCES:
TI ETHYLENE
2" I 20"-131-ET-20001-B2GP01-I
THIS DOCUMENT CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE) OR ANY OF ITS LICENSORS.
2" 2022 2022 2022 2025 2025 2025 FOR GENERAL NOTES AND REFERENCES SEE DRG. FROM PU-PP-152-01000-01÷15.
2223 L TI NOTE 5 L 8207 131-PP-152-20103
L 6303 131-2-25-05 PIPING AND INSTRUMENTATION DIAGRAM-SYMBOLS, ABBREVIATIONS AND GENERAL NOTES.
TW I-2035 TYPE 1A 2230 TW I-2036 TO ETHYLENE CO
I I-2035 L
+ +
TYPE 1A TREATERS 131-VC-203A/B
2022 I-2036 2025
TAH I
S-2011 2230 S-2011
I I-2035 TAH S1 S1 131-2-25-05 Ethylene Drying Pre-Cooling
I-2218 2223 TT I TAHH TYPE 1A TT I TAHH
I-2219
TYPE1A NOTE 1 2023 2023 NOTE 5 2026 2026 NOTE 5
HS 3"-131-P-20215-B2AP01-V 3"-131-UA-62603-A1AU01-V
131-2-14-03
131-2-24-06
131-VC-204A K3C NOTE 1 V
2011 MH K3C TE TI I TAH MH TE TI I TAH B2AP01 A1AU01
STATUS SELECTION 2" 6802 422
M1 2" 2023 2023 2023 M1 2026 2026 2026 3/4" G NOTE 10
I-2036 24" L 6802 422 PLANT AIR
4 I-2035 24" L I NC 4
TW I-2035 TYPE 1A I-2218 TW I-2036
TYPE 1A 131-PP-152-20130 611
EXCEPT PURSUANT TO A WRITTEN AGREEMENT WITH ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE).
I XA + I-2219 +
G 131-2-14-03
NOTE 2, 7 2023 NOTE 2, 7 2026 NOTE 16 NOTE 16
2042 S-2003 FROM CONTROL VALVE
HS 131-SP-2042
131-VC-204 B S-2004 131-FV-2020
2012 NOTE 8
STATUS SELECTION ZE ZS I ZL
V
I-2036 2502 2502 2502
3/4" M
131-VC-204A I XA
131-VC-204B
131-VZ-20005-B2GP01-I 131-VZ-20006-B2GP01-I NC
12" 2030 12" S-2003
N4 N4 6302 M S-2004
6302
ZE ZS I ZL
1-1/2" 14"x12" 1-1/2" 14"x12" I NO
INSUL. INSUL. 2503 2503 2503
14"-131-ET-20231-B2GP01-I 14"-131-ET-20039-B2GP01-I NOTE 10
3"x1-1/2"
13122505-TB-29 FO FO
M NOTE 16 HYDROGEN
+
M 6302
+
NOTE 18 6302 NC 1-1/2"x1"
2440 2441 Q1
I NOTE 18 Q1 I 600# 131-PP-152-20130 8235
600#
13122505-TB-45 3/4"
PG T2715-K 13122505-TB-47131-2-24-06 13G1-2-33-03 NOTE 16 131-2-33-03 FROM CONTROL VALVE
3/4" PG T2715-K
A2GP01 2232 B2GP08 A2GP08 131-FV-2021A
131-SB-20102-13
B2GP01 10"-131-ET-20232-B2GP01-I M
NO POCKETS 2231 NO POCKETS 1-1/2"-131-HY-20026-B2GP08-V
MIN.
NO INSUL I INSUL M NO POCKETS 6406 6408 1"-131-HY-20019-A2GP08-V
1"-131-HF-20166-A2GP01-V 13122505-TB-48
131-2-24-06 131-2-25-06
131-2-25-05 131-2-25-06
3"
NC 6408
601 BP-12
131-2-25-05 131-2-25-06
6303
I
TO HP FLARE NC NC 2"-131-HF-20160-A0KP01-V
131-2-19-02 131-2-24-06600 MM MIN. 600 131-PP-152-09102
I
0.50 %
3/4" M 2057A 2057A I-2037
I-2036 Prepared Checked Approved
1"-131-HF-20159-A2GP01-V NC NC 1" H Rev. Date Description
I
2061 NOTE 4
REGENERATION GAS
ETHYLENE O2 TREATER 1-1/2" I 10"-131-P-20001-B2GP01-I 10" I
TYPE 2A PETROCHEMICALS PROJECT
131-PP-152-20130 8237
6830 131-2-24-06 COMPANY PROJECT NO PROJECT TITLE:
TYPE : PACKED FC
6
NOTE 12 M B2GP01 B2AP01
FROM REGENERATION GAS 4700000900 BOROUGE 4 PROJECT - EPC PACKAGE 3 - 6
TOTAL VOLUME (m³) : 59.12 HEATER 2 131-HH-209
DIA. (mm) : 3300
CONTRACTOR PROJECT NO
4300 - PO
PO UNIT - RUWAIS, UAE
REGENERATION GAS M STREAM 26 (131-AE-2026)
HEIGHT (T/T) (mm) : 6812 10"-131-P-20001-B2GP01-I I
131-PP-152-20103 8221 26714 131-PP-152-00161-09
DRAWING TITLE: PIPING AND INSTRUMENTATION DIAGRAM
DP (barg) : 42/FV NOTE 9 131-0-70-01 UNIT 131 - POLYOLEFINS COMMON
6830 3/4" Q1
DT (ºC) : 185/-45 TO ETHYLENE TO ANALYSER
CO TREATERS 131-VC-203 A/B AT-2026A (H ) & T0470-V ETHYLENE O2 -TREATERS
MOC : LTCS P I
AT-2026V (O²) BOROUGE DOCUMENT CLASS' N PROJECT DRAWING NO REV: Q1
INSUL. : I ²
131-2-24-06 131-0-70-01
CONTRACTOR: 4300-VZ-DM-131020102 SHEET UNIT: 131
1 BOROUGE: 131-PP-152-20102 OF AREA: 2
CADD
A B C D E F REF. 131-PP-152-20102-ISQ1 SCALE:
SHEET
SIZE A1
A B C D E F G H
0.50 % ETHYLENE GENERAL NOTES
2"-131-HF-20149-A0KP01-V I 14"-131-ET-20016-B2GP01-I
131-PP-152-09103 28451 131-PP-152-20102 28754
131-2-19-02 131-2-25-05
607 6303
TO HP FLARE FROM ETHYLENE 02
ETHYLENE
20"-131-ET-20001-B2GP01-I I
TREATERS 131-VC-204A/B
NOTES:
8207 131-PP-152-20102 OFFGAS
131-2-25-05 2"-131-ET-20167-B2GP01-V 1) STAGGER THERMOWELLS AT 120° TO EACH OTHER AND EXTEND MINIMUM 300 MM INTO THE VESSEL
6303
FROM ETHYLENE O2 8220 131-PP-152-20102 IN THE CATALYST BED NOT IN INERT BED.
131-2-22-02
TREATER 131-VC-204 A/B 6303
0.50 % PP TO COMMON LIGHT GAS 2) SUFFICIENT HEIGHT MUST BE AVAILABLE UNDER MANHOLE TO ENABLE DUMPING OF CATALYST.
10"-131-P-20008-B2AP01-PP HEADER
1"-131-HF-20150-A2GP01-V MANHOLE AND HANDHOLE INSERTS TO BE FLUSH FITTING.
1 131-PP-152-09102 582 6802
0.50 % 1
131-2-19-02
4300-VZ-DM-131020103
601 NO INSUL. 6"-131-HF-20452-A0KP01-V 3) REMOVABLE SPOOL PIECE FOR VESSEL ISOLATION WHERE REQUIRED FOR ACCESS AND MAINTENANCE.
TO HP FLARE A2GP01 131-2-19-02 26764 131-PP-152-09103
4) NORMALLY NOT CONNECTED.
1"-131-HN-22627-B2AP01-V B2GP01 NC 6802 V PP INSUL. NO INSUL. 607
B2AP01 TO HP FLARE
36 BARG RAW NITROGEN PP INSUL. NC
131-SB-20103-2 B2GP01 A2GP01 13122505-TB-42 5) HIGH ALARM VALUES DURING :
131-PP-152-20103
131-SB-20103-3
M NC
2"-131-ET-20028-B2GP01-V
131-2-25-07 6830 131-2-19-02 607 7) LINE TOWARDS VENT COOLER 131-HA-268 IS ISOLATED DURING OXIDATION OF CATALYST.
BOROUGE :
600 MM
131-0-74-05 G VA-28 NC REGENERATION GAS 8) SPACE TO BE PROVIDED FOR CATALYST FILLING AND REMOVAL PROCEDURES
MIN.
B2GP01 PP
2"-131-ET-20014-D0KP01-V G TS-09 10"-131-P-20014-B2AP01-PP TO BE CONFIRMED BY CATALYST VENDOR.
131-SB-20103-22 131-PP-152-20102 8219
6303
6306
VA-14 6802 131-2-24-07 9) DISCHARGE AT SAFE LOCATION.
I 14"-131-ET-20011-B2GP01-I BP-11 20"x14" 20"x14" FROM ETHYLENE O2
TREATERS 131-VC-204A/B 10) ALTERNATE DESIGN CONDITION: 343°C AND 11 BARG FOR REGENERATION.
1"-131-HN-20003-B2AP01-V
6302 3/4" M G NOTE 14 G 13122505-TB-41 11) FOR CATALYST PRETREATMENT AFTER LOADING USE PLANT AIR FROM FV-2020 AND N2 FROM FV-2019.
D VA-15 0.50 %
6"-131-HF-20452-A0KP01-V
3"x1-1/2" PSV 6303 1-1/2" X 3" PSV V NOTE 17 14) MAIN INLET AND OUTLET PIPING TO BE SYMMETRIC
1-1/2" X 3" V 3/4" 0.50 %
3"-131-ET-20025-B2GP01-PP M
+
PP
T 3/4" 131-SP-2305 131-2-19-02 LO 6"x3" 607 HIGH ALARM VALUES DURING : PURGING/ HEATING/ COOLING.
607
TYPE 1A 3"-131-ET-20027-B2GP01-PP 300# 131-2-25-07 1-1/2" X 3" ILPE Q1 TO HP FLARE
I
3/4" Q1 600# 3"x1-1/2" 131-2-24-07 131-0-70-01 16) PERSONNEL PROTECTION FOR REGENERATION RETURN LINES HAS TO EXTEND OVER THE WHOLE LENGTH
131-2-25-05
I-2031 131-SP-2303 LO PSET=42.0 barg
V TAH 131-2-19-02 6"x3" 6302 M V T0727-X STREAM 27 (131-AE-2027) OF THE PIPE.
T0727-X
300#
ILME
ILPE 3/4" I
131-SB-20103-21
131-SP-2044 3/4"
+
T NOTE 4 I-2032 2403B M 131-0-70-01 REF. TO SPEC. BGS-LU-013. SPECIAL ITEM TAG REFERS TO INTERLOCKING SYSTEM ONLY.
LC V Q1 6303 131-SP-2310
TI I 2001 NOTE 5 131-SP-2307 TO ANALYSER AT-2027A
131-SP-2046
NO INSUL. PG-01 3/4" T0727-XIP-03 NO INSUL. (H2 ) & AT-2027V (O2 ) Q1 18) CHANGE OF RATING FOR PG MONO FLANGE CONNECTION.
ILME
LO 600# 131-2-19-02 LO P I
B2AP01 2002 ILME TS-02 6302 6"x3"
TS-01 T0471-V
Leq MAX= 102M
131-2-25-07
131-SB-20103-6 NOTE 17 131-SB-20103-8 L 131-SP-2308 3"x1-1/2" V 131-2-25-07 131-2-22-02 REGENERATION GAS
M I INSUL. 131-2-25-07 131-2-22-02 M I INSUL PP
PP
2002 131-0-74-05 S-2011 LC V 10"-131-P-20010-B2AP01-PP
131-0-74-05 3/4" M I TAHH NOTE 17 8208 131-PP-152-20130
131-2-25-07 3/4" 3/4"
COMPRESSOR M 131-SB-20103-9
PP
NO POCKETS
NOTE 3 13122505-TB-25 GENERAL NOTES:
14"-131-ET-20010-B2GP01-I
V TT 131-SP-2045
TH-01 V TT VENT COOLER 131-HA-268
M TV-01 Q1 NC
TV-02 M M M
2002 NOTE 8 HH Q1 T0727-X NC
NC M PP INSUL. NO INSUL. 2001 NOTE 8 HH M A) ALL FLARE LINES TO BE SLOPED TOWARDS THE FLARE HEADER WITH TOP ENTRY.
SP
SP
PG 1"-131-ET-20169-B2GP01-I 600# PP INSUL. NO INSUL.
PP
1"-131-ET-20162-B2GP01-I M 600# PG NOTE 3
TE 2200 NOTE 18 3" 6302 NOTE 18 131-SP-2047
6303
6302
H2 6302 TE 2201 H2 6302 6303 B) SCOPE BREAK BETWEEN VENDOR AND BOROUGE 4 EPC CONTRACTOR IS INDICATED BY: C V
6302 3"
2002 16" N6 2001 TW 16" N6
TW + Q1
+
3/4" S-2011 NC M 2001 S-2011 S-2003 C) PACKAGE DETAILS REFER TO THE CURRENT CONFIGURATION AS REPRESENTED ON
1-1/2"
2002 M 12"
3 I
M
12" N5 I TAHH I 1-1/2" 3/4" N5 T2723-K V S-2004 VENDOR DOCUMENTATION. 3
I TAHH
3/4" M HZEH I HZLH D) DELETED.
2010 NO POCKETS 2013
NO POCKETS 12"x14" 12"x14" 2521 2521 E) ALL INSTRUMENT TAG AND INTERLOCK NUMBERS ON THIS DRAWING HAVE THE PREFIX 131.
MIN.
3/4" M NOTE 1 TI
THIS INFORMATION IS NOT TO BE USED, DISCLOSED, OR REPRODUCED IN WHOLE OR IN PART TO ANYONE OUTSIDE OF ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE) AND ITS SUBSIDIARIES,
10"-131-P-20009-B2AP01-PP
2002 TE 2010 2000 TE 2013 2521 I) DELETED.
K3A 2521 2521
K3A 2010 2" 2013
2" I-2031 TYPE 1A I-2032 TYPE 1A
HH TW HH TW
REFERENCES:
6802
I PI PAH
+ S-2011 I PI PAH
+
2010 2013
THIS DOCUMENT CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE) OR ANY OF ITS LICENSORS.
S-2011
2002 2002 I TAHH 2000 2000
I I TAHH 12" FOR GENERAL NOTES AND REFERENCES SEE DRG. FROM PU-PP-152-01000-01÷15.
I-2031 I 2011 I-2032
N2 PIPING AND INSTRUMENTATION DIAGRAM-SYMBOLS, ABBREVIATIONS AND GENERAL NOTES.
PAL PAL 2014 NOTE 5
TT TI I TAH TT
2002 2000
TI I TAH 131-AS-201
2011 2011 2011 2014
NOTE 15 NOTE 1 L NOTE 15 NOTE 1 2014 2014
2" L 131-2-25-05 Ethylene Drying Pre-Cooling
TE NOTE 5 I-2031 TYPE 1A TE 10" NOTE 13
K3B K3B I-2032 TYPE 1A N1 N3 V
2011 2" 2014 2"
S-2011 I-2032
TW I I-2218 S-2011 C
I-2031 I TAHH TW NOTE 9
I
+
HS TT TI I TAH 2077 TT TI
2037 NOTE 1 2012 2012 2012 NOTE 5
131-VC-203A L STATUS SELECTION NOTE 1 2015 2015
MH I-2032 L S-2011
STATUS SELECTION K3C
TE NOTE 5 I-2031 TYPE 1A K3C TE
I-2031 NOTE 11 I XA NOTE 11 I TAH
M1 2012 M1 2015 XL O XA
I XA 2" 2054 24" 2" 2015
24" 2064 2064
2016 TW TW I-2032 TYPE 1A
NOTE 2 NOTE 2 +
TAHH SHUTDOWN
NOTE 8
+
2012 NOTE 8
2015 B2GP01 D0KP01 D0KP01 13122505-TB-56
A0KP01 131-VC-203 A/B
600 MM MIN. 131-VC-204 A/B
131-AS-201 131-VC-261 A/B
V
131-2-25-05
131-2-19-02
ETHYLENE TREATER SILENCER 131-VC-209A/B
BP-25
3/4" S 0.50 %
TYPE : S 1"-131-HF-20155-A0KP01-V
12" 131-VC-203B 12"
DES. CAPACITY.(kg/h) : 5000 N4 N4 592 131-PP-152-09102
NC 131-2-19-02
DES. DIFF. PRESS (bar) : 131-VC-203A 131-VZ-20004-B2GP01-I NC 607
TO HP FLARE
DP (barg ): 10.3barg/FV 12"x14" 131-VZ-20003-B2GP01-I VA-35 131-SB-20103-15
1-1/2" 6302 1-1/2" 12"x14"
DT (°C) : 345/5.0°C 1"-131-ET-20165-D0KP01-V
MOC (SHELL/ELEMENT) : CS / 6302
INSUL : NONE FO FO 6306
M + M
14"-131-ET-20234-B2GP01-I
+
Q1 6306 Q1 2402
14"-131-ET-20226-B2GP01-I NOTE 18 6302 TF-10
NOTE 18 S NC VA-22
T2723-K NO POCKETS T2723-K TS-13
6302 131-2-25-07 MVA-26
BP-14 M 131
-2-25-07 B2GP01
VA-24 D0KP01
131-SB-20103-10
I
13122505-TB-53
131-SB-20103-17
D0KP01 TO HP FLARE
R.Santangelo/A.Pirani
3/4" G VA-33 D0KP01 A0KP01 VA-34 3/4" S 131-SB-20103-13 0.50 % P 02-Dec-2022 APPROVED FOR DESIGN A.Waykole P.Perego/S.Naik/
R.Soldinger
M 131-2-25-07 NC 14"-131-ET-20021-B2GP01-I NC 2"-131-ET-20166-D0KP01-V
R.Santangelo/A.Pirani
GENERAL NOTES
NOTES:
1) NOZZLE FOR CHEMICAL CLEANING.
2) 131-HE-202 TUBE SIDE PROTECTED BY 131-PSV-2411A/B ON P&ID 131-PP-152-20100
1 1
4300-VZ-DM-131020104
GENERAL NOTES:
A) ALL FLARE LINES TO BE SLOPED TOWARDS THE FLARE HEADER WITH TOP ENTRY.
131-PP-152-20104
B) SCOPE BREAK BETWEEN VENDOR AND BOROUGE 4 EPC CONTRACTOR IS INDICATED BY: C V
PSET=42.0 barg
E) ALL INSTRUMENT TAG AND INTERLOCK NUMBERS ON THIS DRAWING HAVE THE PREFIX 131.
BOROUGE :
PSV
+
F) DELETED.
2833
4"-131-VA-20013-A1AU01-V G) DELETED.
600# H) DELETED.
4"x2" 801 I) DELETED. Q
1-1/2"x1"
Leq MAX = 73 m
TO SAFE
V LOCATION
A2AU16 B2GP01 AT GRADE
TW
+
2816
ETHYLENE
20"-131-ET-20002-B2GP01-PP PP
8191 131-PP-152-20100
131-2-25-05
6301
FROM ETHYLENE CROSS
HEAT EXCHANGER
131-HE-204 A/B
3 C1812-V Q V
3
8"x10"
131-SB-20104-1
3/4"
13122505-TB-18
THIS INFORMATION IS NOT TO BE USED, DISCLOSED, OR REPRODUCED IN WHOLE OR IN PART TO ANYONE OUTSIDE OF ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE) AND ITS SUBSIDIARIES,
NOTE 2
BP-07 2"x3/4"
10" 131-0-01-02
13122505-TB-17 20"
TF-04 131-2-25-05
2"
N1 N6 N4
H
TI
2079 (PP) 131-HE-202
THIS DOCUMENT CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE) OR ANY OF ITS LICENSORS.
131-SB-20104-2
TT TF-03 BP-03 131-0-01-01
2079 2"x3/4"
SHELL: 131-VZ-20007-B2GP01-V
TE 13122505-TB-08 3/4" D
AG 131-2-25-05
2079 C1812-V 166
Q 8"x10" UG 128-0-77-01
BP-26
TW
+
4 2079 1-1/2"
4
ETHYLENE
EXCEPT PURSUANT TO A WRITTEN AGREEMENT WITH ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE).
20"-131-ET-20047-B2GP01-V
131-PP-152-20105 8244
131-2-25-05 TO WASTE WATER
6304
TO ETHYLENE DRYERS COLLECTION SYSTEM
131-VC-205A/B/C
13122505-TB-57
MIN.
COOLING WATER SUPPLY
8"-131-SWS-62601-A2AU16-V 8"-131-SW-62602-B2GP01-V
8243 131-PP-152-09020
131-0-01-01 2"
103 166
A2AU16 B2GP01 D 131-0-01-01
NOTE 1 AG 3/4"
UG 128-0-77-01
5 5
128-0-77-01 Open Drain Network
131-0-01-01 Cooling Water Supply to PO Common
131-0-01-02 Cooling Water Return from PO Common
131-2-25-05 Ethylene Purification Bypass, Filters and Heat Exchangers
TO WASTE WATER
COLLECTION SYSTEM
HOT COLD
CONTRACTOR PROJECT NO
4300 - PO
PO UNIT - RUWAIS, UAE
OT (IN) (ºC) : 65 / 40.0 DRAWING TITLE: PIPING AND INSTRUMENTATION DIAGRAM
OT (OUT) (ºC) : 50.0 / 48.0 UNIT 131 - POLYOLEFINS COMMON
OP (barg) : 29.7 / 4.5 ETHYLENE DRYER PRECOOLER
DP (barg) : 42/FV / 42/FV
BOROUGE DOCUMENT CLASS' N PROJECT DRAWING NO REV: Q
DT (ºC) : 90.0/-45 / 90.0/-45.0
MOC : LTCS / LTCS CONTRACTOR: 4300-VZ-DM-131020104 SHEET UNIT: 131
INSUL. : PP / V 1 BOROUGE: 131-PP-152-20104 OF AREA: 2
CADD SHEET
A B C D E F REF. 131-PP-152-20104-ISQ SCALE: SIZE A1
A B C D E F G H
0.50 % 0.50 % GENERAL NOTES
2"-131-HF-20142-A0KP01-V 2"-131-HF-20148-A0KP01-V
131-PP-152-09103 8258 8262 131-PP-152-09103
131-2-19-02 607
V 607 131-2-19-02
131-SB-20105-7 TO HP FLARE
ETHYLENE
TO HP FLARE
PIC FIC HS 3/4" S 0.50 % NOTES:
20"-131-ET-20047-B2GP01-V NOTE 9 NC NC 131-2-19-02
2"-131-ET-20128-D0KP01-V
8244 131-PP-152-20104 2058 2044 2058 NNF
131-2-25-05 8271 131-PP-152-09102 1) STAGGER THERMOWELLS AT 120° TO EACH OTHER AND EXTEND MINIMUM 300 MM
6304 T 131-2-19-02 IN TO THE VESSEL IN THE CATALYST BED NOT IN INERT BED.
FROM ETHYLENE DRYER TO HP FLARE
0.50 %
PRE COOLER 131-HE-202 PT 600MM 131-2-22-02 2) SUFFICIENT HEIGHT MUST BE AVAILABLE UNDER MANHOLE TO ENABLE DUMPING OF CATALYST.
2"-131-HF-20143-A2GP01-V REGENERATION GAS 2"-131-HF-20165-A0KP01-V
PP T0163-K MIN.
6306
131-PP-152-09103 8261 10"-131-P-20220-B2GP01-PP 2058 MANHOLE AND HANDHOLE INSERTS TO BE FLUSH FITTING.
131-2-19-02 NO INSUL 19410 131-PP-152-20128 D0KP01 A0KP01
1 601 A2GP01 607 3) REMOVABLE SPOOL PIECE FOR VESSEL ISOLATION WHERE REQUIRED FOR ACCESS AND MAINTENANCE. 1
TO HP FLARE 6808 131-2-24-01 PV
4300-VZ-DM-131020105
2058 131-SB-20105-8
PP INSUL NC CONDENSER 131-HE-266A 3/4" S 4) NOT USED.
OFF GAS 131-2-19-02 6040 OFF GAS
131-SB-20105-1 131-2-24-01 2"-131-ET-20026-B2GP01-V 2"x1-1/2" 2"x1-1/2" NO
NNF FT
13122505-TB-13
131-PP-152-20105
19408 131-PP-152-20128 7) SPACE TO BE PROVIDED FOR CATALYST FILLING AND REMOVAL. PROCEDURES TO BE CONFIRMED BY CATALYST VENDOR.
36 RAW PURIFIED T 131-SB-20105-2 M V 600MM V 131-2-24-01
NO POCKETS
6831 G 2"-131-ET-20158-D0KP01-V 2"-131-ET-20160-D0KP01-V NOTE 11 6808 8) ALTERNATE DESIGN CONDITION:343°C AND 11 BARG FOR REGENERATION.
NITROGEN A2GP01 B2GP01 S MIN. S TO REGENERATION GAS
131-0-74-05 131-2-25-08 131-2-24-01 V BP-06 3/4"
1" NO POCKETS NO INSUL PP INSUL 6306 D0KP01 D0KP01 6306 CONDENSER 131-HE-266A 9) MAIN INLET AND OUTLET PIPING FOR 131-VC-205 A/B/C TO BE SYMMETRICAL TO PROMOTE EQUAL PARALLEL FLOW.
8247 131-PP-152-09070-01 Q1 T5059-X 0.50 %
M 3/4" B2GP01 NCVA-09 NC B2GP01 13122505-TB-04 OFF GAS
2"-131-HF-20144-A2GP01-V NC G 13122505-TB-14
131-SB-20105-4 G G BP-05 2"-131-ET-20059-B2GP01-V 10) LOW ALARM VALUES DURING:
131-PP-152-09103 8260 131-2-24-01 6307 6304 131-PP-152-20106 8256 - NORMAL OPERATION / STAND BY / PRESSURIZATION
131-2-19-02 8"-131-HF-20018-A0KP01-V 131-SB-20105-3 NC 6307 6304 VA-08 131-2-22-02
601 2"-131-ET-20058-B2GP01-V 6303 HIGH ALARM VALVES DURING:
TO HP FLARE 131-2-19-02 131-2-24-01 10"-131-P-20038-B2GP01-PP NC131-2-25-08 I INSUL. NO INSUL FROM ETHYLENE
- PURGING / HEATING / COOLING
NO POCKETS 0.50 %
607 G I
TF-01
INSUL NO INSUL 6303 DRYER 131-VC-205 C
131-PP-152-09103 11827
6831 13122505-TB-03 131-2-25-08 131-2-25-05 VA-03
11) PERSONNEL PROTECTION FOR REGENERATION RETURN LINES HAS TO EXTEND OVER THE WHOLE LENGTH OF THE PIPE.
131-2-19-02 MIN. VA-04 ETHYLENE
TO HP FLARE NOTE 9 NOTE 9 12"-131-ET-20050-B2GP01-V
8251 131-PP-152-20106
1"-131-HN-20011-B2AP01-V M 6304 131-2-25-05
BP-01 G 20"x12" 20"x12" TO ETHYLENE DRYER
2 383 131-2-25-08 131-2-19-02 13122505-TB-05 NO POCKETS
VA-06 131-SB-20105-21 131-VC-205 C 2
GENERAL NOTES:
6303
2" X 3" V TS-04
PSET=42.0 barg PSV NOTE 9 12"-131-ET-20047-B2GP01-V 6303
+
3/4" S S NO INSUL
36 RAW PURIFIED 2409 LO 8"x6" A) ALL FLARE LINES TO BE SLOPED TOWARDS THE FLARE HEADER WITH TOP ENTRY.
PP INSUL MIN.
BP-02 M 131-2-25-08 131-2-19-02 V G
NITROGEN
6304 M NC
VA-05 6307
6307
1" 600# 6"x3"131-20105-V1 M NC 131-SB-20105-11 2" X 3" 3/4" 131-SB-20105-13 B) SCOPE BREAK BETWEEN VENDOR AND BOROUGE 4 EPC CONTRACTOR IS INDICATED BY: C V
15820 131-PP-152-09070-01 300# T PSV S
131-2-25-05
131-2-22-02
131-2-25-08
12"-131-ET-20211-B2GP01-I
0.50 %
131-0-74-05 3"x2" 131-SB-20105-10
131-2-22-02
TF-02 3/4" 13122505-TB-06
PSET=42.0 barg +
2410
TS-05
LO 8"x6" 131-2-25-08 8"-131-HF-20020-A0KP01-V
TO HP FLARE
131-2-25-08 V C) PACKAGE DETAILS REFER TO THE CURRENT CONFIGURATION AS REPRESENTED ON
T 3/4" 11822 131-PP-152-09103
12"-131-ET-20049-B2GP01-I
6307
D) DELETED.
PP
383 131-SP-2054
T 131-SP-2052
NO 3"x2" E) ALL INSTRUMENT TAG AND INTERLOCK NUMBERS ON THIS DRAWING HAVE THE PREFIX 131.
6307
131-SB-20105-9
3"-131-ET-20055-B2GP01-PP
NOTE 6 INSUL 3"-131-ET-20057-B2GP01-PP F) DELETED.
NO 6307 B2AP01 3/4" G) DELETED.
1"-131-ET-20012-B2GP01-I
I) DELETED.
1"-131-ET-20049-B2GP01-I
B2GP01 INSUL
I 131-0-74-05
PG INSUL 131-SP-2053 131-SP-2055
NC 131-2-25-08
6307
2207 NOTE 7 SP 2"-131-ET-20056-B2GP01-PP 3/4" NOTE 7 SP NC
HH PG HH
6307
V
M 2208 M M
REFERENCES:
I
TT 3/4" TT
PAH 3/4" M PAH M
K3A 2039 2039 2039 2039 K3A 2017 2017 2017 2017
2" 2"
I-2041 2006 I-2042 2010
TI TI
I PI HH PT TW I PI HH PT TW
+
2039 +
2017
2006 2006 2039 L 2010 2010 2017 L
I
PAL PAL I
2006 2010
THIS DOCUMENT CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION OF ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE) OR ANY OF ITS LICENSORS.
12" 12"
N4 12"-131-ET-20069-B2GP01-I N4
12"-131-ET-20261-B2GP01-I 3/4"
6307 PG
3/4"
6307 PG M 2260
NO POCKETS M 2259 10"-131-ET-20228-B2GP01-I NO POCKETS
NO POCKETS
10"-131-ET-20229-B2GP01-I NO POCKETS 6307 0.50 %
NOTE 9 1"-131-HF-20146-A0KP01-V
6307 8266 131-PP-152-09102
B2GP01 D0KP01 A0KP01 131-2-19-02
131-2-25-05 131-2-25-08
5
131-2-25-08 607 TO HP FLARE
5
B2GP01 D0KP01 A0KP01
131-SB-20105-16
NO
I INSUL
6307
131-SB-20105-15 NC G I
INSUL 6307 M
131-2-25-08 M V 3/4" INSUL.
131-2-24-02 NO 131-SB-20105-19 V
S 6304 3/4"
I
1"-131-HF-20029-A2GP01-V
INSUL
NC NC S
6304
131-2-25-05 0.50 %
NO
6 10"-131-P-20024-B2GP01-I 4700000900 6
TYPE : PACKED FC
131-PP-152-20129 8254
TOTAL VOLUME (m³) : 79.15 6808
131-2-24-02
CONTRACTOR PROJECT NO
4300 - PO
PO UNIT - RUWAIS, UAE
DIA. (mm) : 3500 FROM REGENERATION GAS
HEIGHT (T/T) (mm) : 7060 HEATER 1 131-HH-208 DRAWING TITLE: PIPING AND INSTRUMENTATION DIAGRAM
DP (barg) : 42/FV NOTE 8 PRESSURIZATION UNIT 131 - POLYOLEFINS COMMON
REGENERATION GAS ETHYLENE ETHYLENE DRYERS A & B
DT (ºC) : 90 / -45 I 10"-131-P-20025-B2GP01-I 3/4"-131-ET-20156-B2GP01-V
MOC : LTCS 131-PP-152-20106 8267 131-2-25-05 8253 131-PP-152-20106
131-2-24-02 BOROUGE DOCUMENT CLASS' N PROJECT DRAWING NO REV: Q1
TO ETHYLENE DRYER 6808 6304 TO ETHYLENE DRYER
INSUL. : I
131-VC-205-C 131-VC-205C CONTRACTOR: 4300-VZ-DM-131020105 SHEET UNIT: 131
1 BOROUGE: 131-PP-152-20105 OF AREA: 2
CADD
A B C D E F REF. 131-PP-152-20105-ISQ1 SCALE:
SHEET
SIZE A1
A B C D E F G H
GENERAL NOTES
V
T2029-X T 3/4"
36 BARG RAW NITROGEN Q1
8252 131-PP-152-20105
1"-131-HN-23008-B2AP01-V
131-SP-2001
NOTES:
131-0-74-05 NOTE 7
383 1) STAGGER THERMOWELLS AT 120° TO EACH OTHER AND EXTEND MINIMUM 300 MM INTO THE VESSEL
6808 6831 IN THE CATALYST BED, NOT IN INERT BED.
131-SB-20106-1
REGENERATION GAS 2) SUFFICIENT HEIGHT MUST BE AVAILABLE UNDER MANHOLE TO ENABLE DUMPING OF CATALYST.
10"-131-P-20035-B2GP01-PP PP NC G
MANHOLE INSERTS TO BE FLUSH FITTING.
131-PP-152-20128 19411
1 131-2-24-01 M 3) REMOVABLE SPOOL PIECE FOR VESSEL ISOLATION WHERE REQUIRED FOR ACCESS AND MAINTENANCE. 1
6808 NC
4300-VZ-DM-131020106
TO REGENERATION GAS
NC 131-2-24-01 131-2-25-08 4) NOT USED.
CONDENSER 131-HE-266A 2"-131-P-20210-B2GP01-PP G
3/4" 5) HIGH ALARM VALUES DURING:
131-SB-20106-2
6831 V
131-PP-152-20106
M - PRESSURIZATION
NO POCKETS
NO INSUL PP INSUL
B2GP01
131-2-24-01 2" X 3" - NORMAL OPERATION
131-2-19-02 PSET=42.0 barg 131-2-25-08 131-2-19-02 - HEATING
NC V - PURGING
PSV
+
3/4" S 0.50 %
131-20106-V1 0.50 %
A2GP01
2510 6"x3" 6) MAIN INLET AND OUTLET PIPING FOR 131-VC-205A/B/C TO BE SYMMETRIC TO PROMOTE EQUAL PARALLEL FLOWS.
8"-131-HF-20022-A0KP01-V
CONTRACTOR :
NO INSUL.
131-0-74-05
11821 131-PP-152-09103 7) NORMALLY NOT CONNECTED
B2AP01
0.50 % 600# S 131-2-19-02
BOROUGE :
131-SB-20106-10
TO HP FLARE
NC M
131-2-25-08
I INSUL
B2GP01
10) LOW ALARM VALUES DURING:
Leq MAX = 65 m
0.50 % - NORMAL OPERATION / STAND BY / PRESSURIZATION
2"-131-HF-20140-A0KP01-V HIGH ALARM VALUES DURING:
PP
131-PP-152-09103 8275
PP
131-2-19-02 13122505-TB-09 - PURGING / HEATING / COOLING
607
TO HP FLARE
3"-131-ET-20018-B2GP01-PP
3/4"
131-2-25-05 131-2-19-02
A0KP01 V
D0KP01 M
NC
10"-131-P-20186-B2GP01-PP
6307
1"-131-ET-20149-B2GP01-I
131-SB-20106-4
2 GENERAL NOTES: 2
2"-131-ET-20148-D0KP01-V A) ALL FLARE LINES TO BE SLOPED TOWARDS THE FLARE HEADER WITH TOP ENTRY.
600 MM
MIN.
V 6307 6303
6307
6831
3/4" 6306
13122505-TB-10 PP INSUL NO INSUL B) SCOPE BREAK BETWEEN VENDOR AND BOROUGE 4 EPC CONTRACTOR IS INDICATED BY: C V
D0KP01
V 3/4" M
S 131-SB-20106-5
13122505-TB-01 PG PP OFFGAS
C) PACKAGE DETAILS REFER TO THE CURRENT CONFIGURATION AS REPRESENTED ON
VA-07 NOTE 8 2"-131-ET-20059-B2GP01-V
NC 2308 8256 131-PP-152-20105 VENDOR DOCUMENTATION.
HH 131-2-22-02
B2GP01
M M
SP
2"-131-ET-20050-B2GP01-V G BP-04 NC 131-SP-2002 6303
VA-01 NC NC TO COMMON LIGHT GAS D) DELETED.
NOTE 3 HEADER VIA PV-2058
6304 M 131-2-25-08 131-2-22-02 E) ALL INSTRUMENT TAG AND INTERLOCK NUMBERS ON THIS DRAWING HAVE THE PREFIX 131.
16" 3"
131-SB-20106-3 3/4" M H2 N6
EHTYLENE VA-02 MIN. F) DELETED.
I 12"
12"-131-ET-20050-B2GP01-V NOTE 6 12"-131-ET-20212-B2GP01-I G) DELETED.
8251 131-PP-152-20105 N5
131-2-25-05 G M
6304 6307 H) DELETED.
FROM EHTYLENE DRYER TS-03 NO INSUL I INSUL I-2043 NOTE 5
PRE-COOLER 131-HE-202 3/4" M NOTE 1 I) DELETED.
6304 6307 I-2044
IP-01 131-2-25-08 2" TE TT I TAHH TAH
13122505-TB-02 131-2-25-05
2"
PT 2117 2117 2117 2117
2107 K3A
TW TI
PG-01 I
+
4 4
EXCEPT PURSUANT TO A WRITTEN AGREEMENT WITH ABU DHABI POLYMERS COMPANY LIMITED (BOROUGE).
MH
24"
M1
NOTE 2,8
12"
N4
12"-131-ET-20236-B2GP01-I
6307
6808 6307 I
131-SB-20106-6 3/4"
REGENERATION GAS PG
10"-131-P-20025-B2GP01-I I I 10"-131-ET-20225-B2GP01-I NO POCKETS
8267 131-PP-152-20105 M 2360
131-2-24-02 6808 M G 6307
5 FROM REGENERATION GAS NC NC 5
HEATER 1 131-2-24-02 131-2-25-08
NO POCKETS
131-HH-208
A2GP01 B2GP01
NO INSUL I INSUL V
131-2-25-05 131-2-25-08
NO INSUL I INSUL
B2GP01 B2GP01
131-SB-20106-7
3/4" M M
0.50 %
1"-131-HF-20139-A2GP01-V
131-PP-152-09102 11808
131-2-19-02
131-SB-20106-8
PRESSURIZATION 131-2-19-02
ETHYLENE G 6306 NC 607 N 27-May-2022 ISSUED FOR HAZOP A.Waykole P.Perego/S.Soni/
R.Santangelo/A.Pirani P.Perego
3/4"-131-ET-20156-B2GP01-V NC NC 131-2-25-05 131-2-19-02 TO HP FLARE
600 MM MIN L 14-Feb-2022 ISSUED FOR COMPANY REVIEW A.Waykole P.Perego/S.Soni/
P.Perego
8253 131-PP-152-20105
R.Santangelo/A.Pirani
131-2-25-05 M Approved
6304 Rev. Date Description
Prepared Checked
FROM ETHYLENE DRYER By By By
131-VC-205A/B ETHYLENE
NOTE 6 12"-131-ET-20073-B2GP01-V ABU DHABI POLYMERS COMPANY LIMITED
8257 131-PP-152-20105
G 131-2-25-05 (BOROUGE)
6304
TO ETHYLENE DRYER
131-VC-205C FILTER 131-NF-201A/B
ETHYLENE DRYER PETROCHEMICALS PROJECT
COMPANY PROJECT NO PROJECT TITLE:
6
TYPE : PACKED
4700000900 BOROUGE 4 PROJECT - EPC PACKAGE 3 - 6
BP-05 BP-02
BP-26
BP-06
IP-02
BP-03
IP-03
BP-29
BP-08
BP-09 BP-30
BP-10
BP-28 BP-27
BP-07
BP-19
BP-23
BP-14 BP-31
BP-12
BP-15
BP-11
BP-17
BP-18
BP-22
BP-21
BP-24
BP-25
BP-16
BP-20 BP-13
Borouge 4 Project - EPC Package 3 - PO Unit
TCM IDENTIFICATION CODE
Ruwais, UAE
Job-EC-Type-N°
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING MOD-ITP-XU_001
Date:
PIPING SYSTEM CLEANING
Report No.:
DATA
Cleaning AB CC HJ MC OF SB WF
Method: Air blowing Chemical Hydro jet Mechanical Oil Flushing Steam Water
Cleaning Cleaning blowing flushing
Medium: AIR
Pressure (barg): Temperature (°C):
Cleaning Class: Class (I) Class (II) Class (III)
RESULTS
REMARKS:
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 2
Borouge 4 Project – EPC Package 3 - PO Unit
TCM IDENTIFICATION CODE
Ruwais, UAE
Job-EC-Type-N°
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING MOD-ITP-XU_001
Date:
PIPING SYSTEM CLEANING
Report No.:
Contractor Company
Blowing
Date Result
Point (BP) Name Sign Name Sign
BP-01
BP-02
BP-03
BP-04
BP-04
BP-05
BP-06
BP-07
BP-08
BP-09
BP-10
BP-11
BP-12
BP-13
BP-14
BP-15
BP-16
BP-17
BP-18
BP-19
BP-20
BP-21
BP-22
BP-23
BP-24
BP-25
BP-26
Page 2 of 2
BP-27
BP-28
BP-29
BP-30
BP-31
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 2
Borouge 4 Project - EPC Package 3 - PO Unit
TCM IDENTIFICATION CODE
Ruwais, UAE
Job-EC-Type-N°
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING MOD-ITP-XU_002
Date:
PIPING SYSTEM CHECK LIST
Report No.:
Check that all in line piping components are installed with final
2.
gasket;
Check that flow direction of the check, control and globe valves is
6.
in the correct sense/direction;
Check that test blinds have been removed and process spectacle
7.
blinds have been installed in the correct position;
Page 2 of 2
Borouge 4 Project - EPC Package 3 - PO Unit
TCM IDENTIFICATION CODE
Ruwais, UAE
Job-EC-Type-N°
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING MOD-ITP-XU_002
Date:
PIPING SYSTEM CHECK LIST
Report No.:
Check/Verify that the lines are internally clean and free of debris,
14.
dirt foreign objects, masking tape etc.
REMARKS:
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 2
Borouge 4 Project - EPC Package 3 - PO Unit
TCM IDENTIFICATION CODE
Ruwais, UAE
Job-EC-Type-N°
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING MOD-ITP-XD_002
Date:
PIPING SYSTEM TIGHTNESS TEST OR SERVICE TEST Report No.:
METHODOLOGY
DATA
RESULT
Test (acceptable/not acceptable) Test Date (dd/mm/yy)
REMARKS:
(1) ∆P is the difference between the pressure at beginning of test and the pressure at the end of test.
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 2 of 2
Borouge 4 Project - EPC Package 3 - PO Unit TCM IDENTIFICATION CODEEE Job-
Ruwais, UAE
EC-Type-N° X-U-005
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING
Date:
TEMPORARY BLIND CHECK LIST Report No.:
Installation Removal
Line/Equipment Signature
Blind No. P&ID/UDD No. Date Date
No.
13122505-TB-03
1"-131-HN-20011 131-PP-152-20105
13122505-TB-04 131-PP-152-20105
12"-131-ET-20050
13122505-TB-05 131-PP-152-20105
12"-131-ET-20211
13122505-TB-06 131-PP-152-20105
12"-131-ET-20047
13122505-TB-07 131-PP-152-20104
131-HE-202
13122505-TB-12 131-PP-152-20105
12"-131-ET-20050
13122505-TB-13 131-PP-152-20105
2"-131-ET-20158
13122505-TB-16 131-PP-152-20100
20"-131-ET-20002
13122505-TB-17 131-PP-152-20104
131-HE-202
13122505-TB-20 131-PP-152-20100
3"-131-ET-20003
13122505-TB-21 131-PP-152-20100
6"-131-HF-20242
13122505-TB-23 131-PP-152-20100
1"-131-ET-20137
13122505-TB-24 131-PP-152-20100
3"-131-ET-20004
13122505-TB-25 131-PP-152-20103
14"-131-ET-20010
13122505-TB-26 131-PP-152-20103
14"-131-ET-20001
13122505-TB-27
14"-131-ET-20011 131-PP-152-20103
13122505-TB-29
14"-131-ET-20231 131-PP-152-20102
13122505-TB-30 131-PP-152-20102
14"-131-ET-20001
13122505-TB-31 131-PP-152-20102
20"-131-ET-20009
13122505-TB-32 131-PP-152-20102
14"-131-ET-20035
13122505-TB-33 131-PP-152-20103
14"-131-ET-20234
13122505-TB-35 131-PP-152-20100
131-HE-204B
13122505-TB-36 131-PP-152-20100
20"-131-ET-20017
13122505-TB-37 131-PP-152-20103
14"-131-ET-20235
13122505-TB-38 131-PP-152-20103
14"-131-ET-20021
13122505-TB-39 131-PP-152-20103
2"-131-ET-20014
13122505-TB-41 131-PP-152-20103
2"-131-ET-20216
13122505-TB-42 131-PP-152-20103
14"-131-ET-20001
13122505-TB-43 131-PP-152-20102
2"-131-ET-20173
13122505-TB-44 131-PP-152-20102
14"-131-ET-20001
13122505-TB-45 131-PP-152-20102
14"-131-ET-20039
13122505-TB-46 131-PP-152-20102
14"-131-ET-20001
13122505-TB-47 131-PP-152-20102
2"-131-ET-20174
13122505-TB-48 131-PP-152-20102
14"-131-ET-20001
13122505-TB-50 131-PP-152-20102
14"-131-ET-20035
13122505-TB-51 131-PP-152-20103
2"-131-ET-20164
13122505-TB-52 131-PP-152-20103
14"-131-ET-20017
13122505-TB-53 131-PP-152-20103
2"-131-ET-20166
13122505-TB-54 131-PP-152-20103
14"-131-ET-20021
13122505-TB-56 131-PP-152-20103
14"-131-ET-20016
13122505-TB-57
20"-131-ET-20047 131-PP-152-20104
13122505-TB-60 131-PP-152-20100
20"-131-ET-20017
Remarks
*Note: TB – Temporary Blind // SB – Spectacle, Spade, Spacer Blind // PPB – Permanent Spade (Paddle) Blind
PSB – Permanent Spacer Blind // TPB – Temporary Spade (Paddle) Blind // TSB – Temporary Spacer Blind
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 1
Borouge 4 Project - EPC Package 3 - PO Unit TCM IDENTIFICATION CODEEE
Ruwais, UAE
Job-EC-Type-N° X-U-006
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING
Date:
SPECTACLE BLIND CHECK LIST Report No.:
Position
Location according to Position
Blind Nr. Line/Equipment P&ID/UDD No. Flushing according to Signature
No. Prog. P&ID
Date Indication
Date
131-SB-20106-3 12"-131-ET-20050 131-PP-152-20106
Page 1 of 1
131-SB-20103-10 14"-131-ET-20017 131-PP-152-20103
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 1
Borouge 4 Project - EPC Package 3 - PO Unit TCM IDENTIFICATION CODEEE
Ruwais, UAE
Job-EC-Type-N° X-U-007A
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING
Date:
INSTRUMENT CHECKLIST
(TEMPORARILY REMOVED) Report No.:
Remarks
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 1
Borouge 4 Project - EPC Package 3 - PO Unit
TCM IDENTIFICATION CODE
Ruwais, UAE
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING
Job-EC-Type-N° X-U-008
Date:
FLUSHING AND BLOWING
LINE CHECK LIST Report No.:
Remarks
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 1
Borouge 4 Project - EPC Package 3 - PO Unit TCM IDENTIFICATION CODEEE
Ruwais, UAE
Job-EC-Type-N° X-U-010A
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING
Date:
TEMPORARILY REMOVED PIPING ITEM CHECK LIST
Report No.:
Page 1 of 1
VA-31 14"-131-ET-20001 131-PP-152-20102
VA-32 14"-131-ET-20035 131-PP-152-20102
VA-33 14"-131-ET-20017 131-PP-152-20103
VA-34 14"-131-ET-20021 131-PP-152-20103
VA-35 14"-131-ET-20016 131-PP-152-20103
Remarks
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 1
Borouge 4 Project - EPC Package 3 - PO Unit TCM IDENTIFICATION CODEEE
Ruwais, UAE
Job-EC-Type-N° X-U-010B
PIPING FIELD INSPECTION PLAN PRECOMMISSIONING
Date:
TEMPORARILY INSTALLED PIPING ITEM CHECK LIST
Report No.:
SUBCONTRACTOR
CONTRACTOR
COMPANY
Page 1 of 1